ETM-500LS TowerMill
Installation Manual
Page 1
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Proprietary Information
These documents have been prepared by Nippon Eirich Co., Ltd. They are licensed for use by the
purchaser. Refined solely for the purchaser’s project under the terms and conditions of a separate
agreement and are to be held proprietary to Nippon Eirich Co., Ltd. The recipient agrees by receipt and/or
use of these documents to return them to the purchaser. Refined upon request and not to reproduce, copy,
lend or otherwise disclose or dispose of the contents, directly or indirectly, and not to use them for any
purpose other than that for which they are specifically furnished.
TowerMill Group
Page 2
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Note: “Final Drawing” documents/drawings shall be referred for installation works of the TowerMill.
Page 3
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
CONTENTS
Page 4
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Attachment
Page 5
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
The job of transportation and installation of the TowerMill shall be performed by trained and qualified
personnel only. The personnel performing the unloading and installation assembly are to be trained in
advance and be familiar with this document.
Written confirmation of the receipt of these manuals, as well as the training of personnel concerning all
product documentation, shall be provided by Client and/or Purchaser to Nippon Eirich.
- Before the installation operations of the TowerMill, verify that all handling equipment are capable of
and within operating safety limits for lifting and handling the mass of the equipment.
- Select suitable wire ropes, slings, shackles and etc. capable of carrying the equipment’s mass.
- Note the location of center of gravity and the mass before lifting or transporting the components.
- Do not enter the area below all hoisted equipment while cranes are under operation.
- Hoisting and lowering shall be carried out with safety under supervision by 1 (one) nominee responsible
for the job. The nominee shall determine a strict direction system and direct the workers positively with
whistle, hand-signals and etc.
- Install the firm working deck to prevent high potential accident because the installation and/or assemble
job are undertaken at high position.
- All workers shall put on safety belt and/or safety harness, safety helmet, safety shoes and etc. to
prevent any accidents.
Page 6
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
2. Scope
The illustration in this document of each component and assembly shall differ from actual shapes of each
component of the TowerMill. However, the assembly procedure remains the same as described here.
Page 7
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Ascertain the dimensions, mass and quantities of each component for the TowerMill such as the Mill Shell
assembly, the Screw assembly, the Upper Housing assembly, the Gear Reducer, the Main Drive Motor
and etc. before the installation activities of the TowerMill are started.
Secure both the access way for carrying each component to the site and the work space for unloading
each component from trailers for installation of the TowerMill.
2
H.S. Gear Couplings
3
L.S. Gear Couplings
Machined surface
4 for level check
8
8
6
5
Page 8
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
NOTE: The Mill Shell assembly, Upper housing assembly, and Screw assembly and etc. will be
delivered to the site in a horizontal laid down condition on the trailers and/or trucks.
Therefore, two cranes at the minimum are required to erect each component at the site.
Support
.
Chains or ropes to be used on the lifting eyes The drive shaft support shall be removed before
lifting the whole upper housing
Page 9
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
7. Coarse Classifier
.
Page 10
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Remove the rust inhibitive coating (primer) from each flange surface with solvent (mineral oil, etc.) before
assembling each component. Rust inhibitive coating is applied on the machined surfaces as shown in
Figure-2.
Gear Reducer
Upper Housing assembly
Gear Coupling
(Low Speed side)
Drive Shaft
Screw Shaft
Page 11
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
It is highly recommended that an engineering supervisor shall direct the installation of one unit of the
TowerMill until the completion of all the installation activities.
Page 12
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
- Plan the installation procedure of the anchor bolts by referring “Foundation Drawing Template
Installation procedure” in advance.
- Construct the Concrete foundation by following the drawings on the “Foundation Requirements”.
- The foundation check for the TowerMill is carried out in accordance with the documents above.
- Confirm the following items of each anchor bolt before installation of the TowerMill.
- Position of anchor bolts
- Size of anchor bolts
- Height of anchor bolts that appear above the foundation surface
- Draw the longitudinal center lines, the lateral center lines and the installation reference lines on the
foundations.
- Conformance to industry standards, best practices and the mill manufacturer’s specifications are
essential to the reliability and production quality of the mills. Any deviations from these specifications
will limit the manufacturer’s liability and possibly the warranty conditions of the contract.
Page 13
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
6. Preparation of pad
Prepared
Items Description Qty. Supplied
at work site
Pad Liner 85 x 240 x 22 mm 24 X -
Page 14
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Padding procedure
1) Set 2 (two) pad liners on both sides of anchor bolts shown in the Figure-3.
2) Chip the surface of Concrete foundation.
3) Keep the surface of the Concrete foundation wet by watering 24 hours prior to the padding.
4) Place forms for padding on the Concrete foundation.
5) Put padding mortar (non-shrinking mortar) into the forms for padding.
6) Sink pad liners by tapping with a plastic hammer.
7) Measure the height of each pad liner with level vial respectively. The tolerance of the level shall be
1 mm/m.
NOTE: Top surface of pad liners shall be max 28 mm below the base-plate of Mill Shell
assembly.
8) Remove the forms for the pad gently after confirming the above accuracy.
9) Round each corner of padding.
10) Make cutting grooves on the surface.
Page 15
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Page 16
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Refer to the following drawings for the installation works of Mill Shell assembly.
The following items shall be prepared for installation works of Mill Shell assembly in advance
Prepared
Items Description Qty. Supplied
at work site
Taper Liner 200x75x8/20 mm 48 X -
Plain Washer 42 12 X -
Hex-nut M42 24 X -
Recycle Inlet 1 X -
Page 17
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Set 2 (two) Taper Liners respectively on both each side of Anchor bolts as shown in Figure-3.
2) Ascertain the orientation of the Mill Shell assembly by comparing the position of components such
as Recycle Nozzle, the chute covers of the Ball Discharge and other equipment with the “General
Arrangement Drawing”.
3) Ensure the enough space for installation:
the installation works of swiveling the components, lifting the components, lowering the components,
placing the components on the ground and etc.
4) Prepare the shackles and/or tools with both the proper size and the proper shape and the wire
ropes sustainable against the load to hoist each component.
NOTE: The total mass of Mill Shell assembly is approximately 19,000 kg.
5) Clean off the Concrete foundation surface and installed both taper liners and pad liners. No dust,
rust, defects and other obstacles shall be found on the Concrete foundation surface.
6) Clean the bottom surface of the base-plate of the Mill Shell assembly that attaches to the
foundation.
7) No dust, rust and defects shall be found on the bottom surface of Mill Shell assembly base-plate.
8) Set shackles and wire ropes on lifting lugs of the Mill Shell assembly.
9) Hoist the Mill Shell assembly slowly with 2 (two) heavy duty machines such as the cranes, UNIC
cranes, etc.
10) Place the Mill Shell assembly on the Concrete foundation with care so as not to damage each
anchor bolt.
11) Release the shackles and wire ropes from the lifting lugs of the Mill Shell assembly.
12) Put the following items on each anchor bolt.
- 1 (one) piece of Square Washer (125 x 125 x 25 mm)
- 1 (one) piece of Plain Washer (size 42)
- 2 (two) pieces of Hex-nuts (M42)
NOTE: For details of the parts above-mentioned, refer to “Anchor bolt & Template”.
Page 18
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
NOTE: Do not fully fasten yet all Hex-nuts (M42) firmly at this stage. All Hex-nuts (M42)
shall be fastened firmly after the Upper Housing assembly installed on the Mill
Shell assembly and the level-checks finished.
14) Clean the top flange surface of the Mill Shell assembly with solvent.
WARNING
Confirm that all eye-bolts (M20 and M30) and nuts (M20 and M30) on the Mill Shell
Door and the Ball Discharge Cover are fastened firmly BEFORE lifting, slinging and/or
unloading the Mill Shell assembly.
In the case that any loosened bolts & nuts were found, those bolts & nuts shall be
fastened firmly and surely.
No operations of lifting, slinging and/or unloading the Mill Shell assembly are
permitted until all eye-bolts and nuts are confirmed to be fastened rigidly.
Page 19
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Refer to the following drawings for the installation works of Screw assembly.
The following items shall be prepared for installation works of Screw assembly in advance
Prepared
Items Description Qty. Supplied
at work site
Screw band with Hex-bolts and
(used in screw hanging) 1 set X -
Hex-nuts
Hex-bolt M48 x 350L 4 X -
Shackles 10 - X
Page 20
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Place the hydraulic jack on center of the Mill Shell assembly bottom.
2) Mount the Band on the neck of the Screw assembly as shown in Screw Installation Drawing
(T595024)
3) Set shackles to the holes on the lifting lug of the Band and on the lifting lug of the Mill Shell assembly.
4) Remove the rust inhibitive coating using solvent from the flange surface end of the Screw assembly
connecting to the Drive Shaft.
5) Confirm that no rust, dust, foreign matters and etc. are found on the cleansed portions above.
6) In the case that any defects found on the cleansed portions, remove the defects surely.
7) Set the lift crane used for lifting, and attach the wire ropes and 2 sets of shackles to the M48 eye-
bolts and nuts to the flange surface of the Screw assembly. The other set of shackles and lifting
rope/crane shall be attached to the arm side attached to the screw.
8) Loosen the end plate at the other end of the screw transport and remove all the bolts/nuts installed
preventing the screw from moving with respect to the screw transport.
9) Hoist the Screw assembly slowly with cranes begin lifting horizontally the screw and have it
lifted/separated from the screw transport.
10) When the screw assembly is separated already, lower the screw near the ground and tighten again
the screw end plate previously loosened.
11) Continue lifting the whole screw and beging horizontal to vertical orientation lifting with 2 cranes
12) Release the wirerope hooked on the lifting arm/jig when the screw is vertically positioned already.
13) Disattach the arm from the screw.
14) Lift the screw the Screw assembly and insert it in the mill shell and have it sitted above the hydraulic
jack.
15) Apply hooks of ratchet lever hoist to the shackles tied down to the rib on the Mill Shell assembly.
16) Apply other hooks of ratchet lever hoist to the shackles tied down to the rib on the Band.
17) Tension each chain of ratchet lever hoist.
NOTE-1: Confirm that the distance between flange surface of the Screw assembly and
the top face of the Mill Shell flange shall be around 920 mm.
NOTE-2: The Screw assembly (vertical axis) should be perpendicular to the base-plate of
the Mill Shell assembly when all the chains of ratchet lever hoists are on
tensioned condition.
18) Confirm that all chains of ratchet lever hoist have enough tension to allow the Screw assembly to
stand perpendicular.
19) Release the wires hooked on the eye-bolts and remove the two eyebolts finally. Follow the
procedure in T596024 for installation of the screw agitator blade during upper housing installation.
Page 21
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Refer to the following documents for Installation works of Upper Housing assembly.
The following items shall be prepared for installation works of Upper Housing assembly in advance.
Prepared
Items Description Qty. Supplied
at work site
Hex-bolt M30 x130L 30 X -
Hex-nut M30 30 X -
Plain Washer 30 30 X -
Shackle 6 - X
Page 22
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
NOTE-1: All workers shall put the safety goods such as the safety belts, the safety
harnesses, the safety helmets and etc. while they are engaged in these activities
above.
NOTE-2: Pay the closest attention so as not to drop the items such as Hex-bolts
(M30x130), and tools etc. during these activities above.
12) Place the level vial on the top face of the Upper Housing assembly as shown in Figure-5: Location
of the level vial and check level diagonally.
Level tolerance: 0.1 mm/m
NOTE: Adjust the level by tapping the taper liners beneath the base-plate of the Mill
Shell assembly.
13) Confirm the level on the flange surface of the Upper Housing assembly with level vial.
14) Spot-weld between (1) the upper taper liners and the lower taper liners and (2) the lower taper
liners and the pad liners as shown in Figure-3 after the level-checks are finished.
15) Tighten all the Hex-nuts (M42) for the anchor bolts diagonally, evenly and firmly.
NOTE-1: Conduct finishing works at the top of each Concrete foundation by pouring the
grout after all the level-checks have been finished.
NOTE-2: The covers for the manholes inside of the Upper Housing assembly (lower
section) shall be placed precisely.
Page 23
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Level vial
support
Figure-6: Upper housing (with coupling brace and lower transport frame)
Page 24
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
The following items shall be prepared for installation works of Gear Reducer in advance.
Prepared
Items Description Qty. Supplied
at work site
Hex-bolt M36x150L 24 X -
Hex-nut M36 24 X -
Plain Washer 36 24 X -
Spring Washer 36 24 X -
Hex-bolt M24 4 X
Page 25
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Set shackles and wire ropes on the lifting eyes/holes of the Gear Reducer.
2) Remove the fixing bolts and the nuts that are settling the Gear Reducer on the transportation
frame.
3) Remove the rust inhibitive coating with solvent from (1) both flange-surfaces of the Gear Reducer,
(2) the upper side of L.S. Gear Couplings and (3) the lower side of the H.S. Gear Couplings.
4) Confirm that no rust, dust, foreign matters and etc. are found on the cleansed portions above.
5) In the case that any defects were found on the cleansed portions, remove the defects surely.
6) Hoist the Gear Reducer slowly.
7) Confirm the orientation of the Gear Reducer by comparing the reference drawings before placing
the Gear Reducer onto the Upper Housing assembly.
8) Loosen 4 (four) pieces of the Adjusting push-bolts (M24 x140L) on the mounting flange of the
Upper Housing assembly BEFORE placing the Gear Reducer onto the Upper Housing assembly.
9) Place the Gear Reducer on the flange surface of the Upper Housing assembly.
Note-1: Before fully fastening the bolts of the reducer to the upper housing, alignment with
the L.S Coupling lower part and upper part is necessary (sub steps 9.1 to 9.3)
9.1) Prepare the LS Coupling (Upper and lower half) for alignment.
NCCH-560
LS Coupling
Page 26
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
9.2) Have the surfaces of the LS coupling (upper and lower half) exposed so that a dial gauge
with magnet base can be installed on both sides. (A laser alignment tool is also a good
alternative to use whenever available) See illustration below.
10) Measure the following values between the upper side Coupling center and the lower side
Coupling center respectively. Adjust as necessary the gear reducer centering through the four
adjustment bolts between the upper housing and gear reducer.
+ 1.5 mm
B-C≦0.34 mm D = 28 mm A≦ 0.21mm
- 1.5 mm
NOTE-1: In the case that both measured values and/or either measured values do not
satisfy the allowable tolerances above, the adjustment operations shall be
carried out by inserting and/or taking out the shim-plates between the mounting
flange of the Upper Housing assembly and the lower flange of the Gear
Reducer.
NOTE-2: Record the all activities such as measuring operations, the measured values
and etc.
Page 27
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
11) Lastly, close the sleeves of the L.S. Coupling by lowering the upper sleeve and lifting the lower
sleeve(covers) using the support plates/bolts using spanners and wrenches. Closed the gap
between the sleeves until the two surfaces meet each other, then fasten all the set of bolts and nuts
together. Remove the support and fixed plates and bolts. .
12) Install/tighten twenty four (24) pieces of Hex-bolts (M36x150) with Plain Washers through the
through-holes on the mating flange surface of between the Upper Housing assembly and the Gear
Reducer from the bottom side surface of the Upper Housing assembly.
13) Set Plain Washers and Hex-nuts onto the installed Hex-bolts above.
14) Fasten the Hex-bolts and the Hex-nuts temporarily, not firmly.
NOTE-1: All workers shall put the safety goods such as the safety belts, the safety
harnesses, the safety helmets and etc. while they are engaged in these activities
above.
15) Install the related sensors (vibrationx1pc and temperature sensorx1pc) in accordance with
“Outline Drawing of Gear Reducer”.
NOTE-1: Lower half of H.S. Gear Coupling has been installed on the input shaft of the
Gear Reducer.
NOTE-2: Upper half of L.S. Gear Coupling has been installed on the output shaft of the
Gear Reducer.
Page 28
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Page 29
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Refer to the following documents for Installation works of Main Drive Motor.
The following items shall be prepared for installation works of Main Drive Motor in advance.
Prepared
Items Description Qty. Supplied
at work site
Hex-bolt M24x75L 8 X -
Page 30
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Remove the rust inhibitive coating from (1) the mounting flange surface of the Main Drive Motor
and (2) the upper side of H.S. Gear Couplings installed on the output shaft of the Main Drive
Motor.
2) Confirm that no rust, dust, foreign matters and etc. are found on the cleansed portions above.
3) In the case that any defects were found on the cleansed portions, remove the defects surely.
4) Set shackles and wire ropes on through-holes of the Main Drive Motor.
5) Hoist the Main Drive Motor slowly.
6) Confirm the orientation of the Main Drive Motor by comparing the reference drawings before
placing the Main Drive Motor onto the Gear Reducer.
7) Place the Main Drive Motor on the flange surface of the Gear Reducer.
8) Measure the following values between the upper side Coupling center and the lower side
Coupling center respectively
+ 0.75 mm
B-C≦0.14 mm D = 12 mm A≦ 0.07mm
- 0.75 mm
NOTE-1: In the case that both measured values and/or either measured values do not
satisfy the allowable tolerances above, the adjustment operations shall be carried
out by inserting and/or taking out the shim-plates between the upper mounting
flange of the Gear Reducer and the mounting flange of the Main Drive Motor.
NOTE-2: Record the all activities such as measuring operations, the measured values and
etc.
9) Install eight (8) pieces of Hex-bolts (M24x85) through the through-holes on the mating flange
surface of between the Gear Reducer and the Main Drive Motor from the bottom side surface of
the Gear Reducer.
10) Fasten the Hex-bolts temporarily. Proceed first with HS Coupling alignment.
Page 31
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Figure-14: Installation of the Main Drive Motor with H.S. Gear Couplings
Page 32
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Refer to the following documents for Aligning & Assembly of H.S. Gear Couplings.
The following items shall be prepared for aligning work of High Speed Gear Couplings in advance.
Prepared
Items Description Qty. Supplied
at work site
Reamer-bolt M10 12 X -
O-ring (mounted) 1 X -
(in between
Center plate / o-ring 1 set X -
upper,lower half)
precision 0.01 mm
Dial gauge - - X
with magnetic stand
Offset wrench or spanner M10 - - X
Page 33
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Lift the upper Coupling case carefully and hang it above the teeth of the upper side of the
Coupling center with the annealing wires.
NOTE-1: Tie wires between the through-holes of the upper Coupling case and any
hooking points inside of the Gear Reducer.
NOTE-2: Prepare the wooden plates, the rubber-sheets and/or the waste-clothes on the
upper case of the Gear Reducer for placing the lower Coupling case on the Gear
Reducer during the alignment checks.
2) Clean the surface of both the upper Coupling center and the lower Coupling center (with external
gear teeth).
3) Confirm that no rust, dust, foreign matters and etc. are found on the cleansed portions above.
4) In the case that any defects found on the cleansed portions, remove the defects surely.
5) Measure and check the distance and the angularity between the lower Coupling center and the
upper Coupling center again.
6) Set the Dial-gauge with the magnetic stand on the upper Coupling center.
7) Apply the spindle of the dial-gauge onto the vertical machined-surface of the lower Coupling
center to measure the eccentricity of the H.S. Gear Couplings.
8) Turn the output shaft of the Main Drive Motor by rotating the cooling fan manually.
NOTE-1: Record the measured eccentricity values of the Coupling centers with 4 (four)
points at a minimum.
9) Tighten the eight (8) pieces of Hex-bolts (M20) between the Gear Reducer and the Main Drive
Motor diagonally, evenly and firmly.
10) Remove the Dial-gauge with the magnetic stand from the upper Coupling center.
Page 34
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
③ ① ⑤
⑥
④ ⑨
⑧
②
⑦
NSV 242
Figure-15: Outline of the Gear Reducer and alignment of the H.S. Gear Couplings
5 Motor shaft
11) Record all the measured values such as the eccentricity, the angularity and the distance of the
H.S. Gear Couplings. These recorded values shall be filed for the future maintenance and/or the
overhaul operations.
12) Apply sufficient grease (“Ref. TPD-021-0 Lubrication List) to the internal gear teeth and the
external gear teeth of both sides of the H.S. Gear Couplings.
13) The indication quantities of the grease are as follows:
- Upper side approximately 0.104 kg (0.120 L)
- Lower side approximately 0.127 kg (0.147 L)
14) Insert the O-ring into each ditch on the lower Coupling case respectively.
15) Insert the Center plate with spherical convex prominence between the upper Coupling center and
the lower Coupling center.
NOTE: The direction of the spherical convex prominence on the “Center plate” shall be
downward. Wrong installation direction of the Plate shall cause the critical
damages to the TowerMill.
Page 35
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
18) Set Spring Washers and Hex-nuts onto the installed Reamer-bolts above.
19) Tigthen the Reamer-bolts with the torque wrenches diagonally, evenly and firmly.
Page 36
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Refer to the following documents for Aligning & Assembly of L.S. Gear Couplings.
The following items shall be prepared for aligning work of Low Speed Gear Couplings in advance.
Prepared
Items Description Qty. Supplied
at work site
Reamer-bolt M20 20 X -
Hex-nut M20 20 X -
To be installed in
O-ring / center plate between upper half and 1 set X -
lower half coupling
hanging the
Annealing wire 1 lot - X
upper Coupling case
precision 0.01 mm
Dial gauge 1 - X
with magnetic stand
Page 37
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) For smooth alignment check activities, remove the cooling fan cover of the Main Drive Motor.
2) Ask/prepare one (1) worker on the top of the Main Drive Motor for rotating the cooling fan
manually.
NOTE-1: The worker on the top of the Main Drive Motor shall rotate the cooling fan
manually whenever asked by the site manager (the qualified personnel or the
supervisor).
NOTE-2: The worker on the top of the Main Drive Motor shall put on the safety goods
such as the safety belt, the safety harness, the safety helment and etc. surely.
NOTE-3: The other worker(s) shall stay on the maitenance floor (the same height of the
upper flange of the Upper Housing assembly) and keep sharp eyes on the
worker on the top of the Main Drive Motor so that the worker does not fall down.
NOTE-4: Prepare the wooden plates, the rubber-sheets and/or the waste-clothes on the
upper case of the Bearing Box for placing the lower Coupling case on the
Bearing Box during the alignment checks.
3) Clean the surface of both the upper Coupling center and the lower Coupling center (with external
gear teeth).
4) Confirm that no rust, dust, foreign matters and etc. are found on the cleansed portions above.
5) In the case that any defects found on the cleansed portions, remove the defects surely.
6) Measure and check the distance and the angularity between the lower Coupling center and the
upper Coupling center.
7) Set the Dial-gauge with the magnetic stand on the upper Coupling center (see Figure 16 on next
page)
8) Apply the spindle of the dial-gauge onto the vertical machined-surface of the lower Coupling
center to measure the eccentricity of the L.S. Gear Couplings.
9) Turn the output shaft of the Gear Reducer by rotating the cooling fan manually.
NOTE-1: The site manager, a qualified personnel and/or the supervisor shall suggest the
worker on the top of the Main Drive Motor to continue to rotate the cooling fan
manually until the Dial gauge circuits around the lower Coupling center.
NOTE-2: Record the measured eccentricity values of the Coupling centers with 4 (four)
points at a minimum.
10) Fasten and/or loosen 4 (four) pieces of the Adjusting push-bolts (M24x140) on the base-plate of
the Upper Housing assembly by referring the measured values above.
11) Continue to measure the eccentricity by adjusting the installed position of the Gear Reducer with
the Adjusting push-bolts until the eccentricity values satisfy the allowable values as shown in エ
ラー! 参照元が見つかりません。10.
12) Fasten 4 (four) pieces of Lock nuts on the Adjusting push-bolts so as not to be loosened AFTER
the eccentricity of the Coupling center is confirmed to satisfy the allowable values.
13) Tighten the 12 (twelve) pieces of Hex-bolts (M48x195) & Hex-nuts (M48) between the Upper
Housing assembly and the Gear Reducer diagonally, evenly and firmly.
14) Remove the Dial-gauge with the magnetic stand from the upper Coupling center.
Page 38
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
NCCH 560
Figure-16: Outline of the Gear Reducer and alignment of the L.S. Gear Couplings
Page 39
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
15) Record all the measured values such as the eccentricity, the angularity and the distance of the
L.S. Gear Couplings.These recorded values shall be filed for the future maintenance and/or the
overhaul operations (Figure-10).
16) Apply sufficient grease to the internal and the external gear teeth of both sides of the L.S. Gear
Couplings uniformly.
17) The indicated quantities of the grease/oil lubricant are as follows for NCCH 560 LS coupling:
(Ref. TPD-021-0 Lubrication List)
- Upper side coupling : 2.03 kg (2.247 L)
- Lower side coupling : 1.91 kg (2.118 L)
18) Insert the O-ring in the coupling gap
19) Insert the center support platesand which between the upper Coupling center and the lower
Coupling center
20) Release the tied wires on the upper Coupling case.
21) Lift the lower Coupling case.
22) Install twenty (20) pieces of Reamer-bolts (M20) into the mating flange surface of between the
upper Coupling case and the lower Coupling case from the bottom side surface of the lower
Coupling case.
23) Set Spring Washers and Hex-nuts onto the installed Reamer-bolts above.
24) Tigthen all the Reamer-bolts with the torque wrenches diagonally, evenly and firmly.
Page 40
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
The following items shall be prepared for installation works of Screw assembly in advance.
Prepared
Items Description Qty. Supplied
at work site
Hex-bolt M48 x 280 L 8 X -
Hex-nut M48 24 X -
Spring Washer 48 12 X -
Hydraulic jack 1 X -
Jack base 1 X -
Hammer - - X
Page 41
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Ascertain that 6 (six) pieces of Lock-bolts (M42x120L) on the Bushing Box are loosened before
turning the Drive shaft.
2) Match the direction of the keyway on the Drive Shaft to the direction of the sunk key by turning the
cooling fan of the Main Drive Motor manually.
3) Operate the hydraulic jack slowly to push up the Screw assembly.
NOTE: Pay the closest attention so as not to damage the flange surface of the Drive Shaft
or the edges of the keyway on the drive shaft by the sunk key during the operation
of hydraulic jack.
4) Install first the eight piece of pieces of Hex-bolts (M48x208L) through the through-holes on the
mating flange surface of between the Screw assembly and the Drive Shaft from the bottom side of
the flange surface of the Screw assembly. Refer to T596024 for the arrangement of bolts and the
figure below. Note that the first 8 bolts shall be used for flange to flange direct bolting and not for
the stirring blade of the screw.
5) Next install the remaining 4 pcs of M48x350L bolts sandwiching the two sets of stirring blade plates.
35 kg
Page 42
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
NOTE-1: All workers themselves shall pay the closest attention so as not to drop down.
NOTE-2: Never throw the released hook of the ratchet lever hoist so as not to damage the
inside of Mill Shell assembly or Screw assembly.
10) Release the other shackles from the lugs of the Screw Band.
11) Remove the Band.
NOTE-1: Be sure that at least 2 (two) workers shall engage to dismantle the Band from
the Screw assembly.
NOTE-2: Pulling on the safety belts, all workers themselves shall pay the closest
attention so as not to drop down.
NOTE-3: Pay the closest attention so as not to drop off the dismantled the Band inside
the Mill Shell assembly.
12) All workers shall leave from the inside Mill Shell assembly.
13) Release pressure of hydraulic jack slowly.
Page 43
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Refer to the following documents for Installation works of Coarse classifier and agitator.
The following items shall be prepared for installation works of Coarse classifier and agitator in advance.
Prepared
Items Description Qty. Supplied
at work site
Hex Bolts,nuts set M20 32 set X -
Hex Bolts,nuts, plain washers, spring
M20 4 sets X -
washers set
Coarse classifier Support arm L = 740mm (angle) 2 sets X -
Page 44
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Prepare all lifting tools (shackles, eyebolts, wire ropes, overhead crane or chain block).
2) Pre-install the support arm of the coarse classifier onto the coarse classifier, but lightly tightening
the bolts/nut set to it.
3) Set up the lifting tools so as to carry the whole coarse classifier.
4) Lift the coarse classifier like the way shown in Figure 18 below
5) Install all thirty two (32) sets of M20x80L size hex bolts/nuts in between the flange of the coarse
classifer and mill shell overflow port. Note that the bolt heads shall be coming from mill shell
side overflow port, while nuts shall be located on the coarse classifer side.
a-detail
Coarse classifier
Support arm
Page 45
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
6) After having the coarse classifer installed into the mill shell via the port to port connections
through bolts, next is to fix the support arm on both mill shell side and coarse classifier(to
tightened level).
7) Use the four (4) pieces of M20x65L hex bolts together with the plain and spring washers (6 sets
total).
8) Balance and tighten firmly all the the connecting bolts between mill shell and coarse classifer.
9) Remove all the lifting ropes and shackels when the whole coarse classifer has been secured
and tightened.
NOTE-1: Make sure to clean all mating surface always using the solvent remover and
rugs
NOTE-2: Always observe precation on heavy items that might fall while working. Use
safety harness, ladders, when necessary.
Refer to Figure 19, for the next procedure steps on how to install the agitator body on top of the coarse
classifer.
10) Install the agitator blades(impeller) (2 sets) onto the agitator shaft by tightening the set bolts
(M12x30L) attached to the blade hubs.
11) Install the shaft onto the agitator main body by inserting the shaft and tightening the set bolts
M10x25L (4 sets)
12) Remove the prebolted Agitator base plate on top coarse classifier. There are two half circle
plates, only one need to be removed so that the blades and agitator shaft can be inserted inside
the coarse classifer.
13) Lift the whole agitator unit carefully up and have the shaft/impeller side get inside the coarse
classifier opening.
14) Have the agitator base flange sit on the top of the pre-installed half base plate and bolt the
two(2) sets of M20x50L bolts/PW/SW sets alotted for the installation of the agitator to the base
plate.
Do not tighen yet the bolts fully, tighten them just enough to have the agitator unit temporarily
installed.
15) Bring back the previously remove agitator base plate half (step No. 12), and have it installed in
between the agitator and the coarse classifer body to close now the opening.
16) Install the same remaining bolts sets to secure fully the agitator. These are the same M20x50L
bolts/PW/SW sets (2sets).
17) Make sure that the agitator shaft is centered in between the base plate halves’ hole (circle shape
when completed) so as to prevent the agitator shaft from touching the base plate during
rotation/operation.
18) Tighten firnly all the bolts and make final adjustments when necessary.
19) Remove the old air vent (with pipings) of the agitator gear reducer and replace it witht the
dessicant type air breather. Refer to Figure 20 for the illustration of the old vent and new vent
with air breather
Install it onto the gear reducer part of the Agitator and use a seal tape to seal the pipings.
Note: Make sure the oil inside of the gear reducer does not leak. Also have the agitator
positioned so that the orientation of the air breather will be on the highest side (opposite of the
incline, towards the center)
Page 46
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Page 47
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
The following items shall be prepared for closing of Mill Shell Door in advance.
Prepared
Items Description Qty. Supplied
at work site
Eye-bolt M30x 130 2 X -
Page 48
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Connect the mating flange surface of between the Mill Shell assembly and the Mill Shell Door.
2) Install 1 (one) piece of Hex-bolt (M30x130) through the through-holes on the mating flange in the
hinge area of the door and mill shell.
3) Set Plain Washer and Hex-nut onto the installed Hex-bolt above.
4) Fasten the Hex-bolt and the Hex-nut.
NOTE-1: Initial setting of the gap between the Mill Shell assembly and the Mill Shell Door
shall be approximately 35 mm. During the factory test, this was already preset at
35mm. Make sure that the same measurement can be observed during on site
installation.
NOTE-2: Keep the gap between the Mill Shell assembly and the Mill Shell Door.
NOTE-3: Don’t remove the Stopper-bolts from the flange of the Mill Shall assembly.
5) Install the next piece of Hex-bolts (M30x130) through the through-holes on the mating flange
surface of between the the Mill Shell assembly and the Mill Shell Door from the flange surface of
the Mill Shell assembly in the position 2 and 3 in Figure-16.
6) Set Plain Washers and Hex-nuts onto the installed Hex-bolts above.
7) Continue the procedures: total 6 (six) sets of the Hex-bolts & Hex-nuts in the position 4 to 6 in
Figure-16.
8) Set eye-bolts with Plains Washer and Hex-nuts in sequence 7 to 10 in Figure-16.
9) Fasten the Hex-nuts (M30) evenly.
Page 49
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
5
Bolts & Nuts
4
M30 A
6 Gap
A Initial setting: 35 mm
Eye-bolt
M30 x 175
Stopper-bolt
Initial setting: 12 mm
10
2
Bolts & Nuts 1
M30 3
Page 50
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Refer to the following drawings for the installation works of Lubrication Unit.
The following items shall be prepared for installation works of Lubrication Unit in advance.
Prepared
Items Description Qty. Supplied
at work site
JIS 10K 32A /
Flexible Metal Hose 1 set X -
L=1750mm
JIS 10K 40A /
Flexible Metal Hose 1set X -
L=1750mm
Hex-bolt M12 8 - X
Pipe wrench - - X
Shackle - - X
Page 51
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
1) Install Flexible Metal Hoses on each connection (gear reducer in/out to lubrication unit in/out
ports.
NOTE: Apply the “seal-tape” on the threaded portions of the “male-connection” on the
Gear Reducer BEFORE connecting Union Joints.
NOTE: Depending on the layout plan of the customer, a firm base for the lubrication
unit may be necessary. (e.g. channels or metal frame)
2) Set shackles and wire ropes or chains on the lifting eye bolts of the Lubrication Unit.
3) Hoist the Lubrication Unit slowly.
4) Place the Lubrication Unit on the floor with care so as not to damage it.
5) Position it above the holes of the matching base and insert the bolts and nuts set for installation.
6) Tighten the hex bolt and nuts sets
7) Release the shackles and wire ropes from the lifting lugs of the Lubrication Unit.
8) Connect flexible hoses on the Lubrication Unit and gear reducer side with the pipe wrenches.
9) Make sure to open all valves on the lubricant piping of the Lubrication Unit.
10) Confirm that the “Change handle” of the Duplex filter is at the “OPERATION” position.
11) Close the draining valves.
Page 52
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Prepare lubricants for assembling each component in accordance with the table below.
Bearing Box
MOBIL 600XP150
1 in Upper Housing approximately 50 liters
or ISO VG150
assembly
Page 53
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Page 54
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Page 55
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
The site-manager is requested to remain the following items at a minimum as the “Records of the
installation conditions” for the future maintenance activities
Check Person
Item Condition
date in charge
Loose them approximately
Bushing Box 6 pieces of Lock-bolts
10 mm for Drive shaft's free
Upper Housing Check its condition & Full
Leveling
assembly the inspection sheet
Check its condition & Full
Eccentricity
the inspection sheet
Check its condition & Full
Angular
H.S. Gear the inspection sheet
coupling Check its condition & Full
Distance
the inspection sheet
Mill Shell
Rubber lining Check its condition
assembly
Check condition of each
Fixing bolts and nuts
equipment
All equipment
All opening covers and Check condition of each
doors equipment
Page 56
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
APPENDIX
INSTALLATION DATA SHEET
Page 57
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Appendix-1: Mill Shell assembly leveling record
Page 58
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Appendix-2: Low Speed Gear coupling alignment record
Page 59
NIPPON EIRICH CO., LTD.
PROJECT : QUELLAVECO PROJECT
DOC. ID : TPD-022-0 INSTALLATION MANUAL / ETM-500LS TOWERMILL
Appendix-3: High Speed Gear coupling alignment record
Page 60
Final Drawing
Final Drawing
Final Drawing
Final Drawing
Final Drawing
Final Drawing
1 2 3 4 5 6 7 8 9
T595024
DWG. NO.
A A
1. Before starting the installation of the screw, mount the screw “BAND” on the screw just
below the flange as shown in “detail A”.
Pay close attention so as not to damage the screw’s rubber lining.
2. Place the jack base, and hydraulic jack inside the mill shell, at the center of the base plate.
Make sure that the hydraulic jack is at its lowest position (zero stroke) before starting putting
the screw inside the mill shell
3. Have the screw lifted by the crane (from the screw transport originally carrying it,
B and conduct horizontal to vertical orientation change). B
Lift and put the screw inside the mill shell by inserting it from the top shell flange opening then
have the bottom part (end cap) to sit above the hydraulic jack.
Note: At this period, DO NOT release yet the wire ropes carrying the screw.
4. Set the rachet lever hoist (5 sets) and tension each chain so that the screw shall be sitting
straight perpendicular with respect to the mill shell base plate.
Note: Confirm that the center of the screw flange is at the center of the mill shell upper flange
and the distance from the machined flange is around 920mm.
This is the clearance needed so that around 20mm gap shall be present when the time
to lower the upper housing with drive shaft flange is inserted inside the mill shell.
As much as possible, have the screw flange keyway pointing to the mill shell door.
C 5. When it is time to install the upper housing(with drive shaft on it), match the screw keyway
CHECK THE CENTER ※ direction with that of the drive shaft keyway so the two shall match and be on the same
C C
direction upon bolting the two flanges. Adjustment of the keyway direction can be done by
※ ※ rotating the LS Coupling side of the drive shaft.
6. Raise the hydraulic jack by using the hydraulic manual pump supplied with the parts.
RATCHET DRIVE SHAFT
LEVER HOIST Pay attention so as not to damage the edge of the keyway or flange surface.
7. Insert the first 8 pcs of flange bolts with M48 x L280mm in the arrangement shown in View C.
These are 3pcs in the door side, 3 pcs in the overflow side, and 2 pcs 90degrees with respect
※
to the first two sides.
VIEW C 8. Next, insert the remaining flange bolts with size M48 x L350mm by sandwiching
AROUND 920
the agitator blade plates (2pcs) first and then inserting the 2 bolts per agitator blade plate.
900
※ Insert the first 8 pcs of flange This is shown in second View D.Tighten all bolts firmly.
bolts with M48 x L280mm 9. When all the flange bolts have been installed already, loosen the ratchet hoist and
( Bolt heads lower side ) disassemble them together with the screw band and take out the hydraulic jack and base
D BAND D
A MILL SHELL out of the mill shell.
( JACK UP )
( CLEARANCE )
AGITATING BLADE
DETAIL - A
D
SCREW JACK ( STROKE 0 mm )
E E
TOTAL STROKE 50 mm ※ ※
※ ※
32 140∼146
VIEW D
Next,insert 4 pcs of flange
※ Next,insert 4 pcs of flange bolts with M48 x L350mm
bolts with M48 x L350mm
( Bolt heads lower side )
32
B T595024
1 2 3 4 5 6 7 8 9
Final Drawing
Final Drawing
Final Drawing
Final Drawing
Final Drawing
制御盤回路図
Control Panel Wiring Diagram
納入先
Customer Anlgo American Peru, SA 殿
装置名
M a c h i n e N a m e ETM-500LS Terminal Box-1
機番
Machine No. 990202
製番
Order No. 186232640
図番
Drawing No. 186232640 00
承 認 審 査 作 成
A PPR OV ED CH EC KE D D ESI GN ED
Drawing index
頁 名 称 /CONTENTS 頁 /PAGE
Cover 1
Drawing index 2
Box outside details 3
Inside details 4
Parts List 5
300
正面図/Front view 右側面図/Right side view
W40×H80 4(NO)
1(+)
8
9
圧力 計1 2(4-20mA) 10
Pressure gauge1
3(-)COM 11
TB
275
4(NO) 12
1(+) 13
圧力 計2 2(4-20mA) 14
Pressure gauge2
3(-)COM 15
W40×H80 4(NO)
1(+)
16
17
圧力 計3 2(4-20mA) 18
Pressure gauge3
3(-)COM 19
4(NO) 20
NC 21
流量 計1 COM 22
Flowmeter1
中板部品配置図/Placement of middle part parts NO 23
24
予備 25
Spare
26
27
28
29