Professional Documents
Culture Documents
Abstract
In a 9-month period in 2002, two jack-up drilling units on contract to Shell Group operating
companies suffered leg damage whilst performing cantilevered drilling operations over
company assets. These two events came against a back drop of other incidents, which included
jack-up collapses in the Gulf of Mexico and the Persian Gulf. The prevalence of these incidents
indicated that some of the control measures necessary for the successful deployment of a jack-
up drilling unit were not in place. A review of the procedures used to contract a rig and the
operational controls when on-hire, are described. Opportunities to improve the contractual,
operational and technical management of jack-up deployments are identified.
r 2004 Published by Elsevier Ltd.
1. Introduction
Corresponding author.
necessary control measures are in place so that the risks associated with structural
and/or foundation failure are managed effectively. Several opportunities
for immediate improvement have been identified as a result of in-house and
industry discussions following the GlobalSantaFe Monarch and Transocean
Roger Mowell leg damage incidents. These improvement opportunities are
presented below.
An overview of the key ‘‘structural’’ risks being managed during each stage of a
jack-up deployment, are identified in Table 1. The term structural is used to
distinguish these risks from those associated with the unit’s other activities, such as
accommodation, drilling, hook-up, production or even lifting operations.
Whilst the format of Table 1 suggests that the management of the structural risks
associated with deploying a rig to a new location can be segregated, it is readily
apparent that site specifics, such as soil strength, will have a real impact on the
management of ‘‘Stage 2’’ and ‘‘Stage 3’’ risks. This table also illustrates the range of
technical skills (Marine, Metocean, Naval Architect, Geotechnical, Geophysical,
Offshore Structural, Mechanical, Survey) that are required to manage these risks
more closely.
Table 1
Structural risks associated with each stage of a jack-up deployment
5.0
4.5
4.0
Cost (US$M/operating rig year)
3.5
3.0
2.5
2.0
1.5
1.0
0.5
0.0
1960 1965 1970 1975 1980 1985 1990 1995 2000
5 Years To
Table 2
Jack-up fatality statistics 1955–2000
Since the Al Mariyah accident in 2000, there have been no reported fatalities
associated with structural failures. Initial press reports on the loss of life associated
with the collapse of the Arabdrill 19 in 2002 have since been found to be incorrect.
However, the recent improvement in life safety performance has not been matched
by a reduction in the number or severity of incidents. Some of the more widely
known incidents that have occurred in the last 7 years are presented in Table 3. A
preliminary assessment of the background to each incident has also been made to
enable the incident to be allocated to one of the deployment stages.
The amount of information available on these incidents varies from a few lines in
industry journals to a conference paper or formal report [2,3]. For those that are
currently under investigation, it is hoped that the outcome of the investigations will
be made public so that lateral learning opportunities can be realised.
Despite the lack of detailed information on many of the incidents, some general
observations may be made about the data presented in Table 3.
ARTICLE IN PRESS
Monitor F & G Mod V 1-leg damaged from uneven CNS Fair June 2000
sea-bed
101 KFEL’s modif’d 1-leg damaged from adjacent CNS Fair June 2000
F & G Mod V footprint
Ekhabi Lev MSC CJ50 Punch-through Persian Gulf Fair July 2001
57 F & G Mod II Rapid leg penetration event SCS Fair Oct 2002
Endurer BM 350-IC Rack/pinion damage from SNS Fair April 2003
brake release failure
3 In situ Harvey Ward F & G Mod II Ship impact Indian Ocean Fair Dec 1996
Wijslift 6 Wijsmueller Stern dropped CNS Fair Aug 2000
Monarch F & G Mod V 2-legs damaged from uneven SNS Fair Jan 2002
sea-bed scour
Arabdrill 19 BM 200-H Overturned and sank Persian Gulf Fair Sept 2002
Roger Mowell F & G Mod II 1 leg damaged SCS Fair Sept 2002
John Sandifer Levingston 111S 1 leg damaged from extra leg GOM Hurr. Lili Oct 2002
pen.
Dolphin 105 Pen Eng. Overturned GOM Hurr. Lili Oct 2002
Houston MLT 52S Overturned GOM Hurr. Lili Oct 2002
265
ARTICLE IN PRESS
266 R.J. Hunt, P.D. Marsh / Marine Structures 17 (2004) 261–273
Most of the major rig owners have suffered an incident of some description
resulting in damage or loss
Although neither the rig owners nor the operating company for which they are
working are presented in Table 3, the pattern of these incidents do not appear to be
substantially influenced by either.
Once an incident has occurred it is important to establish if the ‘‘capacity’’ of the
system (e.g. jack-up itself and/or foundations) was less than expected or if
the ‘‘demand’’ (e.g. loading) was greater than expected, or both. The capacity of
the jack-up can be confirmed by reviewing the design, fabrication and maintenance
history of the unit. Capacity of the foundation can be confirmed by a review of
the geophysical & geotechnical data. Confirmation of the operational demands
imposed on the system may present more of a challenge, particularly when extreme
event wind and wave loadings are being considered. Once the characteristics of
the incident are understood, it should be possible to distinguish between those
incidents that have occurred because well-known industry practices were not being
adhered to, and those incidents that have highlighted a need to improve industry
practice.
One issue, that appears to fall into the latter category, and has been found to be
common to four of the incidents listed, is the management of leg distortion when
rack chocks are disengaged. For those rigs designed with rack chocks, which protect
the leg braces from extreme (storm) loads, removal of the leg chocks before jacking
or their non-application after jacking can result in the leg braces being loaded to a
high percentage of their design capacity. This loading on the braces may be due to
eccentric foundation support beneath the leg, particularly if the seabed is uneven. If
the brace load increases further, the brace buckles as an indicator that progressive leg
failure has commenced.
To ensure the rig is being operated inside its design envelope, and to ensure that
the safety margins associated with the jacking operation are consistent with other
stages of the jack-up deployment, the design limit value of vertical leg distortion
(Rack Phase Difference [RPD]) must be known. The RPD design limit value may
then be used as the performance standard during the Jacking Procedure and as such
provides an effective method of mitigating against leg failure. The use of RPD data
in this way is already a feature of one owner’s rig move procedure [4]. Recognition of
the RPD value that causes brace failure then allows the RPD ‘‘integrity envelope’’ to
be defined.
Both BP and the Shell Group operating companies have issued internal safety
alerts [5,6], based on their concerns with operational safety in general and RPD
management in particular. In the UK, the Health and Safety Executive (HSE) issued
a Safety Notice to the industry on RPD management [7]. In response to a request
from Shell Expro for the IADC jack-up committee to consider the preparation of an
‘‘RPD recommended practice’’, the committee has stated that they do not believe it
to be an issue that should be addressed as an industry-wide initiative at this
point, recommending that it be treated by individual owners and designers as
appropriate [8].
ARTICLE IN PRESS
R.J. Hunt, P.D. Marsh / Marine Structures 17 (2004) 261–273 267
Even though the root cause(s) of many of the other incidents in Table 3 may
appear to be (and may indeed be) very different, the volume of these incidents
indicates that many improvement opportunities exist. Whilst some rig owners have
substantially revised their procedures (e.g. Refs. [9,10]), it is also useful for the
operator company responsible for taking the rigs on hire to look at their own
procedures and ensure that the risks associated with deploying a jack-up alongside
their assets are being managed.
Once the requirement for a jack-up drilling rig has been identified by an operating
company, the challenge is to meet the planned ‘‘rig-on-site’’ date. The procedure
used to meet this date varies for different operating companies, but the fundamental
ingredients remain the same and require that candidate rigs are identified both in
terms of availability and their capacity to perform the work. It is imperative that the
anticipated jack-up deployment meets the required standards for safety and integrity
as specified in both the rig owner’s and the operator’s safety management or
corporate management systems.
Over the years, procedures have been developed by the larger operators to define
the process for performing their own evaluation of the suitability of jack-ups against
identifiable hazards and industry safety norms. The essential nature of such a
procedure is to identify the key technical disciplines that are mobilised to assist the
well engineer in performing a safety & integrity assessment of a candidate rig.
For the purpose of this discussion, Safety and Integrity are defined as follows:
Safety describes the overall adequacy of a unit to operate in a secure and
controlled manner such that a safe place of work is provided for all those on
board, and the unit is capable of responding effectively in the event of an
emergency.
Integrity defines the adequacy of the unit to withstand the environmental and
functional loads experienced during operation. The assessment of a unit’s
integrity is based upon the concept of ‘‘fit for purpose’’ by which the unit is
accepted as adequate for its intended purpose provided that conditions that cause
failure are not reached whilst allowing for some degree of misuse in service. [This
requires the existence of a suitable safety factor between the design and failure
conditions].
Table 4
Operating company opportunities for improvement—procedural
1 Confirm that the procedure is current and reflects existing company organisation in terms of
ownership, roles and responsibilities.
2 For locations where site-specific data are available (boreholes data, shallow geophysics seismic data,
metocean data), ensure that the procedure identifies the need for a site-specific assessment in
accordance with SNAME 5-5A rev 2 2002 at invitation to tender
3 For locations where site-specific data are unavailable at invitation to tender, ensure that the
procedure can accommodate this
4 Ensure that Technical Authorities in key disciplines are identified in procedure and are actively
engaged
5 Recognises that the Marine Warranty Surveyor’s assessment may be the only one being performed
and confirm its fitness for purpose
6 Confirm that the rig inspection part of the procedure include verification of the actual physical
condition of the jack-up structure (legs, pinions etc.)
7 Identify the procedure that will be activated to safeguard adjacent company assets, if the rig has a
structural failure
ARTICLE IN PRESS
R.J. Hunt, P.D. Marsh / Marine Structures 17 (2004) 261–273 269
the Technical Authority should participate in the definition of the scope of work.
Some other opportunities for improvement of operating company procedures are
presented as Table 4.
6. Site-specific assessment
The contract should reflect the operating company procedure and provide the
necessary protection in the areas of indemnification for personnel and property and
consequential damages. There is also a need to limit any liabilities that are assumed
ARTICLE IN PRESS
270 R.J. Hunt, P.D. Marsh / Marine Structures 17 (2004) 261–273
Table 5
Opportunities for improvement—technical
General Specific
1 Ensure SNAME 5-5A default load factors of Develop long-term loading parameters that
1.15/1.25 are applicable for the intended deliver the required reliability for a
location? permanently manned or manned-evacuated
jack-up deployment so that load factor is
explicit in ITT
2 Identify any special input parameters e.g. metocean parameters, air gap
requirements, soil strength, mudline
topography, any existing ‘‘footprints’’ at final
& stand-off positions
3 Identify assessment results required by e.g. spudcan penetration, leg strength
Technical Authority utilizations, hull lateral motions
4 If low spud can penetration is expected or leg Calculations showing limit of vertically
stomping over existing foot prints may be eccentric spudcan load based on brace
required , then the definition of the spudcan strength (no moment carried by pinions or
‘‘sweet spot’’ will contribute to the rack chocks) and pinion capacity (no shear
management of these situations loads carried by braces) will define the
amount of eccentric leg load that can be
carried
5 If intended location is prone to rapid leg Punch through rating required e.g. 20 ft. [13]
penetration events (punch through) a punch
through leg load check may be appropriate
Table 6
Opportunities for improvement—contractual
General Specific
Table 7
Opportunities for improvement—operational
General Specific
1 Elastic design limit RPD for chock The elastic RPD limit to be specified in Operations
supported legs Manual. This is the value of RPD, which, if
exceeded, causes the operation to be halted so that
onshore resources can be mobilized
2 RPD measurement method for Electronic measurement systems should be a pre-
chock supported legs requisite for those rigs with a history of losing
control of RPD. Systems to be subject to regular
manual checks
3 Use of RPD data during jacking Must be defined in Jacking Procedure. Some RPD
operation management techniques (e.g. sequential brake
release, single chord jacking, hull trim adjustments)
are complex and must only be performed by
specialized personnel
4 Use of RPD data during leg Must be defined in Jacking Procedure
stomping operation
5 RPD control methods What are they (e.g. single chord jacking) and who
is allowed to use them
6 Loss of RPD control Does the rig owner have an Emergency Response
Procedure for this and does it state who will be
called on to perform the recovery operation
7 Leg chocks must be deployed once Achieving preload does not preclude deterioration
on location of the foundation support. Requirement for the leg
chocks to be inserted must be stated in Op’s
Manual
8 Are the leg penetrations achieved Leg load versus leg penetration prediction curves
during the jacking operation must be available to the rig move personnel so that
consistent with those predicted? any potential for punch through can be identified.
Discrepancies between predicted & actual leg
penetration should be resolved
9 Does the Operations manual Leg reaming, achieved by moving a leg up and
distinguish between leg reaming and down under its own weight whilst the hull is in the
leg stomping? water, may enable initial spudcan penetration to be
controlled but will not substantially alter mudline
topography or the potential for interaction with
existing footprints. Leg stomping requires
considerable load to be applied to the mudline soils
10 Is the person performing the jacking Identity and qualifications of person responsible
operation competent? for the jacking operation must be stated. Define a
minimum competency standard for persons
performing these operations
11 The practice of ‘‘walking’’ a rig onto Leaving one leg down on the sea-bed whilst
location should only be permitted in rotating the jack-up by tow line can introduce
special circumstances significant torsional loads in the legs
12 Weather forecast Recommend that a single reliable forecast is
obtained. Forecast is to benchmarked from site
observations and/or by gaining access to data from
adjacent metocean stations
ARTICLE IN PRESS
272 R.J. Hunt, P.D. Marsh / Marine Structures 17 (2004) 261–273
by the operating company when soil borings and/or bottom surveys are conducted
by the operating company and supplied to the rig owner. In the event that
modifications to the sea-bed are required (e.g. leg stomping, gravel dump), the
contract should cater for this. Other opportunities for improvement are presented in
Table 6.
It will have been apparent from Table 1 that a SNAME 5-5A site specific
assessment in isolation will not provide a sufficient understanding of the challenges
the rig will face at a new location. The risks associated with the in-transit and jacking
stages of a deployment are typically covered by the owners rig move procedures with
the operating company providing marine advisors. Several specific opportunities for
improvement have been identified and are presented in Table 7. These range from the
data provided in the Rig owner’s Operations Manual and/or Jacking Procedure to
the actions defined in the rig’s Emergency Response Procedure.
On the understanding that the hazards associated with offshore jack-up drilling
operations have not diminished, future safety performance will hinge on the ability
to continue to manage those risks. Some of the key activities required to achieve this
goal are believed to be the delivery of a consistent approach to risk management
across the industry, and the dialogue between all parties that makes this possible.
The issues raised in this paper are intended to contribute to this dialogue.
References
[1] Jack RL, Hoyle MJR, Smith NP. The facts behind accident statistics. The eighth international
conference; The jack-up platform; design, construction & operation. London, England: September
2001.
[2] Stonor RWP, Hoyle MJR, Nelson K, Smith NP, Hunt RJ. Recovery of an elevated jack-up with leg
bracing member damage. The ninth international conference; The jack-up platform; design,
construction & operation. London, England:. September 2003.
[3] Aust T. Accident to the mobile offshore drilling unit Maersk victory on November 16 1996. Mines
and energy resources, South Australia: May 1997.
[4] Ensco. Rigs move procedure—preliminary revision, December 2000.
[5] Snell RO. Jack-up platforms with Rack Chock Systems; Rack Phase Difference, June 2002.
[6] Hunt RJ. Safety alert issued October 2002—internal to Shell Group operating companies; jack-up
operational safety.
[7] Offshore Division. Safety Notice 4/2002 Jack-up (Self Elevating) Installations; RPD, UK HSE
August 2002.
[8] IADC Jack-up committee. Recommended Procedure for Excessive RPD, Letter to Shell UK
Exploration and Production (Fao R Hunt), April 2003.
[9] Maersk Contractors. General Soil & Location Survey Requirements, revision 3 April 2002.
ARTICLE IN PRESS
R.J. Hunt, P.D. Marsh / Marine Structures 17 (2004) 261–273 273