3100B WATER SYSTEMS COMMISSIONING RECORDS TO BSRIA GUIDE BG 2/2010:

• Keep a systematic record of commissioning results and distribute as indicated.

• For water systems

• Use record sheets as detailed in BSRIA Guide BG 2/2010 Commissioning Water Systems.

3110 BMS COMMISSIONING - CONTROL SYSTEM SPECIFICATION DETAILS REQUIRED FOR COMMISSION-
ING:

• Ensure that the following information is supplied to the commissioning engineer:

• A network schematic providing a record of the overall control system architecture.

• Schematics of the systems to be controlled indicating the location of sensors and actuators.

• A written description of the configured control strategies.

• Control strategy logic diagrams in the form of logic flow charts.

• Set-points and other control settings such as initial default parameters for control loops relating to the
control strategies.

• Criteria relating to control accuracy and stability.

• A points list including digital inputs/outputs and analogue inputs/outputs.

• Control panel drawings.

• BMS operator workstation graphics and associated point data displaying monitored conditions.

• Trend logging archiving requirements and alarm routing.

• The scope of operational and specified functionality of management software, e.g. utility monitoring and
targeting software.

• Functional requirements of any occupant interfaces.

• Details of any hard-wired interfaces from, or to, other control devices.

• Functionality and scope of data to be transferred over any gateway for use as part of an integrated system.

• Functional profiles for any direct interoperability integration.

W17 Telfair Version 0 TESTING AND COMMISSIONING | Page 9 of 19


Testing & Commissioning Specification Published on 2023-07-17 ID: A828.TNC01
Template ID: MCE-TE-RP-0003; Template Version: 1.0

You might also like