0% found this document useful (0 votes)
153 views13 pages

Mechanical Completion Checksheet

Checklist

Uploaded by

Sumit Tiwari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
153 views13 pages

Mechanical Completion Checksheet

Checklist

Uploaded by

Sumit Tiwari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

MECHANICAL COMPLETION CHECK SHEET

CUSTOMER:

PROJECT NO.:

BOILER DETAIL

CAPACITY

PRESSURE

TEMPERATURE

FUEL

TO FILLED BY ERECTION SITE IN-CHARGE ERECTION CO-ORDINATOR

SIGNATURE

DATE

Page 1 of 13
MECHANICAL COMPLETION CHECK SHEET

NOTE:
Legend A = Completed
B = In progress
C = Not applicable
Status to be circle marked on the appropriate letter

A B C

Acceptance criteria to be tick marked on the relevant columns


Sr. System/ Acceptance Criteria Completion


Description Status
No. Equipment Protocol Date
1. Pressure Parts
a) Mechanical completion A / B / C
b) Permanent supports A / B / C
c) Buck-stay & seismic stoppers A / B / C
d) Removal of temporary supports A / B / C
e) Spring hangers A / B / C
f) Hydro test A / B / C
g) Drum internal A / B / C
h) Mountings & fittings A / B / C

2. IBR Piping
a) Mechanical completion A/B/C
b) Permanent supports A/B/C
c) Removal of temporary supports A/B/ C
d) Hydro test A/B/C
e) IBR clearance A/B/C
f) Instrument mounting & cabling
g) Insulation & cladding A/B/C

3. Non-IBR piping
Page 2 of 13
MECHANICAL COMPLETION CHECK SHEET

a) Mechanical completion A / B / C
b) Permanent supports A / B / C
c) Removal of temporary supports A / B / C
d) Hydro test A / B / C
e) Insulation & cladding A / B / C

4. Instrument air piping


a) Mechanical completion A/B/C
b) Permanent supports A/B/C
c) Instrument mounting &
cabling
d) Leak Test A/B/C

5. Soot Blowers
a) Mechanical completion A/B /C
b) Piping and support A/B /C
c) Instrument mounting & A / B /C
cabling
d) Electrical cabling A/B /C
e) Power supply A/B /C
f) Approach A/B /C

6. Valves & Mountings


a) Mechanical completion A/ B/C
b) Electrical connection A/ B/C
c) Instrument mounting & A / B/C
cabling/piping
d) Power supply A/ B/C
e) Approach A/ B/C

Page 3 of 13
MECHANICAL COMPLETION CHECK SHEET

Sr. System/ Acceptance Criteria Completion


Description Status Date
No. Equipment Protocol Letter MOM
7. Pumps (F.W Transfer / Feed Water/ Oil/Spray Water)
a) Mechanical completion A/B/C
b) Master level of base A / B / C
frame and pumps
c) Suction and discharge A / B / C
piping and supports
d) Final grouting A/B/C
e) Coupling alignment A/B/C
f) Electrical connection A/B/C
g) Power supply A/B/C
h) Cooling water piping A/B/C

8. Dosing system (L.P. & H.P.)


a) Mechanical completion A / B / C
b) Final grouting of skid A / B / C
c) Coupling alignment A / B / C
d) Electrical connection A / B / C
e) Power supply A / B / C
f) Piping and support A / B / C
g) Availability of chemicals A / B / C

9. CBD Tank
a) Mechanical completion A/B/C
b) Piping and support A/B/C
c) CBD to IBD piping and A/B/C
support
d) Final grouting A/B/C
10. IBD Tank
a) Mechanical completion A/B/C
b) Piping and support A/B/C
c) Final grouting A/B/C

Page 4 of 13
MECHANICAL COMPLETION CHECK SHEET

11. Deaerator
a) Mechanical completion A/B /C
b) Instrument mounting & A / B /C
cabling
c) Piping and support A/B /C
d) Hydro test A/B /C
e) Insulation & cladding A/B /C
Sr. System/ Acceptance Criteria Completion
Description Status Date
No. Equipment Protocol Letter MOM
12. H.P. Feed Water Heater
a) Mechanical completion A/B/C
b) Supports A/B/C
c) Hydro test A/B/C
d) IBR clearance A/B/C
e) Insulation A/B/C
F Instrument mounting & A / B / C
cabling
13. L.P. feed water heater
a) Mechanical completion A/B/C
b) Supports A/B/C
c) Hydro test A/B/C
d) Instrument mounting & A / B / C
cabling
e) Insulation A/B/C

14. Air ducts


a) Mechanical completion A / B / C
b) Internal cleaning A / B / C
c) Dampers and actuators A / B / C
d) Supports A / B / C
e) Leak Test A / B / C
f) Insulation A / B / C
g) Instrument mounting & A / B / C
cabling
h) Approach A/B/C
Page 5 of 13
MECHANICAL COMPLETION CHECK SHEET

15 Hoppers in air/flue system


a) Mechanical completion A / B / C
b) Internal cleaning A / B / C
c) Supports A / B / C
d) Insulation & cladding A / B / C
e) Approach A / B / C

Sr. System/ Acceptance Criteria Completion


Description Status Date
No. Equipment Protocol Letter MOM

16. Air pre-heaters


a) Mechanical completion A/B/C
b) Supports A/B/C
c) Leak Test A/B/C
d) Approach A/B/C
e) Insulation & cladding A/B/C
17. Air fan (s) (F.D/P.A/Seal air/S.A/ESP Purge air blower)
a) Mechanical completion A/B/C
b) Final grouting A/B/C
c) Supports A/B/C
d) Coupling alignment A/B/C
e) Actuator erection and A / B / C
grouting
f) Electrical connection A/B/C
g) Instrument mounting & A / B / C
cabling
h) Power Supply A/B/C
i) Insulation & cladding A/B/C

18. I. D. Fan(s)
a) Mechanical completion A / B / C
b) Final grouting A / B / C
c) Coupling alignment A / B / C
d) Electrical connection A / B / C
Page 6 of 13
MECHANICAL COMPLETION CHECK SHEET

e) Instrument mounting & A / B / C


cabling
f) Power supply A/B/C
g) Insulation & cladding A/B/C

Sr. System/ Acceptance Criteria Completion


Description Status Date
No. Equipment Protocol Letter MOM

19. Flue gas ducts


a) Mechanical completion A/ B / C
b) Supports A/ B / C
c) Leak Test A/ B / C
d) Instrument mounting & A / B / C
cabling
e) Insulation & cladding A/ B/C
f) Approach A/ B/C

20. Air pollution control equipment’s (ESP/MDC/Bag Filter/Wet Scrubber)


a) Mechanical completion A/B/C
b) Internal cleaning of A / B / C
system
c) Instrument mounting & A / B / C
cabling
d) Hopper erection and A / B / C
level switch installation
e) Electrical connection A/B/C
f) KGV and RAV A/B/C
g) Air slide and pushing air A / B / C
system
h) Insulation & cabling A/B/C
i) Approach A/B/C
j) U beam erection and A/B/C
alignment
21. OPH Unit
a) Mechanical completion A/B/C
Page 7 of 13
MECHANICAL COMPLETION CHECK SHEET

b) Piping hydro test A / B / C


c) Heater hydro test A / B / C
d) Insulation & cladding A / B / C
e) Pump alignment A / B / C
f) Electrical connection A / B / C
g) Instrument mounting & A / B / C
cabling

Sr. System/ Acceptance Criteria Completion


Description Status
No. Equipment Protocol Letter MOM Date

22. Oil Train


a) Mechanical completion A/B/C
of piping.
b) Permanent support A / B / C
c) Piping hydro test A / B / C
d) Heat tracing A / B / C
e) Instrument mounting & A / B / C
cabling
f) Insulation & cladding A/B/C

23. Day oil Tank


a) Tank leak test A/B/C
b) Insulation & cladding A/B/C
c) Instrument mounting & A/B/C
cabling
d) Oil availability A/B/C
e) Approval from A/B/C
Explosives inspectorate
24. Oil Storage tank
a) Tank leak test A / B / C
b) Heater hydro test A / B / C
c) Insulation A / B / C
d) Instrument mounting & A / B / C
cabling
Page 8 of 13
MECHANICAL COMPLETION CHECK SHEET

e) Oil availability A/B/C


f) Approval from A/B/C
explosives inspectorate

Sr. System/ Acceptance Criteria Completion


Description Status Date
No. Equipment Protocol Letter MOM
25. Burner(s)
a) Mechanical completion A / B / C
b) Burner skid erection A / B / C
c) Piping & valves A / B / C
d) Instrument mounting & A / B / C
cabling
e) Electrical connections A/B/C
f) Process & instrument
A/B/C
piping
26. Refractory & Insulation
a) Furnace A/B/C
b) Travagrate side & rear
A/B/C
seal
c) Travagrate front panel A / B / C
d) Combustor A / B / C
e) Ash hoppers A / B / C
f) Furnace side wall A / B / C
g) Evaporator coil A / B / C
h) Penthouse A / B / C
i) Inner casing A / B / C
j) Outer casing A / B / C
k) Manholes & wall boxes A / B / C

27. Readiness of solid fuel storage system


a) Coal bunker A / B / C
b) Coal chute A / B / C
c) Air blasters A / B / C
d) Bagasse silo/gates A / B / C
e) Pith silo A / B / C
Page 9 of 13
MECHANICAL COMPLETION CHECK SHEET

f) Husk silo A/B/C

Sr. System/ Acceptance Criteria Completion


Description Status Date
No. Equipment Protocol Letter MOM
28. Readiness of solid fuel firing system
a) Travagrate and alarm A/B/C
system
b) Travagrate sealing A/B/C
c) Travagrate A/B/C
electric/hydraulic drive
d) Oil cooler for hydraulic A/B/C
drive and piping
e) Dumping grate A / B / C
f) Pinhole grate A / B / C
g) Combustor A / B / C
h) Pneumatic spreader A / B / C
i) Mechanical spreader A / B / C
j) Twin drum/three drum A / B / C
feeder
k) Rotary Feeder A / B / C
l) Screw feeder A / B / C
m) Under bed feed system A / B / C
n) Drag Chain Feeder A / B / C
29 Readiness of ash handling system
a) Ash hoppers A / B / C
b) Ash drain arrangement A / B / C
c) Bed Ash coolers A / B / C
d) Bed ash cooler inlet, A / B / C
Outlet ducting and
valves
e) KGV erection and A/B/C
cabling
f) RAV and power cable A/B/C
g) Ash screw conveyor A/B/C
h) Air slide A/B/C
Page 10 of 13
MECHANICAL COMPLETION CHECK SHEET

i) Ash conveyors A/B/C


j) Ash silo A/B/C
30 MCC panel
a) Erection A/B/C
b) Power charging A/B/C
31 Illumination system
a) For equipment’s A/B/C
b) For walk ways A/B/C
32. Control Panel
a) Control room readiness A/B/C
b) DCS A/B/C
c) Draft indication A/B/C
d) Annunciator A/B/C

Sr. System/ Acceptance Criteria Completion


Description Status
No. Equipment Protocol Letter MOM Date
33. Readiness of Field Instruments
a) Transmitters A / B / C
b) Analyzers A / B / C
c) Gauges A / B / C
d) Switches A / B / C
e) Valves A / B / C
f) Actuators A / B / C
g) Sensors A / B / C
34. Quality Documents
a) Status of SAR reported A/B/C
b) Hydraulic test
A/B/C
Certification from IBR
c) Permission from IBR for
A/B/C
Firing
d) Permission from PESO
A/B/C
for oil charging
35. Availability of Commissioning inputs
a) Control room A/B/C
b) Fuel handling system A/B/C
Page 11 of 13
MECHANICAL COMPLETION CHECK SHEET

c) Ash handling system A/B/C


d) Lubricants A/B/C
e) Chemicals for boil out A/B/C
f) Chemical for normal
A/B/C
operation
g) Wood for slow firing/
A/B/C
refractory dry out
h) Fuel (oil/ gas/ coal/
A/B/C
bagasse/ rice husk)
i) Pilot gas A/B/C
j) Bed material A/B/C
k) Electric power A/B/C
l) D.M. Water A/B/C
m) Cooling water A/B/C
n) Service air A/B/C
o) Instrument air A/B/C
p) Operating staff A/B/C
q) Tools & tackles A/B/C
r) Drain trench A/B/C

36. Rapping system/Ash cleaning system


a) Mechanical completion
A/B/C
of rapping system
b) Alignment WRT pastel
A/B/C
rod
c) Power cable for drives A/B/C
d) Removal of temporary
A/B/C
supports
e) Erection of sonic
A/B/C
horns/air blowers
f) Air piping and supports A/B/C
g) Erection of control panel A/B/C
and wiring

Page 12 of 13
MECHANICAL COMPLETION CHECK SHEET

37. Spent wash system


a) Erection of tank and
A/B/C
grouting
b) Erection of stirrer and
A/B/C
power cable
c) Erection and alignment
of pumps and final A/B/C
grouting
d) Spent wash piping and
A/B/C
supports
e) Installation of three way
valves, instrument air A/B/C
and cable connections
f) Atomizing steam/air
piping and supports A/B/C

Page 13 of 13

You might also like