Professional Documents
Culture Documents
RDDM Chapter3 Hydrology
RDDM Chapter3 Hydrology
3
Chapter 3
Hydrology and
Design Criteria
June 2003
Road Drainage Design Manual Chapter 3: Hydrology and Design Criteria
Manual Contents
3
Chapter 1
Overview
Chapter 2
Site Assessment
Chapter 3
Hydrology and Design Criteria
Chapter 4
Design
Chapter 5
Erosion and Sediment Control
Chapter 6
Maintenance and Remediation
Chapter 7
Worked Examples
Chapter 8
References
June 2003
Road Drainage Design Manual Chapter 3: Hydrology and Design Criteria
Table of Contents
3.1 Introduction 3-1
3.1.1 Purpose 3-1
3.1.2 When to use Chapter 3 3-2
3.1.3 How to use Chapter 3 3-2
3.1.4 Inputs 3-3
3.1.5 Applying Design Criteria 3-3
3
3.6.2 Tidal Waters 3-29
3.6.2.1 Tide Levels 3-29
3.6.2.2 Storm Surge 3-29
3.6.2.3 The Greenhouse Effect 3-30
3.6.2.4 Tidal Outlets (Ocean and Bays) 3-30
3.6.2.5 Tidal Outlets (Rivers and Creeks) 3-30
3.6.2.6 Design Issues for Tidal Outlets 3-31
3.6.3 Non-Tidal Waters 3-31
3.6.3.1 Large Storage Areas 3-31
3.6.3.2 Small Storage Areas 3-31
3.6.3.3 Open Channels 3-32
3.6.3.4 Protection of Non-Tidal Outlets 3-32
iv June 2003
Road Drainage Design Manual Chapter 3: Hydrology and Design Criteria
June 2003 v
Road Drainage Design Manual Chapter 3: Hydrology and Design Criteria
vi June 2003
Road Drainage Design Manual Chapter 3: Hydrology and Design Criteria
Steering June
1 First Issue
3
Committee 2002
3 Chapter 2
Site Assessment
Chapter 4
Design Introduction
• Purpose
• When to use Chapter 3
• Inputs
• Applying Design Criteria
Selection of Erosion and
Sediment Controls
Selection of Pollution
Controls
Chapter 3
Design Standards
HYDROLOGY AND
Selection of Drainage
Infrastructure DESIGN CRITERIA
Hydraulic Criteria
Ambient Conditions
Hydrology
Fauna Passage
Tailwater Levels
Chapter 3
Hydrology and Design Criteria
3.1 Introduction In Section 3.5, the Rational Method is adopted as
the Department's standard method for the
3.1.1 Purpose determination of design flows (or discharges) for
3
small catchments. A detailed description of this
Chapter 3 of the Road Drainage Design Manual method is provided. Whilst this information must
provides an important link between the collection be utilised during the design phase, its place in
of data (Chapter 2) and the design of drainage this section of the manual reflects the
infrastructure (Chapter 4). This link establishes fundamental importance of hydrology for all
the hydrological conditions and design criteria, aspects of road design.
and facilitates the selection of the most
Section 3.6 provides a discussion of the
appropriate drainage infrastructure at a particular
importance of tailwater levels in designing
location.
effective drainage infrastructure, addressing
The identification of design criteria may also be tailwaters both within a drainage path and as
thought of as the identification of constraints. backwater from tidal and non-tidal water bodies
downstream.
This chapter also provides a link between the
determination of erosion risk, and the selection of Section 3.7 (Fauna Passage) represents the first of
appropriate erosion and sediment controls the “Selection” sections. It provides an overview
(Chapter 5). as to how fauna passage issues should be
considered when assessing drainage structures. In
On this basis, Chapter 3 promotes the some circumstances, Section 3.7 may be applied
consideration of environmental and hydraulic as the primary sizing mechanism for a culvert,
criteria in an integrated manner, along with the with the structure subsequently checked for
influence of external factors. The structure of hydraulic performance.
Chapter 3 (as summarised below) reflects this
philosophy. The influence of ambient conditions on drainage
infrastructure is dealt with in Section 3.8. The
Section 3.1 provides an overview of Chapter 3, purpose of this section is to provide an
reiterating the importance of using all relevant appreciation of the significant influence different
data. conditions can exert on design.
In Section 3.2, an overview of several very broad Section 3.9 guides the user through the selection
criteria is presented, including planning, process in relation to how different types of
maintenance and safety considerations. drainage measures are chosen. Its main purpose is
to ensure that the user of the manual has
Section 3.3 discusses the selection and practical considered all relevant criteria and constraints
application of a design standard, with emphasis on before proceeding to detailed design. The section
flood immunity. also recognises that drainage design is an iterative
Section 3.4 provides a summary of the key process, with many factors influencing the final
hydraulic criteria necessary to undertake the layout of the drainage system.
design of permanent drainage measures. These Section 3.10 deals with the selection of pollution
include permissible velocity, afflux, gradient and controls, for those situations where water quality
tailwater levels. objectives have been defined, and must be
satisfied. The section provides guidance as to
which types of controls will be suitable for the • Determine an initial design standard to aim for;
given set of conditions.
• Work out the hydrological conditions of the site
In Section 3.11, the user is guided as to the (the range of flows) for the desired standard;
selection of erosion and sediment controls, the
majority of which will be used during the • Select possible structure type and sizes that
construction phase of the project. could satisfy the hydraulic, environmental and
external criteria;
3
erosion and sediment controls that may be
Use of this chapter should predominantly occur required.
during the Planning/Preliminary Design phase of
• Proceed to the design process in the following
a project. This ensures that the key factors
chapters.
influencing the hydraulic and environmental
performance of drainage infrastructure are It may be necessary to revisit this chapter to refine
identified and understood prior to detailed design. the design criteria and hydrology after the first
cycle of the design.
However, it is important to note that drainage
design, as with all aspects of road design, is Design criteria relating to road drainage may be
frequently an iterative process. Hence, whilst this grouped into three different types of criteria.
chapter of the manual would normally be applied These are:
at the Planning or Preliminary Design phase of a
project, it could also be used to reassess drainage 1. hydraulic criteria;
options after detailed design had already been
2. environmental criteria; and
completed. For example, detailed design may
result in an unacceptable cost, leading to the 3. external criteria.
subsequent specification of a reduction in the
design standard. Hydraulic criteria may be considered as
including the following:
An integral part of the design process is
knowing when specialist skills are required. • flood immunity/design standard;
The techniques provided in this chapter are
appropriate for the majority of small road • discharge;
drainage design projects. However, in many • permissible velocities; and
instances the complexities of the site may
require the services of a specialist. These • permissible afflux.
situations are highlighted in the appropriate
sections. Establishing the hydraulic criteria requires an
understanding of the hydrological conditions of
the site or project.
3.1.3 How to use Chapter 3
Environmental criteria will vary significantly
The user of this manual must ensure that the from project to project, and hence it is not
provisions of Chapter 3 are considered before practical to list all potential issues in this section.
commencing any design process in the following However, there are two types of environmental
Chapters. The procedure would generally consist criteria for which details have been provided.
of the following steps: These are provision for fauna passage, and the
improvement of water quality. In many projects,
• Determine the general design criteria that it will be important to ensure that the design of
should apply to the situation; drainage infrastructure adequately caters for the
existence of fauna, and also for the maintenance
3
in Section 3.2.5.
requirements, or will maximise the efficiency Surface Drainage incorporates all open drains,
with which specific criteria (eg. pollution control) channels, diversion drains, swales, table drains,
are incorporated into the design. catch drains and kerb and channel within the
extents of the road formation.
3
of the road formation.
3.2.2 Environment
This table illustrates how an REF/IAS may To enable maintenance to be properly and safely
recommend a number of management strategies undertaken during road construction and
to minimise potential environmental harm. These operation, consideration must be given to:
may be in the form of design requirements or
• the provision of adequate access;
implementation of particular construction
techniques which minimise potential • the method of maintenance;
environmental harm (ie. progressive revegetation • equipment to be used (eg. vehicles, slashers,
to reduce soil exposure). These criteria and backhoe etc.); and
techniques are generally based on the
3
requirements of relevant legislation, policy, codes, • the method of operation of maintenance
guidelines and current Best Practice equipment.
Environmental Management for the industry.
3.2.4 Safety
3.2.3 Maintenance
An integral aspect of the detailed design of all
The provision for maintenance is an integral road drainage systems is the underlying
component of the planning and design phases of consideration of safety.
road drainage. Adequate maintenance is necessary
for the proper operation of the drainage system. Some of the safety issues that require
The lack of maintenance is one of the most consideration as part of the road drainage design
common causes of failure of drainage systems process are described below:
(and erosion and sediment controls). This may be • Maintenance Access. Safe access needs to be
attributed to reasons such as a significant provided to all drainage structures that require
reduction in hydraulic or storage capacity (eg. either ongoing (ie. mowing of drains) or
blockage by debris or sediment). occasional (ie. removal of debris) maintenance.
Specific details on maintenance procedures and This access is required for vehicles and/or
requirements for road drainage systems are maintenance crews depending on the type of
provided in Chapter 6 of this manual. maintenance that will be undertaken. Safe
3
safety device needs to ensure that it prevents
both access to the culvert and trapping of a
• Lack of available space.
child against the grate. The effect of any
proposed child safety measure on culvert The Department's Form M2289, Road
capacity and efficiency needs to be checked; Infrastructure Proposal - Project Concept Phase
also lists many other factors which need to be
• Traffic Safety. Projecting culvert ends have the
considered before a decision is made on the
potential to act as obstructions to out of control
standard of new infrastructure. These factors may
vehicles. Where there are no safety barriers
ultimately affect other aspects of road design,
culvert ends should not present an obstruction.
which may in turn affect the provision of drainage
If obstructions from projecting culverts or head
infrastructure.
walls are unavoidable then safety barriers
should be considered;
For rainfall, the average recurrence interval (ARI) (static plus velocity) across a carriageway is
is defined as the average interval in years between equal to 300mm. Refer to Section 4.2.3.5.
exceedances of a specified rainfall.
• Pavement immunity - In this instance,
A similar definition may be applied for floods and immunity is defined with the upstream level
as explained in the introduction above, it is usual being below the pavement base course, which
to define the flood arising from a specified rainfall gives a higher road level. This level will be
as having the same ARI as the rainfall. defined in future as pavement immunity with
the road grade at 'x' mm above a flood of 'y'year
The AEP (annual exceedance probability) is also
3
ARI.
used in relation to flood flows. The AEP is the
probability of exceedance of a given discharge • Time of Closure - This is a measure of the
within a period of one year. It is commonly expected time of closure of a road in a major
considered as the reciprocal of the average flood such as a 50 year ARI. This may be in the
recurrence interval (ARI) in years expressed as a order of days. Time of closure is described in
percentage. detail in Section 4.2.3.5
Table 3.3 Recommended Design Average Recurrence Intervals for Urban Catchments
Category ARI
(i) Major System Design ARI (years) 50
(ii) Minor System Design ARI (years)
Development Category
Central Business and Commercial 10
Industrial 2
Urban Residential High Density 2-10
3
- greater than 5 & up to 20 dwelling units/ha
Rural Residential - 2 to 5 dwelling units/ha 2
Open Space - Parks, etc. 1
Major Road Kerb & Channel 10
Flow (See Note 1)
Cross Drainage 50
(Culverts) (See Note 2)
Minor Road Kerb & Channel As for
Flow relevant,
development
category
Cross Drainage 10
(Culverts) (See Note 2)
Notes:
1. The design ARI for the minor drainage system in a major road will be 10 years for Kerb and Channel Flow and
50 years for Cross Drainage, regardless of the Development Category of the adjacent area.
2. Culverts under roads should be designed to accept the full flow for the minor system ARI shown. In addition, for
major roads the designer should aim to ensure that the 100 year ARI backwater does not enter properties
upstream. Similarly, the 50 year ARI backwater should be used as the check for cross drainage in minor roads.
If upstream properties are at a relatively low elevation it may be necessary to install culverts of capacity greater
than that for the minor system ARI design storm to ensure flooding of upstream properties is not increased. In
addition the downstream face of the causeway embankment may need protection where overtopping is likely to
occur.
3.3.2.2 Standard for State ARI flood trafficability range. However, there are
Controlled Roads - Rural older roads with lower trafficability.
Catchments
It is rare to design a new road with trafficability in
For rural catchments, the generally accepted floods less than 10 years ARI.
standard for cross drainage is a flood immunity of
50 years ARI wherever possible.
3.3.2.3 Standard for National
This standard also applies to rehabilitation/ Highways
reconstruction projects where existing structures Federal Government requirements are that the
are assessed as hydraulically or structurally probability of the Highway being closed to traffic
deficient and need to be completely replaced. by water in any particular year is to be less than:
Designers should check departmental strategies • 1 in 100 where the AADT is expected to exceed
for immunity and / or trafficability requirements 2000 in the next 20 years; or
for specific routes and individual projects.
• 1 in 50 where the AADT is not expected to
Other than in exceptional circumstances, only exceed 2000 in the next 20 years;
roads in remote areas of the State and/or with little
traffic are designed outside the 20 year to 100 year
and the average annual time of closure by water is • The minimum grade for unlined drains,
to be less than 12 hours. including table drains, is 0.5% and for lined
drains, 0.2%. This is to ensure flow and, if
3.3.2.4 Practical Application of applicable, minimize ponding against
Standard formations and pavements.
Although highly desirable, it is not always • Limit flow velocities for longitudinal drainage
possible to meet the above requirements from the to prevent erosion. Limiting flow velocities is
funds available. Therefore, staged construction at preferred over maintaining high flow velocities
3
an initially lower standard is sometimes adopted. and providing armouring. An increase in the
number of outflow points (e.g. turnouts or level
Reference should also be made to Section 3.2.5, spreaders) from the longitudinal drainage
which lists some of the external criteria, that can should be considered.
influence the selection of immunity or design
standard • Limit flow depths to prevent erosion and
inundation of the pavement.
The major/minor drainage system or dual Guidelines for the selection of design standards
drainage system is a concept that has two distinct (average recurrence intervals) for erosion and
components: sediment controls are contained within Section
3.11.
The minor drainage system (refer glossary for
definition) shall be designed to convey the
3
discharge for a minor design storm (ARI as per
Table 3.3) with road flow limited in accordance
3.4 Hydraulic Criteria
with the requirements set out in Chapter 4,
Section 4.4.4.4. 3.4.1 Discharge
The major drainage system (refer glossary for The design discharge for a proposed structure may
definition) conveys the floodwater beyond the not be determined until sufficient hydraulic
capacity of the minor drainage system and shall be analysis is done to define flow patterns, and a
designed in accordance with the requirements set structure size is selected.
out in Chapter 4, Section 4.4.4.4.
The determination of the discharge/ARI
Note: With any proposed drainage system designed relationship is a fundamental requirement for all
adjacent to sensitive areas where flood inundation will drainage designs. Following determination of the
not be tolerated, the design of the major drainage appropriate design standard, the discharge must
system should also consider the flow conveyed in the
underground minor drainage system should this system
be calculated for each proposed structure, and for
fail due to malfunction or blockage. each flood ARI that may need to be tested as a
possible design condition. This can be undertaken
Designers should note that the design discharge manually (refer Section 3.5), or with the aid of
for the major system ARI may require that the computer software, as described in Appendix 3A.
capacity of the gully inlets and underground pipes
be increased beyond that required by the design
discharge for the minor system ARI, in order to 3.4.2 Velocity
meet the major system design criteria.
The velocity of flow (whether in a watercourse or
The minor design storm and the major design overland) is one of the most important criteria
storm correspond to the rainfall events for the ARI dictating the performance of a drainage system,
chosen for the design of the minor system and the the potential for erosion and the subsequent
major system respectively. implications for design.
Velocity criteria may be specified in terms of the dictated by the types of soil and vegetation
average velocity at a location (for a nominated present. The value chosen applies to peak
design event), or in terms of the maximum velocities, but should also be linked to an
velocity at locations of interest, such as the bed of understanding of the duration of flow. For short
a watercourse. duration events, a higher velocity may be
tolerated than for long duration events.
Velocity criteria will typically fit into one of the
following three classifications: Table 3.4 provides a summary of typical
maximum velocity criteria for different
1. Existing;
3
conditions.
2. Desirable maximum; and Where the desirable maximum velocity cannot be
achieved (ie. where it is exceeded), then the
3. Maximum Permissible.
designer will need to look at the selection of
appropriate linings which can withstand the
3.4.2.1 Existing Conditions estimated peak velocities predicted to occur.
The existing velocity regime may be considered
acceptable in those circumstances where minimal 3.4.2.3 Maximum Permissible
changes to a watercourse are proposed, and that Velocity
watercourse is currently stable. However, care
In some circumstances, it will not be possible to
must be taken to ensure that where the bed or
offer bed or bank protection in order to cater for a
banks of a watercourse are disturbed, that
velocity higher than the desired maximum. For
appropriate restoration occurs. Failure to meet this
example, where fish passage is a requirement,
requirement will usually result in erosion, and
there may be specific velocity criteria that apply
possible failure of drainage infrastructure.
to normal and/or low flow. These will typically be
determined through the REF/IAS process and use
3.4.2.2 Desirable Velocity of a fish specialist.
Where works in a watercourse are required, the In these situations, the specified velocity criteria
desirable maximum velocity will typically be must be satisfied, and hence design of the cross
Table 3.4 Maximum permissible velocities (m/s) for earth channels (SCS, 1982)
Erodability Assessment
Cover Channel Low Moderate High Very High
Slope (%)
Kikuyu and other dense high- 1-5 2.6 2.4 2.3 2.2
growing, prostrate perennials 5-10 2.5 2.3 2.2 2.1
>10 2.4 2.2 2.1 2.0
Couch and other low-growing, 1-5 2.1 2.0 1.9 1.7
prostrate perennials 5-10 2.0 1.9 1.8 1.6
>10 1.9 1.8 1.7 1.5
Perennial improved pastures 1-5 1.7 1.6 1.4 1.2
5-10 1.6 1.5 1.3 1.1
>10 1.5 1.4 1.2 1.0
Native tussocky grasses, sparse 1-5 1.4 1.2 1.0 0.8
legumes and annuals 5-10 1.3 1.1 0.9 0.7
Bare soil 1-10 0.7 0.6 0.5 0.4
Note: Maximum permissible velocities for fish passage are detailed in Section 4.2.2.2 of Chapter 4. These velocities
are 0.3 m/s for flow depths of 0.2 to 0.5 m and up to 1.0 m/s in isolated locations (i.e. short channel lengths).
3
water level compared with that without the
structure is defined as afflux. The distance • stability of the watercourse;
upstream that is affected depends on the size of
the afflux, and the hydraulic gradient of the • retention of waterway characteristics
watercourse. The acceptability of this increase is (preservation of flora and fauna); and
defined by the existence of upstream property or
• protection of existing infrastructure from flood
infrastructure, as assets that cannot cope with
damage.
increased flood levels will typically necessitate a
higher capacity culvert.
manual, can be of any size and include: 3.5.2 Methods Available for
Runoff Calculation
• multiple stream / branched catchments,
Techniques for flood estimation in the larger
• large stream / river systems,
catchments, usually associated with major
• catchment areas consisting of several different structures such as bridges and floodways, are not
land uses, described in any detail in this manual. Such
procedures are described in such publications as
• catchments with highly varied slopes, and Australian Rainfall and Runoff (IEAust, 1987)
3
and Hydraulics Training Course (Department of
• catchments / streams with storage capacity.
Main Roads, 1996) and include unit hydrograph
Runoff calculations for these catchments should methods, runoff and storage routing and
be undertaken by or in conjunction with hydraulic frequency analysis. Appendix 3A discusses the
specialists. use of computer models for hydrological and
hydraulics calculations.
Variables such as local depressions/storages and
infiltration rates into different soil types are Other states use the Probabilistic Rational
difficult to quantify and the importance of existing Method. However, there are insufficient long term
flood information cannot be overemphasised, not gauging station records in Queensland to compile
only to calibrate theoretical calculations but also the equivalent method.
for decisions on the magnitude of the design flood
and any future legal litigation. The Department’s
3.5.3 Rational Method
Form M2759, Field Report - Bridge Waterways
gives a guide to the information which should be
The traditional Rational Method is described
sought, such as flood levels, in hydraulically
below.
sensitive locations and for the larger structures.
The Rational Method Formula is:
Calculations based on long term local recorded
flood data should be given precedence over more Qy = k x Cy x Itc,y x A
theoretical calculations, but the reasons for any
inconsistencies should be sought. Where
Actual rainfall of a given average recurrence Qy = peak flow rate (m3/s) for an average
interval (ARI) does not always lead to a flood of recurrence interval (ARI) of y years
the same ARI. Variables such as the magnitude of
Cy = runoff coefficient (dimensionless) for an ARI
antecedent rainfall (ie. wetting of the catchment
of y years
prior to the design event) can lead to significant
variation. However, it is accepted as standard A = area of catchment (km2)
design procedure to designate a calculated flood
with the same ARI as that of the design rainfall. Itc,y = average rainfall intensity (mm/h) for design
duration of tc hours and ARI of y years
The use of recorded data will allow the designer to
vary standard parameters for such factors as k = 0.278 and is merely a conversion factor to
antecedent precipitation with a degree of ensure units are consistent for A in km2
confidence.
k = 0.00278 if A is hectares (ha)
The catchment or watershed area ‘A’ (in hectares • Time of flow in gutters and natural channels;
or km2) can be determined from topographical and
mapping, from aerial photographs used as stereo
pairs or the basis of photogrammetric contour • Time of flow in pipes or channels.
plots or by field survey.
The type of flow will vary along the catchment,
Catchments interpreted from aerial photographs although once channelised, overland flow
in heavily timbered or flat country should be conditions do not normally recur. Overland flow
3 verified by ground inspection or survey to ensure to channel flow and pipe flow back to channel
that major errors do not result from flow can be expected to occur. There may also be
misinterpretation. overland or channel flow parallel with pipe flow
at full capacity. Several flow paths may need to be
In urban areas, catchment areas are frequently examined to determine which is the longest or
modified by roadworks, railway embankments or most critical in terms of design flows.
other earthworks, building works or fences, and
catchment boundaries should be verified by site The procedure for calculating time of
inspection. concentration varies depending on the version of
the Rational Method being used and whether the
The term ‘equivalent impervious area’ is used for catchment is urban or rural. The procedures are
the product of coefficient of runoff and catchment described later in this section.
area.
The minimum time of concentration to be used in
design is 5 minutes, as the effects of depression
3.5.3.2 Time of Concentration storage and surface detention do not permit
In the deterministic interpretation of the Rational shorter times in practice.
Method, the time of concentration, ‘tc’ for a In designing pipes for road crossings, the time of
catchment is defined as the time taken for water to concentration used should allow for development
flow from the most remote point on the catchment of the upstream catchment. Consider the
to the outlet, or the time taken from the start of following example illustrated in Figure 3.1.
rainfall until all of the catchment is
simultaneously contributing to flow at the outlet.
The time of concentration is made up of: Figure 3.1 Hypothetical Catchment Development
3
will be reduced and the time of concentration to A
also reduced. Designers should check the full
range of possible cases.
Rural
tc = time of concentration (h) For catchments less than 5 km2 in area, the time of
concentration may be calculated using the
L = length of mainstream (km) from the outlet to
velocities in Table 3.9 where there is a defined
the catchment divide
channel in most of the flowpath.
Ch = Chezy’s coefficient at the site
Where there is a significant proportion of
R 0.166 overland sheet flow, use Friend’s equation
(= )
n (directly or via Figure 3.3) for a maximum length
of 200 m, then, if longer, assume channel flow and
R = hydraulic radius velocities from Table 3.9.
= 0.75RS where slope of entire stream is fairly A special allowance is made for small catchments
uniform with a short but defined channel as shown in the
note below Table 3.9.
= 0.65RS where slope varies appreciably
along the stream
3
Source: IE Aust, 1977.
Figure 3.3 Overland Sheet Flow Times - Shallow Sheet Flow Only
Example: A creek is 1500 metres long with a well Rainfall intensity for duration tc and the design
defined channel in the flowpath. The top 900 ARI of 50 years shall be determined in accordance
metres of its length flows through hilly country with Section 3.5.3.3.
and the rest (600 m) through flat country. From
Table 3.9 for velocities, Urban
tc = 16.7 + 33.3 minutes Flows can reach outlets via overland flow areas,
natural or paved surfaces or along gutters, pipes,
tc = 50 minutes channels or natural watercourses or by a
combination of means.
Table 3.9 Velocities for Calculation of tc for For single catchment situations, time of
Areas < 5 km² concentration to a structure site will be the
Type of Average Slope Approx. summation of the times of flow in the various
Country of Catchment Velocity of elements encountered along the longest drainage
Surface (%) Stream (m/s)
path. These elements include:
Flat 0 to 1.5 0.3
Rolling 1.5 to 4 0.7 (a) Overland flow;
Hilly 4 to 8 0.9
(b) Kerb and Channel Flow;
Steep 8 to 15 1.5
Very Steep > 15 3.0 (c) Delays at Inlets or Gully Pits;
Rocky
Mountainous (d) Flow in Pipes.
Source: Hee, 1983
Methods of estimating the flow times in each of
Note: For length of catchment less than or equal to these elements are given below.
1000 metres, add 10 minutes to the calculated time of
concentration for the influence of overland flow. To In more complex urban drainage networks, it is
avoid sudden changes, the minimum tc for lengths common for drainage features to be fed by several
longer than 1000m should be the tc for 1000m if this is
catchments or sub-catchments. This complicates
larger than the tc calculated for the actual length.
the time of concentration calculations, as it from Argue (1986). This figure takes into account
becomes necessary to follow all the possible paths the length of flow and fall along the gutter only
and determine the critical time of concentration at and incorporates an assumption about roughness
each point throughout the system. A step by step and flow depth.
procedure for this, illustrated by a worked
example based on a typical catchment and (c) - Standard Inlet Times
stormwater drainage network introduced in
For small sub-catchments or where detailed
Section 4.4.6.4, is given in Appendix 4E.
overland flow and channel flow calculations are
3
(a) - Overland Flow not considered justified, the Standard Inlet Times
shown in the QUDM (1993) may be used. These
Overland sheet flow time may be obtained from are shown in this manual on Table 3.10.
Friend’s Equation or the nomograph on Figure 3.3
based on this equation. The Brisbane City Council and possibly other
Local Authorities use Standard Inlet Times rather
It should be noted that some Local Authorities than the kinematic wave equation.
may require overland flow times to be obtained by
other methods.
Table 3.10 Recommended Standard Inlet Time of
In urban residential areas, the typical length of Concentration to First Inlet
0.20
nt
one
ti
mp
Equivalent Impervious Area
tc x CpAp o
sC
3
ou CpAp = 0.08 ha
rvi
ha
P Pe
0.10
(CA)full
(CA)
ent
(CA)part (CA)part =
pon
CiAi = 0.10 ha t
CiAi [ ti x CiAi]
Com
c
ed
Pav
ti = 20 tc = 20
0 10 20 30 40 50 60
Time (mins)
(d) - Flow in Pipes Figure 3.5. Having determined the velocity and
knowing the length of the pipe, the time of travel
The time of flow in pipes is calculated from can be calculated.
Manning’s formula and assumes that pipes are
flowing full and not under pressure: An approximate figure for the time of flow in a
pipe system may be determined from the values of
R 0.667 S0.5
v= velocity shown in Table 3.11. When the tentative
n pipe system has been designed, this gives an
where approximate check on calculated values.
v = velocity in pipe, metres per second
n = manning roughness coefficient for pipe Table 3.11 Velocities of Flows in Pipes
R = hydraulic radius of pipe flowing full, Type of Country Approx. Velocity for Whole
Pipe System (m/s)
metres (= Area/Wetted Perimeter)
Undulating - Hilly 2.5 to 4.0
S = slope of hydraulic gradient, metres per Flat (< 1.5%) 1.5 to 2.0
metre (= slope of pipe when pipe just runs
full)
3
the Rational Method and increase the calculations
required. The cause may be catchment shape or Figure 3.7 Catchment Example
variations in slopes and land use within the
The areas of the components of the catchment are:
catchment. It may be necessary to check a number
of partial areas. a = area of catchment “a”, ha
The essence of the part area flow estimate is b = area of catchment “b”, ha
shown in Figure 3.6 (Argue, J, 1986). The method
involves using a time of concentration (ti) c = area of catchment “c”, ha
corresponding to flow time from the most remote,
directly connected paved area of the catchment to The flow is required at the catchment outlet ie.
the outfall. Thus, the calculated runoff is that from inlet to pipe YZ:
the impervious portion of the catchment plus that ta = time of concentration for area a
from the pervious part of the catchment which has
begun to contribute up to time ti since the storm tb = time of concentration for area b
began. So, from Figure 3.6, the equivalent
impervious area to be used in the rational formula, tc = time of concentration for area c
ie. the product of C and A is given by the formula:
tp = time of flow in pipe XY
Rainfall intensity is defined as the mean rainfall • 50i (50 year, 12 hr log-normal rainfall
12
intensity assumed to fall uniformly over a intensity) from one of Maps 5.1, 5.2, 5.3, 5.4,
catchment for a given duration and frequency 5.5 or 5.6;
(average recurrence interval).
• 50i (50 year, 72h log-normal rainfall intensity)
72
The normal units for rainfall intensity are from one of Maps 6.1, 6.2, 6.3, 6.4, 6.5 or 6.6;
millimetres per hour.
3
• SKEWNESS FACTOR, G from Map 7b or 7c;
For small catchments, the duration considered
corresponds to the time of concentration or time • GEOGRAPHICAL FACTOR, F2 from Map 8;
of flow from the top of the catchment to the outlet and
of the catchment.
• GEOGRAPHICAL FACTOR, F50 from Map 9.
For the larger catchments, a temporal pattern is
A tabulation of IFD values for durations from 5
applied so that the rainfall intensity varies over
minutes to 72 hours and average recurrence
different periods of the storm duration. For these
intervals from 1 to 100 years is a standard output
catchments also, storms both shorter and longer
from the RAIN2 program but values for non
than the time of concentration are tested until that
standard times are also readily obtained.
giving the peak flow is found.
Prior to the publication of Australian Rainfall and
Also for the larger catchments, an areal factor is
Runoff (IEAust, 1987), rainfall IFD curves were
applied to point rainfall intensities obtained, to
obtained from the Bureau of Meteorology. Typical
allow for actual non-uniform rainfall over the
curves indicative of the range of rainfall
catchment.
intensities in Queensland are shown as Figures
Rainfall intensity varies with location and 3.8, 3.9 and 3.10 for Springwood (near Brisbane),
topography as well as duration and frequency, and Barcaldine and Innisfail.
this should be considered when using the Rainfall
For a fee, the Bureau of Meteorology will still
Intensity - Frequency - Duration (IFD) tabulations
give design rainfall parameters for a given
and curves for many locations in Queensland
location.
obtained from the Bureau of Meteorology.
The use of rainfall data different to that obtained
For design IFD rainfall the computer program
from the Bureau of Meteorology may be justified
RAIN2 already used in most DMR Districts or
by the calibration of actual recorded rainfall
other suitable programs are recommended.
against recorded floods over a significant period
The use of an IFD programme requires the input of time.
of 9 parameters from Maps in Australian Rainfall
The Australian Bridge Design Code, 1996
and Runoff (IEAust, 1987). These parameters and
requires that bridges will be structurally sound in
the relevant maps are:
a 2000 year ARI flood. Although for most bridges
• 2i (2 year, 1 hr log-normal rainfall intensity) in Queensland the largest flood forces occur in a
1
from one of Maps 1.1, 1.2, 1.3, 1.4, 1.5 or 1.6; smaller overtopping flood, there are occasions
when the 2000 year ARI flood needs to be
• 2i
12(2 year, 12 hr log-normal rainfall intensity) calculated. Such calculations are not simple and
from one of Maps 2.1, 2.2, 2.3, 2.4, 2.5 or 2.6; should be carried out by the Bureau of
Meteorology or Engineers on the Department’s
• 2i
72(2 year, 72 hr log-normal rainfall intensity) prequalification register for hydraulic
from one of Maps 3.1, 3.2, 3.3, 3.4, 3.5 or 3.6; calculations.
Figure 3.8
Figure 3.9
Figure 3.10
Runoff Producing Values (in brackets) as % in calculation of “C” for a 50 year average recurrence interval event
Characteristics
Rainfall 100 mm/h 75-100 mm/h 50-75 mm/h 25-50 mm/h 12-25 mm/h 12 mm/h <12 mm/h
Intensity (35) (30) (25) (15) (10) (5) (0)
Relief Very steep Steep country, Hilly, with Rolling with Flat, with
rugged country slopes 8-15% slopes of 4-8% slopes 1.5-4% slopes 0-1.5%
with average
slopes > 15%
3
(10) (5) (5) (0) (0)
Storage Negligible, few surface Well defined system Considerable surface Poorly defined and
depressions. water- of small depressions, overland meandering stream,
courses, steep and thin watercourses flow is significant, some large surface
film of overland flow farm ponds, swamps storage. Soil
and contour banks conservation plan
on 90% catchment
(10) (10) (5) (0)
Notes:
1. For catchments > 50 km², use with extreme caution.
2. Use values below 50% with caution.
3. Use values above 80% only in very high rainfall areas (absolute maximum of 90%) where the antecedent
precipitation conditions for the design storm is a saturated catchment.
Example:
A catchment has the following characteristics:
(i) Intensity 40 mm/hr
(ii) Hilly, average slopes 4-8%
(iii) Well defined system of small watercourses
(iv) Open forest
15 + 5 + 10 + 40
C= = 0.70
100
3.5.3.4 Runoff Coefficient there is no legal obligation to try to assess and add
the extra waterways in the initial construction.
Rural
If specific development proposals are being
This (non-dimensional) coefficient ‘C’ is defined formulated or in the approval process at the time
as the ratio of the maximum rate at which water of the design of road structures, the additional
flows from a catchment area from a given storm to waterway area needed to accommodate the
the mean volume rate at which rain fell on the development would be provided at the
catchment for the duration of the storm. The developer’s cost. However, if the structures are
runoff coefficient is a function of the design ARI.
3
built before the catchment is developed and there
are no development proposals at the time, the
The value of ‘C’ depends on many features of the
additional cost of the structures is not recoverable
catchment area including:
from the future developer.
• Relief or slope of catchment;
In making the decision on whether to allow for Table 3.8 Adjustment Factors for Runoff
future development in the waterways for the new Coefficients for Other Average Recurrence
Intervals
road, the disruption to traffic when the additional
waterways are constructed in the future must be Average Rural Urban
Recurrence Coefficient Coefficient
considered. Other considerations include the Interval (years)
requirements by some Local Governments to not 1 0.8C50 0.8C10
allow any increase in water discharging into
2 0.8C50 0.85C10
culverts in the road corridor from development of
5 0.8C50 0.95C10
an upstream catchment. Detention basins are
3
therefore specified in the design, particularly in 10 0.8C50 1.0C10
small urbanised catchments. In this case there is 20 0.9C50 1.05C10
no need to consider the effect of development. 50 1.0C50 1.15C10
100 1.05C50 1.25C10
Table 3.7 C10 Values
Notes:
Intensity Fraction 1. C50 determined for rural catchments using Table
mm/hr Impervious
3.5.
Range fi
2. C10 determined for urban catchments using Table
I10 0.00 0.20 0.40 0.60 0.80 0.90 1.00
3.7.
39-44 0.32 0.44 0.55 0.67 0.78 0.84 0.90 3. Where runoff coefficients calculated using the
45-49 0.39 0.49 0.60 0.70 0.80 0.85 0.90 above table exceed 1.00, they should be arbitrarily
set to 1.00.
50-54 0.46 0.55 0.64 0.72 0.81 0.86 0.90
55-59 0.53 0.60 0.68 0.75 0.83 0.86 0.90
60-64 0.59 0.65 0.72 0.78 0.84 0.87 0.90
3.6 Tailwater Levels
65-69 0.66 0.71 0.76 0.80 0.85 0.88 0.90
70-90 0.70 0.74 0.78 0.82 0.86 0.88 0.90
3.6.1 Introduction
I10 = One hour rainfall intensity for a 10 year ARI
When an open channel discharges (or outlets) into
C10 = Coefficient of Runoff for a 10 year ARI
a body of stored water, or to another open
fi = Fraction Impervious
channel, the water level at this point will usually
Reference: Queensland Urban Drainage Manual act as the controlling level for channel hydraulics.
(Neville Jones & Associates and AWE, 1993).
This controlling level is called the tailwater level.
There are two types of tailwater levels: tidal and
non-tidal.
Adjustment Factors
A tailwater level is tidal when the channel
Design coefficients of runoff for other design discharges into a water body influenced by tides,
average recurrence intervals should be determined such as oceans, bays, and rivers and creeks close
using Table 3.8. to the coast. Tidal tailwater levels are subjected to
tide levels, storm surges and the rise in sea level
due to the greenhouse effect (refer Section 3.6.2).
The hydraulic design of a bridge or culvert The absolute minimum survey requirements at a
requires the determination of the tailwater level road/bridge site are the times and levels for
just downstream of the structure outlet, even when successive low - high - low tides. Alternatively
it is not affected by a downstream storage or river. successive high - low - high tide information may
In such situations, provided the downstream be found. The more cycles measured the better.
channel is reasonably uniform, the tailwater level
is usually considered to be the normal depth of This information when compared with tide levels
flow in the stream. This is calculated using the at the mouth of the creek will allow experienced
Manning Formula (refer Sections 4.3.5 and 4.3.6). hydraulic engineers to predict approximate design
3
tides such as MHWS (mean high water springs)
and MLWS (mean low water springs) at the job
3.6.2 Tidal Waters site.
Annual tide tables published by the Department of Storm surges occur in major storms such as
Transport give predicted tide levels at various cyclones where there are low atmospheric
coastal locations in Queensland. pressures and the wind blows over reaches of the
ocean.
It is important to note that:
Some predicted surge heights by the James Cook
• the mean sea level given for the location may University of North Queensland (1977) are shown
be different to Australian Height Datum (AHD) in Table 3.12. The estimates are conditional and
which is the average mean sea level of 42 the notes for the table are important. The study
locations around Australia; also provides surge levels based on 50 year and
500 year cyclones.
• tide levels are given at or very close to the
coastline; and There is no correlation with tide levels, nor are
there any predictions for wave break setup and
• tide levels are often specified in terms of low wave runup on the land. These factors will need
water datum. consideration for any design with storm surge as a
factor.
It is very difficult to estimate the tide level at a
location in a stream some distance from the Storm surges would need to be considered with
coastline. The time for the tide to rise along the respect to coastal developments, the protection of
creek and to then flow back in the opposite coastal roads, route immunity for evacuation
direction is one factor. Another is the existence of purposes, and for major coastal drainage designs.
local sand bars or raised areas of the creek bed Local government may also have specific
closer to the mouth of the stream, which may requirements or data in relation to storm surge.
prevent a tide from reaching or falling below a
certain level at a particular road crossing.
Table 3.12 Peak Surges from 100 Year Cyclones Appropriate tide levels for the design of long life
structures near the ocean are indicated in the
Region Peak Surge in 100 Year
(Location) Cyclone (m) following Sections 3.6.2.4 and 3.6.2.5.
Cooktown 0.70-1.10
Cairns (Casuarina Point) 0.80-1.85 3.6.2.4 Tidal Outlets (Ocean and
Innisfail (Flying Fish Point) 1.02-1.84 Bays)
Ingham (Crystal Creek) 1.50-3.04
Local government should be consulted for an
Townsville 2.23-3.32
appropriate design tailwater level for outlets to
3
Bowen 0.52-2.20
tidal waters in oceans and bays.
Mackay (Sarina Inlet) 2.02-3.24
Rockhampton (Emu Park) 2.12-2.80 Unless otherwise specified an appropriate level
Gold Coast (Surfers Paradise) 0.41-0.79 would be MHWS (mean high water springs) +
0.3m to allow for the greenhouse effect.
Notes:
1. These are upper bounds to tropical cyclone surge An allowance for storm surge should be added if
levels and cannot be interpreted in terms of
probability of occurrence of nominated surge required.
levels.
2 Three cyclones were tested for each location with 3.6.2.5 Tidal Outlets (Rivers and
approach directions, 0° (parallel), 75°, and 105° to
the defined coastline, giving the range of peak
Creeks)
surges shown.
The drainage outlet may be located in the tidal
reach of a river or creek.
(2) Calculate the corresponding range, MHWS scouring downstream where required, but the
- MLWS = y at the upstream site. possibility of undermining by wave action and
longshore currents, morphological scour and
(3) Calculate the ratio, y/x. wave impact forces should be considered.
(4) Assume the rise in ocean level due to the Advice should be sought from the local
Greenhouse effect is 0.3 m. government and the Environmental Protection
Agency in regard to the local beach behaviour and
(5) Calculate the equivalent rise at the upstream
littoral processes.
site equal to 0.3 multiplied by y/x. Adopt
3
this rise as the Greenhouse effect at the site Flapgates (floodgates) will prevent the intrusion
for tidal flows. of saltwater upstream of the outlet and may help
to prevent siltation in the pipe system. The
3.6.2.6 Design Issues for Tidal flapgate should be fitted in a chamber just
Outlets upstream of the outlet to protect its operation from
vandalism, wave attack, debris and sand blockage.
This Section is based on Section 7.07 of the Special pipes are required if flapgates are to be
QUDM (Neville Jones and Associates and AWE, installed.
1993).
• State Marine Parks; It may be obvious that outlets into large storage
areas such as lakes and dams will not raise the
• Great Barrier Reef; water level of the storage to any significant
degree.
• Area controlled by a Port Authority; and
In this case, the storage level is taken as the
• Area controlled by a Waterway Authority.
tailwater level. This does not eliminate the need to
Tidal outlets should be sufficiently elevated to calculate the hydraulic grade line and critical
minimise the risk of sand blockage and to depth in culvert outflows.
facilitate inspection and maintenance of pipes.
3.6.3.2 Small Storage Areas
Although aesthetics may dictate that outlets be
located below low tide level, the invert level of For smaller storages there may be a significant
the outlet should preferably be somewhere rise in the water level in the storage prior to peak
between MLWS (mean low water spring) and flow in the open channel or culverts discharging
MSL (mean sea level). The obvert of the outlet into the storage.
should normally be below HAT (highest
astronomical tide). From the discharge hydrograph for the open
channel, the volume of water in the hydrograph
Not only should there be protection against prior to peak discharge should be calculated. This
The outfall may be into an open channel such as a For a given ARI, the peak discharge in the main
natural creek or river or a man made channel. channel, QmT, occurs at time T. Find the
3
corresponding discharge in the side channel, QsT,
For simplicity, say the open channel being
at time T for a storm of the same ARI as for the
designed is the side channel with discharge, Qs,
catchment for the main channel. For the Rational
and that it outfalls into a main channel with
Method for the side channel, use average rainfall
discharge, Qm.
intensity corresponding to time T.
As the two open channels have different
Then
catchment sizes, they will peak at different times.
The combined flow at their junction will give the QcT = QmT + QsT
tailwater level for the channel to be designed.
where QcT is the combined discharge.
The design tailwater should be that corresponding
to the higher of the following discharges: Adopt the higher of Qct or QcT to find the design
tailwater level at the junction (outfall).
(1) peak discharge in the side channel plus
corresponding discharge in the main
3.6.3.4 Protection of Non-Tidal
channel; or
Outlets
(2) peak discharge in the main channel plus
Particular attention should be paid to the
corresponding discharge in the side channel.
possibility of scour at non-tidal outlets of culverts
The method below assumes the same rainfall or open channels. Bridge abutments, for example,
storm on both catchments. have been badly scoured from the mixing and
turbulence from flows from different directions
Combination 1 and the channel discharging into the stream near
an abutment may even be a natural channel not
Assume that the peak discharge for the side considered in design.
(smaller) channel occurs at the time of
concentration for that catchment and the Rational Man made flow outlets have the same potential
Method is used, ie. the peak discharge in the side for erosion particularly if the bed level/soffit is
channel, Qst is obtained from a storm of duration, higher than the bed level of the stream into which
t, (for a time of concentration, tc, for the small it is discharging, or if the outlets are in an unstable
catchment). section of the stream. Liberal use of dumped rock,
rock mattresses or other scour protection is
For the same design average recurrence interval recommended.
(ARI) as for the small catchment, calculate the
hydrograph for the main channel. Find the To a lesser extent, outlets into ponds and lakes
corresponding discharge in the main channel, Qmt, have the potential to cause erosion.
at time, t, on the hydrograph. (A triangular shape
Floodgates which are normally only considered
hydrograph with the base length 2.7 times the
for outlets into tidal waters, may also be used in
time to peak may be adopted for some
non-tidal outlets to prevent back-flooding from
catchments).
the receiving waters and to control siltation from
the receiving waters.
3
In recent times, much research has been
undertaken on developing practices that help
facilitate fauna movement through the road
corridor in a way that minimises road mortalities.
Much of the research has focussed on passages
that are integral with drainage structures.
This chapter provides an overview of what steps Step 2 - Identify the Species Group
need to be taken when the project REF/IAS
process has identified a need for fauna passage to Where fauna pathways have been identified,
be incorporated into drainage design. identify the relevant species group from the list
below:
Completion of these steps may result in the
determination of additional design criteria which • macropods;
may then influence the selection of cross drainage
structures. • arboreal mammals;
Further reading on this topic is available in Fauna • ground dwelling mammals, reptiles and
Sensitive Road Design (Main Roads, 2000). amphibians;
Fauna Type Small pipe Large pipe Small box Large box Bridge
<0.5m dia >0.5m dia culvert <1.2 m h culvert >1.2m h underpass
Small mammal 3 3 3 3 3
Medium mammal 3 3 3 7 3
Large mammal 7 3 7 3 3
Semi-arboreal mammal 7 7 7 3 3
Arboreal mammal 7 7 7 7 7
3
Microchiropteran bats 7 7 7 3 3
Reptile 7 3 7 3 3
Bird 3 7 7 3 3
Amphibian 3 7 3 3 3
Introduced predator 3 3 3 3 3
Source: Queensland Department of Main Roads, 2000.
Caution: This table is based on preliminary research only. Although not confirmed at the time, fauna should pass
through all the culverts larger than the minimum ones shown. Recommended minimum sizes for design are shown in
Section 4.2.2.3 of this Manual.
Five different types of ambient condition are success. Key considerations include soil structure
identified below. For each type, design and velocity of flow.
considerations have been provided to assist the
designer in selecting drainage controls Protection of the drainage asset may be required
appropriate for the conditions. where soils are highly mobile or erodible. That is,
if soils are mobile upstream and downstream of
Design considerations for different ambient the asset, emphasis on stabilisation of the asset
conditions (not identified here) will be added in may be required, rather than prevention of an
the future. existing phenomena.
• Planning of the drainage system. For example, • Controlling runoff so as not to affect natural
where the provision of roadside drainage would stability; and
require the removal of remnant trees,
negotiations should be initiated with the • Limiting slope length.
neighbouring landholders to have the drainage
In addition, the potential for high rainfall
directed through their property and into a
(particularly in coastal regions) brings another set
3
storage dam or contour drain;
of issues for consideration, though this is
• Soil protection. This is very important given the generally covered in the rainfall erosivity section
dominance of erosive soils (eg. sodic soils) in of Chapter 2 of the manual, and in Section 3.5
arid areas. Existing groundcover must be (Hydrology).
subject to minimal disturbance;
3.8.2.3 Coastal Regions
• Outlets should be located in undisturbed areas,
or designed with appropriate erosion Coastal regions provide unique conditions and
protection. The concentration of flow onto hence require special considerations. Conditions
unprotected areas should be avoided; include regular inundation, a corrosive
environment and sandy soils (ie. soils with little
• Selection of revegetation species should focus cohesion). Coastal environments are also highly
on those types which establish and bind the sensitive to pollution.
soil, and which will grow without regular
watering; and Key criteria to consider in coastal environments
include ensuring that:
• Where revegetation is not possible, options
such as rock mulching may be required subject • Legal requirements with respect to the
to the availability of material on or close to the protection of marine environments (eg.
site. protection of fish habitats and marine plants)
are met;
3.8.2.2 Mountainous Terrain
• Natural flow systems (eg. tidal exchange) are
In mountainous terrain, the most common factor properly assessed and will therefore not be
influencing design is gradient. Issues for compromised;
consideration where topography is steep include:
• Corrosion resistant materials are used;
• Control of velocities in roadside drains;
• Potential Acid Sulphate Soils (typically below
• Limited room adjacent to the road; 5m AHD) are identified and managed
appropriately;
• Collection and discharge of water from the
upslope side of the road to the downslope side; • Designs allow for the presence of highly
erodible or mobile materials such as sand; and
• Prevention of erosion at outlets onto steep
areas; and • Consideration is given to directing drainage to
natural channels or swales rather than to hard
• Need for small scale drop structures, weirs or structures.
drop manholes.
It is therefore very important that both cases are 3.8.2.6 Rural Areas
considered during the design of drainage
infrastructure. Additional details are provided in Standard practices for the planning and design of
Section 3.9. road drainage should address most issues that will
arise in rural areas. Additional issues may include:
Regular inundation (ie. changing water levels) can
also accelerate the erosion process, through the • Awareness of local drainage plans;
saturation of banks, which may then fail as water • Ensuring crops will not be affected by an
levels reduce. increase in duration of inundation;
The selection of drainage infrastructure requires For the majority of designs, it will be obvious as
the user to follow a particular process, in order to to whether a bridge or culvert is required at a
ensure that all relevant criteria have been given location. This decision will be made on the
considered in making a selection. This process is basis of serviceability, existing bank height,
discussed in the following sections. potential for debris, and in some cases, the need to
3
allow for the passage of large fauna and on
whether the stream is active or not. In the case of
3.9.2 Factors Affecting an active stream, building a bridge will be easier
Selection of Drainage and will have less impact on the environment.
Infrastructure
In highly reactive or expansive soil conditions or
A summary of those factors used in selecting the where large differential settlements are expected
appropriate size and type of drainage structure is to occur, culverts should be limited to base slabs
provided below. Relevant factors include: not greater than 10 metres long. This may in some
instances lead to a decision to provide a bridge
• The desired level of serviceability or immunity structure, provided a clearance of at least 1.2
(this defines the relevant ARI); metres is available to the underside of the bridge
deck. Specialist advice should be sort in these
• Discharge (for the nominated recurrence
instances.
interval);
3
• geomorphology • Skew of culvert should not be any more than 45°.
• Do not locate culverts on the bends of actively moving
watercourses.
Need for • soil type • Where dispersive soils are present, a barrier must be
Channel Lining • limited available width placed between flowing water and the soil. The barrier can
• steep gradient consist of topsoil and vegetation, blankets, or a permanent
• velocity lining such as rock with filter cloth.
• Velocity reductions will often allow a cheaper or more natural
lining to be utilised. Velocity reductions may be achieved through
a flattening of channel gradient where there is sufficient room
available to compensate for the larger flow width. A flattening of
gradient can be achieved through the incorporation of check
dams, drop structures, or a change in alignment.
Need for Outlet • outlet velocities Outlet protection may be required where outlet velocities are
Protection • soil type sufficient to cause erosion. Management options include:
• erosion risk rating • reduce gradient;
• replace or cover dispersive soils;
• reduce velocities through dissipation (subject to safety
considerations);
• provide protection.
In addition, ambient conditions can dictate the 5. Will the proposed type of longitudinal drainage
suitability of certain culvert types. For example, require regular maintenance?
in corrosive environments (eg. coastal regions),
some types of culverts will not be appropriate. Responses to the above questions will dictate the
(Refer Section 3.8.) feasibility of the available choices, as discussed
below.
Additional details for selecting culvert types are
provided in Section 4.2.2 of Chapter 4. 1. Steep gradients will allow narrower drainage
channels to be used, but can lead to high
velocities, which in turn may require linings
types of drainage infrastructure, including open 3. Consider realignment of the creek away from
channels and drop structures. the proposed crossing.
Location should be a key design criteria in those Option 1 would be favoured wherever possible,
areas where: with Option 2 (and the use of a “soft” engineering
approach) another alternative. The use of “hard”
• the watercourse is not stable; solutions (eg. riprap lining) or creek realignment
is often not favoured, as changes to the creek at
• bed or bank erosion may result from the
one location will often transfer problems to other
presence of new infrastructure;
3
nearby locations.
• soils are highly erodible;
AUSTROADS (1994) provides additional
• the area has high environmental sensitivity; guidelines in relation to the siting of drainage
infrastructure. These guidelines, which will also
• bed slopes are steep; and minimise the potential for damage to the
infrastructure, are reproduced below.
• the face of a structure is not perpendicular to
the watercourse. To minimise environmental impacts the culverts
should be located:
Where potential problems have been identified, it
is important that: • Where satisfactory geological and soil
conditions exist;
(a) an alternative location or alignment is
identified; or • Away from reaches of highly unstable channel;
(b) appropriate protective measures are put in • Where possible adverse effects on other
place to prevent or mitigate the potential existing bridges and hydraulic structures can be
impacts. avoided;
Option (a) should be the first preference, but will • Where it is possible to minimise the hazards
not always be possible in areas where the from floods, landslide, cyclones, earthquake
alignment is fixed. and subsidence;
In those instances where a river or creek is • Where river banks are stable;
obviously active (eroding or accreting), a
geomorphic analysis may be required. • Where ecological impact is acceptable; and
Reference may also be made to Table 3.15. • Where aesthetic considerations are favourable.
Example:
3.9.8 Water Quality
A proposed new road will cross Sandy Creek at a
point where the creek has active bank erosion When water quality (pollution) control devices
owing to the existence of a meander. A series of are required as part of the road drainage system,
box culverts are proposed at this location. The additional considerations must be taken into
following courses of action could be considered: account.
1. Propose a local realignment of the road such For example, the hydraulics of the drainage
that the crossing of Sandy Creek will occur at a system may not be conducive to efficient pollutant
stable location; or removal, or conversely, the proposed pollution
control device may compromise the hydraulic
2. Stabilise the meander if constrained for space;
efficiency of the system.
or
3
• Is the gradient of the system too steep (resulting
in high velocities) to allow effective pollutant Wetland area
removal?
• Can the device be accessed for maintenance For a given project, the significance of pollutant
purposes? export will depend upon the relative sensitivity of
the receiving environment, the type and level of
Examples of design implications are offered vehicle use and climatic factors experienced in the
below: locality. The identification of appropriate
receiving water quality objectives from the
• Wetlands or sediment basins may not operate
REF/IAS can influence design criteria for the
effectively if subject to high velocities during
selection of appropriate drainage infrastructure to
flood events. A high flow bypass is often
maintain or enhance downstream waterways. This
required.
in turn may determine the need for pollution
• When trash racks are installed, provision must control.
be made for high headlosses associated with
An overview of the steps to be taken, when
blockage of the racks. In this case,
pollution control is required, is provided in the
consideration of the potential for flooding of
following section. Completion of these steps will
upstream property must also be assessed.
result in determination of additional design
• Pollution control devices placed in areas with criteria that will then influence the selection of
high tailwater levels may not operate, appropriate drainage infrastructure.
particularly where there is reliance on a floating
boom to trap litter.
3.10.2 Selection Process
Reference should also be made to Section 3.10.
The selection and implementation of stormwater
treatment measures involves six major steps.
These are:
3.10 Pollution Control
1. Ascertain environmental issues and water
3.10.1 Introduction quality objectives - Identify the sensitivity of
the receiving environment, appropriate water
A key environmental consideration in relation to quality objectives for the receiving waters and
road runoff is pollutant export and the resultant establish the key design criteria; (eg. to reduce
impact on water quality. Runoff from road the impact of sediments and heavy metals).
corridors has the potential to adversely effect the
water quality and aquatic biota of receiving 2. Identification of Pollutant Sources and
waters. Impacts may be short or long term. Estimation of Pollutant Loads - Identify
pollutant sources and determine pollutant loads
from the road corridor to resolve the type and
amount of pollutant to be removed (if any).
3. Identify pollutant transport processes - The updated guidelines published in 2001 provide
Identify pollutant transport mechanisms to water quality trigger values for slightly disturbed
assist in identifying appropriate capture and Australian ecosystems, as a function of the
control devices. ecosystem location and the ecosystem type. If a
pollutant concentration exceeds its trigger value,
4. Assess potential pollutant control devices - it will have the potential to cause environmental
Identify all applicable treatments on the basis harm, and a management response will be set off,
of key site selection criteria. Each stormwater or “triggered”. Table 3.16 provides examples of
treatment measure can be accepted or rejected water quality trigger values for typical pollutants
3
on the basis of each screening criteria. (nutrients, suspended solids and salts) for various
locations within Australia and various types of
5. Assess potential pollutant removal - Compare
slightly disturbed ecosystems.
all potential treatments on the basis of
achieving key treatment objectives. Step 2 - Identify Pollutants and Pollutant
Loads
6. Optimise Potential Treatments - Identify and
evaluate tradeoffs between desired treatment Common sources of pollutants in road runoff that
objectives and key site selection criteria. may adversely effect the downstream
Determine the most appropriate stormwater environment have been identified in the
treatment method(s) for achieving objectives. California Storm Water Best Management
Practice Handbook (CDM, 1993). Table 3.17 has
Step 1 - Identify Environmental Issues and
been adapted from this reference to represent
Water Quality Objectives
typical pollutant loads from road corridors.
From the REF/IAS the sensitivity of the receiving
A review of the project REF/IAS should be
environment and the potential impact of the road
undertaken to identify relevant runoff pollutants
corridor will have been identified.
from the project corridor.
Traffic volumes and heavy vehicle content will
Road pollutant loads can be estimated by:
have been identified in the planning report. This
information, in conjunction with the water quality • analysis of data from a good storm-event
requirements documented within the EMP monitoring program;
(Planning), will assist in identifying and selecting • simple computations; and
appropriate key water quality objectives and
design criteria. These may include objectives such • an appropriate water quality model.
as:
The method selected will depend on the
• capture of gross pollutants upstream of a management objective and data availability.
sensitive waterbody; and Average long-term pollutant loads can be
estimated from rainfall data and from simple
• discharges from sediment basin to achieve information about the catchment and road
ANZECC water quality levels owing to the corridor. These estimates provide an indication of
sensitivity of downstream aquatic ecology. the long-term inputs.
Most environmental protection agencies tend to Typical errors in estimating long term pollutant
rely on the Australian Water Quality Guidelines loads are as follows:
for Freshwater and Marine Waters (ANZECC,
• no monitoring - 100 to more than 1,000
2001) developed by the Australian and New
percent;
Zealand Environment and Conservation Council.
These guidelines generally are used as the default • some periodic monitoring - 50 to more than 500
framework for setting water policy objectives for percent; and
managing water resources on a sustainable basis. • detailed event monitoring - 20 to 100 percent.
Table 3.16 Examples of water quality trigger values for typical pollutants (nutrients, suspended solids and
salts) for various locations within Australia and various types of slightly disturbed ecosystems
Pollutants
Location and TN TP Turbidity Salinity
Ecosystem Type (µg/l) (µg/l) (NTU) (µS/cm)
South East Australia
Upland river 250 20 2-25 30-350
Lowland river 500 50 6-50 125-2200
3
Freshwater lakes and reservoirs 350 10 1-20 20-30
Wetlands no data no data no data no data
Estuaries 300 30 0.5-10 n/a
Marine 120 25 0.5-10 n/a
Tropical Australia
Upland river 150 10 2-15 20-250
Lowland river 200-300 10 2-15 20-250
Freshwater lakes and reservoirs 350 10 2-200 90-900
Wetlands 350-1200 10-50 2-200 90-900
Estuaries 250 20 1-20 n/a
Marine 100 10-15 1-20 n/a
South West Australia
Upland river 450 20 10-20 120-300
Lowland river 1200 65 10-20 120-300
Freshwater lakes and reservoirs 350 10 10-100 300-1500
Wetlands 1500 60 10-100 300-1500
Estuaries 750 30 1-2 n/a
Marine 230 20 1-2 n/a
South Central Australia
Upland river no data no data 1-50 100-5000
Lowland river 1000 100 1-50 100-5001
Freshwater lakes and reservoirs 1000 25 1-100 300-1000
Wetlands no data no data no data no data
Estuaries 1000 100 0.5-10 n/a
Marine 1000 100 0.5-10 n/a
TN = Total Nitrogen
TP = Total Phosphorus
NTU = Notional Turbidity Units
µS/cm = Conductivity of water in micro siemens per centimetre
Table 3.17 Common Sources of Pollutants in Road • characterising peak, mean and average annual
Runoff (Chiew et al, 1997) pollutant loads;
Pollutant Sources
• determining seasonal and spatial
Sediment/ Bitumen wear, vehicles
Particulates
characteristics;
Nutrients Roadside fertiliser and herbicide
• study land use change;
Bacteria and Source not common
Viruses • provide inputs to water quality management
Oxygen Demand Road litter, organic debris models.
3
Oil and Grease Lubricants and motor fluids (spills,
leaks etc) However, in the absence of reliable data, water
Heavy Metals Cr, Cu, Pb, Zn, Fe, Cd, Ni, Mn - quality models are potentially no better than
emissions, lubricants, corrosion, estimates calculated using simple analysis
wear of tyres (filler), bearings,
brakes, asphalt, clutch. techniques.
Toxic Materials Fuels, herbicides, pesticides, fuel
combustion
Drapper (2001) has evaluated the FHWA
Floatables Gross Pollutants (eg. paper,
prediction model from the USA and has
plastics, bottles) disregarded the use as a tool for predicting runoff
pollutant concentrations. A prediction program is
currently being developed that may assist in
determining appropriate pollutant loads.
Event Based Monitoring
Step 3 - Identify Pollutant Transport
Event mean concentration (EMC) can be
Mechanism
estimated by monitoring pollutant concentration
and discharge over a storm event. EMC within The determination of additional design criteria to
one catchment can however differ significantly enhance or maintain the downstream water
from storm to storm. The EMC depends on quality will require the knowledge of relevant
catchment and climate characteristics, and can pollutant transport mechanisms.
vary by more than one order of magnitude
between catchments. A good event-monitoring Pollutant runoff from a roadway will be generally
program is essential where accurate estimates of transported by the roadway drainage
pollutant loads are required. infrastructure and will concentrate in gutters,
pipes and channels. The pollutants associated with
Simple Computations the stormwater runoff will be transported as
coarse or bottom sediments, suspended particles
In absence of reliable field data, the range of
or in solution. The rate of pollutant transport is
values presented by Mudgway (1997), Drapper
dependent on water velocity, depth and the degree
(2001) and McRobert (1997) can be used as a
of turbulence.
guide to calculate approximate estimates of
pollutant loads. Fine particulates and dissolved pollutants can
become attached to sediments, or flocculate to
The average long-term pollutant load of an area
form larger particles. Most of the pollutants in
can be estimated using:
sediments are found attached to smaller particles
pollutant load = runoff × EMC owing to their greater surface area relative to
larger particles. Pollutants attached to fine
where EMC = event mean concentration. particles are easily transported because small
Water Quality Modelling flows (and hence low velocities) are sufficient to
mobilise and keep them in suspension.
Computer models may be used to estimate runoff
quantity and quality from a road corridor to Heavy metals from motor vehicles either directly
provide estimates for: fall onto road surfaces or become entrained in air
flows and deposited some distance away achieve the appropriate water quality objectives.
depending on their particle size. Particulate The treatment measures may include primary,
material on the road surface such as bituminous secondary and tertiary treatment measures using
products, rubber from tyre wear and particles an ‘outlet’ or ‘distributed approach’.
coated with oils, actively absorb heavy metals.
The particulates and the associated heavy metals The outlet approach involves a single treatment
temporarily bind themselves to the road surface at the road corridor catchment outlet that
until they are transported by rainfall runoff events. discharges directly into the downstream
environment. The distributed approach requires
3
Heavy metals contained in road runoff will be a number of smaller and potentially different
distributed in either bound or soluble forms. treatments throughout the road corridor catchment
Chromium, iron nickel, lead and hydrocarbons are before discharge to the downstream environment.
predominantly absorbed to particulate matter
providing an opportunity for removal by The selection of the treatment controls for a road
deposition of sediments. Cadmium, copper and corridor catchment under consideration will
zinc appear at higher percentages in the soluble depend on a wide range of key selection criteria to
phase and thus are required to be removed by enable achievement of the water quality objective.
storage and/or uptake by aquatic biota. (Peterson
The selection of the most appropriate stormwater
and Batley, 1992).
treatment methods should be assessed against a
Step 4 - Identify Required Pollutant Treatment number of key selection criteria (eg. catchment
Processes area, slope etc). Common key site and operation
selection criteria are defined as follows:
Stormwater quality improvement measures rely
on a range of mechanisms for reducing pollutant • Slope: Treatment devices that do not store flow
levels within stormwater. The mechanisms may require small velocities and hence gentle
employed may be either or a combination of slopes;
physical, chemical or biological process and their
• Hydraulic Head: Head losses in treatment
effectiveness may be dependent on the site
devices can exert a minor to large impact upon
conditions and stormwater characteristics.
the hydraulic grade line. As a result head losses
Stormwater improvement devices can be grouped
from a treatment device may adversely impact
into three different categories based on their
upon upstream flood levels particularly when
dominant treatment processes. These categories
retrofitting a device into an area;
are:
• Soil Type: Differing treatment devices may be
Primary Treatment - Physical screening or rapid
reliant upon either infiltration or storage of
sedimentation techniques (eg. typically retained
stormwater runoff. For instance, stormwater
contaminants include gross pollutants and course
infiltration will yield better results on highly
sediments).
permeable soils, whilst the storage of
Secondary Treatment - Sedimentation of finer stormwater will require soils with very low
particles and filtration/chemical techniques (eg. permeability.
Typically retained contaminants consist of fine
• Land Availability: The availability of
particles and attached pollutants).
sufficient appropriate land within a sub-
Tertiary Treatment - Enhanced sedimentation and catchment that can be used for a treatment
filtration, biological up-take adsorption onto device may be restricted, thereby reducing the
sediments (eg. typically retained contaminants are size and effectiveness of the device;
nutrients and heavy metals) (Vic EPA, 1998).
• Habitat Enhancement: Treatment devices that
In many circumstances a combination of are able to offer either a wildlife and/or aquatic
treatment mechanisms is required to optimise and habitat enhancement may improve aesthetics;
• Water Table: A high water table depth may achieved by comparing all potential treatments as
reduce the effectiveness for a treatment device follows:
relying on infiltration;
1. Determine the pollutant removal of each short-
• Safety Hazard: Treatment devices may listed control device based on relevant
introduce new safety hazards that may have not performance data or Tables 3.19 to 3.21 (eg.
been present before installation; target 90% reduction of Pb through pollutant
control device).
• Water Supply: Treatment devices such as
wetlands or ponds may require a permanent 2. Determine the area of the catchment for which
water supply to ensure the long term
effectiveness of the device;
the device(s) can treat runoff.
Table 3.18 Site and Operation Selection Criteria Associated with Treatment Device
3
Closed Gross <15 Low NA High Moderate
Pollutant Traps
Sand Filter <2 Note 1 High Generally High Moderate- Min filtration depth of
can be housed in High 400mm dependent
designed concrete on recommended
larger filtration time. Energy
dissipater at inlet.
Note:
1. From 0 - 5% slope preferred but the range can be extended beyond 5%. Buffer zones should only be extended
beyond 5% with careful design.
3
Derived from: NSW EPA (1997) and Mudgeway et al (1997).
Sand 60-90 35-80 40-70 -110-0 65-90 10-80 20-60 60-80 35-70 3
Filter 80 57 55 <0 74 53 40 70 53 studies
Buffer 100 95 1
Strips study
Grassed 4-25 8-24 -4-11 -4-13 -5-22 0-91 34-90 14-60 20-50 3-67 7
Swales 80 15 16 4 5 9 80 70 50 29 35 25 studies
Constructed 40-98 -33-97 0-75 -9-43 13-90 6-94 -29-97 40-99 33-99 12-62 18-34 28
Wetlands 81 50 59 25 32 50 72 50 66 66 37 26 studies
Water 39-98 0-80 70-80 30-85 14-20 24-60 9-95 0-71 0-69 20-70 90-95 13
Quality 69 51 20 75 60 17 42 68 51 40 17 44 30 93 studies
Ponds
3.11 Erosion and Sediment • proposed changes to the site topography for
Control each stage of the project including extent of cut
and fill batters;
3.11.1 Introduction • a map of existing vegetation identifying areas
to be retained;
This section provides the user with guidance and
tools to facilitate the selection of appropriate • details of areas of cleared land at each stage of
erosion and sediment control measures. Reference the development, and the period of time that
to soil types and erosion risk from Chapter 2 will each area will be exposed for;
3 be required.
Detailed design can then be undertaken using the In many cases, erosion and sediment controls are
respective guidelines provided in Chapters 4 and not designed to a specific standard. Instead, they
5. are located on site in keeping with the size of the
contributing catchment, available materials, the
physical constraints of the site and a maintenance
3.11.2 Review of Data schedule.
The need for erosion and sediment control will However, in particular circumstances, such as
have been identified in the REF/IAS and when a site is considered highly erodible, or when
subsequent erosion risk assessment process works are being proposed in an area of high
outlined in Chapter 2. The information which environmental sensitivity, a specific design
should be available will include details of areas of standard may be required.
the environment considered vulnerable to
environmental harm and information pertaining to Factors dictating the required standard will
the nature of potential erosion and sedimentation include:
related impacts.
• erosion risk rating;
Depending on the scale of the project, required
• environmental sensitivity; and
input from Chapter 2 and the project REF/IAS
should include: • duration of construction.
• a map of soil types and their erosion potential; Selection of the appropriate design standard can
be made by:
• an erosion risk rating for specific areas within
the site; • referring to Table 3.22, or
• climate and stream flows;
Table 3.22 Suggested Design Average Recurrence Intervals for Various Erosion and Sediment Control
Measures on Construction Sites (Hunt, 1992)
3
• primary outlet 1-5 5-10 *
• emergency outlet 10-20 20-100 *
Sediment Trap 1-5 5-20 *
Outlet Protection 1-20 20-100 *
Grade Stabilising Structure 1-20 20-100 *
Detention Basin
• primary outlet 1-5 5-10 *
• emergency outlet 10-20 20-100 *
* Full design required in accordance with Major/Minor concept (see ARR, 1987 - Section 14.5).
• use of the following equation (Hunt 1992). It should be noted, however, that this tool is a
guide only and the most appropriate control
L measures may not be fully identified until
ARI = construction commences and measures are
[-ln (1 - P)]
implemented.
where:
The user should identify each of the following for
ARI = design average recurrence interval (yr) the project site:
A review of this information will provide the user post construction. They often require formal
with an understanding of the major soil types and design (refer Chapter 4) and are normally more
erodibility of the site and thus application to the costly.
selection matrix.
Maintenance of all temporary and permanent
measures is required to ensure they function to
3.11.4.3 Areas of Suitability maximum capability.
A description of the different types of
environments that can affect the selection of In many cases, the most effective (and
3
erosion and sediment control measures was practical) approach will involve the siting
provided in Section 3.8, Ambient Conditions. and design of temporary controls to allow
conversion to a permanent measure. This
The user should assess the control measures
should be investigated as part of the design
against the constraints imposed by the
process for all permanent measures.
surrounding environment to gain an
understanding of the most suitable measures for
the site conditions.
Control Type Inundated Coastal Arid Mountainous (1) Concentrated Flow Sheet Flow Permanent Temporary
June 2003
Drainage Control
Catch Drains 3 3 3 3 3 3
Diversion Channels 3 (2) 3 3 3 ?
Chutes 3 3 3 3 3 3 ?
Drop Pipes 3 3 3 3 3 3 3
Unlined (earth) Channels 3 3 3 3
Road Drainage Design Manual
Lined Channels 3 3 3 3 3 3 3
Grass Channels 3 3 3 3 3
Velocity Control
Check Dams 3 3 3 3 3
Drop Structure 3 3 3 3 3 3
Erosion Control
Chemical Surface Stabilisers (3) 3 3 3 3
Erosion Control Blankets 3 3 3 3 3
Mulching 3 3 (4) 3 3
Outlet Protection 3 3 3 3 3
Revegetation 3 3 3 3 3 3
Surface Roughening 3 3 3 3 3
Sediment Control
Buffer Zones 3 3 3 ? 3 3 3
Grassed Filter Strips 3 3 3 3 3
Construction Exits 3 3 3 3
Sediment Fences 3 3 3 3 3
Rock Sediment Trap 3 3 3 ? 3 3 3
Sediment Basins 3 3 3 (5) 3 3 3
Sediment Weirs 3 3 3 3 3 3
Portable Sediment Tanks 3 3 3 3 3 3
Drop/Pipe Inlet Protection 3 3 3 3 3
(1) All control measures, when installed in mountainous areas, might require linings where soils are exposed - Refer to appropriate Fact Sheet in Chapter 5.
(2) Diversion may not be beneficial in large expanses of arid land.
(3) Potential for pollutant generation in runoff to be investigated.
(4) Not suitable in steep areas without application of a binder, if at all.
(5) Dependent on available room and gradient.
? Requires more investigation, refer to Fact Sheet in Chapter 5.
3-53
Chapter 3: Hydrology and Design Criteria
3
Road Drainage Design Manual Chapter 3: Hydrology and Design Criteria
3
the capacity to allow the design or assessment of
5. For significant pipe systems.
complex systems in a much shorter time than
manual methods. Areas for which mathematical
models are routinely used include: 3A.3 Responsibilities of the
• the estimation of design rainfall; Project Manager
• the estimation of discharge; The use of models for the above types of projects
usually requires significant time at a computer,
• the sizing and assessment of culverts; and therefore the work is often carried out by
junior staff. Because the nature of many programs
• the design and assessment of pipe networks;
makes it more difficult for a reviewer/checker to
• the design and assessment of open channels; pick up errors than if a manual analysis had been
made, the use of computer programs therefore
• the estimation of afflux; brings enhanced responsibilities to the designer,
the reviewer/checker, and the technical
• prediction of flood heights; and supervisor. The term project manager below
includes the checker/reviewer.
• assessment of the impacts or capacity of
proposed hydraulic structures. Some of these responsibilities are discussed
below. Project managers must:
3A.2 When to Use Computer • Ensure that the use of the computer model is
Models appropriate and within the limitations of the
model;
For many road projects which are small in scope,
the use of mathematical models will not be • Ensure that the user has a knowledge of the
required. Manual methods (such as the Rational basic theory and especially how each parameter
Method - refer Section 3.5.3) are available for the is selected or calculated; and
prediction of design discharges, and culvert
nomographs may be used to size cross drainage • Ensure that an adequate check is made of the
structures. It should be recognised however that use of the program and that the final results are
environmental issues should also be considered acceptable. This may involve review of the
when determining the size of cross drainage input data, comparison with other results and
structures. perhaps, approximate manual calculations.
• Ensure that the theoretical basis and limitations • Flood level hydrographs (ie. 1D, 2D, & 3D
of the program are known and that such hydrodynamic models);
limitations are not exceeded;
• Sediment transport processes;
• Ensure the program is calibrated against known
flood data whenever possible; • Pollutant export; and
• Flood frequency;
• Hydrology (runoff-routing);
• Culverts;
• Backwater;
District:
Project Name:
3 Contract/Project Number:
Design Standards
Hydraulic Criteria
3
Have watercourse stability, preservation of
flora and fauna, and protection of existing
infrastructure from flood damage been
considered?
Hydrology
Tailwater Levels
3
Fauna Passage
Ambient Conditions
Selection Criteria
Pollution Control
3
the described the sensitivity of the receiving
environment?
Have pollutant sources and types been
identified for the project?
Has the estimation of pollutant loads been
required?
Have the processes for pollutant transport
(e.g. pollutant attached to fine sediment)
been identified for the project?
Have the required pollutant treatment
processes been identified (ie, primary,
secondary or tertiary treatment)?
Have the potential pollutant control device(s)
been assessed and short-listed?
Have the pollutant control device(s) been
assessed for potential pollutant removal?
Have the preferred treatment device(s) been
selected based on an assessment for
achieving key performance objectives?
Other