TRIAL PAVING USING PAVER AND DUMP TRUCK

UPGRADING MANDALIKA
INTERNATIONAL STREET CIRCUIT PROJECT

UPGRADING MANDALIKA INTERNATIONAL


STREET CIRCUIT 2022
UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

1 BACKGROUND AND PURPOSE

2 PROPOSED LOCATION

OUTLINE 3 EQUIPMENT AND MATERIAL LIST

4 WORK METHOD
BACKGROUND AND PURPOSE
TRIAL PAVING USING PAVER AND DUMP TRUCK
NO.

UPGRADING MANDALIKA INTERNATIONAL


STREET CIRCUIT 2022
Background And Purpose UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

Background
• Paving on Track Lane is the main work and most critical work
• We need to do risk assignment before, during, and after paving work
• The operator has to understand the critical part of their job
• Detail method for whole work of paving track lane will be submitted from in another
document

Purpose
• To minimize risk while paving
• To understand the ability of equipment and operator
• To train the operators and evaluation for better rersult
UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

PROPOSED LOCATION
TRIAL PAVING USING PAVER AND DUMP TRUCK
NO.
Proposed Location UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

FINISH

Turn 17
STA 3+970 – 4+140
UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

EQUIPMENT AND MATERIAL


TRIAL PAVING USING PAVER AND DUMP TRUCK
NO.
Equipment List UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

4 Units 16 Units 1 Unit


Asphalt Cutter Machine Dump Trucks Water Tank Truck

2 Units 2 Units 1 Unit 1 Unit


Road Sweeper Power Broom Wheel Loader Air Compressor
Material List UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

240 Tons
Fine Aggregates
WORK METHOD
TRIAL PAVING USING PAVER AND DUMP TRUCK
NO.

UPGRADING MANDALIKA INTERNATIONAL


STREET CIRCUIT 2022
FLOW CHART AND WORK METHOD UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

START

Preparation Work

Equipment Mobilization

Trial Paving
(Using Fine Aggregate)

Clean the Track

FINISH
Work Method UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

1. Preparation Work
• Mark the lane for 3 pavers with 5 meters width each
• Seal the Hauraton drainage inlet using tape to avoid aggregate debris
• Ensure every people understand the role and job

2. Equipment Mobilization
• Ensure the path for Dump Truck Mobilization
• Entrance for Dump Truck is on Turn 1, see figure below
Outer Service Road

Run Off Ashalt Turn 1

Entrance to Track for Dump Truck


While Trial Paving
Work Method UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

3. Trial Paving
• Trial Paving using fine aggregate that loaded on the dump truck. Each Dump Truck
load ±15 tons of fines aggregate.
• Trial Paving is carried out on Track Lane from STA 3+970 - 4+140 to see the most
difficult corner
• There are 3 Critical Phases; entering the turn, in the turn, exiting the turn
• The formation for each phases shown on the figure below,

Formation for The Equipment


While Entering the Turn
Work Method UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

Formation for The Equipment


While In the Turn
Work Method UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

Formation for The Equipment


While Exiting the Turn
Work Method UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022

3. Clean the Track


• After the paving is done, load the fine aggregate to the Dump Truck using Wheel
Loader,
• Use road sweeper and power broom for cleaning debris,
• For cleaning the dust and trapped fine aggregate in the asphalt using water and
air compressor
UPGRADING MANDALIKA INTERNATIONAL
STREET CIRCUIT 2022