You are on page 1of 14

Public Open House | 9 December 2014 | Board 1

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Welcome

WE WANT TO HEAR FROM YOU!

Ask questions, give us your


thoughts & ideas, ill out an exit
survey, and tell us what you
think!

The purpose of today’s open house is to


Representatives from the project team are Large scale versions of the drawings can be
provide project information and obtain your
here to answer your questions and address found on the central tables.
feedback and input regarding the Waverley
any concerns you might have.
Underpass Preliminary Design Study.
All open house materials and the exit survey
We want to hear from you. Ask questions, will be posted to the project website.
give us your thoughts and ideas, fill out an
exit survey, and tell us what you think! www.winnipeg.ca/waverleyunderpass
Public Open House | 9 December 2014 | Board 2

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Project Background and Overview


BENEFITS

A major piece of regional infrastructure


will have differing beneits for different
groups. Some of the major beneits are
as follows:

• Relieve trafic congestion in the area;


• Improve safety for drivers, pedestrians,
and active transportation users;
• Discourage cut-through trafic in
existing neighbourhoods.
• Reduce variability in travel times due
to random train crossing events.

Underpass Site

Key Intersections

Project Study Area

In early 2014, the City of Winnipeg initiated The project team has been tasked with As a complex infrastructure project,
a preliminary design study for the Waverley developing a high level design for a grade the preliminary design includes several
Underpass Project. separation of Waverley Street and the CNR interrelated components, including:
Rivers rail line.
The Waverley Street crossing of the CNR Rivers rail line • Land surveys and geotechnical investigations;
has approximately 30,000 vehicles, and an average The design will also include intersection improvements, • Environmental assessments;
of 40 train movements passing through daily. This and bicycle & pedestrian pathway improvements in • Transportation studies, including active
causes significant tra fic disruption he purpose o this the project area. transportation, tra fic, transit, and access anage ent
project is to undertake the preliminary design of • Railway alignment and detour designs;
several grade separation alternatives for the The project does not include changes to the width of • Drainage studies and hydraulic analysis;
Waverley crossing and determine estimated project Waverley north of Taylor, or changes to streets • Road and bridge alternatives design;
costs. outside of the above noted Project Study Area. • Public consultation and stakeholder engagement;
• Cost estimates and construction phasing;
A though the project has been identified as a City • Noise, safety, and risk assessments.
priority, it has not yet received funding in the capital
budget, and therefore there is no current timeline for
construction.
Public Open House | 9 December 2014 | Board 3

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Public Consultation
SPRING/SUMMMER 2014 Here are some of the
AUTUMN 2014 WINTER 2015
ROUND 1 stakeholders we’ve met
ROUND 2 with so far:

1 Present a ternatives and • Residents within the Study Area


1 Inform and communicate project detai preferred options • Area Councillor
GOAL s 2 Demonstrate how concerns have
1 Report on consu tation process • CN
2 Gauge concerns and record been considered and/or addressed
3 Continue communication
2 Report on a feedback and input • Winnipeg umane Society
• Waverley and Rosewood Retirement
Residence
• Reh-Fit Centre
• Piazza De Nardi
RESIDENT MEETINGS
• Winnipeg Rapid Transit Coalition
• Living adjacent to Waver ey and
RESIDENT MEETINGS within project study area
• i4e Winnipeg
• Living adjacent to Waver ey and • City of Winnipeg 5various departments6
within project study area STAKEHOLDER MEETINGS (15 Meetings) • rant emorial Church inden Christian
• Landowners School
MEETINGS/ STAKEHOLDER MEETINGS (19 • Businesses CONSULTATION REPORT
• Pembina Trails School Division
EVENTS/ Meetings) • Property Managers Winnipeg School Division
REPORTS • Landowners • Interest Groups • Par4er Wetlands Conservation Committee
• Businesses • Government Departments
• Property Managers • Other Groups
• Nearby usinesses and Property anagers
• Interest Groups • Area =mployers

PUBLIC OPEN HOUSE


December 9th, 2014 WE ARE
HERE

• Ana yzed feedback • Se ect preferred a ternative

OUTCOMES • Worked with design team to


• Continue working with design team
address issues and concerns • Bina pre iminary design study
• Deve oped design options to address issues and concerns submitted to City of Winnipeg

PRELIMINARY DESIGN COMPLETED

As a part of the project, the team has


Generally, the feedback for the project has
designed a comprehensive public
been positive, and input from stakeholders
consultation program. From June 2014 until
can roughly be grouped into the following
now, the team has met with various
themes:
stakeholders in two separate rounds of
consultations.
• Majority supported the project • Some noted that the Hurst/Waver ey intersection
• Many asked whether Ster ing Lyon to Tay needed improvement
The purpose of the consu tation strategy has been
or/Pembina was sti being considered • Many asked whether the rai ines cou d be moved
to de iver information to key stakeho ders in a time y
• Many asked whether a southern rai detour cou d be outside of the City
manner, whi e receiving input on potentia project
made permanent • Most supported the eastern road detour option
impacts and design options. The consu tation team
• Most supported a Tay or twinning a the way • Some e)pressed concern that cut*through traffic in
works direct y with the design team to he p address
through to Kenaston River Heights wou d increase as a resu t of the
stakeho der concerns, identify a ternatives, and
• Most noted that the southbound Waver ey (from project
mitigate potentia impacts where possib e.
westbound Tay or) movement needed to be • Many asked whether traffic wou d increase as a resu
improved t of the project
• A few were concerned about project costs and benefits
Public Open House | 9 December 2014 | Board 4

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Constraints
Key Constraints:
Two rail lines must be operational at all times;
Waverley road detour must include two lanes in each d
Construction must not involve closure of Waverley or
prolonged period;
Waverley must not be widened in the residential area
Streets outside of the Project Study Area should not b

Hydro Overhead

Hydro Underground

Gas

Feedermain

Watermain

Sewer

As with most major infrastructure projects,


Constraints can be classified into several Property
the design team has to deal with existing
categories, including: As with any major project in a built up area, there are
constraints and challenges.
property, land, and building constraints. While most
Operations of the project can be built on City land, there will be
The map above outlines some of the infrastructure
A key project requirement is that the two rail lines and impacts to some adjacent properties during
challenges that the project team must consider while
four anes of Waver ey Street traffic continue to flow construction, and in some cases, permanently.
designing the underpass. All need to be considered
throughout the duration of construction. This can
and addressed as part of the preliminary design.
pose a challenge in terms of construction staging and
design. Natural Features
The project team must also consider the natural
Infrastructure characteristics of the area, including land drainage and
The project team must carefully work around both above soil conditions.
ground and subsurface infrastructure in the design,
inc uding and drainage sewers, water mains, fiber
optics, power cables, distribution lines, and roads.
Public Open House | 9 December 2014 | Board 5

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Environmental, Noise, and Drainage Studies

An environmental investigation was A noise study is being completed as part of There are several challenges that the
undertaken as part of this project. the project. project team must deal with regarding
drainage:
A tota of 10 boreho es were conducted on CN right- The project wi ensure that noise impacts on the
of-way and City of Winnipeg properties to a depth of surrounding area are either improved, or at the very • Poor and drainage in the area;
4.5 metres be ow ground surface. Soi s co ected east, stay consistent with the current situation. • Drainage systems in the area that are at or near
were screened for hydrocarbon vapor concentrations capacity;
and se ect soi samp es were submitted for ana ysis. The project wi a so invo ve reconstruction of the • The project area intersects three different and
A tota of 44 samp es were submitted. Based on existing rai embankment and new joint free rai for the drainage districts; and,
aboratory ana ysis, evidence of arsenic exceeding CN Rivers Sub rai crossing. Experience has • Two of those drainage districts are combined sewer
the se ected criteria was found in 1 of the 10 boreho indicated that this may resu t in reductions in vibration districts.
es. A other soi samp es co ected from the site were and noise from rai operations. The underpass wi require a ift station to drain the
one order of magnitude be ow the se ected guide ines project area. The project team is current y working
suggesting the arsenic found in the soi is not wide y out the detai s regarding its size, ocation, capacity,
distributed across the site and further assessment is and out et. The drainage improvements for this
not warranted. project wi ensure that existing drainage cha enges
are not exacerbated, and may actua y improve.
Public Open House | 9 December 2014 | Board 6

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Transportation Study
Intersection Capacity Utilization (ICU)
is a measure of how much of an
intersection’s ability to carry its maximum theoretical volume of trafic has been used.
These maps show the ICU during morning (A ) periods for three time periods; existing (2014), during detour (2017), and future road impro

2014 AM Intersection Capacity Utilization

2037 AM Intersection Capacity Utilization

ICU 0-75% Little to moderate congestion

ICU 75-85% Moderate congestion

ICU 85%-100% Typical rush hour congestion


Detour AM Intersection Capacity Utilization
ICU 100%+ Over capacity, signiicant trafic delays

In order to make recommendations on


turning lane lengths, signal timing, and to upcoming construction work on the Pembina Highway • Based on traffic mode ing, in 2014, the Waver ey
intersection improvements, the project team underpass at Jubi ee, and other projects identified in and Tay or intersection is over capacity and the Waver
undertook a comprehensive transportation the CityUs capita budget. ey and Wi kes intersection is approaching maximum
study. capacity during rush hour. As a resu t, improvements
The trafffic study's key findings include: to key intersections were suggested. See Board 10.
The study inc uded traffic counts, pedestrian/cyc ist
• Predominant turning movements at Waver ey and • The detour wi operate we if certain vehicu ar
counts, vo ume projections, and an active
Tay or are northbound to eastbound during the AM movements are e iminated. See Board 7.
transportation (AT) faci ity review. The team used
traffic software mode ing for short, medium, and ong- peak (right turn during morning rush hour) and
westbound to southbound during the PM peak ( eft turn • In 2037, the furthest date to which traffic projections
term time ines, taking into account popu ation growth,
during evening rush hour). are made, the intersection wi operate near capacity
deve opment, and commuting patterns in the cityUs
with the intersection improvements. See Board 10.
southwest quadrant. The study a so accounts for
potentia traffic changes due
Public Open House | 9 December 2014 | Board 7

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Construction Detours
Detour Options Considered:
• An East side road detour
• A West side road detour
• A North rail detour
• A South rail detour
• A North South one track couplet detour

Key Findings:
• A North rail detour may result in signiicant
permanent impacts to existing buildings and
facilities;
• An East road detour may result in signiicant
permanent impacts to existing buildings and
facilities;
• The South rail and West road detours are
the preferred options;
• Some vehicular movements at the Waverley
and Taylor intersections must be eliminated
for the detour to operate safely and eficiently.
Alternate routes are available.

For the CN rail line to maintain continuous In order ffor Waverley's trafffic volumes to The active transportation and pedestrian
rail operations throughout the duration of continue to low through the area during route must also detour during construction,
construction, a rail detour (shooly) must be construction, a road detour maintaining four and ensure active transportation users and
constructed prior to the construction of the lanes off vehicular trafffic was required. pedestrians are located safely away from
underpass. the construction zone.
The design team had to consider rail operations and
Due to several constraints, including infrastructure, crossing safety, property constraints, infrastructure, An active transportation and pedestrian route will be
land, building, and phasing, a southern rail detour soil conditions, safety concerns, turning radii and road provided on the west side of the Waverley detour,
was deemed most feasible. geometry, among other factors, when deciding where and link to a similar facility on the north side of
to place the detour. A western road detour has been Taylor.
identified as the preferred a ternative.
Public Open House | 9 December 2014 | Board 8

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Draft Concept - Overall Plan

A E

The project team has developed the concept


The project team arrived at this concept for
above for the preliminary design.
the preliminary design after considering:
The design includes an underpass of the CN
• An overpass option. Due to clearance requirements
mainline, roadway and active transportation
and grades, an overpass option would have
improvements along Waverley between Grant and
significant impacts on surrounding properties and
Wilkes, connections to the future Southwest Rapid
neighbourhoods.
Transit Corridor for transit vehicles and to the
associated active transportation corridor, and • No grade separated crossing. The transportation
intersection improvements at three of the key study indicated that existing congestion challenges
intersections. The project team also recommends would increase in the future without an improved
making Taylor four lanes, from Waverley to Lindsay. crossing.
Public Open House | 9 December 2014 | Board 9

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Draft Concept - Cross Sections

A The Waverley Underpass D Taylor Avenue - West of Waverley (Looking East)

B Waverley Street (Looking North) E Right Turn Lane Waverley Northbound at Taylor

C Hurst Avenue - East of Waverley (Looking East)


These cross sections illustrate the changes
The design of the underpass is shown in A.
to the roadways and active transportation
networks.
The tracks are raised by approximately 1 foot. The
preferred option for the rail bridge is a cast-in-place
In the sections above, the blue marks pedestrian
two track ballast deck girder bridge. The bridge has
pathways, the green marks active transportation
been designed to meet minimum vehicle clearance
pathways, and the brown marks roadways.
requirements, with 5.3 metres from the road surface
to the bottom of the bridge structure.
Public Open House | 9 December 2014 | Board 10

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Intersection Improvements
WILKES

Major recommendations for intersection improvements based on the trafffic stu


The project team has recommended various other improvements to turning movements, pedestri

Dual Eastbound Left

GRANT
WAVERLEY ST
Northbound Right Turn lane Eastbound Right Channel
Through Lane

Dual Westbound Left

WAVERLEY ST WAVERLEY ST

Westbound Transit Queue Jump

Through Lane Dual Southbound Left

TAYLOR
HURST

CAMBRIDGE

Waverley & Wilkes/Hurst Recommendations


Waverley & Taylor Recommendations Waverley & Grant Recommendations

Waverley & Wilkes/Hurst Recommendations Waverley & Taylor Recommendations Waverley & Grant Recommendations

• Widen Waver ey Street to three anes in each • Twin Tay or Avenue (make it 4 anes) for its entire • Add a second eft turn ane from westbound Grant
direction through the Wi kes intersection to improve ength between Waver ey Street and Lindsay Street; Avenue to southbound Waver ey Street.
capacity; • Add a second eft turn ane from westbound Tay or
• Add a second eft turning ane from eastbound Wi Avenue to southbound Waver ey Street, and
kes Avenue to northbound Waver ey. increase the storage distance;
• Add a third ane northbound from Wi kes to Tay or
as a dedicated right turn ane onto eastbound Tay
or;
• The intersection of Waver ey and Tay or wi be
owered by approximate y 900mm (3 feet) to maintain
c earance under the underpass.
Public Open House | 9 December 2014 | Board 11

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Transit

Winnipeg Transit Routes and Stops - Existing Winnipeg Transit Routes and Stops - During Construction Winnipeg Transit Routes and Stops - After

Winnipeg Transit will need to alter some of


There is the potential for the transit network
their routes and relocate a handful of bus
to connect into the future Phase 2 of the
stops in order to maintain transit operations
SouthWest Rapid Transit Corridor.
during construction.
Queue jumps and diamond lanes could potentially be
The maps above show where routes and stops are
implemented along Hurst Way and Wilkes Avenue in
located currently, as well as where they will be
the Waverley area, to provide improved transit service
located after construction.
to southwest Winnipeg.
Public Open House | 9 December 2014 | Board 12

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Active Transportation (AT) and Pedestrian Network

Multi-Use Path (MUP)

WILKES AVE

Sidewalk/Bicycle Path (S/BP)


4.50
S/BP
3.001.50

Off Street Path

W
A
V
E
STERLING LYON

On Street Route/Facility
MUP

AT network before construction


S/BP Sidewalk
Existing Sidewalk
S/BP
MUP

MUP
S/BP
Reconstruct Existing MUP

S/BP

WILKES AVE
Off Street Path
MUP Sidewalk
On Street Route/Facility
Bike Boulevard

W
A
V
E
STERLING LYON
Future SWRT Path
Connection to Southwest Rapid Transit Corridor

Proposed AT network after construction

It is important that this project incorporate


Following an AT facility review, the project
active transportation (AT) and pedestrian
team has designed an overall concept that The AT paths wi be inked to the existing AT network
facilities that are safe, direct, and up to
utilizes : and to the AT corridor adjacent to the Southwest
current standards.
Rapid Transit (SWRT) Corridor.
• separated sidewa ks and bike paths (S/BP) with 1.5
As with vehic es, the AT network between Wi kes and
metres for pedestrian sidewa ks and 3.0 metres for Due to the open design of the underpass, there wi
Tay or is the zpinch pointU across the rai way, and hand
bike paths be p enty of natura ight. Night ighting wi be added
es the most AT vo umes of the area. A high order faci ity
• mu ti-use paths (MUP) that are a tota of 3.5 metres to increase safety.
that provides a separation of cyc ists and pedestrians
wide and are shared between cyc ists and
is best ab e to hand e future AT growth. A separated
pedestrians.
sidewa k/ bike path (S/BP) wi be on both sides of
Waver ey.
Public Open House | 9 December 2014 | Board 13

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Frequently Asked Questions

When will this be built? Will properties be required, either during Will trafffic increase as a result off this project?
A though identified as a regiona infrastructure priority construction or post-construction? The resu ts of the transportation study and traffic
by the City, capita funding has not been set aside nor It is anticipated that the vast majority of the project mode ing indicate that traffic as a who e may
has any funding agreement been signed at this point. can be bui t on City owned and and right-of-way. increase due to overa growth in the southwest
There is no construction time ine at the moment. However, construction easements or sma parce s of quadrant of the city. However, traffic is expected to
and may be needed for the construction of this flow better due to the proposed road and intersection
Will Waverley and Taylor be closed? project. The project team has been in contact with improvements and due to re ieving the congestion
Both Waver ey Street and Tay or Avenue wi remain potentia y affected caused by frequent train crossings.
open to traffic during construction, however some andowners throughout the design process.
vehicu ar movements wi be e iminated. P ease see Will the project involve changes to street
the proposed detour map on Board 7 for detai s about How will transit and active transportation ffunction and design in River Heights, such
how traffic wi flow during construction. work during construction? as the current one-way designation on
Bus routes, bus stops, and active transportation Waverley north off Grant?
How much is this going to cost? pathways wi need to be re ocated or rerouted during No. The project invo ves the pre iminary design of
A major component of this pre iminary design study is construction. See Boards 7, 11 and 12. the underpass, street improvements, pedestrian and
to deve op a high eve cost estimate for the bicyc e infrastructure, and associated intersection
underpass and major road works. A C ass 3 cost Was an overpass considered? improvements within the study area on y. No
estimate wi be provided to the City as part of the An overpass was considered ear y on in the design changes are proposed for the existing street
pre iminary design report. A C ass 3 estimate is process. However, due to heights, c earance functions and patterns in River Heights.
defined by the City of Winnipeg as a construction cost requirements, property impacts, and other
estimate based on a pre iminary design, and is engineering constraints, this option was deemed Is a Sterling Lyon connection to Taylor or
deemed to be accurate within unfeasib e. Pembina still being considered?
+30% to -20% of the fina construction cost. No, this option was examined by the City of
Estimated costs wou d be refined to a higher eve of What are the environmental impacts? Winnipeg, and is no onger being considered. The
detai as part of the detai ed design process. There are no environmenta impacts of note that wou Waver ey
d resu t from this project. Soi samp ing within the ocation continues to be the preferred rai crossing
How will the project be paid ffor? proposed underpass area indicates no issues of ocation, and has been identified as a potentia crossing
Discussions are ongoing; however, the project wi concern, and is consistent with Manitoba Conservation ocation since at east the ear y 1970Us. The right-of
more than ike y be funded by the City of Winnipeg regu ations. The project wou d a so invo ve way and property required for the Waver ey
and other reconstruction of the existing rai bed and rep acement Underpass is
eve s of government, as we as contributions by CN. of the rai tracks in the study area with seam ess rai , arge y assemb ed, and wou d have minima property
The Waver ey Underpass project wi need to be which may decrease vibration and noise from rai impacts. In addition, there is an existing agreement
considered in the City of WinnipegUs Capita activities. in p ace with CN for a grade separated rai crossing
Infrastructure budgeting process. CN Rai way has a at Waver ey, which ob igates the rai way to pay for a
financia ob igation for a portion of rai crossing under Can the rail line be moved out off the city? portion of the crossing.
an existing agreement with the City of Winnipeg. The Rai ways fa under Federa jurisdiction, and cannot be
Federa Government has been approached as an forced to move by the City. Moreover, as a main ine,
infrastructure funding partner, and discussions are moving the ine wou d be extreme y cost y and affect
ongoing with the Provincia Government. Funding severa businesses and industries that re y on regu ar
commitments wi need to be fina ized before the rai service within the city.
project may proceed.
Public Open House | 9 December 2014 | Board 14

Waverley Underpass (CN Rail Line) - Preliminary Design Study

Next Steps
If you have any further questions,
please don’t hesitate to contact
the public consultation team:

Brendan Salakoh
Phone: 204-453-2301 ext. 4060
Email: bsalakoh@dillon.ca
MAY 2014 JUNE - SEPT 2014 OCT 2014 - JAN 2015 FEB 2015
David Marsh
Phone: 204-453-2301 ext. 4094
Refine the preferred Email: dmarsh@dillon.ca
Dillon and Develop Submit preliminary
design option
AECOM awarded design design report to PRELIMINARY DESIGN COMPLETED
contract to options City of Winnipeg
complete a
WE
ARE
HERE

TO BE CONFIRMED

Capital budget Detailed design Tender and select Construction


commitment (approx. 8 - 12 contractor(s) (approx. 18-24
and funding months) months)
agreement

The feedback collected today will be


If funding for this project is allocated in the Thank you for attending! We want to hear
analyzed and further utilized by the design
City’scapitalbudget, furtherconsultationand ffrom you. Please take a moment to
team, as they refine the prefferred design.
communication with affected stakeholders complete and submit the exit survey.
We will continue to communicate with
would take place through the duration of
stakeholders informally, and through the City
design and construction. All open house materials and the exit survey
of Winnipeg’s Major Projects webpage.
will be posted to the project website.

www.winnipeg.ca/waverleyunderpass

You might also like