SPECIFICATIONS
FOUNDATION BOLT 30 MM
FDL DIA 'ØD'
L1 7000 X 3 MM
L2 LANTERN CARRIAGE WITH HEAD FRAME
L2 7000 X 3 MM
L
L3 7000 X 4 MM
FOUNDATION BOLT G3
NO OF HOLES 8 NOS
OVERLAPPING
PCD
ØA
NOTES:-
1. ALL DIMENSIONS ARE IN MM.
2. MATERIALS:
1200 MM INBUILT POWER 2.1 SHAFT:GRADE IS 2062 E350.
TOOL 2.2 BASE PLATE : AS PER IS 2062 E250.
2.3 FOUNDATION BOLTS - EN8 GRADE.
2.4 PIPE AS PER IS 1239 PART - I.
3. FINISHING : HOT DIP GALVANIZED
Ø HOLE 65 MICRONS AVERAGE
4. TOLERANCE AS PER IS 2102 (PART-I), TABLE -1,
VERY COARSE.
POLE BOTTOM 5. GALVANIZING COATING THICKNESS 86 MICRONS
'D2' AVERAGE.
6. MAKE OF THE POLE 'MOHAN INDUSTRIES'.
CLIENT
CONTRACTOR
WINDOW DETAILS
MANUFACTURER
TITLE 20 MTR LONG HIGH MAST POLE WITH ALL ACCESSORIES 23.12.2022