RTU560 PLC Workflow

RTU560 Training
RTU560 Introduction R 1.8
1
RTU560 Data Engineering (1)

 Data Engineering:
 With Windows® based tool
RTUtil560
 With Microsoft Excel®
templates

 PLC configuration:
 With Multiprog wt
 Download to RTU560

RTU560 Training
RTU560 Introduction R 1.8
2
RTU560 Data Engineering (2)
Data entry

Excel-Pattern
Project pattern • Signal parameter
• HW configuration • Addresses
Excel Import
• Signal names

Multiprog wt Export RTUtil560

Download PLC configuration


Multiprog

Upload/download of configuration data RTU560 Web-


Server

RTU560 Training
RTU560 Introduction R 1.8
3
RTUtil560 Data Engineering (Step 1 - Initialize)
RTUti560 Mutiprog WebServer

1 Initialize project

RTU560 Training
RTU560 Introduction R 1.8
4
RTUtil560 Data Engineering (Step 2 - Network)
RTUti560 Mutiprog WebServer

Initialize project
1

2 Network Tree

RTU560 Training
RTU560 Introduction R 1.8
5
RTUtil560 Data Engineering (Step 3 - Hardware)
RTUti560 Mutiprog WebServer

Initialize project
1

2 Network Tree

3 Hardware Tree

RTU560 Training
RTU560 Introduction R 1.8
6
RTUtil560 Data Engineering (Step 4 - Export)
RTUti560 Mutiprog WebServer

Initialize project
1

2 Network Tree

3 Hardware Tree

4 Excel Export

RTU560 Training
RTU560 Introduction R 1.8
7
RTUtil560 Data Engineering (Step 5 – Add PLC)
RTUti560 Mutiprog WebServer

Initialize project
1

2 Network Tree

3 Hardware Tree

4 Excel Export

5 Add PLC signals

RTU560 Training
RTU560 Introduction R 1.8
8
RTUtil560 Data Engineering (Step 5 – add PLC)

 PLC Signals mapping

RTU560 Training
RTU560 Introduction R 1.8
9
RTUtil560 Data Engineering (Step 6 - Import)
RTUti560 Mutiprog WebServer

Initialize project
1

2 Network Tree

3 Hardware Tree

4 Excel Export

5 Add PLC signals

6 Excel import

RTU560 Training
RTU560 Introduction R 1.8
10
RTUtil560 Data Engineering (Step 6 - Import)

 After Excel import check the PLC signal structure

RTU560 Training
RTU560 Introduction R 1.8
11
RTUtil560 Data Engineering (Step 7 - Build)
RTUti560 Mutiprog WebServer

Initialize project
1

2 Network Tree

3 Hardware Tree

4 Excel Export

5 Add PLC signals

6 Excel import

7 Build Project

RTU560 Training
RTU560 Introduction R 1.8
12
RTUtil560 Data Engineering (Step 8 - Export)
RTUti560 Mutiprog WebServer

Initialize project
1

2 Network Tree

3 Hardware Tree

4 Excel Export

5 Add PLC Signals

6 Excel import

7 Build Project

8 Multiprog Export I/Os

RTU560 Training
RTU560 Introduction R 1.8
13
RTUtil560 Data Engineering (Step 8 - Export)

Template

RTU560 Training
RTU560 Introduction R 1.8
14
PLC Data Engineering (Step 1 - Build)
RTUti560 Mutiprog WebServer

Initialize project Create Mulprog Template


1 1

2 Network Tree

3 Hardware Tree

4 Excel Export

5 Initialize Excel

6 Add PLC signals

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
15
PLC Data Engineering (Step 1 - Build)

RTU560 Training
RTU560 Introduction R 1.8
16
PLC Data Engineering (Step 2 - Import)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template


1 1

2 Network Tree 2 Import RTUnt File

Only for Multiprog 2


3 Hardware Tree

4 Excel Export

5 Initialize Excel

6 Add PLC signals

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
17
PLC Data Engineering (Step 2 – Import: only for Multiprog2)

RTU560 Training
RTU560 Introduction R 1.8
18
PLC Data Engineering (Step 3 – Build Logic)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template


1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics

4 Excel Export

5 Initialize Excel

6 Add PLC signals

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
19
PLC Data Engineering (Step 3 – Build Logic)

RTU560 Training
RTU560 Introduction R 1.8
20
PLC Data Engineering (Step 4 – Assign Prog)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template


1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog

4 Excel Export 4 Assign Prog to Task

5 Initialize Excel

6 Add PLC signals

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
21
PLC Data Engineering (Step 4 – Assign Prog)

RTU560 Training
RTU560 Introduction R 1.8
22
PLC Data Engineering (Step 5 – Set IP Addr)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template


1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog

4 Excel Export 4 Assign Prog to Task

5 Initialize Excel 5 Set IP Address

6 Add PLC signals

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
23
PLC Data Engineering (Step 5 – Set IP Addr)

RTU560 Training
RTU560 Introduction R 1.8
24
PLC Data Engineering (Step 6 - Make)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template


1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog

4 Excel Export 4 Assign Prog to the Task

5 Initialize Excel 5 Set IP Address

6 Add PLC signals 6 Make Build

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
25
PLC Data Engineering (Step 6 - Make)

RTU560 Training
RTU560 Introduction R 1.8
26
RTU560 Web Server (Step 1 - Connect)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template Connect as Load, Load


1 1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog

4 Excel Export 4 Assign Prog to the Task

5 Initialize Excel 5 Set IP Address

6 Add PLC signals 6 Make Build

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
27
RTU560 Web Server (Step 1 - Connect)

RTU560 Training
RTU560 Introduction R 1.8
28
RTU560 Web Server (Step 2 - Download)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template Connect as Load, Load


1 1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog


2 Download RTU Data Base

4 Excel Export 4 Assign Prog to the Task

5 Initialize Excel 5 Set IP Address

6 Add PLC signals 6 Make Build

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
29
RTU560 Web Server (Step 2 - Download)

RTU560 Training
RTU560 Introduction R 1.8
30
RTU560 Web Server (Step 3 - Restart)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template Connect as Load, Load


1 1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog


2 Download RTU Data Base

4 Excel Export 4 Assign Prog to the Task

5 Initialize Excel 5 Set IP Address

3 Restart the RTU


6 Add PLC signals 6 Make Build

7 Excel import

8 Build Project

9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
31
RTU560 Web Server (Step 3 - Restart)

RTU560 Training
RTU560 Introduction R 1.8
32
RTU560 Web Server (Step 4 – Enable PLC)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template Connect as Load, Load


1 1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog


2 Download RTU Data Base

4 Excel Export 4 Assign Prog to the Task

5 Initialize Excel 5 Set IP Address

3 Restart the RTU560


6 Add PLC signals 6 Make Build

7 Excel import

8 Build Project
4 Enable PLC online
9 Multiprog Export

RTU560 Training
RTU560 Introduction R 1.8
33
RTU560 Web Server (Step 4 – Enable PLC)

RTU560 Training
RTU560 Introduction R 1.8
34
PLC Data Engineering (Step 7 – Download PLC)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template Connect as Load, Load


1 1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog


2 Download RTU Data Base

4 Excel Export 4 Assign Prog to the Task

5 Initialize Excel 5 Set IP Address

3 Restart the RTU560


6 Add PLC signals 6 Make Build

7 Excel import

8 Build Project
4 Enable PLC online

9 Multiprog Export

7 Download PLC (Ram, Flash)

RTU560 Training
RTU560 Introduction R 1.8
35
PLC Data Engineering (Step 7 – Download PLC)

RTU560 Training
RTU560 Introduction R 1.8
36
PLC Data Engineering (Step 8 – Cold Start)
RTUti560 Mutiprog WebServer

Initialize project Create Multiprog Template Connect as Load, Load


1 1 1

2 Network Tree 2 Import RTUnt File

3 Hardware Tree 3 Create PLC Logics, Prog


2 Download RTU Data Base

4 Excel Export 4 Assign Prog to the Task

5 Initialize Excel 5 Set IP Address

3 Restart the RTU560


6 Add PLC signals 6 Make Build

7 Excel import

8 Build Project
4 Enable PLC online

9 Multiprog Export

7 Download RAM, Flash

8 Make Cold Start


RTU560 Training
RTU560 Introduction R 1.8
37
PLC Data Engineering (Step 8 – Cold Start)

RTU560 Training
RTU560 Introduction R 1.8
38
RTU560 Data Engineering (Step 9 – Build project)

RTU rcd files


 File: Contains all the information to establish the communication:
(RTU, Cabinet, Rack, Line parameters)

 File: Contains all informations about the process data points and
their parameters:

 File: Contains the text to be printed:


Events related to I/O signals may be printed !

PLC Project must be Synchronized with RTU DataBase !

RTU560 Training
RTU560 Introduction R 1.8
39
RTU560 Introduction, Additional Information

For addition information see:

RTU560 System Description


Document Ident 1KGT 150 588

RTU560 Training
RTU560 Introduction R 1.8
40