Construction Schedule Bhubaneswar

Project Name: V CRAFT Strart Date: 10/6/2023 Total Duration:

Project Manager: Vijay End Date: 5/25/2025

TASK DESCRIPTION STATUS IN CHARGE START DATE END DATE DURATION


Earth work Not Started 10/6/2023 11/25/2023 50
PCC (for Foundation) Not Started 10/16/2023 12/5/2023 50
Brick Masonry Not Started 10/18/2023 12/8/2023 51
Column &Retaing Wall Not Started 10/24/2023 12/20/2023 57
PCC (for Foundation) Not Started 11/16/2023 12/5/2023 19
Reinforement&Centring forNot Started 11/20/2023 12/20/2023 30
Filling Fondation &Plinth Not Started 12/22/2023 12/27/2023 5
Raft concreting Not Started 12/26/2023 1/5/2024 10
Column&Retaining Wall ( Not Started 1/10/2024 1/30/2024 20
Filling Basement Floor LvL Not Started 1/20/2024 1/30/2024 10
P C C (Below B.L Not Started 1/24/2024 2/3/2024 10
Column (B. Floor) Not Started 2/2/2024 4/10/2024 68
Retaining Wall (Basement Not Started 2/4/2024 4/10/2024 66
Beams&Slab(B.Floor) Not Started 2/6/2024 6/10/2024 125
Column(G.F) Not Started 3/10/2024 6/15/2024 97
Beams&Slab(G.Floor) Not Started 3/16/2024 7/15/2024 121
Column(F.Floor) Not Started 4/14/2024 7/20/2024 97
Beams&Slab(F.Floor) Not Started 4/20/2024 8/20/2024 122
Brick Masonry (B.Floor) Not Started 5/10/2024 7/5/2024 56
Column(S.Floor) Not Started 5/24/2024 9/20/2024 119
Plastering (B.F) Not Started 5/26/2024 7/15/2024 50
Beams&Slab(S.Floor) Not Started 5/30/2024 10/30/2024 153
Brick Masonry (G.Floor) Not Started 6/16/2024 7/30/2024 44
Plastering (G.Floor) Not Started 6/26/2024 8/10/2024 45
Column(T.Floor) Not Started 7/4/2024 12/5/2024 154
Beams&Slab(T.Floor) Not Started 7/10/2024 1/10/2025 184
Column(F.Floor) Not Started 7/16/2024 1/15/2025 183
Beams&Slab(F.Floor) Not Started 7/20/2024 2/20/2025 215
Brick Masonry (First Floor) Not Started 8/6/2024 9/25/2024 50
Plastering (First Floor) Not Started 8/16/2024 10/5/2024 50
Column(Fifth Floor) Not Started 8/24/2024 2/25/2025 185
Beams&Slab(Fifth Floor) Not Started 8/30/2024 3/25/2025 207
Brick Masonry (S.Floor ) Not Started 9/30/2024 10/25/2024 25
Plastering (S.Floor ) Not Started 10/8/2024 11/5/2024 28
Brick Masonry (T.Floor ) Not Started 10/30/2024 12/20/2024 51
Plastering (T.Floor) Not Started 11/10/2024 12/30/2024 50
Brick Masonry(Fifth Floor ) Not Started 1/10/2025 3/5/2025 54
Plastering (Fifth Floor ) Not Started 1/16/2025 3/15/2025 58
Plastering (Out Side ) Not Started 3/10/2025 5/25/2025 76
Not Started 0
Complete Not Started 10/6/2023 5/25/2025 597
ar
597