Professional Documents
Culture Documents
Document Submittal Approval Form: 667084 - District Cooling Scheme For KFUPM Business Park
Document Submittal Approval Form: 667084 - District Cooling Scheme For KFUPM Business Park
APPROVAL FORM
PROJECT NO./NAME: 667084 - District Cooling Scheme for KFUPM Business Park
Discipline Engineer
JAG Representative
Note: This review does not relieve the Contractor of his responsibility to comply with the requirements detailed in his
contract.
Form No.: 667084-A-37SN-0000-0003 Rev.No:00 King Fahad University of Petroleum and Minerals
Date: 13-Mar-2019
DISTRICT COOLING PLANT-KFUPM-SNC LAVALIN
Dhahran-Saudi Arabia
Commissioning Plan
Table of Contents
.................................................................................................. 4
................................................................................................... 5
........................................................................................ 7
....................................................................................................... 8
...................................................................................................... 8
..................................................... 8
...................................................................................................... 9
........................................................................................................... 9
................................................................................................... 9
.................................................................................................... 9
................................................................. 9
................................................................... 11
................................................................................................ 12
.............................................................................................................. 12
............................................................................................... 12
....................................................................................................... 12
.................................................................................................. 12
...................................................................................................... 13
............................................................. 13
........................................................................................................ 14
................................................................................... 14
.................................................................................. 17
................................................................................................. 17
........................................................................................ 17
..................................................................................... 18
.................................................................................................................. 19
........................................................................................................... 20
....................................................................................................... 20
.................................................................................................... 20
.......................................................................... 21
................................................................................................ 22
.......................................................................... 23
Page: 2 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
................................................................................ 24
................................................................................... 25
.................................................................................... 29
.................................................................... 30
........................................................................................... 31
......................................................................................................... 32
...................................................................................... 33
....................................... 34
..................................................................................... 35
............................................................................ 38
................................................................................................ 44
..................................................................... 45
.............................................................................................. 46
Page: 3 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 4 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 5 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 6 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 7 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 8 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
o
o
o
o
o
Page: 9 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 10 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 11 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
a)
b)
c)
Page: 12 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
d)
Page: 13 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 14 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
o
o
o
o
Page: 15 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
o
o
Page: 16 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 17 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 18 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
TBC
Client: Dhahran Valley Cooling Company
Name Designation Phone E-mail
TBC
Consultant: TBC
Name Designation Phone E-mail
TBC
TBC
Cx Contractor: TBC
Name Designation Phone E-mail
TBC
TAB: TBC
Page: 19 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 20 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 21 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 22 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 23 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 24 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Design/ Specialist/
Client CxA Contractor
Supervision Supplier
SN Systems to be Commissioned
SNC
DVCC TBC Alpin MEP ICC TAB Supplier
Lavalin
Develop/Obtained Operations
1.12 A A/V V L L/S N N S
and Maintenance manuals (O&M)
Page: 25 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Design/ Specialist/
Client CxA Contractor
Supervision Supplier
SN Systems to be Commissioned
SNC
DVCC TBC Alpin MEP ICC TAB Supplier
Lavalin
System/Equipment’s Start-up &
2.1.2 I A/W V W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
2.1.3 I A/W W/V W L/S A/W L S
Functional Test (ATP-2)
Commissioning/Functional
2.1.4 Test/Performance Test & Dynamic I A/W W/V W L/S A/W L S
Test (ATP-3)
System Controls Integration (ATP-
2.1.5 I A/W W/V W L A/W S L
4)
Installation of system/equipment
2.2.1 I A/W V S L/S A/W N S
and components
System/Equipment’s Start-up &
2.2.2 I A/W V W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
2.2.3 I A/W W/V W L A/W L S
Functional Test (ATP-2)
Commissioning/Functional
2.2.4 Test/Performance Test & Dynamic I A/W W/V W L A/W L S
Test (ATP-3)
System Controls Integration (ATP-
2.2.5 I A/W W/V W L/S A/W S L
4)
2.3 Fans
Installation of system/equipment
2.3.1 I A/W V S L/S A/W N S
and components
System/Equipment’s Start-up &
2.3.2 I A/W V W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
2.3.3 I A/W W/V W L A/W L S
Functional Test (ATP-2)
Commissioning/Functional
2.3.4 Test/Performance Test & Dynamic I A/W W/V W L A/W L S
Test (ATP-3)
System Controls Integration (ATP-
2.3.5 I A/W W/V W L/S A/W S L
4)
Installation of system/equipment
2.4.1 I A/W V S L/S A/W N S
and components
System/Equipment’s Start-up &
2.4.2 I A/W V W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
2.4.3 I A/W W/V W L A/W L S
Functional Test (ATP-2)
Commissioning/Functional
2.4.4 Test/Performance Test & Dynamic I A/W W/V W L A/W L S
Test (ATP-3)
System Controls Integration (ATP-
2.4.5 I A/W W/V W L/S A/W S L
4)
Installation of system/equipment
2.5.1 I A/W V A/W L/S A/W V S
and components
3 Commissioning of Plumbing
Page: 26 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Design/ Specialist/
Client CxA Contractor
Supervision Supplier
SN Systems to be Commissioned
SNC
DVCC TBC Alpin MEP ICC TAB Supplier
Lavalin
Phase 4: Chemical Treatment upon
3.1.4 I A/W W/V W L A/W N L
Commissioning
Phase 5: System Analysis
3.1.5 I A/W W/V W L A/W N L
procedure
Installation of system/equipment
3.2.1 I A/W V W L A/W N S
and components
Installation of system/equipment
3.4.1 I A/W V W L A/W N S
and components
System/Equipment’s Start-up &
3.4.2 I A/W V W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
3.4.3 I A/W W/V W L A/W N S
Functional Test (ATP-2)
Commissioning/Functional
3.4.4 Test/Performance Test & Dynamic I A/W W/V W L A/W N S
Test (ATP-3)
System Controls Integration (ATP-
3.4.5 I A/W W/V W L A/W N L
4)
Installation of system/equipment
3.5.1 I A/W V A/W L A/W N S
and components
Installation of system/equipment
3.6.1 I A/W V W L A/W N S
and components
System/Equipment’s Start-up &
3.6.2 I A/W V W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
3.6.3 I A/W W/V W L A/W N S
Functional Test (ATP-2)
Commissioning/Functional
3.6.4 Test/Performance Test & Dynamic I A/W W/V W L A/W N S
Test (ATP-3)
System Controls Integration (ATP-
3.6.5 I A/W W/V W L A/W N L
4)
Installation of system/equipment
3.7.1 I A/W V W L A/W N S
and components
System/Equipment’s Start-up &
3.7.2 I A/W I W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
3.7.3 I A/W W/V W L A/W N S
Functional Test (ATP-2)
Page: 27 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Design/ Specialist/
Client CxA Contractor
Supervision Supplier
SN Systems to be Commissioned
SNC
DVCC TBC Alpin MEP ICC TAB Supplier
Lavalin
Commissioning/Functional
3.7.4 Test/Performance Test & Dynamic I A/W W/V W L A/W N S
Test (ATP-3)
System Controls Integration (ATP-
3.7.5 I A/W W/V W L A/W N L
4)
Installation of system/equipment
4.1.1 I A/W V W L A/W N S
and components
System/Equipment’s Start-up &
4.1.2 I A/W I W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
4.1.3 I A/W I W L A/W N S
Functional Test (ATP-2)
Commissioning/Functional
4.1.4 Test/Performance Test & Dynamic I A/W I W L A/W N S
Test (ATP-3)
4.1.5 Lux Level test I A/W W/V W L A/W N L
Installation of system/equipment
4.2.1 I A/W V W L A/W N S
and components
System/Equipment’s Start-up &
4.2.2 I A/W I W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
4.2.3 I A/W W/V W L A/W N S
Functional Test (ATP-2)
Commissioning/Functional
4.2.4 Test/Performance Test & Dynamic I A/W W/V W L A/W N L
Test (ATP-3)
Systems Control Integration (ATP-
4.2.5 I A/W W/V W L A/W N L
4)
Electrical, BTU and water
4.3
metering
Installation of system/equipment
4.3.1 I A/W V W L A/W N S
and components
System/Equipment’s Start-up &
4.3.2 I A/W I W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
4.3.3 I A/W W/V W L A/W N S
Functional Test (ATP-2)
Commissioning/Functional
4.3.4 Test/Performance Test & Dynamic I A/W W/V W L A/W N S
Test (ATP-3)
Systems Control Integration (ATP-
4.3.5 I A/W W/V W L A/W N L
4)
Installation of system/equipment
4.4.1 I A/W V W L A/W N S
and components
System/Equipment’s Start-up &
4.4.2 I A/W V W L A/W N L
Static Test (ATP-1)
Pre-Commissioning or Pre-
4.4.3 I A/W W/V W L A/W N S
Functional Test (ATP-2)
Commissioning/Functional
4.4.4 Test/Performance Test & Dynamic I A/W W/V W L A/W N S
Test (ATP-3)
Systems Control Integration (ATP-
4.4.5 I A/W W/V W L A/W N L
4)
Page: 28 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 29 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 30 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 31 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 32 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 33 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 34 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 35 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Comments:
Page: 36 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 37 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 38 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 39 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 40 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 41 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 42 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 43 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 44 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 45 of 46
© 2020, Alpin Limited
DISTRICT COOLING PLANT-KFUPM
Commissioning Plan
Page: 46 of 46
© 2020, Alpin Limited