Professional Documents
Culture Documents
Welcome
Underpass Site
Key Intersections
In early 2014, the City of Winnipeg initiated The project team has been tasked with As a complex infrastructure project,
a preliminary design study for the Waverley developing a high level design for a grade the preliminary design includes several
Underpass Project. separation of Waverley Street and the CNR interrelated components, including:
Rivers rail line.
The Waverley Street crossing of the CNR Rivers rail line • Land surveys and geotechnical investigations;
has approximately 30,000 vehicles, and an average The design will also include intersection improvements, • Environmental assessments;
of 40 train movements passing through daily. This and bicycle & pedestrian pathway improvements in • Transportation studies, including active
causes significant tra fic disruption he purpose o this the project area. transportation, tra fic, transit, and access anage ent
project is to undertake the preliminary design of • Railway alignment and detour designs;
several grade separation alternatives for the The project does not include changes to the width of • Drainage studies and hydraulic analysis;
Waverley crossing and determine estimated project Waverley north of Taylor, or changes to streets • Road and bridge alternatives design;
costs. outside of the above noted Project Study Area. • Public consultation and stakeholder engagement;
• Cost estimates and construction phasing;
A though the project has been identified as a City • Noise, safety, and risk assessments.
priority, it has not yet received funding in the capital
budget, and therefore there is no current timeline for
construction.
Public Open House | 9 December 2014 | Board 3
Public Consultation
SPRING/SUMMMER 2014 Here are some of the
AUTUMN 2014 WINTER 2015
ROUND 1 stakeholders we’ve met
ROUND 2 with so far:
Constraints
Key Constraints:
Two rail lines must be operational at all times;
Waverley road detour must include two lanes in each d
Construction must not involve closure of Waverley or
prolonged period;
Waverley must not be widened in the residential area
Streets outside of the Project Study Area should not b
Hydro Overhead
Hydro Underground
Gas
Feedermain
Watermain
Sewer
An environmental investigation was A noise study is being completed as part of There are several challenges that the
undertaken as part of this project. the project. project team must deal with regarding
drainage:
A tota of 10 boreho es were conducted on CN right- The project wi ensure that noise impacts on the
of-way and City of Winnipeg properties to a depth of surrounding area are either improved, or at the very • Poor and drainage in the area;
4.5 metres be ow ground surface. Soi s co ected east, stay consistent with the current situation. • Drainage systems in the area that are at or near
were screened for hydrocarbon vapor concentrations capacity;
and se ect soi samp es were submitted for ana ysis. The project wi a so invo ve reconstruction of the • The project area intersects three different and
A tota of 44 samp es were submitted. Based on existing rai embankment and new joint free rai for the drainage districts; and,
aboratory ana ysis, evidence of arsenic exceeding CN Rivers Sub rai crossing. Experience has • Two of those drainage districts are combined sewer
the se ected criteria was found in 1 of the 10 boreho indicated that this may resu t in reductions in vibration districts.
es. A other soi samp es co ected from the site were and noise from rai operations. The underpass wi require a ift station to drain the
one order of magnitude be ow the se ected guide ines project area. The project team is current y working
suggesting the arsenic found in the soi is not wide y out the detai s regarding its size, ocation, capacity,
distributed across the site and further assessment is and out et. The drainage improvements for this
not warranted. project wi ensure that existing drainage cha enges
are not exacerbated, and may actua y improve.
Public Open House | 9 December 2014 | Board 6
Transportation Study
Intersection Capacity Utilization (ICU)
is a measure of how much of an
intersection’s ability to carry its maximum theoretical volume of trafic has been used.
These maps show the ICU during morning (A ) periods for three time periods; existing (2014), during detour (2017), and future road impro
Construction Detours
Detour Options Considered:
• An East side road detour
• A West side road detour
• A North rail detour
• A South rail detour
• A North South one track couplet detour
Key Findings:
• A North rail detour may result in signiicant
permanent impacts to existing buildings and
facilities;
• An East road detour may result in signiicant
permanent impacts to existing buildings and
facilities;
• The South rail and West road detours are
the preferred options;
• Some vehicular movements at the Waverley
and Taylor intersections must be eliminated
for the detour to operate safely and eficiently.
Alternate routes are available.
For the CN rail line to maintain continuous In order ffor Waverley's trafffic volumes to The active transportation and pedestrian
rail operations throughout the duration of continue to low through the area during route must also detour during construction,
construction, a rail detour (shooly) must be construction, a road detour maintaining four and ensure active transportation users and
constructed prior to the construction of the lanes off vehicular trafffic was required. pedestrians are located safely away from
underpass. the construction zone.
The design team had to consider rail operations and
Due to several constraints, including infrastructure, crossing safety, property constraints, infrastructure, An active transportation and pedestrian route will be
land, building, and phasing, a southern rail detour soil conditions, safety concerns, turning radii and road provided on the west side of the Waverley detour,
was deemed most feasible. geometry, among other factors, when deciding where and link to a similar facility on the north side of
to place the detour. A western road detour has been Taylor.
identified as the preferred a ternative.
Public Open House | 9 December 2014 | Board 8
A E
B Waverley Street (Looking North) E Right Turn Lane Waverley Northbound at Taylor
Intersection Improvements
WILKES
GRANT
WAVERLEY ST
Northbound Right Turn lane Eastbound Right Channel
Through Lane
WAVERLEY ST WAVERLEY ST
TAYLOR
HURST
CAMBRIDGE
Waverley & Wilkes/Hurst Recommendations Waverley & Taylor Recommendations Waverley & Grant Recommendations
• Widen Waver ey Street to three anes in each • Twin Tay or Avenue (make it 4 anes) for its entire • Add a second eft turn ane from westbound Grant
direction through the Wi kes intersection to improve ength between Waver ey Street and Lindsay Street; Avenue to southbound Waver ey Street.
capacity; • Add a second eft turn ane from westbound Tay or
• Add a second eft turning ane from eastbound Wi Avenue to southbound Waver ey Street, and
kes Avenue to northbound Waver ey. increase the storage distance;
• Add a third ane northbound from Wi kes to Tay or
as a dedicated right turn ane onto eastbound Tay
or;
• The intersection of Waver ey and Tay or wi be
owered by approximate y 900mm (3 feet) to maintain
c earance under the underpass.
Public Open House | 9 December 2014 | Board 11
Transit
Winnipeg Transit Routes and Stops - Existing Winnipeg Transit Routes and Stops - During Construction Winnipeg Transit Routes and Stops - After
WILKES AVE
W
A
V
E
STERLING LYON
On Street Route/Facility
MUP
MUP
S/BP
Reconstruct Existing MUP
S/BP
WILKES AVE
Off Street Path
MUP Sidewalk
On Street Route/Facility
Bike Boulevard
W
A
V
E
STERLING LYON
Future SWRT Path
Connection to Southwest Rapid Transit Corridor
When will this be built? Will properties be required, either during Will trafffic increase as a result off this project?
A though identified as a regiona infrastructure priority construction or post-construction? The resu ts of the transportation study and traffic
by the City, capita funding has not been set aside nor It is anticipated that the vast majority of the project mode ing indicate that traffic as a who e may
has any funding agreement been signed at this point. can be bui t on City owned and and right-of-way. increase due to overa growth in the southwest
There is no construction time ine at the moment. However, construction easements or sma parce s of quadrant of the city. However, traffic is expected to
and may be needed for the construction of this flow better due to the proposed road and intersection
Will Waverley and Taylor be closed? project. The project team has been in contact with improvements and due to re ieving the congestion
Both Waver ey Street and Tay or Avenue wi remain potentia y affected caused by frequent train crossings.
open to traffic during construction, however some andowners throughout the design process.
vehicu ar movements wi be e iminated. P ease see Will the project involve changes to street
the proposed detour map on Board 7 for detai s about How will transit and active transportation ffunction and design in River Heights, such
how traffic wi flow during construction. work during construction? as the current one-way designation on
Bus routes, bus stops, and active transportation Waverley north off Grant?
How much is this going to cost? pathways wi need to be re ocated or rerouted during No. The project invo ves the pre iminary design of
A major component of this pre iminary design study is construction. See Boards 7, 11 and 12. the underpass, street improvements, pedestrian and
to deve op a high eve cost estimate for the bicyc e infrastructure, and associated intersection
underpass and major road works. A C ass 3 cost Was an overpass considered? improvements within the study area on y. No
estimate wi be provided to the City as part of the An overpass was considered ear y on in the design changes are proposed for the existing street
pre iminary design report. A C ass 3 estimate is process. However, due to heights, c earance functions and patterns in River Heights.
defined by the City of Winnipeg as a construction cost requirements, property impacts, and other
estimate based on a pre iminary design, and is engineering constraints, this option was deemed Is a Sterling Lyon connection to Taylor or
deemed to be accurate within unfeasib e. Pembina still being considered?
+30% to -20% of the fina construction cost. No, this option was examined by the City of
Estimated costs wou d be refined to a higher eve of What are the environmental impacts? Winnipeg, and is no onger being considered. The
detai as part of the detai ed design process. There are no environmenta impacts of note that wou Waver ey
d resu t from this project. Soi samp ing within the ocation continues to be the preferred rai crossing
How will the project be paid ffor? proposed underpass area indicates no issues of ocation, and has been identified as a potentia crossing
Discussions are ongoing; however, the project wi concern, and is consistent with Manitoba Conservation ocation since at east the ear y 1970Us. The right-of
more than ike y be funded by the City of Winnipeg regu ations. The project wou d a so invo ve way and property required for the Waver ey
and other reconstruction of the existing rai bed and rep acement Underpass is
eve s of government, as we as contributions by CN. of the rai tracks in the study area with seam ess rai , arge y assemb ed, and wou d have minima property
The Waver ey Underpass project wi need to be which may decrease vibration and noise from rai impacts. In addition, there is an existing agreement
considered in the City of WinnipegUs Capita activities. in p ace with CN for a grade separated rai crossing
Infrastructure budgeting process. CN Rai way has a at Waver ey, which ob igates the rai way to pay for a
financia ob igation for a portion of rai crossing under Can the rail line be moved out off the city? portion of the crossing.
an existing agreement with the City of Winnipeg. The Rai ways fa under Federa jurisdiction, and cannot be
Federa Government has been approached as an forced to move by the City. Moreover, as a main ine,
infrastructure funding partner, and discussions are moving the ine wou d be extreme y cost y and affect
ongoing with the Provincia Government. Funding severa businesses and industries that re y on regu ar
commitments wi need to be fina ized before the rai service within the city.
project may proceed.
Public Open House | 9 December 2014 | Board 14
Next Steps
If you have any further questions,
please don’t hesitate to contact
the public consultation team:
Brendan Salakoh
Phone: 204-453-2301 ext. 4060
Email: bsalakoh@dillon.ca
MAY 2014 JUNE - SEPT 2014 OCT 2014 - JAN 2015 FEB 2015
David Marsh
Phone: 204-453-2301 ext. 4094
Refine the preferred Email: dmarsh@dillon.ca
Dillon and Develop Submit preliminary
design option
AECOM awarded design design report to PRELIMINARY DESIGN COMPLETED
contract to options City of Winnipeg
complete a
WE
ARE
HERE
TO BE CONFIRMED
www.winnipeg.ca/waverleyunderpass