Professional Documents
Culture Documents
Water Supply Final
Water Supply Final
Table of Contents
List of Tables ............................................................................................................................... 3
List of Figures ............................................................................................................................. 3
EXECUTIVE SUMMARY ......................................................................................................... 4
1.0 Introduction .......................................................................................................................... 5
1.1 Background ........................................................................................................................... 5
1.2 Goal of the Project................................................................................................................. 5
1.3 Specific objectives of the assignment. .................................................................................. 5
2.0 DESIGN APPRAOCH AND METHODOLOGY ............................................................... 6
2.1 Appreciation of the assignment ............................................................................................. 6
2.2 Study Methodology, flow chart of design steps. ................................................................... 6
2.3 Data collection method for engineering design studies ........................................................ 6
2.4 Design criteria and design standards to be used .................................................................... 7
3.0 INITIAL ACTIVITIES AND BASELINE ASSESSMENT ............................................... 8
3.1 Desk Study and review of document..................................................................................... 8
3.2 Findings from site visit and initial consultation .................................................................... 8
3.3 Baseline Assessment ............................................................................................................. 9
4.0 ENGINEERING DESIGN STUDIES ............................................................................... 10
4.1 Distribution Scheme ............................................................................................................ 10
4.2 Network Configuration ....................................................................................................... 10
4.3 Population Projections......................................................................................................... 12
4.4 Water Demand................................................................................................................ 12
4.4.1Average water demand ................................................................................................. 12
4.4.2 Average Nodal Demands ............................................................................................. 13
4.4.3 Peak Design flows........................................................................................................ 13
4.5 Sizing of Pipes..................................................................................................................... 14
4.5 Height of Elevated Tank And Pump Head ..................................................................... 15
4.6 Water Resources and Storage ......................................................................................... 16
4.6.1 Boreholes Characteristics and Design ......................................................................... 16
Storage: Sizing of Tanks ..................................................................................................... 17
4.6.2 Elevated Tank and Ground Reservoir Specifications ...................................................... 18
4.7 Borehole Pumps ............................................................................................................. 19
Final Report-Water Supply and Distribution (Grp. 9)
2|Page
Final Report-Water Supply and Distribution (Grp. 9)
List of Tables
Table 1Peak Demands at Nodes ................................................................................................... 14
Table 2 Pipe Diameters and Velocities ......................................................................................... 15
Table 3 Summary of Velocities and Head Losses ........................................................................ 15
Table 4 Summary of water supply to sectors ................................................................................ 16
List of Figures
Figure 1 Flow chart of design steps ................................................................................................ 6
Figure 2Site for phase two covered with vegetation Figure 3Phase one under construction....... 8
Figure 4Sketch of the branch network configuration considered. ................................................ 11
3|Page
Final Report-Water Supply and Distribution (Grp. 9)
EXECUTIVE SUMMARY
The Kwame Nkrumah University of Science and Technology, Kumasi (KNUST) is undertaking
the construction of a new 800-bed teaching hospital in two phases. Phase one, which has
comprehensive structural and building services designs for a teaching hospital. Phase two
includes the additional ancillary support facilities, as well as drainage, water supply and waste
management for the entire Teaching Hospital.
To this end, the Client has commissioned M/s EDCIV 2015/16 Civil Groups to undertake the
design of the Civil Engineering Infrastructure Works for the said Phase Two of the new
Teaching Hospital project for the University in Kumasi.
This is a report of the engineering design studies carried out by the consultant. The designs
conform to existing standards for water supply as approved by the appropriate agency such as
CWSA, GWCL, EPA, etc. The report contains the following:
Designs for the recommended distribution scheme, taking into account appropriate design
standards and criteria - supply area, population projections (if necessary), levels of
services and per capita consumption, demand estimation and variations in water demand.
The distribution scheme a gravity supply scheme with a branched pipe network serviced
by two boreholes. It has two elevated tank and a ground storage tank for water storage
and distribution.
Water distribution drawings consisting of plans and profiles of pipelines detailing the
location of all fittings and appurtenances.
Bill of quantities and cost estimates
Environmental impact assessment.
4|Page
Final Report-Water Supply and Distribution (Grp. 9)
1.0 Introduction
1.1 Background
The Kwame Nkrumah University of Science and Technology, Kumasi (KNUST), the
premier Institution in Ghana responsible for the training of engineers. Medical
personnel, scientists and technologists required to support the industrial and socio-
economic development of Ghana is undertaking the construction of a new 800-bed
teaching hospital.
The site for the new hospital is located near Boadi, opposite the Ghana Telecom
Exchange station, along the Boadi Junction-Emena Road. The new hospital is being
constructed in two phases. Phase one, which was comprehensive structural and
building services designs for a teaching hospital, has been awarded on contract and
construction is already in progress at the site. Phase two, which is at the design stage,
was originally planned to cater for staff accommodation. However, it was later
decided to incorporate additional ancillary support facilities, as well as drainage,
water supply and waste management for the entire Teaching Hospital.
The Management of KNUST, the Client, has commissioned the Development Office
of the University to undertake the general planning and the design of the architectural
aspects of the Teaching Hospital scheme. Similarly, the client has engaged the
services of Engineering Consultants for the design of the mechanical and the
electrical engineering aspects of the proposed Teaching Hospital Scheme. Preliminary
planning and designs of the various units for the Phase Two scheme have been
completed and approved by the Client. It is now required to undertake the design of
the Civil Engineering Infrastructure Works for this phase.
5|Page
Final Report-Water Supply and Distribution (Grp. 9)
Design of
transmission mains •Sizing of pipes
•Sizing of pipes
•location of pump
Design of
station and elevated
distribution
tank
network
•Design drawings
6|Page
Final Report-Water Supply and Distribution (Grp. 9)
7|Page
Final Report-Water Supply and Distribution (Grp. 9)
Figure 2Site for phase two covered with vegetation Figure 3Phase one under construction
8|Page
Final Report-Water Supply and Distribution (Grp. 9)
9|Page
Final Report-Water Supply and Distribution (Grp. 9)
10 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
11 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
Hospital (Institutional)
Using CWSA guidelines, the Handbook for the Assessment of Catchment Water Demand
(HR Wallingford) and EPA research findings the following calculations were made:
800 Beds:
Water consumption per bed (including laundry, cleaning, kitchen) = 350 l/bed/d
Water consumption for 800 beds = 280000 l/d
12 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
Staff:
Water demand = 14160 l/d (40 l/cld)
Node 7 (8 houses)
40 people = 4000 l/d
Node 3 (8 houses)
40 people = 4000 l/d
13 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
Criteria:
Peak Flow is used to size pipes
Minimum pipe diameter: 75 mm (as stated by CWSA)
The total flow of water passing through a particular pipe is used in sizing the pipe.
14 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
15 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
= 1.35
Therefore 2 boreholes were provided
Table 4 Summary of water supply to sectors
16 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
Sector 2:
2 day volume = 193.08 m3
Only an elevated tank will be provided in this sector
Size of the elevated tank = 196 m3
Dimensions
Length = 7 m
Breadth = 7 m
Height = 4 m
17 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
18 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
235.47
Q(pump) = 5 𝑥 60 𝑥 60
= 0.0131 m3/s
𝑄 𝐻𝑝 𝜌𝑔
Pump power = 𝑒𝑓𝑓𝑖𝑒𝑐𝑖𝑒𝑛𝑐𝑦
96.54
Q(pump) = 5 𝑥 60 𝑥 60
= 0.0054 m3/s
𝑄 𝐻𝑝 𝜌𝑔
Pump power = 𝑒𝑓𝑓𝑖𝑒𝑐𝑖𝑒𝑛𝑐𝑦
19 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
20 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
21 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
22 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
J811 nr 1
Wash Out Nominal Bore 75mm
TOTAL
23 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
24 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
The EIA was carried out taking into consideration Ghana’s Environmental Protection Agency’s
legislation and regulations and other international environmental regulations relating to the
project. Furthermore, prevailing demographic, environmental and social issues pertaining to the
project location (along the Boadi Junction–Emena Road) were analyzed to determine the
magnitude of the impact of the project on the socio-economic development of the project
locations and the country as a whole.
7.1.3Methodology Adopted
The study team carried out with the other members, an observation on the physical environment
at the project site. Secondary data on policy issues relating to environmental protection in Sierra
Leone were collected to quantify the nature and magnitude of environmental impacts envisage
from construction activities, and to analyze how the impacts relates within the context of the
legislation and policy matters.
7.1.4 Nature and Magnitude of Environmental Issues
Potential environmental impacts from construction works may include dust generation, air
pollution, and ground water pollution, noise, loss of soil resources and vegetation, sedimentation
and changes in land use and topography at the sites.
7.2 BASELINE STUDY
The project site of the 800 bed teaching hospital is located along the Boadi Junction–Emena
Road in Boadi-Emena, near KNUST. It is located in the Kumasi Metropolis district in the
Ashanti region of Ghana. The Kumasi metropolis district has the highest population in the
Ashanti region with about 2,035,064 (Ghana Statistical service, 2010). The total land area for the
project is about 72,166m2. The project site is located at the outskirts of the Kumasi Metropolis.
The major land use at the moment is farming, although various infrastructure are also fast rising
in the area. Water used in irrigating their crops are from open surface water. The land area has a
considerable slope with an elevation which ranges between 268 – 283 meters above mean sea
level. The main source of water for domestic activities is GWCL. But due to the rapidly
increasing population in the region (2.7% growth rate) pressure is exerted on the socio-economic
facilities over a short period of time. As such water supply to the area is limited. GWCL pumps
water for about 10 to 12 hours daily.
25 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
26 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
27 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
28 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
eyes and ear mufflers (when using pneumatic drills, grinders, etc.). Likewise fire prevention
measures should be in place, including the deployment of adequate functional extinguishers
and simple dry sand buckets. The project monitoring programme should include inspection of
safety equipment use.
Basic hygiene standards should be required at all residential and other contractor facilities,
with proper approved waste disposal arrangements. HIV Aids awareness development and
disease spread mitigation should be fostered by the contractor among his staff. Contact with a
appropriate specialist to conduct basic training and awareness among workers should be
facilitated.
29 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
8.0 CONCLUSION
The design of the water supply distribution has been successfully designed in accordance with
the Terms of reference and appropriate design guides.
All drawing necessary for the execution of the project have been produced and are ready for use.
30 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
9.0 REFERENCES
DEMAND
Consumption per bed
Handbook for the Assessment of Catchment Water Demand and Use. HR Wallingford in
collaboration with the Department for Water Development: page 135, table 7.15
Percentage Water consumption in hospitals (EPA):
(http://www3.epa.gov/watersense/commercial/types.html)
Daily Visits
Statistics from Komfo Anokye Teaching Hospital, a 1200 bed hospital, show that they record an
average of about 800 out-patients a day which is two-thirds of the bed capacity of the hospital.
This statics was used to estimate the number of visits per day to the out-patient department of the
new hospital as 530.
Peak Factors
Daily peak factor: Ministry of Water Resources, Works and Housing. Community Water and
Sanitation Agency. Small Town Sector Design Guidelines (Volume 3, December, 2010) Page: 5
Design life- Design of water supply pipe networks by Prabhatak K., Asahok K. (page 109)
EIA- Environmental Impact Assessment and Environmental Management Plan for
Upgrading of
Lungi International Airport, Sierra Leone – Final Report. January 2005.
31 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
32 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
10.0 APPENDIX A
DEMAND CALCULATIONS
Residential:
Assumption: There are 5 people per house.
There are:
30 No. 2 bedroom flats
12 No. 2 bedroom type bungalows
4 No. 3 bedroom type bungalows.
Total number of houses = 46
Total number of residents = 230
Residential demand = 23000 l/d (100 l/c/d)
Using CWSA guidelines, the Handbook for the Assessment of Catchment Water Demand
and Use. (HR Wallingford) and EPA research findings the calculations were made:
800 Beds:
Water consumption per bed (including laundry, cleaning, kitchen) = 350 l/bed/d
Water consumption for 800 beds = 280000 l/d
Staff:
Number of staff = 200 – (46 resident staff) + 200 (students) = 354
Water demand = 14160 l/d (40 l/c/d)
Peak factor: 3
Peak Demands (Sample Calculations)
Node 10 (Mortuary, plant/Eng. Maintenance, kitchen, laundry
3 x 0.25(280000+14160) = 220620 l/d
Node 5 (Administration block Annex)
3 x 6900 = 20700 l/d
Node 12 (800 bed hospital)
3 x (0.75 x 294160 + 7950) = 685710 l/d
34 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
8.0 APPENDIX B
HYDRAULIC CALCULATIONS
Sizing of pipes
Sample Calculations
Q = AV
Assume initial Velocity of 1 m/s.
For Pipe 11-12
𝑄𝑋4
D =√𝑉 𝑋 𝜋
D = 0.1 m
Therefore choose 100 mm (minimum pipe diameter)
Actual velocity
𝑸𝒙𝟒
V= 𝑫𝟐 𝑿 𝝅
V = 1.01 m/s
𝟏 𝟓. 𝟏𝟐𝟖𝟔 𝑲
= −𝟐 𝒍𝒐𝒈 ( +
√𝝀 𝑹𝒆𝟎.𝟖𝟗 𝟑. 𝟕 𝑫
Reynolds number,
Kinematic viscosity
35 | P a g e
Final Report-Water Supply and Distribution (Grp. 9)
Parameters
T = 20 degrees Celsius
K = 0.02 mm (For HDPE pipes)
𝜆 =0.028
hf = 4.995m
The tank will be placed at an elevation of 12 m to achieve a minimum pressure of 5 meters in the
system,
36 | P a g e