Professional Documents
Culture Documents
Moisture in HV Power Transformers in Service Kalicki Ziomek IW 2010 - Final
Moisture in HV Power Transformers in Service Kalicki Ziomek IW 2010 - Final
Introduction
The high moisture content significantly reduces
transformer life expectance and limits transformers loading
capability, e.g. it reduces duration and level of short and
long term overloads due to possible bubble generation, or
damage to cellulose insulation. These limitations have
significant impact on the transformers’ operation.
Hydro One delivers electricity across Canadian province
Ontario and is interconnected with other Canadian and USA
utilities. Hydro One fleet of 500kV, 750 MVA
autotransformers – the backbone of power grid in Ontario -
was experiencing problems in service due to the high
moisture content in the transformer insulation system.
Failure rate was unacceptably high (one failure per two
years) and overloading became unsafe. It prompted the
investigation into measuring and control of moisture content
in the transformer insulation. The purpose of this
investigation was the assessment of the moisture content in
the transformers solid insulation based on (i) moisture
content in transformer oil, (ii) direct moisture measurements
in insulation samples and (iii) statistical analysis of moisture
activity over long period of time. As a result of the
investigation, on site dry-out plan was established and close
monitoring of the suspected units took place.
In order to establish behavior of so called “wet” and so Direct moisture measurements on insulation samples
called “dry” transformer, comparison was made between
two units connected to the same 500 kV bus. Both Two independent laboratories were contacted to
transformers were subjected to the same load fluctuation. perform the direct measurements of moisture content in
The same location ensured identical ambient temperature insulation parts which were using two different Karl-Fischer
conditions. titration methods:
Unit Cherrywood T16 (red) was built by a Canadian (i) Heating (Weidmann lab)
transformer manufacturer and put in service in 1980. This The sample is heated in an external oven and gas with
unit is equipped with “free breathing system” - which water vapour is led into the reaction vessel. The results can
means that atmospheric air has direct contact with the be obtained by the measured content of the water vapour in
transformer oil. the released gases. This laboratory tests two different parts
of insulation – so called “outer” and “inner” layers of the
Unit Cherrywood T17 (blue) was built by another sample - thus surface and sample core moisture is
Canadian manufacturer in late 90’s but put in service in measured.
2003, after catastrophic failure of its predecessor unit built
by same manufacturer. Unit T17 is equipped with a (ii) Extraction with alcohol (Morgan-Schaffer lab)
maintenance free dehydrating breather, which prevents The sample is immersed in methanol to extract the
atmospheric moisture penetration into the transformer oil. water. The solution is then separated to extract the water.
Usually this is done in reaction vessel by evaporation of the
40 40
methanol. The procedure is based on single measurement
35
of the insulation pieces taking from the sample by drilling a
30 little hole across the insulation and the average water
30 content of the pressboard sample can be measured.
The results from both labs for samples taken from three
High Temperature (Deg Celsius)
20
25 T17 Water ppm units are presented in the Table I. The unit 13 and unit 14
T16 Water ppm
Water (PPM)
Temperature Celsius were subjected to filed dry-out by hot oil circulation and
20 10
Avg T16 Water ppm
Avg T17 Water ppm
vacuum application.
Avg temperature Celsius
15
0
10
Table I Direct moisture measurements in insulation samples
-10 for three units before and after dry-out
5
0 -20
2/1/2005
3/12/2005
8/27/2005
11/26/2004
12/12/2004
12/25/2004
1/7/2005
1/19/2005
2/14/2005
2/27/2005
3/24/2005
4/6/2005
4/19/2005
5/3/2005
5/16/2005
5/29/2005
6/11/2005
6/23/2005
7/6/2005
7/19/2005
8/1/2005
8/14/2005
9/8/2005
9/21/2005
10/4/2005
10/17/2005
10/29/2005
Time
Fig.4. Water in oil content [ppm] during a year in service for unit
T16 (red) and T17 (blue); average ambient temperature also
shown;
The water in oil levels for free-breathing unit T16 (red) The moisture content results from insulation samples
are much higher than compared to those in the unit T17 indicated that drying method used by Hydro One (heating
(blue), especially in summertime, when the unit T16 and vacuum) seems to remove surface moisture from the
reaches 25-30ppm of moisture, while moisture level in the transformer solid insulation.
unit T17 remains around 5ppm only.
Based on these level one may estimate using the Field dry-out
relationship between the moisture in cellulose and the
relative saturation of oil/cellulose system.
There are three mainstream methods that are used
currently, which can be employed on-line or off-line with
The following can be concluded:
application of (i) heat and vacuum, (ii) cooling and (iii)
filtration.
During winter months amounts of moisture in At HONI on-site dry-outs for initial drying program were
transformer oil is relatively low and readings of performed using a Hot Oil Circulation plus Vacuum (HOV)
“wet” and “dry” units are identical. method, which is standard practice for smaller units.
During summer month a “wet’ transformer Extreme size of these units and deep penetration of the
shows significant increase in moisture activity moisture in the cellulose parts required numerous hot
in opposite to a “dry” transformer which only oil/vacuum cycles which resulted in long-lasting transformer
slightly releases moisture in to the oil
outages. To improve moisture removal effectiveness, a The results for the unit subjected to dry-out process are
diffusion pump was used to achieve a very deep vacuum - shown in Fig.5. One may see that after dry-out in the spring
50 microns (0.067mBar). This process requires long 2006 the moisture in oil for 3 years does not increase above
outages lasting approximately 8 weeks. 5-6 ppm, indicating vey low moisture level in cellulose
insulation, however most recent results (2009) are not as
A new method - Low Frequency Heating (LFH) was optimistic as these obtained right after dryout in 2006.
used on two 750 MVA, 500 kV autotransformer with much It can be compared to the results for the unit T16 which
better results [4]. With the LFH method, ac current is did not undergo drying in the field (see Fig.6). In the unit
applied to the windings in order to heat the transformer T16 the relative saturation in summertime is reaching 20-
more effectively at a higher temperature. The current is 25% which corresponds to moisture in cellulose higher than
applied at frequency 1 - 50 mHz that has two critical 1.5%. According to Hydro One experience this level of
advantages: (i) the impedance voltage is much reduced moisture is already alarming for 500 kV voltage class
with low frequency meaning the required applied voltage is equipment. This particular unit was removed from service
low; the LFH is applied when the oil is removed from the and replaced by a new one, in order to maintain emergency
unit but the applied voltage is thus low enough to eliminate overload beyond nameplate ratings without risk of failure.
any risk of flashover; (ii) the leakage flux is negligible so the
temperature across the winding is uniform (under normal ac
operation, leakage flux causes uneven winding heating). Conclusions
Drying outage can be as short as 2 weeks.
• Even relatively low average moisture levels,
around 1.5-2%, in large high voltage transformer
can lead to catastrophic field failure;
• Dry-out using heat (hot oil circulation) and vacuum
method removes effectively surface moisture, but
some moisture remains trapped within thick
insulation parts. It requires also long outages,
approximately 8 weeks;
• Low frequency heating (LFH) allows for more
effective field drying. Drying outage can be as
short as 2 weeks;
• In order to successfully operate 500kV class large
units, including overloads up to 2 p.u. for 15 min,
the moisture level in solid cellulose insulation
should remain below 1%
References
[1.] T . V . O o m m e n , J . T h o m p s o n , B . W a r d ,. Moisture
Estimation in Transformer Insulation, Panel session IEEE
Fig.5. Trafalgar T14, dry-out in May-June 2006 Transformer Committee, March 2004
2005
Apr
May
Jun
Jul
______________________________
Aug
2007
Sep
Oct
Nov
Dec
Month Authors: