Malinau Neo Project - R9B - Schedule
Malinau Neo Project - R9B - Schedule
nit Price Total Price Wheight Duration Baseline Start Baseline Finish Actual Start Actual Finish Predecessors
Mode Volume Aug '23 Sep '23 Oct '23 Nov '23 Dec '23
(Number2) 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18
1 Malinau Neo Project 0 Rp0 Rp38,400,400,334 87.25 305 days? Mon 7/17/23 Thu 5/16/24 NA NA
2 I. EARLY PERMIT ADMINISTRATION WORK 1 Rp0 Rp0 0 5.33 days Mon 7/17/23 Mon 8/21/23 NA NA
3 Permit Work 1 lot Rp0 Rp0 0 5.33 days Mon 7/17/23 Mon 8/21/23 NA NA
4 II. PRE‐PREPARATION WORK 0 Rp0 Rp30,619,450,000 69.57 48 days Mon 8/7/23 Tue 11/7/23 NA NA 10/24
5 A. EARLY LAND PREPARATION 0 Rp0 Rp25,575,450,000 58.11 44 days Thu 8/10/23 Mon 10/30/23 NA NA
6 Mobilization 1 lot Rp150,000,000 Rp150,000,000 0.34 5.33 days Wed 8/2/23 Mon 8/21/23 NA NA
7 Soil excavation 146850 m3 Rp78,000 Rp11,454,300,000 26.02 9.33 days Sun 8/20/23 Thu 9/7/23 NA NA
8 Tree logging 10000 m2 Rp26,300 Rp263,000,000 0.6 9.33 days Sun 8/20/23 Thu 9/7/23 NA NA
9 Land leveling 128200 m3 Rp47,000 Rp6,025,400,000 13.69 10 days Fri 9/8/23 Thu 9/28/23 NA NA
10 Land disposal 18650 m3 Rp27,000 Rp503,550,000 1.14 10 days Tue 9/26/23 Mon 10/16/23 NA NA
11 Landfill and compaction 128200 m3 Rp56,000 Rp7,179,200,000 16.31 10 days Tue 10/10/23 Mon 10/30/23 NA NA
12 B. ROAD ACCESS WORK 0 Rp0 Rp2,405,700,000 5.47 20.67 days Tue 9/26/23 Tue 11/7/23 NA NA
13 Slope Protection 5670 m2 Rp210,000 Rp1,190,700,000 2.71 10 days Tue 9/26/23 Mon 10/16/23 NA NA
14 Road Pavement 2700 m2 Rp450,000 Rp1,215,000,000 2.76 14 days Tue 10/10/23 Tue 11/7/23 NA NA
15 C. INFRASTRUCTURE 0 Rp0 Rp2,298,200,000 5.22 14 days Mon 8/7/23 Mon 9/4/23 NA NA
16 Direksi keet 90 m2 Rp4,250,000 Rp382,500,000 0.87 7.33 days Mon 8/7/23 Mon 8/21/23 NA NA
17 Laboratorium 45 m2 Rp4,250,000 Rp191,250,000 0.43 7.33 days Thu 8/10/23 Thu 8/24/23 NA NA
18 Clinic Facilities 45 m2 Rp4,250,000 Rp191,250,000 0.43 7.33 days Thu 8/10/23 Thu 8/24/23 NA NA
19 Material Warehouse 108 m2 Rp3,800,000 Rp410,400,000 0.93 7.33 days Thu 8/10/23 Thu 8/24/23 NA NA
20 Worker's Camp 90 m2 Rp3,800,000 Rp342,000,000 0.78 7.33 days Mon 8/7/23 Mon 8/21/23 NA NA
21 Workshop 120 m2 Rp3,800,000 Rp456,000,000 1.04 7.33 days Thu 8/10/23 Thu 8/24/23 NA NA
22 Sharing Bathroom & Toilet 36 m2 Rp3,500,000 Rp126,000,000 0.29 7.33 days Mon 8/7/23 Mon 8/21/23 NA NA
23 Water reservoirs 18 m3 Rp5,600,000 Rp100,800,000 0.23 14 days Mon 8/7/23 Mon 9/4/23 NA NA
24 Water and sewerage systems 175 m1 Rp560,000 Rp98,000,000 0.22 14 days Mon 8/7/23 Mon 9/4/23 NA NA
25 D. OTHERS 0 Rp0 Rp340,100,000 0.77 6.67 days Mon 8/7/23 Fri 8/11/23 NA NA
26 Laptop 4 lot Rp20,000,000 Rp80,000,000 0.18 3.33 days Mon 8/7/23 Fri 8/11/23 NA NA
27 Printer 4 Rp9,000,000 Rp36,000,000 0.08 3.33 days Mon 8/7/23 Wed 8/9/23 NA NA
28 Dispenser air minum 2 Rp2,450,000 Rp4,900,000 0.01 3.33 days Mon 8/7/23 Wed 8/9/23 NA NA
29 Genset kap. 12 kVa 2 Rp60,000,000 Rp120,000,000 0.27 3.33 days Mon 8/7/23 Wed 8/9/23 NA NA
30 Radio RIG 1 Rp65,000,000 Rp65,000,000 0.15 3.33 days Mon 8/7/23 Wed 8/9/23 NA NA
31 Bak sampah 9 Rp3,800,000 Rp34,200,000 0.08 3.33 days Mon 8/7/23 Wed 8/9/23 NA NA
32 III. PREPARATION 0 Rp0 Rp249,500,000 0.57 10 days Mon 8/28/23 Mon 9/18/23 NA NA 9/3
33 Land clearing 5848 m2 Rp0 Rp0 0 10 days Mon 8/28/23 Fri 9/15/23 NA NA TBA-C 1,TBA-C 2,TBA-C 3,TBA-G 1,TBA-G 2
34 APD 1 lot Rp7,500,000 Rp7,500,000 0.02 1.33 days Mon 8/28/23 Tue 8/29/23 NA NA TBA-G 3
35 Direksi keet 160 m3 Rp450,000 Rp72,000,000 0.16 0.67 days Mon 8/28/23 Mon 8/28/23 NA NA
36 Operasional 1 lot Rp50,000,000 Rp50,000,000 0.11 9.33 days Mon 8/28/23 Thu 9/14/23 NA NA TBA-G 1,TBA-G 2,TBA-G 3
37 Electrical & watersource 1 lot Rp75,000,000 Rp75,000,000 0.17 5.33 days Mon 8/28/23 Wed 9/6/23 NA NA TBA-G 1,TBA-G 2,TBA-G 3
38 Shop drawing, as built drawing & engineering 1 lot Rp45,000,000 Rp45,000,000 0.1 9.33 days Wed 8/30/23 Mon 9/18/23 NA NA
39 IV. DETONATOR 20x15 0 Rp0 Rp960,526,000 2.18 75.33 days? Mon 9/4/23 Fri 1/12/24 NA NA
40 a. Soil work 0 Rp0 Rp14,490,000 0.03 33 days? Mon 9/4/23 Tue 10/3/23 NA NA
41 Land clearing 500 m2 Rp0 Rp0 0 5.33 days Mon 9/4/23 Wed 9/13/23 NA NA TBA-C 1,TBA-C 2,TBA-C 3
42 Bouwplank 90 m1 Rp50,000 Rp4,500,000 0.01 0.67 days Mon 9/4/23 Mon 9/4/23 NA NA TBA-C 4,TBA-C 5,TBA-C 6
43 Soil excavation 40.5 m3 Rp150,000 Rp6,075,000 0.01 4 days Thu 9/7/23 Thu 9/14/23 NA NA TBA-C 6,TBA-C 7,TBA-C 8
44 Sand fill 2.7 m3 Rp450,000 Rp1,215,000 0 4.67 days Mon 9/18/23 Tue 9/26/23 NA NA TBA-C 1,TBA-C 2
45 Lean concrete 1.35 m3 Rp2,000,000 Rp2,700,000 0.01 7 days Wed 9/27/23 Tue 10/3/23 NA NA TBA-C 3,TBA-C 4,TBA-C 5
46 Lean elevation 0 m3 Rp0 Rp0 0 5 days NA NA NA NA
47 b. Concrete work 0 Rp0 Rp345,704,000 0.79 50.67 days Fri 9/29/23 Fri 1/12/24 NA NA
48 Foot plat 1000x1000 mm 9.45 m3 Rp5,600,000 Rp52,920,000 0.12 20.67 days Fri 9/29/23 Fri 11/10/23 NA NA TBA-C 1,TBA-C 2,TBA-S 1,TBA-S 2,TBA-S 3
49 Edge beam 200x250 mm 8.5 m3 Rp5,600,000 Rp47,600,000 0.11 20.67 days Fri 9/29/23 Fri 11/10/23 NA NA TBA-C 3,TBA-C 4,TBA-S 5,TBA-S 6,TBA-S 7
50 Edge beam 200x200 mm 0.16 m3 Rp5,600,000 Rp896,000 0 20.67 days Fri 9/29/23 Fri 11/10/23 NA NA TBA-C 1,TBA-C 2,TBA-S 1,TBA-S 2,TBA-S 3
51 Column 200x250 mm 3.6 m3 Rp5,600,000 Rp20,160,000 0.05 20.67 days Thu 10/5/23 Thu 11/16/23 NA NA TBA-C 3,TBA-C 4,TBA-S 5,TBA-S 6,TBA-S
52 Column 200x200 mm 1.98 m3 Rp5,600,000 Rp11,088,000 0.03 20.67 days Thu 10/5/23 Thu 11/16/23 NA NA TBA-C 1,TBA-C 2,TBA-S 1,TBA-S 2,TBA-S
53 Column 150x150 mm 0.47 m3 Rp5,600,000 Rp2,632,000 0.01 20.67 days Fri 10/6/23 Fri 11/17/23 NA NA TBA-C 3,TBA-C 4,TBA-S 5,TBA-S 6,TBA-S
54 Beam 150x200 mm 5.1 m3 Rp5,600,000 Rp28,560,000 0.06 20.67 days Fri 12/1/23 Fri 1/12/24 NA NA
55 Ringbalk 150x150 mm 1.58 m3 Rp5,600,000 Rp8,848,000 0.02 20.67 days Fri 12/1/23 Fri 1/12/24 NA NA
56 Floor 100 mm 30 m3 Rp5,600,000 Rp168,000,000 0.38 20.67 days Fri 12/1/23 Fri 1/12/24 NA NA
57 Ramp 1 unit Rp5,000,000 Rp5,000,000 0.01 7.33 days Tue 12/5/23 Tue 12/19/23 NA NA TBA-C 1,TBA-C
58 c. Wall work 0 Rp0 Rp217,375,000 0.49 36 days Thu 10/5/23 Tue 12/19/23 NA NA
59 Brick wall 245 m2 Rp155,000 Rp37,975,000 0.09 20.67 days Thu 10/5/23 Thu 11/16/23 NA NA TBA-C 3,TBA-C 4,TBA-S 5,TBA-S 6,TBA-S
60 Plaster and skim wall 490 m2 Rp115,000 Rp56,350,000 0.13 14 days Thu 11/16/23 Thu 12/14/23 NA NA TBA-C 3,TBA-C 4,T
61 Steel door 2 unit Rp27,000,000 Rp54,000,000 0.12 1.33 days Thu 11/16/23 Fri 11/17/23 NA NA TBA-C 1,TBA-C 2,TBA-S 1,TBA-S 2,TBA-S
62 Air vent 100 unit Rp470,000 Rp47,000,000 0.11 14 days Thu 11/16/23 Thu 12/14/23 NA NA TBA-G 1,TBA-G 2
63 Wall painting 490 m2 Rp45,000 Rp22,050,000 0.05 10 days Tue 11/28/23 Mon 12/18/23 NA NA TBA-C 1[200%]
64 d. Roof work 0 Rp0 Rp354,522,000 0.81 46.67 days Wed 10/4/23 Mon 1/8/24 NA NA
65 Roof frame 462 m2 Rp290,000 Rp133,980,000 0.3 20.67 days Wed 10/4/23 Wed 11/15/23 NA NA TBA-S 3,TBA-S 4,TBA-S 5,TBA-S 6
66 Metal roof 462 m2 Rp380,000 Rp175,560,000 0.4 10 days Wed 11/15/23 Tue 12/5/23 NA NA TBA-S 6,TBA-S 7
67 Roofmesh 462 m2 Rp56,000 Rp25,872,000 0.06 10 days Tue 12/5/23 Mon 12/25/23 NA NA TBA-S 6,T
68 Lisplank 78 m1 Rp245,000 Rp19,110,000 0.04 10 days Tue 12/19/23 Mon 1/8/24 NA NA
69 e. Drainage work 0 Rp0 Rp28,435,000 0.06 14.67 days Mon 11/6/23 Fri 12/1/23 NA NA
70 Concrete floor 50 mm 3.9 m3 Rp2,550,000 Rp9,945,000 0.02 13.33 days Mon 11/6/23 Fri 12/1/23 NA NA TBA-C 1,TBA-C 2,TBA-C 3
71 Drainage 86 m1 Rp215,000 Rp18,490,000 0.04 14 days Mon 11/6/23 Mon 12/4/23 NA NA TBA-C 4,TBA-C 5,TBA-C 6
72 V. DYNAMITE 20x12 0 Rp0 Rp813,326,000 1.85 115.33 days Mon 9/11/23 Tue 3/26/24 NA NA
73 a. Soil work 0 Rp0 Rp10,660,000 0.02 32.67 days Mon 9/11/23 Wed 10/4/23 NA NA
74 Land clearing 375 m2 Rp0 Rp0 0 4.67 days Mon 9/18/23 Tue 9/26/23 NA NA TBA-C 1,TBA-C 2,TBA-C 3
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
12/28
S3
S7
S3
TBA-S 7
TBA-S 3
6,TBA-S 7
TBA-C 3,TBA-C 4,TBA-S 5,TBA-S 6,TBA-S 7
TBA-C 1,TBA-C 2,TBA-S 1,TBA-S 2,TBA-S 3
TBA-C 1,TBA-C 2,TBA-S 1,TBA-S 2,TBA-S 3
1,TBA-C 2,TBA-S 1,TBA-S 2,TBA-S 3
TBA-S 7
A-C 4,TBA-S 5,TBA-S 6,TBA-S 7
,TBA-S 3
A-G 2
[200%],TBA-C 2[200%],TBA-C 3[200%],TBA-C 4[200%]
BA-S 6,TBA-S 7
TBA-G 1
A-C 3
TBA-C 6
3/13
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
3/1
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: MalinauNeo
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Mon 8/21/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress