Questions Option A B
1 Periodical medical examination is carried out for every? 3 years 5 years
2 The workman inspector shall be employed if the number of persons employed 500 exceed ? 1500
3 The number of members are nominated in the safety committee is? 5 10
4 The quantity of drinking water to be provided in a mine or 1 lit
any part thereof shall
2 lit be on a scale of atleast.......for eve
5 The scale of latrine accommodation shall be atleast one seat for every......males 25 or females employed
50 in every min
6 The first aid room shall have a floor space of not less than10...?sq.m 14 sq.m
7 At every mine where more than ...persons are ordinarly employed;there50 shall be provided adequete
25 and suitable s
8 Register of employes;termination of employment;noticeFORM of work A is maintainedFORM in the?
B
9 No adult shall work above ground ina mine for more than36....in hoursany week? 24 hours
10 Maximum maternity leave allowed is? 4 weeks 6 weeks
11 The maximum working hours in a day is? 6 hours 8 hours
12 No woman shall be employed in any mine above ground6exept AM to between
7 PM the5hours AM toof..?6 PM
13 Adult means a person who has completed? 16 th year 18 th year
14 Reportable injury means any injury which involves the enforced24 hoursabsence of the 36 hours
injured person from work for a per
15 Any injury which involves the permanant loss of any partMinor or section
injuryof the body
Reportable
is called?injury
16 The drinking water points shall not be situated within ....of 6 many washing place;urinal
15m or latrine?
17 A person appointed to superinted the lowering and raising Banksman
of persons tools andOnsetter
materials and to to transmit signal
18 A competent person means he is attained the age of? 18 years 16 years
19 Accident due to firedamp explosion can be prevented by-not allowing drunk person by usingtowellworkmaintained
in the mine flame safety
20 In case of C.I or R.I fails to inspect the place of accident within........of
24 hours occurance
36 hours
the work may be resumed?
21 What are the features of good wage system- it should be fair for workers
employershouldand employee
be satisfied by the wag
22 Stopping of work by body of persons employed in any industry lockouts under a comman strikesunderstanding of a perticular dem
23 The blasting which is done in the face without giving anyCut freeblasting
face is called asSolid
- blasting
24 FAB is prepared - as near as possible to at the irrespirable
surface zone
25 In case any member of rescue team feels discomfort during rescur
thework
rescueshould
work-only
be continue
that person return to the FAB
26 Winding rope shall be test once in ...? a day 7 days
27 Indirect loss is ....times more than the direct loss due to accident? 1 2
28 The termination of the services of a worker by way of disciplinary
Retrenchmentaction is called?
lockout
29 Every worker has to go vocational training once in..........years? 3 5
30 The most important function of the management is? Organisation Planning
31 Minimum number of persons to form the trade union is.. 5 6
32 The protective footwear shall be supplied at intervals of 3 atleast...?
months 1 year
33 The shot firer shall carefully test for inflammable gas at all12places
m within a radius
18 mof.....of the place of firing?
34 No solid blasting shall be done when a geological disturbance has been 0.30%
detected or methane 0.50%exceeds....?
35 The cogging members shall be not less than .....in length?2.5 m 1.8 m
36 No workings shall be made and no work of extraction or 30 reduction
m of pillars 45
shall
m be conducted any point within.....
37 No road for trucks and dumper shall have a gradient steeper 1 in 6than atleast.....at
1 inany7 place?
38 Every traveling roadway shall be not less than atleast........in
1.2mheight? 1.5 m
39 In signalling the code for raise the cage is ? 1 rap 2 raps
40 Financial year of the mine means period of 12 months is..? 31 dec to 31 dec 1st day april to 31 st of march
41 Which of the following is not a reason of accident- misadventure drinking water in UG
42 Accident due to overhead lines are categorised in- accident due to explosive
accident due to falls
43 Accident due to blown out shots are categorised in - accident due to explosive
accident due to falls
44 the lowest part of the mine entrances shall be ……above 5m HFL. 3m
45 HFL stands for High Fluoride level Highest flood level
46 No coal winning machinery shall operate at the face when methane exceeds-
0.50% 1%
47 Blasting in OCM shall be done during night during day
48 Through the haulage roadway any person can travel
only mine manager can travel at any ti
49 A compansation paid by an employer to an employee in exchange
money exchange
of workdone
wagesis called as-
50 Skilled labour shall give………….wages than unskilled labour.
more less
51 CIL is an example of line organisation functional organization
52 the strike in which strikers lay down their tools is a- stay away strike token or protest strike
53 The blasting in development gallery without giving cut isCut
called
blasting
as blasting in face
54 air within 4.5m of face shall not less than 200 m3/min 384 m3/min
55 The plans and section shall be maintained and up to date 3months
which is not earlier
2months
than?
56 An accident is known as reportable when period of enforced 24hours
absence of injured
36hours
person exceeds?
57 Rescue station is situated within the radius of? 30km 35km
58 Full form of SCAMP is? strata control and management
strata controlplan
and monitoring plan.
59 Explosives in any hole in degree 2 seam shall not exceed?1000g 565g
60 As per regulation detonator shall be approved by? DGMS manager
61 How many sets of self contained breathing appratus should 56 be provided in Rescue
54 station?
62 The wet bulb temperature in any working place does not30degree
exceed?C 30.5degree C
63 Before starting depillaring permission shall be taken from? manager DGMS
64 All haulage and travelling roads and roadways shall be inspected
7days once in ? 15days
65 workmens Inspector writes a report in ? Form U Form P
66 As per cmr what should be representetive factor of plans?
1:2000 or 1:1000 2000:1 or 1000:1
67 At what distance solid blasting can not be done within any 90m geological disturbances?
70m
68 As per mine rule what is the floor space of first aid room?
less than 10sq mtr not less than 10sq mtr
69 As per standard of ventillation methane at any place
not more
in the
than
mine
0.75percent
should
not more
be?than 0.5percent
70 surface and u.g plans shall show suface contours at a interval 2.5mof? 3m
71 Manager appointed under regulation ? reg.25 reg.26
72 Annual return in respect of the preceeding year shall be submitted
1st day of february
on or before
31st march
73 As per Cmr 2017, what is the provision no. for duties and responsibilities47 of overman? 48
74 Provision regarding misfire is given in regulation no. ……. In CMR 2017. 204 207
75 A person riding on a Tub of direct haulage and falls henceaccident
get injured.
due to
This
fallaccident
accidentisdue
categorised
to rope in
76 the size of pillar for 120 m depth having width of gallery 3.6 is 19.5 30.5
77 the diameter of the winding drum is …… times the diameter of rope. 100 200
78 By using Automatic contrivance, the speed of the cage during
1 m/slanding is not exceed
1.2 m/s-
79 Rope shall be recapped once in 3 months 6 month
80 signalling arrangement shall be provided for the haulage40 exceeding
m 50 m
81 the voltage of the signalling arrangement shall not exceeds10 v 110 v
82 every man hole shall be white washed both inside and for 0.1
a distance
m of not less
0.5 mthan……… around the aperture.
83 haulage rope should have factor of safety not less than …. 10 7
84 The parting left between any two seams or sections shall5m not be less than …………..
7m In thickness
85 No working shall be made from any mine boundry within3monthsa distace of- 15m
86 The sirdar should inspect his district with …. Of commencement
1hr of work. 2hr
87 The provision no. for standard of ventillation as per CMR 2017 is 130 153
88 Two seams are said to have contiguous seam when parting 3m between them is5m less than
89 the full form of DGMS is Directorate generalDirector
of minesGeneral
safety of Mines Safety
90 P5 explosive used for solid blasting cut blasting
91 CIMFR stands for Central Institute of mining
center ofand
investigation
fuel research
of mines fuel re
92 The safety committee shall meet atleast once in? 15 days 7 days
93 The vessals where water is stored if the water is not supplied
everyby
daytaps;shall be2 cleaned
days once in?
94 If the number of males employed in the mine is 253 then the number of latrines 4 required is? 5
95 No person below.....years of age shall be allowed to work in any mine or 16 part thereof? 18
96 Who frame the systematic support rule Asst. Manager Safety manager
97 Concillation officer shall send a report to govt. within .....days of start of concillation
7 proceedings?
14
98 After 1957, coal mines regulations is updated on- 27th Nov., 2017 17th Nov., 2017
99 No gallery in a seam or section shall exceed atleast .....in3width?
m 2.5 m
100 who among the following comes under category of supervisior- safety officer asst manager
C D Ans
6 years 4 years B
1000 100 A
13 15 C
3 lit 4 lit B
100 150 B
20 sq.m 18 sq.m A
75 100 A
FORM C FORM D B
48 hours 60 hours C
9 weeks 12 weeks D
9 hours 12hours C
6 AM to 6 PM 5 AM to 7 PM A
20 year 23 year B
72 hours 144 hours C
Fatal injury Serious bodily injuryD
10m 12 m A
Trammer Insetter A
20 years 23 years C
by increasing production
by dressing B
48 hours 72 hours D
skilled worker mustall gain
of the
moreabove
wages than
D unskilled
layoffs all of the above B
controlled blasting secondary blasting B
in the seald off areanear the shaft stationA
whole team return to twothepersons
FAB from the C team return to the FAB
14 days 30 days D
3 4D
dismissal layoff C
6 4B
staffing Controlling A
7 8C
2 years 6 months D
22 m 25 m B
0.80% 1% B
1.5 m 1.2 m D
100 m 60 m B
1 in 10 1 in 14 D
1.8 m 2.5 m C
3 raps 4 raps A
1 st day jan to 31 st none
dec B
lack of supervision fault of co workers B
accident due to electricity
combustible material C
accident due to electricity
combustible material A
15m 7m B
High Flood Level none of the above C
1.20% 5% A
at evening at any time B
only haulge operatorthecan
person
travelwho engaged
D in work of inspection and have have legal order from superior official can travel
bonus all of the above B
same not justify A
committee organization
project organizationA
tools down strike wild cat strike C
solid blasting pre spliting C
284 m3/min 6 m3/min C
15days 1 month A
48hours 72hours D
28km 32km B
strata control and managing plannone B
500g 556g B
Regional Inspector chief Inspector D
52 48 B
33.5degree C 35.5degree C C
District authority All of these. B
30days 2-3months A
Form WI Form I A
both none B
20m 60m D
at least 100sq mtrmore than 100sq mtB
not more than 1.25percent
not more than 19 percent C
5m 4.5 C
reg.27 reg.28 C
31st april 31st december A
37 41 A
177 35 A
accident in haulageaccident due to improper
C signalling
48 28.5 A
50 60 A
1.5 m/s 3 m/s C
1 year 3.5 year B
20 m 30 m D
250 v 30 v D
0.3 m 1m C
8 15 C
9m 3m D
7.5m 30m C
3hr 4hr B
143 123 B
9m 10m C
Direcctor of mines safety
none of the above B
ocm blasting all of the above A
central invention ofnon
minesof and
the above
fuel research
A
6 months 30 days D
5 days 6 days A
6 7C
20 23 B
manager Sirdar C
30 60 B
26th Nov., 2017 07th Nov., 2017 A
4.8 m 5.5 m C
Mining Sirdar all of the above C