Project Schedule

Inter-Regional Connectivity between Baltistan Division and Diamer-Astore Division


(Construction/ Metaling of Road from Gorikote Astore to Shagharthang Skardu)
PERIODS (Months)
S.NO

PLAN START PLAN DURATION


ACTIVITIES
(Months) (Months) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

1 Preliminaries 1 2

2 Earth Work 3 7

3 Road Works 10 6

Drainage &
4 Erosion Works 16 5

5 Culverts 21 2

6 Bridges 23 8

7 Misc. Works 31 2

8 Completion 33 1

9 Handing Taking 34 1