You are on page 1of 80

QUANTITY ANALYSIS

Sump Well (20m3)


sfo{s|d M—vfg]kflg tyf ;/;kmfO{
cfof]hgfsf] gfd M—a;Gtk'/ lnkm\6 vfg]kflg of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M—ltgfp,# a;Gtk'/
lelq 4.5 3.2 1.6
SN Item NO Length Breadth Height Quantity Remarks
1 Site clearance work 1 10.00 8.00 80.00 m2
2 E/W excavation in B.M. Soil
Foundation 1 6.70 5.40 0.70 25.33
Total 25.33 m3
3 Boulder soling without sand packing
Foundation 1 6.70 5.40 0.15 5.43
Total 5.43 m3
4 P.C.C. Work(1:2:4)
Foundation 1 6.70 5.40 0.12 4.34
Total 4.34 m3
5 R/R masonary in 1:4 C/S mortar
Trapezoidal portion 1 18.10 0.68 1.60 19.55
19.55 m3
6 R.C.C. Work(1:2:4)
slab 1 5.40 4.10 0.10 2.21
Total 2.21 m3
7 Reinforcement work
10mm dia. Bar
main bar 35 4 140.00
distribution bar 28 5.1 142.80
282.80 Rm
@ 0.62 kg/m 175.34 Kg
8 Form work for P C C:
RCC slab 1 4.50 3.20 14.40
Edge of slab 1 19.00 0.10 1.90
Foundation pcc 1 24.20 0.12 2.90
19.20 m2
9 20 mm thick cement plaster 1:4
Inside floor portion 1 4.50 3.20 14.40
wall portion 1 15.40 1.60 24.64
Outside wall 1 24.20 1.60 38.72
Total 77.76 m2

10 3mm thick cement punning(1:1) same qnty as plastered work 77.76


Total 77.76 m2
11 Manhole cover 600mm dia. 1 1.00 No.
12 Installation of pipes and fittings 1 1.00 Job
QUANTITY ANALYSIS
Sump Well (20m3)
sfo{s|d M—vfg]kflg tyf ;/;kmfO{
cfof]hgfsf] gfd M—9'ª\u|] vf]nf vfg]kflg of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M—dfyfu9L,^ uf]7fbL
lelq 4.5 3.5 1.5
SN Item NO Length Breadth Height Quantity Remarks
1 Site clearance work 1 10.00 8.00 80.00 m2
2 E/W excavation in B.M. Soil
Foundation 1 6.70 5.70 0.70 26.73
Total 26.73 m3
3 Boulder soling without sand packing
Foundation 1 6.70 5.70 0.15 5.73
Total 5.73 m3
4 P.C.C. Work(1:2:4)
Foundation 1 6.70 5.70 0.12 4.58
Total 4.58 m3
5 R/R masonary in 1:4 C/S mortar
Trapezoidal portion 1 18.70 0.68 1.50 18.93
18.93 m3
6 R.C.C. Work(1:2:4)
slab 1 5.40 4.40 0.10 2.38
Total 2.38 m3
7 Reinforcement work
10mm dia. Bar
main bar 35 4 140.00
distribution bar 28 5.1 142.80
282.80 Rm
@ 0.62 kg/m 175.34 Kg
8 Form work for P C C:
RCC slab 1 4.50 3.50 15.75
Edge of slab 1 19.60 0.10 1.96
Foundation pcc 1 24.80 0.12 2.98
20.69 m2
9 20 mm thick cement plaster 1:4
Inside floor portion 1 4.50 3.50 15.75
wall portion 1 16.00 1.50 24.00
Outside wall 1 24.80 1.50 37.20
Total 76.95 m2

10 3mm thick cement punning(1:1) same qnty as plastered work 76.95


Total 76.95 m2
11 Manhole cover 600mm dia. 1 1.00 No.
12 Installation of pipes and fittings 1 1.00 Job
QUANTITY ANALYSIS
Sump Well (10m3)
sfo{s|d M—vfg]kflg tyf ;/;kmfO{
cfof]hgfsf] gfd M—a;Gtk'/ lnkm\6 vfg]kflg of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M—ltgfp,# a;Gtk'/
lelq 4 2 1.5
SN Item NO Length Breadth Height Quantity Remarks
1 Site clearance work 1 10.00 8.00 80.00 m2
2 E/W excavation in B.M. Soil
Foundation 1 6.20 4.20 0.70 18.23
Total 18.23 m3
3 Boulder soling without sand packing
Foundation 1 6.20 4.20 0.15 3.91
Total 3.91 m3
4 P.C.C. Work(1:2:4)
Foundation 1 6.20 4.20 0.12 3.12
Total 3.12 m3
5 R/R masonary in 1:4 C/S mortar
Trapezoidal portion 1 14.70 0.68 1.50 14.88
14.88 m3
6 R.C.C. Work(1:2:4)
slab 1 4.90 2.90 0.10 1.42
Total 1.42 m3
7 Reinforcement work
10mm dia. Bar
main bar 35 4 140.00
distribution bar 28 5.1 142.80
282.80 Rm
@ 0.62 kg/m 175.34 Kg
8 Form work for P C C:
RCC slab 1 4.00 2.00 8.00
Edge of slab 1 15.60 0.10 1.56
Foundation pcc 1 20.80 0.12 2.50
12.06 m2
9 20 mm thick cement plaster 1:4
Inside floor portion 1 4.00 2.00 8.00
wall portion 1 12.00 1.50 18.00
Outside wall 1 20.80 1.50 31.20
Total 57.20 m2

10 3mm thick cement punning(1:1) same qnty as plastered work 57.20


Total 57.20 m2
11 Manhole cover 600mm dia. 1 1.00 No.
12 Installation of pipes and fittings 1 1.00 Job
QUANTITY ANALYSIS
Pump control room (int. size 2.2m*2.05m), ht:-2.15m
in Size 2.20 2.05 2.15 0.40
SN Description NO Length Breadth Height Quantity Remarks
1 Site clearance work 1 5.00 4.00 20.00 m2

2 E/W excavation in B.M. Soil h=(1.25+1.05)/2


wall 1 10.10 0.60 0.60 3.64
Total 3.64 m3
3 Boulder soling without sand packing
Foundation 1 10.10 0.60 0.15 0.91
Total 0.91 m3
4 P.C.C. Work(1:2:4)
Foundation 1 10.10 0.60 0.10 0.61
DPC 1 10.10 0.45 0.075 0.34
Total 0.95 m3
5 R/R masonary in 1:4 C/S mortar
1st step 1 10.10 0.60 0.25 1.52
2nd step 1 10.10 0.45 0.20 0.91
above GL 1 10.10 0.40 2.15 8.69
Deduction, Door 1 0.90 0.40 1.85 -0.67
w1 1 0.90 0.40 1.20 -0.43
Total 10.01 m3
6 Sal wood work for choukosh
Door 1 4.60 0.10 0.075 0.03
Window 1 5.40 0.10 0.075 0.04
Total 0.08 m3
7 Sal wood work for panel shutter
Door 1 0.80 1.80 1.44
Window 1 0.75 1.10 0.83
Total 2.27 m2
8 Steel
Main bar 25 3.55 0.62 54.78 10mm
Distribution bar 22 4.00 0.62 54.32 10mm
Total 109.10 kg
9 Rcc
1 4.00 3.55 0.10 1.42
Total 1.42 m3
10 Flooring work/Plastering work
a. Stone soling 1 2.20 2.05 0.15 0.33 m3

b. PCC(1:2:4) 1 2.20 2.05 0.10 0.45


Total 0.45 m3

c. 20 mm thick cement plaster 1:4


floor/celling 2 2.20 2.05 9.02
Inside wall 1 8.50 2.15 18.28
Outside wall 1 11.70 2.15 25.16
Deduction, Door 1 0.90 1.85 -1.67
w1 1 0.90 1.20 -1.08
Total 49.71 m2
d. 3mm cement punning
floor 1 2.20 2.05 4.51
Total 4.51 m2
11 Two coat snowcem painting
same qnty as item no.10© 49.71 m2
12 Two coat enamel painting work
Door(1*2.25) 2.25 0.90 1.85 3.75
Window,w(1*2.25) 2.25 0.90 1.20 2.43
Total 6.18 m2
13 Form work for RCC
Inside pannel 1 2.20 2.05 4.51
Chhaja 2 4.00 0.45 3.60
Chhaja 2 2.85 0.45 2.57
Side bar 1 15.10 0.10 1.51
QUANTITY ANALYSIS
Pump control room (int. size 2.2m*2.05m), ht:-2.15m
in Size 2.20 2.05 2.15 0.40
SN Description NO Length Breadth Height Quantity Remarks
Total 12.19 m2
Entrance Gate
For barbed wire fencing Type-A
S.N. Description No. Length Breadth Height Quantity Unit
1 Earthwork in excavation for foundation work in hard soil
2 0.40 0.40 0.60 0.19 m³
2 Dry stone soling 2 0.40 0.40 0.15 0.05 m³
3 Stone masonry in 1:6 c-s mortar for support pillars
In foundation 2 0.40 0.40 0.45 0.14
Above Ground 2 0.40 0.40 1.60 0.51
Deduct for holdfast PCC blocks 3 0.40 0.40 0.20 -0.10
Total 0.55 m³
4 Plain Cement Concrete (1:2:4)
for holdfast blocks 3 0.40 0.40 0.20 0.10
on top of pillar 2 0.40 0.40 0.10 0.03
Total 0.13 m³
5 12.5 mm thick 1:4 c - s plaster
-Pillars 8 0.40 - 1.60 5.12
-On top 2 0.40 0.40 - 0.32
Total 5.44 m²
6 Mild steel angle (ISA 25×25×3) framed gate with iron grill shutter (0.95 x 1.00 no
1.5 m size) all complete including fixing
Two (primary, first & second)coats of
7 readymade enamel painting work 1 0.95 - 1.50 1.43 m²
Sub Total

Barbed Wire Fencing ( Type - A)


Total length of fencing = 24 m
S.N. Description No. Length Breadth Height Quantity Unit
1 Earthwork in excavation for foundation work in hard soil
17 0.35 0.35 0.60 1.25 m³
2 Plain Cement Concrete (1:2:4)
For anchoring blocks 17 0.35 0.35 0.60 1.25 m³
3 MS angle post(ISA 40×40×6 - 2.1 17 2.10 @ 3.50 kg/m 124.95 kg
4 Barbed wire fencing
- horizontal ( 7 layers) 7 12.00 84.00
- Diagonals 32 1.82 58.23
Total 142.23 m
5 Two (primary, first &
second)coats of readymade
enamel painting work
17 1.50 0.16 4.08 m²
Sub Total
Total
S.N. Description No. Length Breadth Height Quantity Unit Remarks

Earthwork Excavation for pipe line trench for


1 different types of soil by Manually 1 4700.00 0.4 0.6 1128 m³
Earthwork excavation in Hard soil for Roadway &
i Drain for hard soil @ 75 % 846 m³
Earthwork excavation in Roadway & Drain for hard
ii soil @ 22 % 248.16 m³
Earthwork excavation for structures for Roadway
iii & Drain for Ordinary rock @ 3 % 33.84 m³
2 Earth Filling Work 1 4700.00 0.4 0.6 1128 m³

Prepared By Checked By Approved By


augf;sfnL ufpFkfnLsf
ufpFsfo{kfnLsfsf] sfof{no
lrt'{Ëwf/f,kfNkf
% g+=k|b]z g]kfn
nfut cg'''dfdg kmf/d
sfo{s|d M— ;fdflhs ljsf; If]q
cfof]hgfsf] gfd M—nfDbL lzv/8f8f 5]n'Ëf lnlˆ6ª vfg]kfgL of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M— augf;sfnL–^,kfNkf
Pipe Procurement

S.N. Description of item Length Rate Amount


Remarks

1 400 336.29 134516


HDPE Pipe(63mm) - 10 kgf/cm2

2 300 225.25 67575


HDPE Pipe(63mm) - 6 kgf/cm2
3 HDPE Pipe(50mm) - 10 kgf/cm2 3200 210.94 675008 9950

HDPE Pipe(40mm) - 10 kgf/cm2 2300

HDPE Pipe(40mm) - 10 kgf/cm2 1800


Sub Total 877099.00
Add VAT @ 13% of Total 114022.87
Total 991121.87
Grand Total 991121.87

Prepared By Checked By Approved By


`

Prepared By Checked By Approved By


SN Description Unit Count Rate Amount (Rs)
1 Adjustable Spanner 12" no 1 300 300
2 File-half round 10" no 2 200 400
3 Hacksaw Blade no 10 20 200
4 Hacksaw Frame no 2 100 200
5 Heating Plate (100 mm dia.) no 1 650 650
6 Heating Plate (150 mm dia.) no 1 900 900
7 Pipe Wrench 12" no 2 350 700
8 Pipe Wrench 18" no 2 700 1400
augf;sfnL ufpFkfnLsf
ufpFsfo{kfnLsfsf] sfof{no
lrt'{Ëwf/f,kfNkf
% g+=k|b]z g]kfn
b/ ljZn]if0f

sfo{s|d M— ;fdflhs ljsf; If]q


cfof]hgfsf] gfd M— arfª\b]—/]n]—l6Dn] vfg]kfgL of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M— augf;sfnL–^,kfNkf
cfg'bfg /sd M— !))))))=))
v'b e'StfgL /sd M— (&))))=))

A. Labour District Rate

Skilled labour =Rs 800


Unskilled labour =Rs 600
Plumber =Rs 800
Helper (Asistant plumber) =Rs 600
Carpenter =Rs 800
Painter =Rs 800
Rate including
B. Material District Rate
transportation
1) Cement per bag (Ppc) =Rs 664.00 773.48
2) Sand per M³ 1 1=District rate

2= Collection and
Sand 3300.00 3300.00 transportation
Quarrying capacity 4 1 < 30% 3=district rate +trans.
2 31 to 50 %
3 51 to 65 %
4 >65 %
3) Stone m3 1 1=stone from collection
Block stone/bond stone 2,109.23 2190.88 2= stone from excavation
5) M.S. bar 8 mm ø to 12 mm ø per kg. =Rs 77.00 88.21
6) 10 mm ø per kg =Rs 77.00
7) Binding wire per kg. =Rs 95.00 108.32
8) Barbed wire per kg =Rs 100.00 114.20
9) M.S. Angle per kg. =Rs 82.00 93.86
10) Plain wire per kg 8-10 gauge per kg =Rs 96.00 109.45
11) Local wood per m³ =Rs 42,000.00 42000.00
12) Snowcem paint per kg. =Rs 55.00 63.12
13) Nail per kg. =Rs 100.00 114.20
14) Enamel paint per lit. =Rs 500.00 565.97
15) Primer per lit. =Rs 310.00 351.27
16) Almunium paint =Rs 525.00 594.22
17) Polythene sheet per sqm =Rs -
18) Aggregate 3 1= District rate
2= District rate
i)5 - 10 mm size per m3 =Rs 1,650.00 7552.45 +portering 7552.45
3= River bed
material with
ii) 10 - 20 mm size per m³ =Rs 1,650.00 5080.45 transportation 5080.45
4=crushed stone
iii) 20 -40 mm size per m³ =Rs 1,650.00 3952.45 with transportation 3952.45
17) Mud per m 3
=Rs 300.00
18) Brick per no. =Rs 15.75 2 15.75 1=District rate
2=District rate +
transportation
3=Factory rate +
transportation
21) Sal wood Rate/ m3 =Rs 168,000.00
22) Bamboo / no =Rs 200.00
23) Chicken wire (90 cm wide) 3
20 gauge /m 2
=Rs 190.00 214.94 1 = 20 gauge
22 gauge /m 2
=Rs 190.00 2 = 22 gauge
24 gauge /m 2
=Rs 190.00 3 = 24 gauge
24) Screw No =Rs 1.00
25) Holdfast No =Rs 25.00
25) Bitumin Paint / kg =Rs 74.10 84.70
26) Drilling holes / no =Rs 2.00
27) Manhole cover ,60cm dia /set =Rs 2,000.00
28) Iron grill gate /sqm =Rs -
29) CGI sheet 28 gauge /bundle =Rs -
30) GI Plain Sheet 28 gauge /sqm =Rs -
Kerosene ltr =Rs 90.00
MS Grill kg =Rs 120.00
C. Transportation
Transportation of materials
1 by vehicle in pitch road
(Truck) per quintal
per km
a Easy goods =Rs 2.20
per quintal
per km
b Uneasy goods =Rs 2.90

Transportation of materials
2 by vehicle in earthen road
(Truck) per quintal
per km
a Easy goods =Rs 3.10
per quintal
per km
b Uneasy goods =Rs 3.70

Transportation of materials
3 by vehicle in earthen road
(Tractor) per quintal
per km
a Easy goods =Rs 3.40
per quintal
per km
b Uneasy goods =Rs 4.10
4 Transportation by porter per quintal
per km 105.66=3.4/3
a Easy goods =Rs 105.66
per quintal .218*100
per km 133.62=4.3/3
b Uneasy goods =Rs 133.62
.218*100

D. Cost of local material at site


1 STONE per m3 Density = 2200.00 Kg/m3
Collection, tranportation and
a.
potering Lead (vehicle) = 2.50 Km
Lead (Porter) = 0.50 Km
Unskilled labour
Collection 1.40 md 600 840.00
Transportation (Portering) 2.12 md 600 1269.23
(Porter can carry 40kg load
Through 13 km per day.) 2109.23 per m3
Production by breaking,
b. collection, transportation and
portering
Unskilled labour
Breaking stone using
5.50 md 600.00 3300.00
3.11 chiesel and hammer
Transportation (vehicle) 22.00 Quintal 187.00
Transportation (Portering) 2.12 md 600 1269.23
4756.23 per m3

2 AGGREGATE per m3 Density = 1600.00 Kg/m3


Lead (vehicle)
Pitch (Truck) = 0.00 Km
Earthen (Truck) = Km
Earthen (Tractor) = 13.00 Km
Lead (Porter) = 0.50 Km

Transportation
District rate Tractor
Aggregate size /Production
Truck (Pitch) Truck (Earthen)
(Earthen) Porter Total
1 5 mm to 10 mm size
District rate 1650.00 0.00 0.00 707.20 845.25 3202.45
3.2.ka River bed material (10 md) 6000.00 0.00 0.00 707.20 845.25 7552.45
Crushed stone (21.5md) 12900.00 0.00 0.00 707.20 845.25 14452.45
2 10mm to 20 mm size
District rate 1650.00 0.00 0.00 707.20 845.25 3202.45
3.2.kha River bed material (5.88 md 3528.00 0.00 0.00 707.20 845.25 5080.45
Crushed stone (15 md) 9000.00 0.00 0.00 707.20 845.25 10552.45
3 20 mm 40 mm size
District rate 1650.00 0.00 0.00 707.20 845.25 3202.45
3.2.ga River bed material (4 md) 2400.00 0.00 0.00 707.20 845.25 3952.45
Crushed stone (9md) 5400.00 0.00 0.00 707.20 845.25 6952.45

3 Sand per m3 Easy


District rate 1600.00
Density 1600.00 Kg/m3
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 707.20
Porter 845.25
3152.45 per m3
3152.45 per m3
E. Transportation distance for non local material
per Bag Lead (vehicle)
Pitch (Truck) = 0.00 Km
Earthen (Truck) = 0.00 Km
Earthen (Tractor) = 13.00 Km
Lead (Porter) = 0.50 Km

4 CEMENT Easy
District rate 664.0
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 22.10
Porter 1.06
Sub-Total 687.16
13% VAT 86.32
773.48
MS BARS 8 MM to 12
5 per Kg
MM DIA. Uneasy
District rate 77.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.53
Porter 0.67
Sub-Total 78.20
13% VAT 10.01
88.21

6 BINDING WIRE per Kg Easy


District rate 95.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.44
Porter 0.53
Sub-Total 95.97
13% VAT 12.35
108.32

1 BARBED WIRE per Kg Uneasy


District rate 100.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.53
Porter 0.67
Sub-Total 101.20
13% VAT 13.00
114.20
2 M S ANGLE per Kg Uneasy
District rate 82.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.53
Porter 0.67
Sub-Total 83.20
13% VAT 10.66
93.86

9 PLAIN WIRE per Kg Easy


District rate 96.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.44
Porter 0.53
Sub-Total 96.97
13% VAT 12.48
109.45
CHICKEN WIRE (90
3 cm) m2 Transportation
(Choose appropriate no for gauge 1=20 gauge 2=22 gauge 3=24 gauge
selection)
Tractor
District rate Truck (Pitch) Truck (Earthen) Porter Total (Rs.)
District rate (Earthen) vat 13%
20 gauge 190.00 0.00 0.00 0.14 0.17 24.70 215.01 Density=0.26/
22 gauge 190.00 0.00 0.00 0.12 0.15 24.70 214.98 Density=0.23/
24 gauge 190.00 0.00 0.00 0.11 0.13 24.70 214.94 Density=0.20/

12 LOCAL WOOD per m3


District rate 42000.00

13 SNOWCEM PAINT per Kg Easy


District rate 55.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.44
Porter 0.53
Sub-Total 55.97
13% VAT 7.15
63.12

14 NAILS
District rate 100.00 Uneasy
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.53
Porter 0.67
Sub-Total 101.20
13% VAT 13.00
114.20
15 ENAMEL PAINT Per L Easy
District rate 500.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.44
Porter 0.53
Sub-Total 500.97
13% VAT 65.00
565.97
16 Primer per lit. Per L Easy
District rate 310.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.44
Porter 0.53
Sub-Total 310.97
13% VAT 40.30
351.27
17 Almunium paint Per L Easy
District rate 525.00
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.44
Porter 0.53
Sub-Total 525.97
13% VAT 68.25
594.22
18 BITUMIN PAINT Per L Easy
District rate 74.10
Transportation
Truck (pitch) 0.00
Truck (Earthen) 0.00
Tractor 0.44
Porter 0.53
Sub-Total 75.07
13% VAT 9.63
84.70
Easy
17 BRICK per No. Density = 1800.00 Kg/m3
Lead (vehicle)
Pitch (Truck) = 0.00 Km
Earthen (Truck) = 0.00 Km
Earthen (Tractor) = 0.00 Km
Lead (Porter) = 0.00 Km
Transportation
District rate Tractor
Truck (Pitch) Truck (Earthen)
Brick /Factory rate (Earthen) Porter Total
District rate 15.75 0.00 0.00 0.00 0.00 15.75
Factory rate 0 0.00 0.00 0.00 0.00 Error
(Don,t fortet to enter factory rate if applicable)

1. E./W in excavation in gravel and boulder mixed soil for 1 m³ Norms S.N. 2_14

Unskilled labour 1.59 Nos. @ Rs. 600.00 per No/day = Rs. 954.00
T & P 3% of labour cost 28.62
982.62
Total = Rs. 982.62
Earthwork/ Sand work
Earthwork in excavation in soft clay and silt (1.5m lift & 10m lead)
Analyzed for: 1 m³ Norms S.N. 2-1

Res
ourc Level / Type Quantity Unit Rate per unit Amount Remarks
es

Labours Unskilled 0.7 no. 300.00 210.00


Tools & equipments @ 3% of total labour cost 6.30
Grand-Total 216.30
2. Back filling in trench in gravel mixed soil 1 m³

Unskilled labour 0.60 Nos. @ Rs. 600.00 per No/day = Rs. 360.00
T & P 3% of labour cost 10.80
370.80
Total = Rs. 370.80

3. E./W in excavation in hard soil for 1 m³


Unskilled labour 1.25 Nos. @ Rs. 600.00 per No/day = Rs. 750.00
T & P 3% of labour cost 22.50
772.50
Total = Rs. 772.50
4. E./W in excavation in soft soil for 1 m³
Unskilled labour 1 Nos. @ Rs. 600.00 per No/day = Rs. 600.00
T & P 3% of labour cost 18.00
618.00
Total = Rs. 618.00
5. E./W Refilling in trench in hard soil 1 m³

Unskilled labour 0.63 Nos. @ Rs. 600.00 per No/day = Rs. 378.00
T & P 3% of labour cost 11.34
389.34
Total = Rs. 389.34
6. E/W Refilling in trench in soft soil 1 m³

Unskilled labour 0.50 Nos. @ Rs. 600.00 per No/day = Rs. 300.00
T & P 3% of labour cost 9.00
309.00
Total = Rs. 309.00
7 E/W Refilling in trench in soft Rock 1 m³

Unskilled labour 1.10 Nos. @ Rs. 600.00 per No/day = Rs. 660.00
T & P 3% of labour cost 19.80
679.80
Total = Rs. 679.80
8. E./W in excavation in Soft rock for 1 m³
Unskilled labour 3 Nos. @ Rs. 600.00 per No/day = Rs. 1800.00
T & P 3% of labour cost 54.00
1854.00
Total = Rs. 1854.00

9. Boulder soling in foundation with sand packing per m³


Sand 0.71 M³ @ Rs. 3300.00 per m³ =Rs 2343.00
Unskilled labour 1.50 Nos. @ Rs. 600.00 per No/day = Rs. 900.00
Block Stone 1.00 M³ @ Rs. 2190.88 per m³ = Rs. 2190.88
Bond Stone 0.20 M³ @ Rs. 2190.88 per m³ = Rs. 438.18
Total = Rs. 5872.05
Total = Rs. 5872.05

10. Stone soling in foundation without sand packing per m³ Norms S.N. dob/6.5
Unskilled labour 1.50 Nos. @ Rs. 600.00 per No/day = Rs. 900.00
Block Stone 1.00 M³ @ Rs. 2190.88 per m³ = Rs. 2190.88
Bond Stone 0.10 M³ @ Rs. 2190.88 per m³ = Rs. 219.09
Total = Rs. 3309.96
Total = Rs. 3309.96

11. R/R Masonary in (1:6) C.S. mortar per m³


Norms S.N. dob/38.d
Cement 1.84 bag. @ Rs. 773.48 per bag = Rs. 1423.20
Sand 0.50 M³ @ Rs. 3300.00 per m³ = Rs. 1650.00
Block Stone 1.00 M³ @ Rs. 2190.88 per m³ = Rs. 2190.88
Bond Stone 0.10 M³ @ Rs. 2190.88 per m³ = Rs. 219.09
Skilled labour 1.50 nos. @ Rs. 800.00 per no. = Rs. 1200.00
Unskilled labour 3.29 nos. @ Rs. 600.00 per no. = Rs. 1974.00
Total = Rs. 8657.16
Total = Rs. 8657.16

12. R/R Masonary work in (1:4) mortar for 1 m³ Norms S.N. dol/38.c
Cement 2.32 bag. @ Rs. 773.48 per bag = Rs. 1794.47
Sand 0.47 M³ @ Rs. 3300.00 per m³ = Rs. 1551.00
Block Stone 1.00 M³ @ Rs. 2190.88 per m³ = Rs. 2190.88
Bond Stone 0.10 M³ @ Rs. 2190.88 per m³ = Rs. 219.09
Skilled labour 1.50 nos. @ Rs. 800.00 per no. = Rs. 1200.00
Unskilled labour 3.24 nos. @ Rs. 600.00 per no. = Rs. 1944.00
Total = Rs. 8899.43
Total = Rs. 8899.43

13. Dry stone wall for 1 m³ Norms S.N. 6-2-1


Skilled labour 1.00 nos. @ Rs. 800.00 per nos. = Rs. 800.00
Unskilled labour 2.00 nos. @ Rs. 600.00 per nos. = Rs. 1200.00
Block Stone 1.00 M³ @ Rs. 2190.88 per m³ = Rs. 2190.88
Bond Stone 0.10 M³ @ Rs. 2190.88 per m³ = Rs. 219.09
Total = Rs. 4409.96
Total = Rs. 4409.96

14.Brick work in (1:4)c/s mortar for 1 m³


Cement 2.00 bag @ Rs. 773.48 per bag = Rs. 1546.95
Brick 560.00 Nos @ Rs. 15.75 per Nos = Rs. 8820.00
Sand 0.28 M³ @ Rs. 3300.00 per m³ = Rs. 924.00
Skilled labour 1.50 nos. @ Rs. 800.00 per nos. = Rs. 1200.00
Unskilled labour 4.20 nos. @ Rs. 600.00 per nos. = Rs. 2520.00
Total = Rs. 15010.95
Total = Rs. 15010.95

15. P.C.C. (1:2:4) in foundation,wall etc. 1 m³


Norms S.N. dol/41.b
Cement 6.40 bag @ Rs. 773.48 per bag = Rs. 4950.25
Sand 0.440 M³ @ Rs. 3300.00 per m³ = Rs. 1452.00
Aggregate
40 mm ø 0.52 M³ @ Rs. 3202.45 per m³ = Rs. 1665.27
20 mm ø 0.22 M³ @ Rs. 3202.45 per m³ = Rs. 704.54
10 mm ø 0.11 M³ @ Rs. 3202.45 per m³ = Rs. 352.27
Skilled labour 1.00 nos. @ Rs. 800.00 per nos. = Rs. 800.00
Unskilled labour 4.06 nos. @ Rs. 600.00 per nos. = Rs. 2436.00
Total = Rs. 12360.33
Total = Rs. 12360.33

16. P.C.C. (1:2:4) for R.C.C. work beam, slab etc for 1 m³

Cement 6.40 bag @ Rs. 773.48 per bag. = Rs. 4950.25


Sand 0.445 M³ @ Rs. 3300.00 per m³ = Rs. 1468.50
Aggregate
40 mm ø 0.52 M³ @ Rs. 3952.45 per m³ = Rs. 2055.27
20 mm ø 0.22 M³ @ Rs. 5080.45 per m³ = Rs. 1117.70
10 mm ø 0.11 M³ @ Rs. 7552.45 per m³ = Rs. 830.77
Skilled labour 0.80 nos. @ Rs. 800.00 per nos. = Rs. 640.00
Unskilled labour 7.00 nos. @ Rs. 600.00 per nos. = Rs. 4200.00
Total = Rs. 15262.49
Total = Rs. 15262.49

17. P.C.C. (1:1½:3) in foundation for 1 m³ Norms S.N. dol/41.B.b


Cement 8.00 bag @ Rs. 773.48 per bag = Rs. 6187.81
Sand 0.420 M³ @ Rs. 3300.00 per m³ = Rs. 1386.00
Aggregate
20 mm ø 0.57 M³ @ Rs. 5080.45 per m³ = Rs. 2895.85
10 mm ø 0.29 M³ @ Rs. 7552.45 per m³ = Rs. 2190.21
Skilled labour 1.00 nos. @ Rs. 800.00 per nos. = Rs. 800.00
Unskilled labour 5.12 nos. @ Rs. 600.00 per nos. = Rs. 3072.00
Total = Rs. 16531.88
Total = Rs. 16531.88

18. P.C.C. (1:3:6) for foundation for 1 m³


Cement 4.40 bag @ Rs. 773.48 per bag = Rs. 3403.30
Sand 0.470 M³ @ Rs. 3300.00 per m³ = Rs. 1551.00
Aggregate
40 mm ø 0.65 M³ @ Rs. 3952.45 per m³ = Rs. 2569.09
20 mm ø 0.24 M³ @ Rs. 5080.45 per m³ = Rs. 1219.31
Skilled labour 1.00 nos. @ Rs. 800.00 per nos. = Rs. 800.00
Unskilled labour 4.00 nos. @ Rs. 600.00 per nos. = Rs. 2400.00
Total = Rs. 11942.69
Total = Rs. 11942.69

19. 12.5 mm thick (1:2) cement plaster for 100 m² Norms S.N. dol/41.B.b
Cement 18.00 bag @ Rs. 773.48 per bag = Rs. 13922.58
Sand 1.220 M³ @ Rs. 3300.00 per m³ = Rs. 4026.00
Skilled labour 12.00 nos. @ Rs. 800.00 per nos. = Rs. 9600.00
Unskilled labour 16.00 nos. @ Rs. 600.00 per nos. = Rs. 9600.00
Total = Rs. 37148.58
Total = Rs. 37148.58
Rate per m2 371.49

20 12.5 mm thick (1:3) cement plaster for 100 m²


Norms S.N. dob/12.1.kha
Cement 12.50 bag @ Rs. 773.48 per bag = Rs. 9668.46
Sand 1.280 M³ @ Rs. 3300.00 per m³ = Rs. 4224.00
Skilled labour 12.00 nos. @ Rs. 800.00 per nos. = Rs. 9600.00
Unskilled labour 16.00 nos. @ Rs. 600.00 per nos. = Rs. 9600.00
Total = Rs. 33092.46
Total = Rs. 33092.46
Rate per m2 330.92

21) 12.5 mm thick (1:4) cement plaster for 100 m² Norms S.N. dol/37.B.c

Cement 7.26 bag @ Rs. 773.48 per bag = Rs. 5615.44


Sand 1.46 M³ @ Rs. 3300.00 per m³ = Rs. 4818.00
Skilled labour 12.00 nos. @ Rs. 800.00 per nos. = Rs. 9600.00
Unskilled labour 11.59 nos. @ Rs. 600.00 per nos. = Rs. 6954.00
Total = Rs. 26987.44
Total = Rs. 26987.44
Rate per m2 269.87

22) 12.5 mm thick (1:6) cement plaster for 100 m²

Cement 7.64 bag @ Rs. 773.48 per bag = Rs. 5909.36


Sand 1.570 M³ @ Rs. 3300.00 per m³ = Rs. 5181.00
Skilled labour 12.00 nos. @ Rs. 800.00 per nos. = Rs. 9600.00
Unskilled labour 16.00 nos. @ Rs. 600.00 per nos. = Rs. 9600.00
Total = Rs. 30290.36
Total = Rs. 30290.36
Rate per m2 302.90

23) 20 mm thick (1:4) cement plaster for 100 m²


Norms S.N. dob/12.4.kha
Cement 16.20 bag @ Rs. 773.48 per bag = Rs. 12530.32
Sand 2.20 M³ @ Rs. 3300.00 per m³ = Rs. 7260.00
Skilled labour 14.00 nos. @ Rs. 800.00 per nos. = Rs. 11200.00
Unskilled labour 19.00 nos. @ Rs. 600.00 per nos. = Rs. 11400.00
Total = Rs. 42390.32
Total = Rs. 42390.32
Rate per m2 423.90

24) 20 mm thick (1:6) cement plaster for 100 m²


Cement 11.40 bag @ Rs. 773.48 per bag = Rs. 8817.63
Sand 2.35 M³ @ Rs. 3300.00 per m³ = Rs. 7755.00
Skilled labour 14.00 nos. @ Rs. 800.00 per nos. = Rs. 11200.00
Unskilled labour 19.00 nos. @ Rs. 600.00 per nos. = Rs. 11400.00
Total = Rs. 39172.63
Total = Rs. 39172.63
391.73
25) 3 mm thick cement punning for 1 m² Norms S.N. dor/11.20
Cement 0.11 Bag @ Rs. 773.48 = Rs. 82.41
Skilled labour 0.10 nos. @ Rs. 800.00 per nos. = Rs. 80.00
Unskilled labour 0.10 nos. @ Rs. 600.00 per nos. = Rs. 60.00
Total = Rs. 222.41
Total = Rs. 222.41

26) Cement pointing on stone wall in 1:3 cement mortar for 100 m²

Cement 6.12 bag @ Rs. 773.48 per bag = Rs. 4733.68


Sand 0.63 M³ @ Rs. 3300.00 per m³ = Rs. 2079.00
Skilled labour 10.00 nos. @ Rs. 800.00 per nos. = Rs. 8000.00
Unskilled labour 14.00 nos. @ Rs. 600.00 per nos. = Rs. 8400.00
Total = Rs. 23212.68
Total = Rs. 23212.68
Rate per m2 232.13

27) 3 mm thick cement sand punning (1:1) for 100 m²

Cement 6.72 bag @ Rs. 773.48 per bag = Rs. 5197.76


Sand 0.23 M³ @ Rs. 3300.00 per m³ = Rs. 759.00
Skilled labour 10.00 nos. @ Rs. 800.00 per nos. = Rs. 8000.00
Unskilled labour 10.00 nos. @ Rs. 600.00 per nos. = Rs. 6000.00
Total = Rs. 19956.76
Total = Rs. 19956.76
Rate per m2 199.57

28) M.S. bar binding, binding for R.C.C. for 1.00 M.T. Norms S.N. dol/40
M.S. bar 1.05 M.T.@ Rs. 88211.1 per m.t. = Rs. 92621.67
Binding wire 10.00 kg @ Rs. 108.32 per kg = Rs. 1083.20
Skilled labour 7.00 nos. @ Rs. 800.00 per nos. = Rs. 5600.00
Unskilled labour 7.00 nos. @ Rs. 600.00 per nos. = Rs. 4200.00
Total = Rs. 103504.88
Total = Rs. 103504.88
Rate per kg 103.50

29) Form work for R.C.C. slab for 1.00 m² Norms S.N. dol/39.A
Local wood 0.0104 M³ @ Rs. 42000.00 per m³ x0.75/ = Rs. 54.60 0.0104 0
Nails 0.35 kg @ Rs. 114.20 per kg = Rs. 39.97
Carpenter 0.150 nos. @ Rs. 800.00 per nos. = Rs. 120.00
Unskilled labour 0.20 nos. @ Rs. 600.00 per nos. = Rs. 120.00
Total = Rs. 334.57
Total = Rs. 334.57

1) Form work for Ferrocement tank for 1.00 m²


Bamboo 0.3330 nos. @ Rs. 200.00 per nos. = Rs. 66.60
Nails 0.014 kg @ Rs. 114.20 per kg = Rs. 1.60
Binding wire 0.083 kg @ Rs. 108.32 per kg = Rs. 8.99
Carpenter 0.167 nos. @ Rs. 800.00 per nos. = Rs. 133.60
Unskilled labour 0.111 nos. @ Rs. 600.00 per nos. = Rs. 66.60
HDPE pipe 32 mm 6 kg/cm² (4 coils for 100m 2 ) to be used from stock
Total = Rs. 277.39
Total = Rs. 277.39
2) Steel bar binding for Ferrocement work for 1.00 m²
Binding wire 0.111 kg @ Rs. 108.32 per kg = Rs. 12.02
Steelbar 8 & 10 mm ø 2.593 kg @ Rs. 88.21 per kg = Rs. 228.73
Chicken wire 90 cm wide 1.806 m2 @ Rs. 214.94 per m = Rs. 388.18
Plain wire 3.5 mm ø 2.083 kg @ Rs. 109.45 per kg = Rs. 227.98
Skilled labour 0.25 nos. @ Rs. 800.00 per nos. = Rs. 200.00
Unskilled labour 0.083 nos. @ Rs. 600.00 per nos. = Rs. 49.80
Total = Rs. 1106.72
Total = Rs. 1106.72

3) Bitumen paint two coats work for 1.00 m² Norms S.N. dob/13.4 kha
Bitumen paint 0.12 kg @ Rs. 84.70 per kg = Rs. 10.16
Painter 0.05 nos. @ Rs. 800.00 per nos. = Rs. 40.00
Unskilled labour 0.05 nos. @ Rs. 600.00 per nos. = Rs. 30.00
Total = Rs. 80.16
Total = Rs. 80.16

33) Snowcem painting first and 2nd coat for 1.00 m² Norms S.N. dob/13.4 kha
Snowcem paint 0.05 kg @ Rs. 63.12 per kg = Rs. 3.06
Painter 0.050 nos. @ Rs. 800.00 per nos. = Rs. 40.00
Unskilled labour 0.050 nos. @ Rs. 600.00 per nos. = Rs. 30.00
Total = Rs. 73.06
Total = Rs. 73.06

34) Enamel painting 2 coats for 1.00 m² dob/13.5.ka+kha+ga


Primer 0.08 lit @ Rs. 351.27 per lit = Rs. 28.45
Enamel paint 0.16 lit @ Rs. 565.97 per lit = Rs. 90.56
Painter 0.120 nos. @ Rs. 800.00 per nos. = Rs. 96.00
Unskilled labour 0.080 nos. @ Rs. 600.00 per nos. = Rs. 48.00
Total = Rs. 263.01
Total = Rs. 263.01

35) GI barbed wire for fencing work (Assume1m=0.12kg) for 100 m dob/24.6
Barbed wire 110.00 Rm 13.70 per m = Rs. 1507.45
U-hook 0.16 LS 0.00 per no = Rs. 0.00
Skilled 1.076 nos. @ Rs. 800.00 per nos. = Rs. 860.80
Unskilled 5.38 nos. @ Rs. 600.00 per nos. = Rs. 3228.00
Total = Rs. 5596.25
Total = Rs. 5596.25
Rate per m 55.96

35) Site clearence for 1.00 m²

Unskilled labour 0.16 nos. @ Rs. 600.00 per nos. = Rs. 96.00
Total = Rs. 96.00
Total = Rs. 96.00

36 Gabion work (3*1*1) m3 mesh size (80*100) m2 hexagonal with all complete
Skilled labour 0.63 nos. @ Rs. 800.00 per nos. = Rs. 504
Unskilled labour 1.38 nos. @ Rs. 600.00 per nos. = Rs. 828
G.I. Wire 35.1 kg @ Rs. 52.50 per kg = Rs. 1842.75
SelvEge wire 4.1 kg @ Rs. 52.50 per kg = Rs. 215.25
Binding wire 1.6 kg @ Rs. 52.50 per kg = Rs. 84
Stone 3.3 M³ @ Rs. 715.20 per m³ = Rs. 2360.16
Sub Total 5834.16
Per box 5834.16

37 Salwood work for chaukhat per m3


Skilled labor 34 md @ Rs. 800.00 per md = Rs. 27200
Unskilled labor 3.4 md @ Rs. 600.00 per md = Rs. 2040
Salwood 1.1 M³ @ Rs. 168000.00 per m³ = Rs. 184800
Holdfast 92 nos. @ Rs. 25.00 per nos. = Rs. 2300
Screw nail 184 nos. @ Rs. 1.00 per nos. = Rs. 184
Sub Total = Rs. 216524
Total = Rs. 216524

38 38mm thick salwood panelled shutters(1.07*1.98=2.12m²)


Skilled labor 10 md @ Rs. 800.00 per md = Rs. 8000
Unskilled labor 1 md @ Rs. 600.00 per md = Rs. 600
Salwood 0.084 M³ @ Rs. 168000.00 per m³ = Rs. 14112
Hinge ,handle,locking
set,nails, tower bolt etc. L.S. = Rs. 300
Sub Total = Rs. 23012
Total = Rs. 23012
Per m2 10854.72
39 Iron grill works per Sq.m including fixing
Iron grill (2kg/ft2) 21.52 kg @ Rs. 120.00 kg @ Rs. = Rs. 2582.40
Skilled labor 0.34 md @ Rs. 800.00 per md = Rs. 275.46
Unskilled labor 0.52 md @ Rs. 600.00 per md = Rs. 309.89
Sub Total = Rs. 3167.74
Total = Rs. 3167.74

40 Laying and Jointing of GI pipes (15 and 20 mm) per m (17- 4(ka))
Plumber 0.017 md @ Rs. 800.00 per md = Rs. 13.60
Helper 0.033 md @ Rs. 600.00 per md = Rs. 19.80
Unskilled labor 0.033 md @ Rs. 600.00 per md = Rs. 19.80
Sub Total = Rs. 53.20
Red lead paint etc. 10% of lab cost = Rs. 5.32
Contigencies 2.5% = Rs. 1.33
Sub Total = Rs. 59.85
Total = Rs. 59.85

41 Laying and Jointing of GI pipes (25 and 32 mm) per m


Plumber 0.017 md @ Rs. 800.00 per md = Rs. 13.60
Helper 0.050 md @ Rs. 600.00 per md = Rs. 30.00
Unskilled labor 0.050 md @ Rs. 600.00 per md = Rs. 30.00
Sub Total = Rs. 73.60
Red lead paint etc. 10% of lab cost = Rs. 7.36
Contigencies 2.5% = Rs. 0.00
Sub Total = Rs. 80.96
Grand total 80.96
42 Laying and Jointing of GI pipes (40 and 50 mm) per m
Plumber 0.025 md @ Rs. 800.00 per md = Rs. 20.00
Helper 0.067 md @ Rs. 600.00 per md = Rs. 40.20
Unskilled labor 0.067 md @ Rs. 600.00 per md = Rs. 40.20
Sub Total = Rs. 100.40
Red lead paint etc. 10% of lab cost = Rs. 10.04
Contigencies 2.5% = Rs. 2.51
Sub Total = Rs. 112.95
112.95

43 Laying of 65-80 mm dia GI pipe per m. length


Plumber 0.042 md @ Rs. 800.00 per m.d = Rs. 33.60
Helper 0.067 md @ Rs. 600.00 per m.d = Rs. 40.20
Unskilled labor 0.1 md @ Rs. 600.00 per m.d = Rs. 60.00
Sub Total = Rs. 133.80
Red lead paint etc. 10% of lab cost = Rs. 13.38
Contigencies 2.5% = Rs. 3.35
Sub Total = Rs. 150.53
Total = Rs. 150.53

44 Laying of 100mm dia GI pipe per m. length


Plumber 0.058 md @ Rs. 800.00 per m.d = Rs. 46.4
Helper 0.067 md @ Rs. 600.00 per m.d = Rs. 40.20
Unskilled labour 0.133 md @ Rs. 600.00 per m.d = Rs. 79.80
Sub Total = Rs. 166.40
Red lead paint etc. 10% of lab cost = Rs. 16.64
Contigencies 2.5% = Rs. 4.16
Sub Total = Rs. 187.20
Total = Rs. 187.20

45 Laying of 125mm dia GI pipe per m. length


Plumber 0.067 md @ Rs. 800.00 per md = Rs. 53.6
Helper 0.083 md @ Rs. 600.00 per md = Rs. 49.80
Unskilled labour 0.167 md @ Rs. 600.00 per md = Rs. 100.20
Sub Total = Rs. 203.60
Red lead paint etc. 10% of lab cost = Rs. 20.36
Contigencies 2.5% = Rs. 5.09
Sub Total = Rs. 229.05
Total = Rs. 229.05

4 Barbed wire fencing (7 layer hor.+2 layer diagonal.) per 100 m


Skilled labor 11.60 nos. @ Rs. 800.00 per nos. = Rs. 9280.00
Unskilled labor 58.20 nos. @ Rs. 600.00 per nos. = Rs. 34920.00
Barbed wire 1082.00 m @ Rs. 16.31 per m³ = Rs. 17652.23
Sub Total = Rs. 61852.23
Total = Rs. 61852.23
Per m 618.52

5 Laying and jointing of HDPE Pipes (20 and 25 mm) per 1000 m
Plumber 1.00 md @ Rs. 800.00 per md = Rs. 800.00
Helper 1.00 md @ Rs. 600.00 per md = Rs. 600.00
Unskilled labour 2.00 md @ Rs. 600.00 per md = Rs. 1200.00
Sub Total 2600.00
T and P 1.00 Day 30 Day = Rs. 30.00
Sundries (2.5%) of labour = Rs. 65.00
Fuel 0.25 ltr 90.00 ltr = Rs. 22.50
Total = Rs. 2717.50
Grand total = Rs. 2717.50
Rate per m 2.72

6 Laying and jointing of HDPE Pipes 32 mm per 1000 m


Plumber 1.00 md @ Rs. 800.00 per md = Rs. 800.00
Helper 1.00 md @ Rs. 600.00 per md = Rs. 600.00
Unskilled labour 3.00 md @ Rs. 600.00 per md = Rs. 1800.00
Sub Total 3200.00
T and P 1.00 Day 30 Day = Rs. 30.00
Sundries (2.5%) of labour = Rs. 80.00
Fuel 0.25 ltr 90.00 ltr = Rs. 22.50
Total = Rs. 3332.50
Grand total = Rs. 3332.50
Rate per m 3.33

7 Laying and jointing of HDPE Pipes 40 and 50 mm per 1000 m


Plumber 1.50 md @ Rs. 800.00 per md = Rs. 1200.00
Helper 1.50 md @ Rs. 600.00 per md = Rs. 900.00
Unskilled labour 3.00 md @ Rs. 600.00 per md = Rs. 1800.00
Sub Total 3900.00
T and P 1.00 Day 30 Day = Rs. 30.00
Sundries (2.5%) of labour = Rs. 97.50
Fuel 0.37 ltr 90.00 ltr = Rs. 33.30
Total = Rs. 4060.80
Grand total = Rs. 4060.80
Rate per m 4.06

8 Laying and jointing of HDPE Pipes 63mm, 75mm,and 90mm per 50 m


Plumber 1.00 md @ Rs. 800.00 per md = Rs. 800.00
Helper 1.00 md @ Rs. 600.00 per md = Rs. 600.00
Unskilled labour 2.00 md @ Rs. 600.00 per md = Rs. 1200.00
Sub Total 2600.00
T and P 1.00 Day 30 Day = Rs. 30.00
Sundries (2.5%) of labour = Rs. 65.00
Fuel 0.5 ltr 90.00 ltr = Rs. 45.00
Total = Rs. 2740.00
Grand total = Rs. 2740.00
Rate per m 54.80

9 M.S. angle 40*40*5 (2.1 m long) per pc 15-28 (ka-1)

M.S. angle pole 2.94 kg @ Rs. 93.86 per kg = Rs. 275.95


Drilling of holes 7.00 nos @ Rs. 2.00 per nos. = Rs. 14.00
Skilled labour 0.05 Md @ Rs. 800.00 per Md = Rs. 37.63
Unskilled labour 0.07 Md @ Rs. 600.00 per Md = Rs. 42.34
Total = Rs. 369.92
Total = Rs. 369.92
Rate per kg 125.82

10 Laying polythene sheet 500swg on and around foundation for 1 sqm.

Polythene sheet 1.10 sqm @ Rs. 12.00 per sqm = Rs. 13.20
Skilled labour 0.06 Md @ Rs. 800.00 per Md = Rs. 48.00
Unskilled labour 0.06 Md @ Rs. 600.00 per Md = Rs. 36.00
Total = Rs. 97.20
Total = Rs. 97.20
`
Density=0.26/m2
Density=0.23/m2
Density=0.20/m2
77000
92.66
Rate Analysis
Jhadewa Water Supply & Sanitation Project
Location: Jhadewa
A. Labour District Rate

Skilled labour =Rs 510


Unskilled labour =Rs 275
Plumber =Rs 400
Helper (Asistant plumber) =Rs 280
Carpenter =Rs 400
Painter =Rs 400
Rate including
District Rate
B. Material transportation
1) Cement per bag =Rs 525.00 631.39
2) Sand per M³ 2 1=District rate
2= Collection and
Sand 1700.00 1978.45 transportation
Quarrying capacity 4 1 < 30% 3=district rate +trans.
2 31 to 50 %
3 51 to 65 %
4 >65 %
3) Stone m 3
1 1=stone from collection
Block stone/bond stone 1,680.00 660.00 2= stone from excavation
5) M.S. bar 8 mm ø to 12 mm ø per kg. =Rs 68.00 77.85
6) 10 mm ø per kg =Rs 67.00
7) Binding wire per kg. =Rs 90.00 102.46
8) Barbed wire per kg =Rs 108.00 123.05
9) M.S. Angle per kg. =Rs 110.00 125.31
10) Plain wire per kg 8-10 gauge per kg =Rs 87.00 87.68
11) Local wood per m³ =Rs 26,000.00 26000.00
12) Snowcem paint per kg. =Rs 60.00 60.68
13) Nail per kg. =Rs 90.00 90.90
14) Enamel paint per lit. =Rs 342.00 342.68
15) Primer per lit. =Rs 287.00
16) Almunium paint =Rs 490.00
17) Polythene sheet per sqm =Rs 12.00
18) Aggregate 3 1= District rate
2= District rate
i)5 - 10 mm size per m3 =Rs 2,000.00 3175.00 +portering
3= River bed material
ii) 10 - 20 mm size per m³ =Rs 2,040.00 2042.00 with transportation
4=crushed stone with
iii) 20 -40 mm size per m³ =Rs 1,940.00 1525.00 transportation
17) Mud per m3 =Rs 215.00
18) Brick per no. =Rs 10.20 2 17.07 1=District rate
2=District rate +
transportation
3=Factory rate +
transportation
21) Sal wood Rate/ m3 =Rs 80,000.00
22) Bamboo / no =Rs 150.00
23) Chicken wire (90 cm wide) 3
20 gauge /m 2
=Rs 134.00 128.18 1 = 20 gauge
22 gauge /m 2
=Rs 130.00 2 = 22 gauge
24 gauge /m 2
=Rs 128.00 3 = 24 gauge
24) Screw No =Rs 0.85
25) Holdfast No =Rs 25.00
25)Bitumin Paint / kg =Rs 79.00 79.68
26)Drilling holes / no =Rs 2.00
27)Manhole cover ,60cm dia /set =Rs 1,800.00
28)Iron grill gate /sqm =Rs 2,831.40
29)CGI sheet 28 gauge /bundle =Rs 5,290.00
30)GI Plain Sheet 28 gauge /sqm =Rs 304.87
Kerosene ltr =Rs 92.92
MS Grill kg =Rs 110.00
C Transportation
Transportation of materials
1 by vehicle in pitch road
(Truck)
per quintal per
a Easy goods km =Rs 1.95
per quintal per
b Uneasy goods km =Rs 2.85

Transportation of materials
2 by vehicle in earthen road
(Truck)
per quintal per
a Easy goods km =Rs 2.70
per quintal per
b Uneasy goods km =Rs 3.20

Transportation of materials
3 by vehicle in earthen road
(Tractor)
per quintal per
a Easy goods km =Rs 2.85
per quintal per
b Uneasy goods km =Rs 3.35
4 Transportation by porter
a Easy goods Per kg per km =Rs 0.53
b Uneasy goods Per kg per km =Rs 0.70

D Cost of local material at site


1 STONE per m3 Density = 2200.00 Kg/m3
Collection, tranportation and
a.
potering Lead (vehicle) = 0.00 Km
Lead (Porter) = 0.50 Km
Unskilled labour
Collection 1.40 md 275 385.00
Transportation (Portering) 1.00 md 275 275.00
(Porter can carry 40kg load
Through 13 km per day.) 660.00 per m3
Production by breaking,
b. collection, transportation and
portering
Unskilled labour
Breaking stone using
5.50 md 275.00 1512.50
3.11 chiesel and hammer
Transportation (vehicle) 22.00 Quintal 0.00
Transportation (Portering) 2.12 md 275 581.73
2094.23 per m3

2 SAND per m3 Density = 1600.00 Kg/m3


Lead (vehicle)
Pitch (Truck) = 0.00 Km
Earthen (Tractor) = 13.00 Km
Lead (Porter) = 1.00 Km
(Labour required for collection
including transportation upto 10 Quarrying
km) capacity
<30 % 4.54 md
31 to 50 % 3.45 md
51 to 65 % 2.50 md
>65 % 1.43 md
Unskilled labour
Collection 1.43 275 393.25
Transportation (vehicle)
Pitch 35.00 Quintal 0.00
Earthen 13.00 Quintal 481.65
Transportation (Portering) 3.08 md 275 846.15
Load unlaod 1.98 md 130 257.40
1978.45 per m3

3 AGGREGATE per m3 Density = 1600.00 Kg/m3


Lead (vehicle)
Pitch (Truck) = Km
Earthen (Truck) = 0.00 Km
Earthen (Tractor) = 0.00 Km
Lead (Porter) = 0.50 Km

Transportation
District rate Tractor
Aggregate size /Production
Truck (Pitch) Truck (Earthen)
(Earthen) Porter Total
1 5 mm to 10 mm size
District rate 2000.00 0.00 0.00 0.00 425.00 2425.00
3.2.ka River bed material (10 md) 2750.00 0.00 0.00 0.00 425.00 3175.00
Crushed stone (21.5md) 5912.50 0.00 0.00 0.00 425.00 6337.50
2 10mm to 20 mm size
District rate 2040.00 0.00 0.00 0.00 425.00 2465.00
3.2.kha River bed material (5.88 md 1617.00 0.00 0.00 0.00 425.00 2042.00
Crushed stone (15 md) 4125.00 0.00 0.00 0.00 425.00 4550.00
3 20 mm 40 mm size
District rate 1940.00 0.00 0.00 0.00 425.00 2365.00
3.2.ga River bed material (4 md) 1100.00 0.00 0.00 0.00 425.00 1525.00
Crushed stone (9md) 2475.00 0.00 0.00 0.00 425.00 2900.00
Transportation distance
for non local material
per Bag Lead (vehicle)
Pitch (Truck) = 18.00 Km
Earthen (Truck) = 12.00 Km
Earthen (Tractor) = 0.00 Km
Lead (Porter) = 0.00 Km

4 CEMENT Easy
District rate 525.0
Transportation
Truck (pitch) 17.55
Truck (Earthen) 16.20
Tractor 0.00
Porter 0.00
Sub-Total 558.75
13% VAT 72.64
631.39
MS BARS 8 MM to 12
5 per Kg
MM DIA. Uneasy
District rate 68.00
Transportation
Truck (pitch) 0.51
Truck (Earthen) 0.38
Tractor 0.00
Porter 0.00
Sub-Total 68.90
13% VAT 8.96
77.85

6 BINDING WIRE per Kg Easy


District rate 90.00
Transportation
Truck (pitch) 0.35
Truck (Earthen) 0.32
Tractor 0.00
Porter 0.00
Sub-Total 90.68
13% VAT 11.79
102.46

7 BARBED WIRE per Kg Uneasy


District rate 108.00
Transportation
Truck (pitch) 0.51
Truck (Earthen) 0.38
Tractor 0.00
Porter 0.00
Sub-Total 108.90
13% VAT 14.16
123.05
8 M S ANGLE per Kg Uneasy
District rate 110.00
Transportation
Truck (pitch) 0.51
Truck (Earthen) 0.38
Tractor 0.00
Porter 0.00
Sub-Total 110.90
13% VAT 14.42
125.31

9 PLAIN WIRE per Kg Easy


District rate 87.00
Transportation
Truck (pitch) 0.35
Truck (Earthen) 0.32
Tractor 0.00
Porter 0.00
87.68
CHICKEN WIRE (90
11 cm) m2 Transportation
(Choose appropriate no for gauge 1=20 gauge 2=22 gauge 3=24 gauge
selection)
Tractor
District rate Truck (Pitch) Truck (Earthen) Porter Total (Rs.)
District rate (Earthen)

20 gauge 134.00 0.13 0.10 0.00 0.00 134.23


22 gauge 130.00 0.12 0.09 0.00 0.00 130.21
24 gauge 128.00 0.10 0.08 0.00 0.00 128.18

12 LOCAL WOOD per m3


District rate 26000.00

13 SNOWCEM PAINT per Kg Easy


District rate 60.00
Transportation
Truck (pitch) 0.35
Truck (Earthen) 0.32
Tractor 0.00
Porter 0.00
60.68

14 NAILS
District rate 90.00 Uneasy
Transportation
Truck (pitch) 0.51
Truck (Earthen) 0.38
Tractor 0.00
Porter 0.00
90.90
15 ENAMEL PAINT Per L Easy
District rate 342.00
Transportation
Truck (pitch) 0.35
Truck (Earthen) 0.32
Tractor 0.00
Porter 0.00
342.68
16 BITUMIN PAINT Per L Easy
District rate 79.00
Transportation
Truck (pitch) 0.35
Truck (Earthen) 0.32
Tractor 0.00
Porter 0.00
79.68
Easy
17 BRICK per No. Density = 1800.00 Kg/m3
Lead (vehicle)
Pitch (Truck) = 57.00 Km
Earthen (Truck) = Km
Earthen (Tractor) = 8.00 Km
Lead (Porter) = 1.50 Km
Transportation
District rate Tractor
Truck (Pitch) Truck (Earthen)
Brick /Factory rate (Earthen) Porter Total
District rate 10.20 3.57 0.00 0.73 2.56 17.07
Factory rate 0 3.57 0.00 0.73 2.56 Error
(Don,t fortet to enter factory rate if applicable)

1. E./W in excavation in gravel and boulder mixed soil for 1 m³

Unskilled labour 1.59 Nos. @ Rs. 275.00 per No/day = Rs. 437.25
T & P 3% of labour cost 13.12
450.37
Total = Rs. 450.37
2. Back filling in trench in gravel mixed soil 1 m³

Unskilled labour 0.60 Nos. @ Rs. 275.00 per No/day = Rs. 165.00
T & P 3% of labour cost 4.95
169.95
Total = Rs. 169.95

3. E./W in excavation in hard soil for 1 m³


Unskilled labour 1.25 Nos. @ Rs. 275.00 per No/day = Rs. 343.75
T & P 3% of labour cost 10.31
354.06
Total = Rs. 354.06
4. E./W in excavation in soft soil for 1 m³
Unskilled labour 1 Nos. @ Rs. 275.00 per No/day = Rs. 275.00
T & P 3% of labour cost 8.25
283.25
Total = Rs. 283.25
5. E./W Refilling in trench in hard soil 1 m³

Unskilled labour 0.63 Nos. @ Rs. 275.00 per No/day = Rs. 173.25
T & P 3% of labour cost 5.20
178.45
Total = Rs. 178.45
6. E/W Refilling in trench in soft soil 1 m³

Unskilled labour 0.50 Nos. @ Rs. 275.00 per No/day = Rs. 137.50
T & P 3% of labour cost 4.13
141.63
Total = Rs. 141.63
7 E/W Refilling in trench in soft Rock 1 m³

Unskilled labour 1.10 Nos. @ Rs. 275.00 per No/day = Rs. 302.50
T & P 3% of labour cost 9.08
311.58
Total = Rs. 311.58
8. E./W in excavation in Soft rock for 1 m³
Unskilled labour 3 Nos. @ Rs. 275.00 per No/day = Rs. 825.00
T & P 3% of labour cost 24.75
849.75
Total = Rs. 849.75

9. Boulder soling in foundation with sand packing per m³


Sand 0.71 M³ @ Rs. 1978.45 per m³ =Rs 1404.70
Unskilled labour 1.50 Nos. @ Rs. 275.00 per No/day = Rs. 412.50
Block Stone 1.00 M³ @ Rs. 660.00 per m³ = Rs. 660.00
Bond Stone 0.20 M³ @ Rs. 660.00 per m³ = Rs. 132.00
Total = Rs. 2609.20
Total = Rs. 2609.20

10. Boulder soling in foundation without sand packing per m³


Unskilled labour 1.50 Nos. @ Rs. 275.00 per No/day = Rs. 412.50
Block Stone 1.00 M³ @ Rs. 660.00 per m³ = Rs. 660.00
Bond Stone 0.20 M³ @ Rs. 660.00 per m³ = Rs. 132.00
Total = Rs. 1204.50
Total = Rs. 1204.50

11. R/R Masonary in (1:6) C.S. mortar per m³

Cement 2.12 bag. @ Rs. 631.39 per bag = Rs. 1338.54


Sand 0.47 M³ @ Rs. 1978.45 per m³ = Rs. 929.87
Block Stone 1.00 M³ @ Rs. 660.00 per m³ = Rs. 660.00
Bond Stone 0.10 M³ @ Rs. 660.00 per m³ = Rs. 66.00
Skilled labour 1.50 nos. @ Rs. 510.00 per no. = Rs. 765.00
Unskilled labour 5.00 nos. @ Rs. 275.00 per no. = Rs. 1375.00
Total = Rs. 5134.41
Total = Rs. 5134.41

12. R/R Masonary work in (1:4) mortar for 1 m³


Cement 3.18 bag. @ Rs. 631.39 per bag = Rs. 2007.81
Sand 0.45 M³ @ Rs. 1978.45 per m³ = Rs. 890.30
Block Stone 1.00 M³ @ Rs. 660.00 per m³ = Rs. 660.00
Bond Stone 0.10 M³ @ Rs. 660.00 per m³ = Rs. 66.00
Skilled labour 1.50 nos. @ Rs. 510.00 per no. = Rs. 765.00
Unskilled labour 5.00 nos. @ Rs. 275.00 per no. = Rs. 1375.00
Total = Rs. 5764.12
Total = Rs. 5764.12

13. Dry stone wall for 1 m³


Skilled labour 1.00 nos. @ Rs. 510.00 per nos. = Rs. 510.00
Unskilled labour 2.00 nos. @ Rs. 275.00 per nos. = Rs. 550.00
Block Stone 1.00 M³ @ Rs. 660.00 per m³ = Rs. 660.00
Bond Stone 0.10 M³ @ Rs. 660.00 per m³ = Rs. 66.00
Total = Rs. 1786.00
Total = Rs. 1786.00

14.Brick work in (1:4)c/s mortar for 1 m³


Cement 2.00 bag @ Rs. 631.39 per bag = Rs. 1262.78
Brick 560.00 Nos @ Rs. 17.07 per Nos = Rs. 9557.48
Sand 0.28 M³ @ Rs. 1978.45 per m³ = Rs. 553.97
Skilled labour 1.50 nos. @ Rs. 510.00 per nos. = Rs. 765.00
Unskilled labour 4.20 nos. @ Rs. 275.00 per nos. = Rs. 1155.00
Total = Rs. 13294.22
Total = Rs. 13294.22

15. P.C.C. (1:2:4) in foundation,wall etc. 1 m³

Cement 6.40 bag @ Rs. 631.39 per bag = Rs. 4040.88


Sand 0.445 M³ @ Rs. 1978.45 per m³ = Rs. 880.41
Aggregate
40 mm ø 0.52 M³ @ Rs. 1525.00 per m³ = Rs. 793.00
20 mm ø 0.22 M³ @ Rs. 2042.00 per m³ = Rs. 449.24
10 mm ø 0.11 M³ @ Rs. 3175.00 per m³ = Rs. 349.25
Skilled labour 1.00 nos. @ Rs. 510.00 per nos. = Rs. 510.00
Unskilled labour 4.00 nos. @ Rs. 275.00 per nos. = Rs. 1100.00
Total = Rs. 8122.78
Total = Rs. 8122.78

16. P.C.C. (1:2:4) for R.C.C. work beam, slab etc for 1 m³

Cement 6.40 bag @ Rs. 631.39 per bag. = Rs. 4040.88


Sand 0.445 M³ @ Rs. 1978.45 per m³ = Rs. 880.41
Aggregate
40 mm ø 0.52 M³ @ Rs. 1525.00 per m³ = Rs. 793.00
20 mm ø 0.22 M³ @ Rs. 2042.00 per m³ = Rs. 449.24
10 mm ø 0.11 M³ @ Rs. 3175.00 per m³ = Rs. 349.25
Skilled labour 0.80 nos. @ Rs. 510.00 per nos. = Rs. 408.00
Unskilled labour 7.00 nos. @ Rs. 275.00 per nos. = Rs. 1925.00
Total = Rs. 8845.78
Total = Rs. 8845.78

17. P.C.C. (1:1½:3) in foundation for 1 m³


Cement 8.00 bag @ Rs. 631.39 per bag = Rs. 5051.10
Sand 0.425 M³ @ Rs. 1978.45 per m³ = Rs. 840.84
Aggregate
20 mm ø 0.57 M³ @ Rs. 2042.00 per m³ = Rs. 1163.94
10 mm ø 0.29 M³ @ Rs. 3175.00 per m³ = Rs. 920.75
Skilled labour 0.80 nos. @ Rs. 510.00 per nos. = Rs. 408.00
Unskilled labour 7.00 nos. @ Rs. 275.00 per nos. = Rs. 1925.00
Total = Rs. 10309.63
Total = Rs. 10309.63

18. P.C.C. (1:3:6) for foundation for 1 m³


Cement 4.40 bag @ Rs. 631.39 per bag = Rs. 2778.11
Sand 0.470 M³ @ Rs. 1978.45 per m³ = Rs. 929.87
Aggregate
40 mm ø 0.65 M³ @ Rs. 1525.00 per m³ = Rs. 991.25
20 mm ø 0.24 M³ @ Rs. 2042.00 per m³ = Rs. 490.08
Skilled labour 1.00 nos. @ Rs. 510.00 per nos. = Rs. 510.00
Unskilled labour 4.00 nos. @ Rs. 275.00 per nos. = Rs. 1100.00
Total = Rs. 6799.31
Total = Rs. 6799.31

19. 12.5 mm thick (1:2) cement plaster for 100 m²


Cement 18.00 bag @ Rs. 631.39 per bag = Rs. 11364.98
Sand 1.220 M³ @ Rs. 1978.45 per m³ = Rs. 2413.71
Skilled labour 12.00 nos. @ Rs. 510.00 per nos. = Rs. 6120.00
Unskilled labour 16.00 nos. @ Rs. 275.00 per nos. = Rs. 4400.00
Total = Rs. 24298.69
Total = Rs. 24298.69
Rate per m2 242.99

20 12.5 mm thick (1:3) cement plaster for 100 m²


Cement 12.50 bag @ Rs. 631.39 per bag = Rs. 7892.34
Sand 1.280 M³ @ Rs. 1978.45 per m³ = Rs. 2532.42
Skilled labour 12.00 nos. @ Rs. 510.00 per nos. = Rs. 6120.00
Unskilled labour 16.00 nos. @ Rs. 275.00 per nos. = Rs. 4400.00
Total = Rs. 20944.76
Total = Rs. 20944.76
Rate per m2 209.45

21) 12.5 mm thick (1:4) cement plaster for 100 m²

Cement 10.76 bag @ Rs. 631.39 per bag = Rs. 6793.73


Sand 1.46 M³ @ Rs. 1978.45 per m³ = Rs. 2888.54
Skilled labour 12.00 nos. @ Rs. 510.00 per nos. = Rs. 6120.00
Unskilled labour 16.00 nos. @ Rs. 275.00 per nos. = Rs. 4400.00
Total = Rs. 20202.27
Total = Rs. 20202.27
Rate per m2 202.02

22) 12.5 mm thick (1:6) cement plaster for 100 m²

Cement 7.64 bag @ Rs. 631.39 per bag = Rs. 4823.80


Sand 1.570 M³ @ Rs. 1978.45 per m³ = Rs. 3106.17
Skilled labour 12.00 nos. @ Rs. 510.00 per nos. = Rs. 6120.00
Unskilled labour 16.00 nos. @ Rs. 275.00 per nos. = Rs. 4400.00
Total = Rs. 18449.97
Total = Rs. 18449.97
Rate per m2 184.50

23) 20 mm thick (1:4) cement plaster for 100 m²

Cement 16.20 bag @ Rs. 631.39 per bag = Rs. 10228.48


Sand 2.20 M³ @ Rs. 1978.45 per m³ = Rs. 4352.60
Skilled labour 14.00 nos. @ Rs. 510.00 per nos. = Rs. 7140.00
Unskilled labour 19.00 nos. @ Rs. 275.00 per nos. = Rs. 5225.00
Total = Rs. 26946.08
Total = Rs. 26946.08
Rate per m2 269.46

24) 20 mm thick (1:6) cement plaster for 100 m²


Cement 11.40 bag @ Rs. 631.39 per bag = Rs. 7197.82
Sand 2.35 M³ @ Rs. 1978.45 per m³ = Rs. 4649.37
Skilled labour 14.00 nos. @ Rs. 510.00 per nos. = Rs. 7140.00
Unskilled labour 19.00 nos. @ Rs. 275.00 per nos. = Rs. 5225.00
Total = Rs. 24212.18
Total = Rs. 24212.18
242.12
25) 3 mm thick cement punning for 1 m²
Cement 0.11 Bag @ Rs. 631.39 = Rs. 67.18
Skilled labour 0.10 nos. @ Rs. 510.00 per nos. = Rs. 51.00
Unskilled labour 0.10 nos. @ Rs. 275.00 per nos. = Rs. 27.50
Total = Rs. 145.68
Total = Rs. 145.68

26) Cement pointing on stone wall in 1:3 cement mortar for 100 m²

Cement 6.12 bag @ Rs. 631.39 per bag = Rs. 3864.09


Sand 0.63 M³ @ Rs. 1978.45 per m³ = Rs. 1246.43
Skilled labour 10.00 nos. @ Rs. 510.00 per nos. = Rs. 5100.00
Unskilled labour 14.00 nos. @ Rs. 275.00 per nos. = Rs. 3850.00
Total = Rs. 14060.52
Total = Rs. 14060.52
Rate per m2 140.61

27) 3 mm thick cement sand punning (1:1) for 100 m²

Cement 6.72 bag @ Rs. 631.39 per bag = Rs. 4242.92


Sand 0.23 M³ @ Rs. 1978.45 per m³ = Rs. 455.04
Skilled labour 10.00 nos. @ Rs. 510.00 per nos. = Rs. 5100.00
Unskilled labour 10.00 nos. @ Rs. 275.00 per nos. = Rs. 2750.00
Total = Rs. 12547.97
Total = Rs. 12547.97
Rate per m2 125.48

28) M.S. bar binding, binding for R.C.C. for 1.00 M.T.
M.S. bar 1.05 M.T.@ Rs. 77853.6 per m.t. = Rs. 81746.29
Binding wire 10.00 kg @ Rs. 102.46 per kg = Rs. 1024.63
Skilled labour 12.00 nos. @ Rs. 510.00 per nos. = Rs. 6120.00
Unskilled labour 12.00 nos. @ Rs. 275.00 per nos. = Rs. 3300.00
Total = Rs. 92190.92
Total = Rs. 92190.92
Rate per kg 92.19

29) Form work for R.C.C. slab for 1.00 m²


Local wood 0.0526 M³ @ Rs. 26000.00 per m³ x0.75 = Rs. 170.95
Nails 0.25 kg @ Rs. 90.90 per kg = Rs. 22.72
Carpenter 0.172 nos. @ Rs. 400.00 per nos. = Rs. 68.80
Unskilled labour 0.25 nos. @ Rs. 275.00 per nos. = Rs. 68.75
Total = Rs. 331.22
Total = Rs. 331.22

30) Form work for Ferrocement tank for 1.00 m²


Bamboo 0.3330 nos. @ Rs. 150.00 per nos. = Rs. 49.95
Nails 0.014 kg @ Rs. 90.90 per kg = Rs. 1.27
Binding wire 0.083 kg @ Rs. 102.46 per kg = Rs. 8.50
Carpenter 0.167 nos. @ Rs. 400.00 per nos. = Rs. 66.80
Unskilled labour 0.111 nos. @ Rs. 275.00 per nos. = Rs. 30.53
HDPE pipe 32 mm 6 kg/cm² (4 coils for 100m2 ) to be used from stock
Total = Rs. 157.05
Total = Rs. 157.05
31) Steel bar binding for Ferrocement work for 1.00 m²
Binding wire 0.111 kg @ Rs. 102.46 per kg = Rs. 11.37
Steelbar 8 & 10 mm ø 2.593 kg @ Rs. 77.85 per kg = Rs. 201.87
Chicken wire 90 cm wide 1.806 m2 @ Rs. 128.18 per m = Rs. 231.49
Plain wire 3.5 mm ø 2.083 kg @ Rs. 87.68 per kg = Rs. 182.63
Skilled labour 0.25 nos. @ Rs. 400.00 per nos. = Rs. 100.00
Unskilled labour 0.083 nos. @ Rs. 275.00 per nos. = Rs. 22.83
Total = Rs. 750.19
Total = Rs. 750.19

32) Bitumen paint two coats work for 1.00 m²


Bitumen paint 0.12 kg @ Rs. 79.68 per kg = Rs. 9.56
Painter 0.05 nos. @ Rs. 400.00 per nos. = Rs. 20.00
Unskilled labour 0.05 nos. @ Rs. 275.00 per nos. = Rs. 13.75
Total = Rs. 43.31
Total = Rs. 43.31

33) Snowcem painting first and 2nd coat for 1.00 m²


Snowcem paint 0.50 kg @ Rs. 60.68 per kg = Rs. 30.34
Painter 0.065 nos. @ Rs. 400.00 per nos. = Rs. 26.00
Unskilled labour 0.065 nos. @ Rs. 275.00 per nos. = Rs. 17.88
Total = Rs. 74.21
Total = Rs. 74.21

34) Enamel painting 2 coats for 1.00 m²


Primer 8.10 lit @ Rs. 287.00 per lit
Enamel paint 0.16 lit @ Rs. 342.68 per lit = Rs. 54.83
Painter 0.120 nos. @ Rs. 400.00 per nos. = Rs. 48.00
Unskilled labour 0.080 nos. @ Rs. 275.00 per nos. = Rs. 22.00
Total = Rs. 124.83
Total = Rs. 124.83

35) Site clearence for 1.00 m²

Unskilled labour 0.16 nos. @ Rs. 275.00 per nos. = Rs. 44.00
Total = Rs. 44.00
Total = Rs. 44.00

36 Gabion work (3*1*1) m3 mesh size (80*100) m2 hexagonal with all complete
Skilled labour 0.63 nos. @ Rs. 510.00 per nos. = Rs. 321.3
Unskilled labour 1.38 nos. @ Rs. 275.00 per nos. = Rs. 379.5
G.I. Wire 35.1 kg @ Rs. 52.50 per kg = Rs. 1842.75
SelvEge wire 4.1 kg @ Rs. 52.50 per kg = Rs. 215.25
Binding wire 1.6 kg @ Rs. 52.50 per kg = Rs. 84
Stone 3.3 M³ @ Rs. 715.20 per m³ = Rs. 2360.16
Sub Total 5202.96
Per box 5202.96

37 Salwood work for chaukhat per m3


Skilled labor 34 md @ Rs. 510.00 per md = Rs. 17340
Unskilled labor 3.4 md @ Rs. 275.00 per md = Rs. 935
Salwood 1.1 M³ @ Rs. 80000.00 per m³ = Rs. 88000
Holdfast 92 nos. @ Rs. 25.00 per nos. = Rs. 2300
Screw nail 184 nos. @ Rs. 0.85 per nos. = Rs. 156.4
Sub Total = Rs. 108731.4
Total = Rs. 108731.4

38 38mm thick salwood panelled shutters(1.07*1.98=2.12m²)


Skilled labor 10 md @ Rs. 510.00 per md = Rs. 5100
Unskilled labor 1 md @ Rs. 275.00 per md = Rs. 275
Salwood 0.084 M³ @ Rs. 80000.00 per m³ = Rs. 6720
Hinge ,handle,locking
set,nails, tower bolt etc. L.S. = Rs. 300
Sub Total = Rs. 12395
Total = Rs. 12395
Per m2 5846.70
39 Iron grill works per Sq.m including fixing
Iron grill (2kg/ft2) 21.52 kg @ Rs. 110.00 kg @ Rs. = Rs. 2367.20
Skilled labor 0.34 md @ Rs. 510.00 per md = Rs. 175.60
Unskilled labor 0.52 md @ Rs. 275.00 per md = Rs. 142.03
Sub Total = Rs. 2684.84
Total = Rs. 2684.84

40 Laying and Jointing of GI pipes (15 and 20 mm) per m (17- 4(ka))
Plumber 0.017 md @ Rs. 510.00 per md = Rs. 8.67
Helper 0.033 md @ Rs. 280.00 per md = Rs. 9.24
Unskilled labor 0.033 md @ Rs. 275.00 per md = Rs. 9.08
Sub Total = Rs. 26.99
Red lead paint etc. 10% of lab cost = Rs. 2.70
Contigencies 2.5% = Rs. 0.67
Sub Total = Rs. 30.36
Total = Rs. 30.36

41 Laying and Jointing of GI pipes (25 and 32 mm) per m


Plumber 0.017 md @ Rs. 510.00 per md = Rs. 8.67
Helper 0.050 md @ Rs. 280.00 per md = Rs. 14.00
Unskilled labor 0.050 md @ Rs. 275.00 per md = Rs. 13.75
Sub Total = Rs. 36.42
Red lead paint etc. 10% of lab cost = Rs. 3.64
Contigencies 2.5% = Rs. 0.91
Sub Total = Rs. 40.97
Grand total 40.97
42 Laying and Jointing of GI pipes (40 and 50 mm) per m
Plumber 0.025 md @ Rs. 510.00 per md = Rs. 12.75
Helper 0.067 md @ Rs. 280.00 per md = Rs. 18.76
Unskilled labor 0.067 md @ Rs. 275.00 per md = Rs. 18.43
Sub Total = Rs. 49.94
Red lead paint etc. 10% of lab cost = Rs. 4.99
Contigencies 2.5% = Rs. 1.25
Sub Total = Rs. 56.18
56.18

43 Laying of 65-80 mm dia GI pipe per m. length


Plumber 0.042 md @ Rs. 510.00 per m.d = Rs. 21.42
Helper 0.067 md @ Rs. 280.00 per m.d = Rs. 18.76
Unskilled labor 0.1 md @ Rs. 275.00 per m.d = Rs. 27.50
Sub Total = Rs. 67.68
Red lead paint etc. 10% of lab cost = Rs. 6.77
Contigencies 2.5% = Rs. 1.69
Sub Total = Rs. 76.14
Total = Rs. 76.14

44 Laying of 100mm dia GI pipe per m. length


Plumber 0.058 md @ Rs. 510.00 per m.d = Rs. 29.58
Helper 0.067 md @ Rs. 280.00 per m.d = Rs. 18.76
Unskilled labour 0.133 md @ Rs. 275.00 per m.d = Rs. 36.58
Sub Total = Rs. 84.92
Red lead paint etc. 10% of lab cost = Rs. 8.49
Contigencies 2.5% = Rs. 2.12
Sub Total = Rs. 95.53
Total = Rs. 95.53

45 Laying of 125mm dia GI pipe per m. length


Plumber 0.067 md @ Rs. 510.00 per md = Rs. 34.17
Helper 0.083 md @ Rs. 280.00 per md = Rs. 23.24
Unskilled labour 0.167 md @ Rs. 275.00 per md = Rs. 45.93
Sub Total = Rs. 103.34
Red lead paint etc. 10% of lab cost = Rs. 10.33
Contigencies 2.5% = Rs. 2.58
Sub Total = Rs. 116.25
Total = Rs. 116.25

46 Barbed wire fencing (7 layer hor.+2 layer diagonal.) per 100 m


Skilled labor 11.60 nos. @ Rs. 510.00 per nos. = Rs. 5916.00
Unskilled labor 58.20 nos. @ Rs. 275.00 per nos. = Rs. 16005.00
Barbed wire 1082.00 m @ Rs. 17.58 per m³ = Rs. 19020.57
Sub Total = Rs. 40941.57
Total = Rs. 40941.57
Per m 409.42

47 Laying and jointing of HDPE Pipes (20 and 25 mm) per 1000 m
Plumber 1.00 md @ Rs. 510.00 per md = Rs. 510.00
Helper 1.00 md @ Rs. 280.00 per md = Rs. 280.00
Unskilled labour 2.00 md @ Rs. 275.00 per md = Rs. 550.00
Sub Total 1340.00
T and P 1.00 Day 30 Day = Rs. 30.00
Sundries (2.5%) of labour = Rs. 33.50
Fuel 0.25 ltr 92.92 ltr = Rs. 23.23
Total = Rs. 1426.73
Grand total = Rs. 1426.73
Rate per m 1.43

48 Laying and jointing of HDPE Pipes 32 mm per 1000 m


Plumber 1.00 md @ Rs. 440.00 per md = Rs. 440.00
Helper 1.00 md @ Rs. 310.00 per md = Rs. 310.00
Unskilled labour 3.00 md @ Rs. 305.00 per md = Rs. 915.00
Sub Total 1665.00
T and P 1.00 Day 30 Day = Rs. 30.00
Sundries (2.5%) of labour = Rs. 41.63
Fuel 0.25 ltr 92.92 ltr = Rs. 23.23
Total = Rs. 1759.86
Grand total = Rs. 1759.86
Rate per m 1.76

49 Laying and jointing of HDPE Pipes 40 and 50 mm per 1000 m


Plumber 1.50 md @ Rs. 510.00 per md = Rs. 765.00
Helper 1.50 md @ Rs. 280.00 per md = Rs. 420.00
Unskilled labour 3.00 md @ Rs. 275.00 per md = Rs. 825.00
Sub Total 2010.00
T and P 1.00 Day 30 Day = Rs. 30.00
Sundries (2.5%) of labour = Rs. 50.25
Fuel 0.37 ltr 92.92 ltr = Rs. 34.38
Total = Rs. 2124.63
Grand total = Rs. 2124.63
Rate per m 2.12

50 Laying and jointing of HDPE Pipes 63mm, 75mm,and 90mm per 50 m


Plumber 1.00 md @ Rs. 510.00 per md = Rs. 510.00
Helper 1.00 md @ Rs. 280.00 per md = Rs. 280.00
Unskilled labour 2.00 md @ Rs. 275.00 per md = Rs. 550.00
Sub Total 1340.00
T and P 1.00 Day 30 Day = Rs. 30.00
Sundries (2.5%) of labour = Rs. 33.50
Fuel 0.5 ltr 92.92 ltr = Rs. 46.46
Total = Rs. 1449.96
Grand total = Rs. 1449.96
Rate per m 29.00

51 M.S. angle 40*40*5 (2.1 mm long) per pc 15-28 (ka-1)

M.S. angle pole 3.24 kg @ Rs. 125.31 per kg = Rs. 406.02


Drilling of holes 7.00 nos @ Rs. 2.00 per nos. = Rs. 14.00
Skilled labour 0.05 Md @ Rs. 510.00 per Md = Rs. 26.44
Unskilled labour 0.08 Md @ Rs. 275.00 per Md = Rs. 21.38
Total = Rs. 467.84
Total = Rs. 467.84
Distribution line
Project Name:-Dhandkon WSSP F/Y:-2072-73
Location:-Gothadi,Palpa
S.N. Description Quantity Unit Rate Amount Remarks
1 Earthwork in excavation for BMS 1128 m³ 412.00 464,736.00
2 Refilling with BMS 1128 m³ 100.00 112,800.00
3 Laying and jointing of HDPE Pipes (20 and 25 mm) Err:509 m 1.88 Err:509
4 Laying and jointing of HDPE Pipes 32 mm Err:509 m 2.29 Err:509
5 Laying and Jointing of GI pipes (25 and 32 mm) m 1260 m 0.00 -
Government of Nepal
Ministry of Local Development
Office of District Development Committee
Valuation
Summary of the works

Project Name:Jhedawa water supply and sanitation scheme

Int CC TLO Total


SN Description Unit Rate Amount
1 3 2 1+2+3

1 Site Clearance 6.00 #NAME? #NAME? m2 #REF! #REF!


2 E/W in excavation in GBM soil 4.82 #NAME? #NAME? m3 #REF! #REF!
3 Earthwork in excavation for fondation work in hard soil Err:509 #NAME? Err:509 m3 #REF! #REF!
4 RRM in 1:4 C/S mortar 2.34 #NAME? #NAME? m3 #REF! #REF!
5 Dry stone masonry work Err:509 Err:509 m3 #REF! #REF!
6 PCC (1:2:4) work 0.51 #NAME? #NAME? m3 #REF! #REF!
7 Formwork for concrete work Err:509 #NAME? Err:509 m 2
#REF! #REF!
8 3mm punning with 1:1 c/s mortar Err:509 #NAME? Err:509 m 2
#REF! #REF!
10 20mm plaster in (1:4) c/s mortar 11.68 #NAME? #NAME? m 2
#REF! #REF!
11 Installation of Pipes & fittings Err:509 #NAME? Err:509 m 2
#REF! #REF!
13 Gabion works Err:509 Err:509 m #REF! #REF!

14 #NAME? #NAME? Kg 99.69 #NAME?


Steel Reinforcement, 8 mm dia @ 100 mm c/c bothway

17 E/W excavation for HDP pipe laying work (Transmission line) 1128 1128.00 m3 Err:509 Err:509

18 E/W back filling for HDP pipe (Transmission line) 1128 1128.00 m3 Err:509 Err:509

19 HDP pipe laying & jointing work (Transmission line) Err:509 Err:509 Rm Err:509 Err:509

Prepared By Checked By Approved By


Government of Nepal
Ministry of Local Development
Office of District Development Committee
Valuation
Summary of the works

Project Name:Jhedawa water supply and sanitation scheme

Int CC TLO Total


SN Description Unit Rate Amount
1 3 2 1+2+3

20 Manhole cover for VC #NAME? #NAME? No #NAME?


2000
Total #REF!

Prepared By Checked By Approved By


TRANSPORTATION Estimate
sfo{s|d M— ;fdflhs ljsf; If]q
cfof]hgfsf] gfd M— nfDbL lzv/8f8f 5]n'Ëf lnlˆ6ª vfg]kfgL of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M— augf;sfnL–^,kfNkf

Type of
load
Unconve
nient?
S.N. Materials Unit (Yes/No) 0 Transportation cost by Tractor Transportation cost by Tractor Transportation cost by Manual Transportation Cost per m
Rate per kg Rate per kg Rate per kg
Distance per km in Distance per km in Distance per km in Amount
(km) metal road Amount (km) Earthen road Amount (km) Earthen road Amount per kg length amount

[1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [9] [10] [11] [11] [12]=[8]+[11]
0
1 HDPE Pipe(75mm) -6 kgf/cm2 r.m. yes 0.978 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 10.5938 0
2 HDPE Pipe(63mm) -10 kgf/cm1 r.m. yes 1.058 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 11.4604 0
3 HDPE Pipe(63mm) -6 kgf/cm2 r.m. yes 0.689 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 7.46332 0
4 HDPE Pipe(50mm) -6 kgf/cm2 r.m. yes 0.441 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 4.77696 0
5 HDPE Pipe(50mm) -10 kgf/cm2 r.m. yes 0.667 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 7.22501 3200 23120.03
6 HDPE Pipe(40mm) -6 kgf/cm2 r.m. yes 0.286 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 3.09798 0 0
7 HDPE Pipe(40mm) -10 kgf/cm2 r.m. yes 0.431 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 4.66864 0 0
8 HDPE Pipe(32mm) -6 kgf/cm2 r.m. yes 0.187 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 2.0256 0 0
9 HDPE Pipe(32mm) -10 kgf/cm2 r.m. yes 0.279 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 3.02216 0 0
10 HDPE Pipe(25mm) -10 kgf/cm2 r.m. yes 0.138 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 1.49483 0 0
11 HDPE Pipe(25mm) -10 kgf/cm3 r.m. yes 1.138 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 12.3269 0 0
12 HDPE Pipe(25mm) -10 kgf/cm4 r.m. yes 2.138 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 23.159 0 0
13 HDPE Pipe(25mm) -10 kgf/cm5 r.m. yes 3.138 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 33.9911 0 0
1 G.I. Pipe(40mm)1.5"-MC r.m. yes 3.68 56 0.165 9.24 4 0.231 0.924 0.5 1.34 0.6681 10.8321 39.8621 0 0
Total 23120.03
`
augf;sfnL ufFpkfnLsf
ufFpsfo{kfnLsfsf] sfof{no
lrt'{Ëwf/f,kfNkf
% g+=k|b]z g]kfn
nfut cg'''dfg kmf/fd
sfo{s|d M— ;fdflhs ljsf; If]q
cfof]hgfsf] gfd M— nfDbL lzv/8f8f 5]n'Ëf lnlˆ6ª vfg]kfgL of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M—augf;sfnL–^,kfNkf
Intake -2
qm=;+= sfdsf]] ljj/0f ;+VofnDjfO{{{
rf}}}}}]8fO{
prfO{ kl/df0f OsfO{ b/ /sd s}lkmot
1 sfo{ If]q ;/;kmfO{ ug]{ sfd 1 5 1 5.00 j=dL= 24.00 120.00

2 df6f] vGg] sfd s8f df6f]df


afw 1 5 0.5 0.6 1.5
1.50 3=dL= 1236.00 1854.00

3 kL=;L=;L= !M@M$ cg'kftdf sf] 9nfg


d'xfgsf] ;xfos kvf{n / e'O{df 1 5 1.1 0.1 0.55
Soflkª\ lk=l;=l;=kvf{n 1 5 0.4 0.08 0.15
d'xfgsf] kvf{n 1 5.5 0.4 0.8 1.76
2.46 3=dL= 12360.33 30406.41

4 ;'Vvf uf/f]
d'xfgsf] kvf{n dfly tkm{ 1 5 0.4 0.6 1.2
1.20 3=dL= 4409.96 5291.96
5 9'Ëfsf] ;f]lnË sfo{ 1 5 0.6 0.3 0.90 3=dL= 3309.96 2978.97

6 kmdf{ nufpg] sfo{


d'xfgsf]] dfly 1 5.5 0.1 0.55
2 5.5 0.8 8.8
9.35 j=dL= 334.57 3128.23
hDdfM 43779.56

Prepared By Checked By Approved By


`

Prepared By Checked By Approved By


Reinforcement Cement Concrete Required data from
40 m3 capacity Leveling height=
Height of stagnant water = 0.15 m Exposed height
Stone soling
Adopt inner diameter, d = 5.00 m Total tank height = 2.25 m PCC(1:3:6) in base
Thickness of wall = 0.16 m Effective Volume = 41.23 m³ PCC(1:1.5:3) in base slab
Dome rise, h = 1.00 m Lantern Opening(dia) = 0.75 m Offset of base slab
40 m³ capacity Size of VC
Length/
S.N. Description No. Radius Radius Breadth Height Qty. Unit Ring beam
1 Site clearance(L= d+4 m,B=d+4 m) 9.00 9.00 81 m² Thickness of dome =
2 Earthwork in excavation for foundation in hard soil Haunch(inner)
- for leveling 0.5 6.50 6.50 2.00 42.25
Storage tank(π r²h, r = d/2+t+1.00) π 3.66 3.66 - 1.25 52.60
π 2.96 2.96 - 0.60 16.52
Valve Chamber 1 1.90 1.90 1.45 5.23 Reinforcement in base slab
Washout pipe trench 10.00 0.60 1.13 6.75 Bottom(both ways)
Protection Wall 5.00 0.70 0.50 1.75
Total earth work 125.10 m³ Top(both ways)
3 Earthwork in back filling work circumferencial
in storage tank : total trench (πr²h) π 3.66 3.66 - 1.25 52.60 distribution
Washout pipe trench 10.00 0.60 1.13 6.75 Reinforcement in Wall
Behind protection wall 5.00 2.00 1.00 10.00
Deduct tank portion (πr²h'): r=d/2+t π 2.66 2.66 - 1.25 -27.79 Inner rings
Net backfilling work 41.57 m³ Inner rings
4 Stone soling work Outer rings
Storage tank(π r²h, r = d/2+t+0.30) π 2.96 2.96 - 0.20 5.51 Outer rings
Valve Chamber 1 1.90 1.90 0.20 0.72 verical -inner
Total soling work 6.23 m³ Verical -outer
5 Stone masonry in 1:6 c-s mortar haunch
Valve Chamber 5.80 0.45 1.25 3.26 Central half angle of dome, F
Protection Wall 5.00 0.60 1.50 4.50
Wing Wall 2 2.00 0.55 1.25 2.75
10.51 m³
6 PCC (1:3:6) in foundation central radius of C.dome
- tank foundation(π r²h, r = d/2+t+0.30) π 2.96 2.96 0.15 4.129 slanted side of dome
wall foundation 9.00 0.70 0.10 0.630
Wall capping 9.00 0.50 0.05 0.225
4.98 m³ total height of with slab
7 PCC (1:1½:3) for RCC work Rise of dome slab-centre
for tank base slab(π r²h, r = d/2+t+0.30) π 2.96 2.96 - 0.25 6.881 outer radius of dome slab
- for wall portion(2π r't, r'=d/2+t/2) 2π 2.580 0.16 2.25 5.836 Reinforcement in dome
- for inner haunch portion 2π/2 2.40 0.20 0.20 0.302 Ring beam
- for outer fillet portion 2π/2 2.76 0.20 0.20 0.347 main
-for maintaining floor slope( slope 1:100) π/2 2.50 2.50 0.05 0.491 Stirrups
Total PCC works 13.856 m³ Dome reinforcement
8 PCC (1:2:4) for RCC dome work meridional bars
- ring beam 2π 2.80 0.3 0.3 1.580 distribution
- conical dome
V=p.L.h1.t.tan¢ : L = √[h1²+(D/2)²] π 2.95 5.25 0.10 4.870
Parapet at the edge of ring beam ( for water collection) 2π 2.45 0.1 0.1 0.154
-ring beam at top of dome 2π 0.53 0.15 0.15 0.070
-pillars at top of dome 4 0.15 0.15 1.00 0.090
-slab at top of dome 1.76 1.76 0.1 0.310
- Deduction for
-Manhole cover for tank and VC 1 0.75 0.75 0.05 -0.028
Total 7.046 m³
9 Shuttering works for RCC for vertical walls
- inner portion 2π 2.500 2.25 35.34
- outer portion 2π 2.660 2.25 37.60
-Ringbeam -inner and outer 2×2π 2.650 0.30 9.99
-soffit 2π 2.730 0.14 2.40
Total shuttering works 85.34 m²

Approved By
Prepared By Checked By
10 Shuttering works for RCC for dome portion
A=p.L.h1.tan¢ : L = √[h1²+(D/2)²] π 2.69 5.00 42.290 m²
11 Steel reinforcement
-Base slab
Bottom main bars 10Ø @ 180 mm C/C -2 directions 2.00 34.00 5.92 ×0.8 @ 0.617 kg/m 198.55
top main bars 10Ø @ 180 mm C/C -2 directions 2.00 34.00 5.92 ×0.8 @ 0.617 kg/m 198.55
Circumferential reinforcement for 1.5 m outer width
Bottom main bars 10 @ 180 mm C/C -2 layers 2π 9.00 4.42 ×1.1 @ 0.617 kg/m 169.51
Distribution bars 10 @ 200 mm C/C -2 layers 2.00 94.00 1.5 '@ 0.617 kg/m 173.86
total reinforcement in foundation 740.48
Vertical walls
vertical bars- inner :10 mmØ @ 170 c/c 95 4.00 @ 0.617 kg/m 234.28
vertical bars- outer :10 mmØ @ 170 c/c 98 4.00 @ 0.617 kg/m 241.68
Inner rings of 12 mmØ bars 170 mm c/c upto 1 m height 2π 7 nos 2.541 ×1.1 @ 0.888 kg/m 109.14
Inner rings of 12 mmØ bars 170 mm c/c upto 1.25 m height 2π 8 nos 2.541 ×1.1 @ 0.888 kg/m 124.74
Outer rings of 12 mmØ bars 170 mm c/c upto 1 m height 2π 7.00 2.619 ×1.1 @ 0.888 kg/m 112.49
Outer rings of 12 mmØ bars 170 mm c/c upto 1.25 m height 2π 8.00 2.619 ×1.1 @ 0.888 kg/m 128.56

total reinforcement in wall 950.90


conical Dome
Ring beam- main bar 10 mmØ 4 15.71 @ 0.617 kg/m 38.74
stirrups - 2 legged 8 mmØ @150 mm c/c 104 1.15 @ 0.395 kg/m 47.02
meridional bars 10 mmØ @ 180 mm c/c
for whole length 12 3.44 @ 0.617 kg/m 25.45
for 7/8 length 12 3.08 @ 0.617 kg/m 22.79
for 3/4 length 23 2.72 @ 0.617 kg/m 38.57
for 1/2 length 46 2.01 @ 0.617 kg/m 57.01
distribution bars assuming average value
distribution bars 10 mmØ @ 180 mm c/c 17 8.65 1.1 @ 0.617 kg/m 102.02
Ring beam- main bar mmØ
total reinforcement in dome 331.60 kg
Total reinforcement work 2022.98 kg
12 12.5 mm thick 1:3 cement-sand plaster
-floor of tank π 2.30 2.30 16.62
- fillet portion 2π 2.40 0.28 4.27
- inner wall portion 2π 2.50 2.35 36.91
Total plaster work 57.80 m²
13 3 mm thick cement sand punning as per plaster work in item no 13 57.80 m²

14 12.5 mm thick 1:4 cement-sand plaster


-outer wall portion 2π 2.66 2.05 34.26
-outer fillet portion 2π 2.76 0.28 4.90
-beam soffit 2π 2.73 0.14 2.40
-beam outer face 2π 2.80 0.30 5.28
-beam upper face 2π 2.600 0.20 3.27
-outer surface of dome
A=p.L.h.tan¢ : L = √[h²+(D/2)²] π 3.21 5.510 55.48
Total plaster work 105.60
15 Bitumen paint on the buried surface of storage tank
-outer wall portion(buried portion) 2π 2.66 1.25 20.89 m²
16 Exterior paint on exposed surface of storage tank
- Wall portion(exposed portion) 2π 2.66 1.00 16.71
-beam soffit 2π 2.73 0.14 2.40
-beam outer face 2π 2.80 0.30 5.28
-beam upper face 2π 2.600 0.20 3.27
-outer surface of dome
A=p.L.h.tan¢ : L = √[h²+(D/2)²] π 3.21 5.510 55.48
Total snowcem painting 83.14 m²

17 GI water stopper 150mm wide, 20 SWG


at three sections of concrete joint(20% overlap) 3×2π×1.2 2.58 58.36 m
18 32 mmØ GI pipe ladder 45cm width -for tank inside 3.1 m long 1.00 no
19 Water Level indicator 1.00 no
20 Standard Manhole cover set 75×75 cm size 2.00 set
21 Installation of Pipes & fittings 1.00 job
22 Site levelling work 1.00 job
Total cost of Reservoir tank with fencing and gate

Approved By
Prepared By Checked By
Required data from design sheet

0.50 m
= 1.00 m
= 0.20 m
= 0.15 m
= 0.25 m Central half angle of lantern, d #DIV/0!
= 0.30 m
= 1.90 m × = 1.90 m

= 0.30 m × = 0.30 m
100 mm
= 0.20 m × = 0.20 m

3.96

10 mmØ 180 mm c/c

10 mmØ 180 mm c/c


10 mmØ 180 mm c/c for 1.50 m
10 mmØ 200 mm c/c 5.92

12 mmØ 170 mm c/c for 1.00 m


12 mmØ 170 mm c/c for 1.25 m
12 mmØ 170 mm c/c for 1.00 m
12 mmØ 170 mm c/c for 1.25 m
10 mmØ 170 mm c/c
10 mmØ 170 mm c/c
10 mmØ 200 mm c/c
= 78.69°

2.755
2.949

###
###
###

10 mmØ 4 nos
8 mmØ 150 mm c/c

10 mmØ 180 mm c/c


10 mmØ 180 mm c/c

4800
96
30000

Approved By
Prepared By Checked By
nfut cg'''dfg kmf/fd ufpFkfnLsf
ufpFsfo{kfnLsfsf] sfof{no
lrt'{Ëwf/f, kfNkf

nfut cg'''dfg kmf/fd

sfo{s|d M— ;fdflhs ljsf; If]q cf=a M—)&%÷&^


cfof]hgfsf] gfd M— nfDbL lzv/8f8f 5]n'Ëf lnlˆ6ª vfg]kfgL of]hgf ldlt M–@)&^÷)@÷!$
:yn÷uf=kf=—j8f g+M ÷g=kf M— augf;sfnL–^,kfNkf a=p=lz=g M—
cfg'bfg /sd M— 5110362
v'b e'StfgL /sd M—$(%&)%!.!$

qm=;+= sfdsf]] ljj/0f kl/df0f OsfO{ b/ /sd s}lkmot


1 xf]8Lª af]8{ 1.00 ;+Vof 3,000.00 3,000.00 cg'dflgt
2 6+sL lgdf{0f $) 3=dL= 2.00 ;+Vof 1,039,768.64 2,079,537.27

3
df6f] vGg] sfd :6«Sr/df g/d
df6f]df 3=dL=
846.00 618.00 522,828.00
4 df6f] vGg] sfd s8f df6f]df 248.16 3=dL= 370.00 91,819.20
5 df6f] vGg] g/d r§fgdf 33.84 3=dL= 2,472.00 83,652.48
6 df6f] k'g{] sfd s8f df6f]df 1,128.00 3=dL= 150.00 169,200.00
7 d'xfg lgdf{0f sfo{ 2.00 ;+Vof 43,779.56 87,559.13
8 d'xfg lgdf{0f sfo{ 1.00 ;+Vof 54,219.28 54,219.28

9
ljleGg ;fO{hsf]
Pr=l8=lk=O{=kfO{k vl/b 1.00 991,121.87 991,121.87
10 9'jflg 1.00 23,120.03 23,120.03
hDdf 4106057.25
;dk'/s sf]if augf;sfnL uf kf 2555362.00
;dk'/s sf]if % g+=k|b]z g]kfn 2555000.00
cg'bfg /sd 5110362.00
sG6]Gh]G;L #Ü 153310.86
v'b e'StfgL
hg>dbfg #VALUE!

tof/ ug]{M l;kmf/L; ug]{M :jLs[t ug]{M


`
141,778.40
606,480.48

775,680.48 94699800

#VALUE! #VALUE!

2632022.86
185400
76660.86 618000
augf;sfnL ufFpkfnLsf
ufFpsfo{kfnLsfsf] sfof{no
lrt'{Ëwf/f,kfNkf
% g+=k|b]z g]kfn
nfut cg'''dfg kmf/fd
sfo{s|d M—;fdflhs ljsf; If]q
cfof]hgfsf] gfd M— nfDbL lzv/8f8f 5]'n'Ëf lnlˆ6ª vfg]kfgL of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M—augf;sfnL–^,kfNkf
INTAKE -1
qm=;+= sfdsf]] ljj/0f ;+VofnDjfO{{{
rf}}}}}]8fO{
prfO{ kl/df0f OsfO{ b/ /sd s}lkmot
! sfo{ If]q ;/;kmfO{ ug]{ sfd 1 3 2 6.00 j=dL= 24.00 144.00

,@ df6f] vGg] sfd s8f df6f]df

afw u=2.15*2+
i 1 7.3 1.1 0.6 4.818 1.5*2
4.82 3=dL= 1236.00 5955.05

# kL=;L=;L= !M@M$ cg'kftdf sf] 9nfg


i d'xfgsf] ;xfos kvf{n / e'O{df 1 7.3 0.4 0.1 0.292
ii Soflkª\ lk=l;=l;=kvf{n 1 7.3 0.4 0.08 0.219
0.51 3=dL= 12360.33 6316.13
$ 9'Ëfsf] kv{fn nufpg] sfd !M$ l;d]G6
jfn'jf d;nfdf
i d'xfgsf] ;xfos kvf{n 1 7.3 0.4 0.8 2.336
2.34 3=dL= 15010.95 35065.59

% ,@) ld=ld= df]6fO{df !M$ sf] cg'kftdf


knf:6/ ug{] sfd
d'xfgsf] ;xfos kvf{n sf] lelq / aflx/L
i efudf 2 7.3 0.8 11.68
11.68 j=dL= 423.90 4951.19

# ld=ld= df]6fO{df klgª\ knf:6/ ug{]


^
sfd
i d'xfgsf] ;xfos kvf{n sf] lelq efudf 1 7.3 0.8 5.84
5.84 j=dL= 222.41 1298.85
* kmdf{ nufpg] sfo{
i d'xfgsf]] dfly 2 7.3 0.1 1.46
1.46 j=dL= 334.57 488.47
hDdfM 54219.28

Prepred By Checked By Approved By


s}lkmot

Prepred By Checked By Approved By


`

Prepred By Checked By Approved By


augf;sfnL ufpkfnLsf
ufpFsfo{kfnLsfsf] sfof{no
lrt'{Ëwf/f, kfNkf
%g+= k|b]z g]kfn
nfut cg'''dfg kmf/fd
cf=a M—)&^÷&&
cfof]hgfsf] gfd M— nfDbL lzv/8f8f 5]n'Ëf vfg]kfgL of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M— augf;sfnL–^,kfNkf a=p=lz=g M—
cfg'bfg /sd M—
v'b e'StfgL /sd M–
qm=;+= sfdsf]] ljj/0f kl/df0f OsfO{ b/ /sd s}lkmot
A Hoarding Board 1 nos 3000 3000.00
B RCC Fero tank(40cum) Reservoir Tank
1 Site clearance(L= d+4 m,B=d+4 m) 81 m2 25.6 2073.60
2 Earthwork in excavation for foundation in hard soil 125.10413 m3
1318.4 164937.28
3 Earthwork in back filling work 41.568582 m3
160 6650.97
4 Stone soling work 6.2270756 m3 3515.16 21889.17
5 Stone masonry in 1:6 c-s mortar 10.5125 m3 9156.82 96261.07
6 PCC (1:3:6) in foundation 4.9838067 m3 10545.44 52556.43
7 PCC (1:1½:3) for RCC work 13.856466 m3 15096.88 209189.40
8 PCC (1:2:4) for RCC dome work 7.045573 m3
12886.86 90795.31
9 Shuttering works for RCC for vertical walls 85.339479 m 2
517.68 44178.54
10 Shuttering works for RCC for dome portion 42.29 m 2
733.3 31011.26
11 Steel reinforcement 2022.9835 kg 102.9 208165.00
12 12.5 mm thick 1:3 cement-sand plaster 57.797906 m2 353.46 20429.25

Prepared by Checked by Approved by


13 3 mm thick cement sand punning 57.797906 m2 239.91 13866.30
14 12.5 mm thick 1:4 cement-sand plaster 105.59683 m 2
286.65 30269.33
15 Bitumen paint on the buried surface of storage tank 20.891591 m 2
80.17 1674.88
16 Exterior paint on exposed surface of storage tank 83.142947 m 2
294.12 24454.00
18 32 mmØ GI pipe ladder 45cm width -for tank inside 1 nos 5000 5000.00
20 Standard Manhole cover set 75×75 cm size 2 nos 5000 10000.00
21 Installation of Pipes & fittings 1 nos 5000 5000.00
Total 1038401.79
B Ferrocement Distribution Tank(20 m ) 3

1 Site clearance 48 m² 25.6 1228.80


2 Earthwork in excavation for foundation work in hard soil 45.186147 m³ 1318.4 59573.42
3 Earthwork in back filling with hard soil 13.713052 m³ 160 2194.09
4 Dry stone soling 3.570305 m³ 3515.16 12550.19
5 Stone masonry in 1:6 c-s mortar 2.0125 m³ 9156.82 18428.10
6 Plain cement concrete (1:2:4) 0.395 m³ 12886.86 5090.31
7 Plain Cement Concrete (1:1½:3) 1.8152515 m³ 15096.88 27404.63
8 Steel reinforcement 12.6 kg 102.9 1296.54
9 Centering & shuttering works for PCC/RCC 1.1572567 m² 271.85 314.60
10 HDPE pipe formwork for ferrocement work 37.041341 m² 264.1 9782.62
Bar bending work including chicken wire mesh, steel bar,
11
GI wire, for ferrocement 37.041341 m² 970.6 35952.33
12 12.5 mm thick 1:2 c-s plaster 148.16536 m² 364.02 53935.16
13 12.5 mm thick 1:3 c-s plaster 12.566371 m² 322.98 4058.69
14 12.5 mm thick 1:4 c-s plaster 4.94 m² 260.7 1287.86
15 3 mm thick 1:1 c-s punning 35.185838 m² 198.22 6974.54
16 Two(first & second) coats of bitumen paint 0 m² 80.7 0.00
17 Two(ist & 2nd) coats of snowcem painting 19.894135 m² 73.06 1453.47
Supply and installation of standard man hole cover - 600
18
mmØ 2 set 2000 4000.00
Total: 245525.33

Prepared by Checked by Approved by


Fittings of 20cum Ferotank 3 nos 54409.75 163229.25
C No of distribution tank 3 nos 245525.328 899805.23
Earthwork Excavation for pipe line trench for
C different types of soil by Manually

1 Earthwork excavation in Roadway & Drain for hard soil


248.16 m3 329.6 81793.54
Earthwork excavation in Hard soil for Roadway & Drain
2
for hard soil 846 m3 370.8 313696.80
Earthwork excavation for structures for Roadway & Drain
3
for Ordinary rock 33.84 m3 1236 41826.24
4 Earth filling work of pipe line for all types of soil and rock 1128 m3
160 180480.00
Total 617796.58
D Intake construction
1 Intake 1 1 nos 54219.276742 54219.28
2 Intake 2 2 nos 43779.562844 87559.13
Total 141778.40
E HDP pipe Purchase of different size and pressure

1 HDPE Pipe(63mm) - 10 kgf/cm2 1600 Rm 336.29 538064.00


2 HDPE Pipe(63mm) - 6 kgf/cm2 700 Rm 225.25 157675.00
3 HDPE Pipe(50mm) - 6 kgf/cm 2
1000 Rm 143.63 143630.00
4 HDPE Pipe(40mm) - 10 kgf/cm2 6900 Rm 136.21 939849.00
5 HDPE Pipe(32mm) - 10 kgf/cm 2
1100 Rm 92.05 101255.00
6 HDPE Pipe(25mm) - 10 kgf/cm2 900 Rm 55.67 50103.00
7 HDPE Pipe(20mm) - 10 kgf/cm 2
2500 Rm 36.93 92325.00
8 GI pipe (20mm ) 600 Rm 165 99000.00
Sub total 2121901.00
vat 13% 275847.13

Prepared by Checked by Approved by


2397748.13
8 Transportation Charge 52114.32
9 HDP Pipe Jointing (for 1m ) Norms
i HDPE Pipe(63mm) - 10 kgf/cm2 600 Rm 0 0.00
ii HDPE Pipe(63mm) - 6 kgf/cm 2
700 Rm 0 0.00
iii HDPE Pipe(50mm) - 6 kgf/cm2 1000 Rm 4.07 4070.00
iv HDPE Pipe(40mm) - 10 kgf/cm 2
6900 Rm 4.07 28083.00
v HDPE Pipe(32mm) - 10 kgf/cm2 1100 Rm 3.37 3707.00
vi HDPE Pipe(25mm) - 10 kgf/cm 2
900 Rm 3.37 3033.00
vii HDPE Pipe(20mm) - 10 kgf/cm2 1600 Rm 2.8 4480.00
sub total 43373.00
F Fittings of 40cum Ferotank 1 nos 46089.1631 46089.16
G Fencing wire for ferotank 1 nos 41171.9185 41171.92
Grand Total 5444507.78

Prepared by Checked by Approved by


214

0.66666666667

Prepared by Checked by Approved by


57600

42.6666666667

617,796.58

79.20

201,774.00

67,258.00

2,397,748.13

Prepared by Checked by Approved by


Prepared by Checked by Approved by
40 cum ferotank fittings item
S.N. Description Units Quantity Rate(Rs) TotalAmount(Rs)
Inlet GI Pipe Size 25 1.25"
1 GI Socket 32 mmØ no 3 129 387
2 GI Elbow (32 mmØ) no 2 176 352
3 Brass Union (32 mmØ) no 1 596 596
4 GI Pipe (32mm)-MC straight pipe m 1 410 410
5 GI Pipe (32 mm)-MC vertical pipe m 0.5 410 205
6 GI Pipe (32 mm)-MC vertical pipe m 2.35 410 963.5 2.85-0.5
Outlet GI Pipe Size 50 2.5"
1 GI Socket 15 mmØ air vent no 2 41 82
2 GI Elbow (15 mmØ) air vent no 4 45 180
3 GI Elbow (63 mmØ) no 2 368 736 50mm
4 GI Union (15 mmØ) no 2 124 248 6"
5 GI Union (63 mmØ) nos 1 633 633 50
6 GI Nipple (63 mmØ) nos 4 284 1136 5"
7 GI Nipple (15 mmØ) no 4 47 188 5"
9 GI Unequal Tee (50x15 mmØ) no 1 517 517
10 GM Gate Valve (63 mmØ) no 1 4557.52 4557.52
11 GI Pipe (15mm)-MC m 0.6 165 99
12 GI Pipe (15mm)-MC m 0.7 165 115.5
higher than inlet pipe
13 GI Pipe (15mm)-MC m 2.65 165 437.25 air vet
14 GI Pipe (63 mm)-mc m 0.45 820 369
15 GI Pipe (63mm)-mc m 0.25 820 205
16 GI Pipe (63mm)-mc m 0.3 820 246
17 GI Pipe (63 mm)-mc m 0.4 820 328
18 Brass Union (65 mmØ) nos 1 4565 4565 65mm
40
18 GI Union (63 mmØ) nos 1 633 633
19 GI Nipple (63 mmØ) nos 4 284 1136 5"
20 GI Unequal Tee (63 x15 mmØ) no 1 517 517
21 GM Gate Valve (63 mmØ) no 1 4557.5 4557.5
22 GI Pipe (63 mm)-mc m 0.25 820 205
23 GI Pipe (63 mm)-mc m 0.3 820 246
24 GI Pipe (63 mm)-mc m 0.4 820 328
25 Brass Union (63 mmØ) nos 1 633 633

Overflow GI Pipe Size 40


1 GI Socket 50 mmØ no 1 268 268
2 GI Elbow (50 mmØ) no 3 368 1104
3 GI Nipple (50 mmØ) no 2 284 568 4"
4 GI Pipe (50mm)-MC nos 0.25 642 160.5
6 GI Pipe (50mm)-MC m 2.55 642 1637.1 15
7 GI Pipe (50mm)-MC m 0.7 642 449.4
Washout GI Pipe Size 40
1 GI Elbow (50 mmØ) no 1 368 368
2 GI Nipple (50 mmØ) no 4 284 1136 4"
3 GI Equal Tee(50 mmØ) no 1 460 460
4 GI Union (50 mmØ) no 2 633 1266
5 GM Gate Valve (50 mmØ) no 1 4,557.50 4557.5
6 Brass Union (50x50 mmØ) no 1 1,364.00 1364
7 GI Pipe (50mm)-MC m 0.25 642 160.5
8 GI Pipe (50mm)-MC m 2.3 642 1476.6 3
Sub Total 40,786.87
Sub total 40,786.87
Vat@13% 5302.29

Prepared by Checked by Approved by


Grand Total 46089.16

Prepared by Checked by Approved by


2.85

Prepared by Checked by Approved by


augf;sfnL ufpFkflnsf
ufpFsfo{kflnsfsf] sfof{no
lrt'{Ëwf/f, kfNkf
%g+=k|b]z g]kfn
nfut cg'''dfg kmf/fd

sfo{s|d M— ;fdflhs ljsf; If]q cf=a M—)&%÷&^


cfof]hgfsf] gfd M— nfDbL lzv/8f8f 5]n'Ëf lnlˆ6ª vfg]kfgL of]hgf
ldlt M–@)&^÷)@÷!$
:yn÷uf=kf=—j8f g+M ÷g=kf M— augf;sfnL–^,kfNkf a=p=lz=g M—
cfg'bfg /sd M— 5110362
v'b e'StfgL /sd M—$(%&)%!.!$
nfut cg'''dfdg kmf/d

Ferrocement Storage Tank


20 m³ Capacity
Diameter, d = 4.0 m Tank wall height, h = 1.8 m
Dome height, = 0.7 m

Length/
S.N. Description No. Radius Breadth Height Qty. Unit Remarks
Radius

1 Site clearance
(L= d+2*2.0m,B=d+1m) 8.00 6.00 48.00 m²
2 Earthwork in excavation for foundation work in hard soil
Valve Chamber 1.70 1.50 1.30 3.32
Storage tank π 2.80 2.80 - 1.70 41.87
(Q = p x R² x h, R = d/2+0.05+0.75
Total 45.19 m³
3 Earthwork in back filling with hard soil
in storage tank : total trench (p*R2*h') π 2.80 2.80 - 1.20 29.56 m³
Deduct tank portion (p*r2*h'): r=d/2+.05 π 2.05 2.05 - 1.20 -15.84 m³
Net backfilling work 13.71 m³
4 Dry stone soling
Valve Chamber 1.70 1.50 0.15 0.38
Storage tank π 2.30 2.30 - 0.20 3.32
(Q = p x r² x h, r = d/2+0.05+0.25
deduction for overlapping with VC portion 1.70 0.40 0.20 -0.14
Total 3.57 m³
5 Stone masonry in 1:6 c-s mortar
Valve Chamber 5.00 0.35 1.15 2.01 m³
6 Plain cement concrete (1:2:4)
Cover slab of valve chamber 1.70 1.50 0.10 0.255
Deduction for manhole opening π 0.30 0.30 - 0.05 -0.014
(Q = p x r² x h, r = 0.30)
Manhole Cover of tank π 0.30 0.30 - 0.05 0.014

Prepared by Checked by Approved by


Pipe embeddment block 2 1.00 0.35 0.20 0.140
Total 0.395 m³
7 Plain Cement Concrete (1:1½:3)
for tank base(Q = p x r² x h, r = d/2+0.05+0.10 π 2.15 2.15 - 0.125 1.815 m³

8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
Deduction for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg
9 Centering & shuttering works for PCC/RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
Deduction for manhole opening π 0.30 0.30 -0.283
Total 1.16 m²
10 HDPE pipe formwork for ferrocement work
- Wall portion (Q = 2 x p x r x h, r = d/2+.025) 2π 2.03 - 1.80 22.90
- Roof portion 2π 3.28 0.70 14.42
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole opening Q=pxr², r=0.30 π 0.30 0.30 -0.28
Total form work 37.04 m²
11 Bar bending work including chicken wire
mesh, steel bar, GI wire, for ferrocement

as per HDPE form work 37.04 m²

12 12.5 mm thick 1:2 c-s plaster


4 layers for ferrocement
- Wall portion (Q = 4x2 p x r x h, r = d/2+.025) 4×2π 2.03 1.80 91.61
- Roof portion 4×2π 3.28 0.700 57.69
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole opening 4×2π 0.30 0.30 -1.13
(Q = 4 x p x r², r = 0.60/2 = 0.30)
Total plaster 148.17 m²
13 12.5 mm thick 1:3 c-s plaster
sand mortar for
- Floor portion of storage tank π 2.00 2.00 12.57 m²
(Q = p x r², r = d/2)

14 12.5 mm thick 1:4 c-s plaster


- Floor portion of valve chamber 1.00 0.80 0.80
- inner wall of valve chamber 3.60 1.15 4.14
Total plaster 4.94 m²

15 3 mm thick 1:1 c-s punning


- Floor portion of storage tank(Q = p x r², r = d/2)π 2.00 2.00 12.57
- Wall portion of storage tank (Q = 2 x p x r x h) 2π 2.00 1.80 22.62
Total punning 35.19 m²
16 Two(first & second) coats of bitumen paint
(Q = 2 x p x r x h, r = d/2+0.05) 2π 2.05 1.40 0.00 m²

17 Two(ist & 2nd) coats of snowcem painting


- Wall portion 2π 2.05 0.40 5.15

Prepared by Checked by Approved by


(Q = 2 x p x r x h, r = d/2+0.05)
- Roof portion 2π 3.35 0.70 14.74
(Q = 2xpxRxh, R = (D²+4h²)/8h, D = d+0.10, h= dome height)
Total 19.89 m²

18 Supply and installation of standard man hole


cover - 600 mmØ
2 set
Total

Prepared by Checked by Approved by


inner
Design of Ferrocement
DomeTankTotal tank diameter of
RT size(m³) Height(m) height(m) Tank(m)
1 0.3 0.9 1.5
2 0.3 1.4 1.5
3 0.4 1.2 2
4 0.4 1.5 2
5 0.4 1.3 2.5
6 0.4 1.5 2.5
7 0.4 1.65 2.5
8 0.4 1.85 2.5
9 0.5 1.5 3
10 0.5 1.65 3
12 0.5 1.9 3
14 0.6 1.7 3.5
16 0.6 1.9 3.5
18 0.7 1.65 4
20 0.7 1.8 4
25 0.8 1.9 4.3

Prepared by Checked by Approved by


fencing
length(m)
18
18
18
18
21
21
21
21
21
24
24
24
24
24
24
24

Prepared by Checked by Approved by


ltgfp ufFpkfnLsf
ufFpsfo{kfnLsfsf] sfof{no
bf]efg,kfNkf
FITTINGS For RVT, INTAKE & Sump Well

sfo{s|d M—vfg]kflg tyf ;/;kmfO{


cfof]hgfsf] gfd M—u8\8f lnkm\6 vfg]kflg of]hgf
:yn÷uf=kf=—j8f g+M ÷g=kf M—ltgfp,# u8\8f
FITTINGS For RVT, INTAKE & Sump Well

Fittings for RVT 20 cum


S.N. Description Units Quantity Rate(Rs) TotalAmount(Rs)
Inlet GI Pipe 65 2.5"
1 GI Socket 65 mmØ no 1 653 653
2 GI Elbow (65 mmØ) no 2 952 1904
3 GI Union (65 mmØ) no 1 830 830
4 GI Pipe (65mm)-MC m 0.9 745 670.5
5 GI Pipe (65mm)-MC m 0.5 745 372.5
6 GI Pipe (65mm)-MC m 1.51 745 1124.95 6 no
Outlet -1 GI Pipe 65 2.5"
1 GI Socket 15 mmØ no 1 41 41
2 GI Elbow (15 mmØ) no 2 45 90
3 GI Elbow (40 mmØ) no 2 242 484
4 GI Union (15 mmØ) no 1 124 124
5 GI Union (40 mmØ) no 2 307 614
6 GI Nipple (15 mmØ) no 2 64.2 128.4 5"
7 GI Nipple (40 mmØ) no 4 210 840 5"
8 GI Equal Tee (15 mmØ) no 1 71 71
9 GI Unequal Tee (40x15 mmØ) no 1 326 326
10 GM Gate Valve (40 mmØ) no 1 2950.4 2950.4
11 Brass union (40*50 mmØ) no 1 853 853
12 GI Pipe (15mm)-MC m 0.6 150 90
13 GI Pipe (15mm)-MC m 0.7 150 105
14 GI Pipe (15mm)-MC m 1.56 150 234 20 no
15 GI Pipe (40mm)-MC m 0.45 428 192.6
15 GI Pipe (40mm)-MC m 0.25 428 107
16 GI Pipe (40mm)-MC m 0.3 428 128.4
17 GI Pipe (40mm)-MC m 0.4 428 171.2
Overflow GI Pipe Size 40 1.5"
1 GI Socket 40 mmØ no 1 173 173
2 GI Elbow (40 mmØ) no 2 242 484
3 GI Nipple (40 mmØ) no 1 160 160 4"
4 GI Pipe (40mm)-MC m 0.4 428 171.2
5 GI Pipe (40mm)-MC m 1.36 428 582.08 15 no
6 GI Pipe (40mm)-MC m 0.7 428 299.6
Washout GI Pipe Size 40 1.5"
1 GI Elbow (40 mmØ) no 1 242 242
2 GI Nipple (40 mmØ) no 4 160 640 4"
3 GI Equal Tee(40 mmØ) no 1 294 294
4 GI Union (40 mmØ) no 2 455 910
5 GM Gate Valve (40 mmØ) no 1 2,950.44 2950.44
6 Brass Union (40x50 mmØ) no 1 853.00 853
7 GI Pipe (40mm)-MC m 0.25 428 107
8 GI Pipe (40mm)-MC m 2.35 428 1005.8 3no
9 HDPE Pipe(63mm)-4Kg/cm2 m 5 146.25 731.25
Sub Total 22,708.32
Outlet-2 GI Pipe 40
1 GI Elbow (15 mmØ) no 1 45 45
2 GI Union (40 mmØ) no 1 455 455
3 GI Nipple (40 mmØ) no 3 200.1 600.3 5"
4 GI Unequal Tee (40*15 mmØ) no 1 326 326
5 GM Gate Valve (40 mmØ) no 1 2950.4 2950.4
6 Brass Union (40x50 mmØ) no 1 853 853
7 GI Pipe (15mm)-MC m 0.7 150 105
8 GI Pipe (40mm)-MC m 0.8 428 342.4
Over Flow GI Pipe 40
1 GI Pipe (40mm)-MC m 0.7 428 299.6
2 GI Elbow (40mmØ) no 1 242 242
Washout GI Pipe 40
1 GI Socket 40 mmØ no 1 173 173
2 GI Pipe (40mm)-MC m 0.7 428 299.6
3 CI End Plug (40mmØ) no 1 52 52
Sub Total 6,743.30
Pipe Line Works
S.N. Description Units Quantity Rate(Rs) TotalAmount(Rs)
Outlet -1 GI Pipe Size 25 1"
1 Saddle (32 mmØ) no 10 150 1500 for piplne
2 Saddle (40 mmØ) no 4 200 800 for piplne
3 Frulle (15 mmØ) no 14 695 9730 for piplne
4 GI Elbow (15 mmØ) no 14 45 630 for piplne
5 GI Nipple (15 mmØ) 4" no 14 51.4 719.6 for piplne
6 Brass Union (15x20 mmØ) no 14 171 2394 for piplne
7 HDPE Pipe(63mm) - 4 kgf/cm2 m 20 146.25 2925 for Drain
Sub Total 18,698.60
`

Sub total 48,150.22


Vat@13% 6259.53
Grand Total 54409.75

You might also like