Professional Documents
Culture Documents
TDP Grp2 Inception - Copy Standard
TDP Grp2 Inception - Copy Standard
KUMASI
INFRASTRUCTURE FACILITIES
NEW TEACHING HOSPITAL
(PHASE II DEVELOPMENT)
INCEPTION REPORT
January, 2014
-
NEW TEACHING HOSPITAL PHASE II ENGINEERING DESIGN OF INFRASTRUCTURE
DEVELOPMENT FACILITIES
TABLE OF CONTENTS
EXECUTIVE SUMMARY 4
1.0 Background 4
2.0 Objectives 4
3.0 Progress of Work, and Work Schedule 5
1.0 INTRODUCTION 6
1.1 Background 6
1.2 Objectives 7
1.3 Scope of the Project 7
1.3.1 Site Layout 7
1.3.2 Geotechnical Investigation for Road Pavement Design 8
1.3.3 Pavement Design of Roads and Parking Facilities 8
1.3.4 Geometric Design of Road Network 8
1.3.5 Storm Drainage 9
1.3.6 Environmental Impact Assessment Report: 9
1.3.7 Costing and Contract Documentation: 10
1.3.8 Economic Appraisal of the Project: 11
1.4 Project Information Available 11
2.0 PROJECT LOCATION AND AREA 12
2.1 Geology and Soils of the Area 12
2.2 Climate & Rainfall 12
2.3 Demographic characteristics 14
2.3.1 Population 14
2.3.2 Growth Rate 15
2.3.3 Population Density 15
2.3.4 Household Sizes and Characteristics 16
2.3.5 Occupational Distribution 17
EXECUTIVE SUMMARY
1.0 Background
The Kwame Nkrumah University of Science and Technology, Kumasi (KNUST), the premier
Institution in Ghana is undertaking the construction of a new 800-bed teaching hospital. The
KNUST Teaching Hospital is to become a referral centre for hospitals in the Ashanti Region
in order to ease the pressure currently on the Komfo Anokye Teaching Hospital, Kumasi. The
Phase One was awarded on contract and construction is in progress at the site. Phase two,
which is at the design stage comprises staff accommodation, ancillary support facilities, as
well as drainage, water supply and waste management for the entire Teaching Hospital.
The Client has commissioned M/s RTEP 2013/14 Groups (i.e. students of the master’s
programme in Road and Transportation Engineering (RTEP)) to undertake the design of the
Transportation Engineering Infrastructure Works for the said Phase Two of the new Teaching
Hospital project for the University in Kumasi, with a view to equipping students with the
knowledge and skill that will enable them better manage a road network.
This inception report is the first report of M/s RTEP 2013/14 (Group 2) on the assignment.
2.0 Objectives
The objective of the assignment is to provide engineering designs for components of
transportation infrastructure works required for ensuring the efficient functioning of the
- Road Network
- Vehicular Parking
- Drainage
practicing engineers has familiarized itself with the Terms of Reference and the project site.
A desk study of available project drawings, standards and specifications has been performed.
an Engineering Designs Draft Final Report on 28th March and a Detailed Engineering
1.0 INTRODUCTION
1.1 Background
The Kwame Nkrumah University of Science and Technology, Kumasi (KNUST), the premier
Institution in Ghana responsible for the training of engineers, medical personnel, scientists
Ghana is undertaking the construction of a new 600-bed teaching hospital. The KNUST
Teaching Hospital is to become a referral centre for hospitals in the Ashanti Region in order
to ease the pressure currently on the Komfo Anokye Teaching Hospital, Kumasi. The new
hospital is being constructed in Two phases. Phase One, which has comprehensive
structural and building services designs for a teaching hospital, was awarded on
contract and construction is in progress at the site. Phase two, which is at the design stage,
was originally planned to cater for staff accommodation. However, it was later decided to
incorporate additional ancillary support facilities, as well as drainage, water supply and waste
The Management of KNUST, the Client, commissioned the Development Office of the
University to undertake the general planning and the design of the architectural aspects of the
Teaching Hospital scheme. Similarly the Client engaged the services of Engineering
Consultants for the design of the mechanical and the electrical engineering aspects of the
proposed Teaching Hospital scheme. Preliminary planning and designs of the various units
for the Phase Two scheme have been completed and approved by the Client. It is now
required to undertake the design of the Civil Engineering Infrastructure Works for this phase.
To this end, the Client has commissioned M/s RTEP 2013/14 Groups (i.e. students of the
design of the Transportation Engineering Infrastructure Works for the said Phase Two of the
new Teaching Hospital project for the University in Kumasi, with a view to equipping
students with the knowledge and skill that will enable them better manage a road network.
This inception report is the first report of M/s RTEP 2013/14 (Group 2) on the assignment. It
covers an understanding of the scope and expected deliverables of the assignment, site
familiarisation, challenges encountered, modus operandi for subsequent work and schedule of
1.2 Objectives
The objective of the assignment is to provide engineering designs for components of
transportation infrastructure works required for ensuring the efficient functioning of the
- Road Network;
- Vehicular Parking
- Drainage
given below:
the following:
Drainage network
Provision of the necessary information about the sources and quality of construction
All vertical and horizontal alignment details required for the proper setting out of the
works.
All traffic management features that are required for the safe and efficient operation
Liaising with relevant road agencies such as Department of Urban Roads and Ghana
appropriate flood return periods that will ensure adequate sizing of drains and related
Storm drainage ensuring that adjacent properties are not unreasonably hampered and
Assessment of Traffic impacts, especially at the main entrance from the network of
roads around the development during construction and operation of the development.
and temporary works. Bill of Quantities for all works should also be prepared using
documents also prepared using the latest version of the Standard Bidding Document
of the Public Procurement Act, 2003 (Act 663) of the Republic of Ghana.
Development of rates for various work items, compared with rates from recent tenders
and adjustments made if necessary. Pricing of the bill of quantities based on these
rates, to obtain an estimate of the cost of the works. Estimation of the cost of
Net Present Value (NPV), Economic Internal Rate of Return (EIRR) and Benefit/Cost
Ratio.
Proposed site layout drawing showing the proposed location of the buildings and
associated infrastructure
The site for the proposed Phase Two of the new Teaching Hospital is located on the North-
eastern side of the KNUST campus near Boadi, and opposite the Ghana Telecom Exchange
folded Birimian metalavas. It is divided mainly into upper and lower Birimian. The project
area which is within Ashanti region falls within the upper Birimian. These consist chiefly of
metalavas (metamorphosed basaltic and andesitic lavas). The Birimian System in Ghana is
part of the Birimian supracrustal sequence of West Africa, which extends from Ghana
The Birimian rocks consist of interlayered sedimentary and volcanic flow rocks
metamorphosed to low green schist facies of Barrovian type. It is divided mainly into upper
and lower Birimian. From visual inspection, it was discovered that, the soil at the project site
is lateritic intermixed with fused laterite.
throughout the course of the year. Kumasi is noticeably wetter than nearby Accra, the capital
The city almost features two different rainy seasons, a longer rainy season from March
through July and a shorter rainy season from September to November. In actuality, the month
of February through to November is one long wet season, with a relative lull in precipitation
in August. Similar to the rest of West Africa, Kumasi experiences the Harmattan during the
“low sun” months. Lasting from December to February, the Harmattan is the primary source
Details:
The coolest average min/ low temperature is xxx °C (xxxx °F) in January, February &
December.
On balance there are 137 days annually on which greater than 0.1 mm (0.004 in) of
The month with the driest weather is January when on balance 20 mm (0.8 in) of rain
The month with the wettest weather is June when on balance 234 mm (9.2 in) of rain
Mean relative humidity for an average year is recorded as 83.2% and on a monthly
basis it ranges from 75% in February to 87% in June, July, August, September &
October.
There is an average range of hours of sunshine in Kumasi of between 2.3 hours per day
On balance there are 1900 sunshine hours annually and approximately 5.2 sunlight
The Kumasi metropolis is the most populous district in the region. It has a population of
1,170,270 (1,538,623 IN 2005 projected) which accounts for just under a third (32.4%) of the
region’s population. Kumasi has attracted such a large population partly because it is the
regional capital, and also the most commercialized town in the region. Other reasons include
the centrality of Kumasi as a nodal town with major road arteries to other parts of the country
and the increasing number of educational institutions; a polytechnic, three teachers training
colleges and universities. Kumasi is also the traditional seat of the Ashanti King.
This, coupled with the many historic and other attractions such as the cultural centre, the
military museum, the legendary Okomfo Anokye and the Manhyia Palace, among others, may
Ashanti Region is currently the second most urbanized in the country, after Greater Accra
(87.7%).The large urban population in the region is mainly due to the fact that the Kumasi
metropolis is not only entirely urban but accounts for a third of the region’s population. The
growth of industries and the increase in commercial activities, in and around Kumasi, may
The Population has grown rapidly over the inter-censual periods from 16,724 in 1970, 22,636
in 1984 to 1,170,270 in 2000. Based on these census reports the estimated growth rate is 5.5
per cent
Ashanti Region has a relatively high population density of 148 per sq. km, having increased
persons per sq km in 1984. The region’s density, which was around the fifth in the country up
to 1984, rose to the third densely populated region (148 sq km) after the Greater Accra (895
per sq km) and the Central (162 per sq km) Regions in 2000. The high population density of
the region may be explained by the fact that it has the second largest economy in the country,
after the Greater Accra Region, which tends to attract people to the region.
KMA has a total land surface of about 211.6 square kilometres (2000 Census) with a
population density of 5319 persons. The Kumasi metropolis (5319) has not only the second
highest population density in the country but is also only slightly lower than the Accra
metropolis (5530).
The average household size in Ashanti is 5.3 persons, the same as Brong Ahafo. It is lower
The average household size in KMA is 5.1. The average number of households per house in
KMA is also 3.4. The relatively large number of households per house in Kumasi may be due
Children constitute 34.0 the highest proportion of household members in all the Metropolis.
Several factors may account for the high proportion of children of household heads in the
District. In addition to minors who may still be living with their parents, there could also be
children, particularly females, who may move to stay with their parents, in accordance with
tradition, during the latter part of pregnancy, well into the post natal weaning period, before
returning to their spouses. Divorced, widowed, unemployed or even destitute children may
also fall back to live with their parents while sorting themselves out. All these are indications
of the fall-back support system that is the bedrock of the traditional family structure.
Other relatives form the second highest proportion of the population in households in the
districts after children, constituting between 12.9 and 43.3 per cent of households. A number
of socio-economic factors may account for the high proportion of “other relatives” in
persons who stay with relatives while actively searching for jobs on their own dwelling units.
Large households exert pressure on housing, thus leading to large population per room or
overcrowding.
Sales and Production work are the major occupations in the Kumasi metropolis. The fact that
the Kumasi metropolis is the main commercial and industrial centre in the region, may partly
account for the large proportion of the population in Sales and Production work. The
proportions of the economically active population in Professional and Technical work are
relatively small.
The government’s policy of making the private sector the engine of growth of the economy
needs to be encouraged, since a greater proportion of the population in the district tends to be
engaged in this sector. The private sector, as presently constituted with such high proportions
of single person enterprises, cannot be an engine of growth. Such enterprises do not expand
to absorb the ever-increasing labour force. Moreover, they contribute next to nothing to taxes.
Policies aimed at improving the private sector and creating an enabling environment, should
therefore aim at capacitating such enterprises to expand their base in order to be able to
absorb extra labour. The self-employed without employees, in the private informal sector,
many of whom are not even properly registered, also raise problems of mobilization for such
social welfare issues as social security and health insurance, which are becoming important
concerns for Government. Appropriate policies to integrate this sector into the various social
sector schemes will therefore need to be evolved. Such integration can even have an indirect
positive effect on the growth and expansion of such private sector enterprises.
3.1 Mobilization
3.1.1 The Project Team
The RTEP 2015/16 Group2 comprises five (5) students most of whom have acquired some
practical professional experience prior to enrolment on the programme.
The roles and designations of the team members on the assignment are shown in Table 3.1.1.
traversed the entire site on foot inspecting the features of the existing road, traffic operations
and conditions, drainage structures and how they were functioning, available right-of-way,
presence of utility lines and features among others. The visits were useful in enabling the
Team to gain appreciation of existing site conditions and to help conceive what needed to be
3.2.1 Terrain
The existing ground features three (3) slopes, namely two gentle inward slopes from KNUST
SHS and Phase One site towards the centre of the site (i.e. N-S and S-N), and one relatively
steep outward E-W slope across the centre of the site towards the Boku stream (a tributary to
laterite. As one goes down westward along the slope, the surface soil changes to loamy and
clayey material. The upper reaches of the site is sparsely covered with grass, shrubs and
intermittent trees. The vegetation cover becomes denser as one descends towards the Boku
stream. Parches of maize farms can be seen on site, and along the Boku stream are strips of
vegetable plantations.
Figure 3.2.2.1: A vegetable plantation along the Boku stream Figure 3.2.2.2: Site showing lateritic soil and vegetation cover
main Boadi Junction – Emena road through the site to the Phase One site entrance. There are
also a number of foot tracks providing access to the vegetable plantations. Bordering the site
on the eastern side is the Boadi Junction – Emena road. The proposed main entrance to the
site is located on this road. By the DUR road classification system the Boadi Junction –
Emena road is a Collector/distributor handling traffic between access roads along it, Boadi,
Figure 3.2.3: Existing site access (LHS picture) and proposed access location (RHS picture) on Boadi Jn.-Emena road
The Team agreed on the fact that the main entrance configuration was a critical aspect of the
design given the current traffic volume, speeds of vehicles observed, as well as the estimated
future traffic upon completion of the project. It was observed that vehicles travelling on the
road between the proposed project site and the adjacent ECG substation/Ghana Telecom
office through to Boadi were travelling at relatively high speeds. This could pose a challenge
for the vehicles entering/exiting the traffic stream from the hospital since current visibility for
vehicles in this section may not be adequate. Both the current access point and the proposed
entrance are in horizontal curves. Visibility is impaired near the current access point due to
the steep upward vertical profile on the approach from Emena. The proposed entrance
location is not close to the vertical curve but has entrances to the ECG and Ghana Telecom
premises in close proximity. It is recommended that the location of the intersection must
therefore be moved a few meters from the proposed location in order to avoid some of these
challenges and improve general safety. The current superelevation of the main road may need
Besides the intersection, most parts of the site did not seem to present any challenges. The
terrain is gently undulating and it is not expected that there would be many cuts or fills
3.2.4 Traffic
The traffic on site is mainly construction-related and therefore limited to periodic vehicular
and pedestrian movement between the Boadi Junction – Emena road and the Phase One site.
A few crop farmers also cross over the site to their farms. The Boadi Junction – Emena road
however carries medium traffic with significantly high speeds. Traffic on this road is free-
flowing.
3.2.5 Drainage
As stated in 3.2.1 above the site features appreciable slopes that make it well-drained. The
surface slopes are such that runoff collects naturally towards the centre and then flows
outward to the east into the Boku stream. Due to the good slopes and the high elevation of the
site from the Boku stream it is not expected that groundwater would in any way hinder
3.2.6 Environment
The project is expected to impact various components of the environment from construction
to its operational stages. Some envisaged social, physical and biological impacts are
discussed below.
3.2.6.1 Social
Positive impacts
Negative impacts
- Loss of livelihood through loss of farm land (through borrowing and construction)
3.2.6.2 Physical
Negative impacts
- Pollution of water bodies by earthworks, fuel and lubricants, night soil, bath water and
- Pollution of water bodies by effluent from mortuary and other hospital facilities
- Air and soil pollution from refuse and litter during and after construction
3.2.6.3 Biological
Negative impacts
approach to the proposed entrance. There is also a pronounced vertical curve on the Emena
approach. There are currently no road signs to warn road users of crossing vehicles and
pedestrians. The road is not marked and so one cannot tell the carriageway from the
shoulders. The bituminous road surface is also bleeding and would make the road slippery in
Figure 3.2.7: Existing road showing approach curve, bleedng and open drain
The roadside drains are also and open concrete u-drains – a safety hazard for both pedestrians
and vehicles.
entrance location, size of parking areas the KNUST Development Office was consulted with
the hope of obtaining an engineering/architectural consultant’s report. The team was referred
to the Faculty of Architecture for the said report, only to be informed that all such reports had
been handed over to a foreign consultant who never returned them. The team is therefore not
in possession of any information forming the basis of the road layout concept.
(BRRI), Fumesua-Kumasi for accident data on the Boadi Jn. – Emena road revealed that the
division has no accident data record on the road. The reasons given were that, the road is not
among the selected roads in Kumasi where they conduct routine accident data collection and
also, the Accident division has not received any accident report on the Boadi Jn. – Emena a
road from the Police. It can be inferred that the road is currently accident-free.
and hydraulic analyses and design. Investigations into the use of rates of similar works as
well the survey of inputs encompassing machine, labour wages, cost materials for use for
sample rate analysis are underway. Scoping of potential impacts of the project on
components of the environment has been done and will be the basis of the determination of
mitigation measures.
of the project. Available reports and data on materials, traffic volumes, axle load factors, and
hydrological data have been collated and studied to inform the appropriate design of the
various features.
The desk study and review of available data entailed the use of documents on standards and
specifications as well reports and/or data relevant to the assignment. These include the
following:
as well as its bearing capacity to sustain the traffic load that will be imposed on it. The insitu
test that will be carried out will include Dynamic Cone penetration (DCP) test and trial
pitting along the road corridor as well as the car parks. The Dynamic cone penetration (DCP)
Test will be conducted at ranges of 50m interval .This is because the Dynamic cone
penetration test (DCP) determines the sub grade strength and also informs the decision on the
design of the pavement layers. The trial pitting will be conducted at 100m intervals since the
project area is a small area and as such does not span across different soil formations. Sample
of the insitu soil will also be taken to the laboratory for the relevant test to be conducted.
Soil samples from identified borrow pits will also be tested to decide their suitability for the
road works and identified car parks. Some of the laboratory test that will be conducted will
include grading, compaction, California bearing ratio, atterberg limits and moisture content.
Quarry aggregates that will be used for sealing works will also tested at the laboratory to
determine its suitability. Grading, ten percent fines, Los Angeles Abrasion (LAA) and
flakiness Index (FI) are some of the test that will be conducted on the aggregates.
Investigations into borrow materials – gravel, crushed rock and sand – are will also be carried
out. Samples would be taken from some existing borrow sites to validate their suitability.
All soil and aggregates test will be conducted in accordance with the Ministry of Roads and
determine the parking needs, pavement design and other traffic characteristics of the
proposed development. Also the access requirements and the impact of the project on the
adjoining road will be determined. The chosen comparative site is the Komfo Anokye
Teaching Hospital (KATH) in Bantama, Kumasi. This facility has similar land use as the
proposed development and will assist in the forecasting of traffic for the proposed
development. It will also help the consultant to assess the adequacy of parking provided for
The following traffic studies will be conducted so as to achieve the objectives of the project:
2. Proposed development
Data Collection
A 12 hours traffic volume count will be conducted on the Boadi Junction – Emena road d in
front of the proposed development and the proxy site from 6:00am to 6:00pm. The volume
count on the Boadi Junction – Emena road will inform the consultant on the current traffic
situation on the road. In addition, the volume count at the proxy site will inform the
consultant on the traffic generated by the proxy facility. This will serve as a basis upon which
the consultant will predict the traffic that will be generated by the proposed development.
Two count locations have been identified at the proxy site. (i.e. the KATH roundabout
entrance to the site and the Emergency Unit entrance: off Steward Avenue). Directional and
classified traffic volume counts (including both motorized and non-motorized transport) will
be conducted manually on Monday, Wednesday and Saturday to reflect the beginning, middle
and end of the week. In this way the trend for the week will be fairly covered.
Analysis of Data
The Consultant will largely employ in-house programmed spreadsheet for the analysis of
data. The summaries of the analysis will include the computation of:
Monthly variation factor – needed for the estimation of Base year AADT
Average Daily Traffic (ADT) volume for each vehicle type /group and the total ADT
Base Year Annual Average Daily Traffic (AADT), volume for each vehicle type/group
Growth rate to be adopted for forecasting the traffic will be determined based on historic
Parking Studies
defined as the maximum number of vehicles parked at any time at the location understudy.
The average accumulation of vehicles at the proxy site will be used to estimate the parking
demand of the proposed development. An appropriate parking layout will be developed for
for the proposed construction layout. The following activities are being undertaken in order to
Drainage Survey
Hydrological Analysis
Hydraulic Analysis
During the field reconnaissance survey the surface topography through which the Boku
stream flows was documented. The layout provided for the site features the topography of the
project area and would be used to undertake the necessary hydrological studies, hydraulic
Hydrological Analysis
Meteorological information for the Kumasi area has been obtained. Using a hydrologic model
and return period recommended by DUR in conjunction with the proposed land use of the site
catchment areas and their slopes appropriate peak flows would be estimated.
Hydraulic Analysis
Based on the estimated peak flows, alignment slopes, preferred conveyance structure and
material drainage structures would be sized. A sensitivity analysis would be carried out using
Drainage Schedule
On completion of the hydraulic analyses a schedule summarising all drain types, sizes,
The necessary standards and guidelines have already been collated to aid the drainage
1. The design of the Vertical and Horizontal alignment of the roads showing details for
all relevant traffic management features (such as traffic signs, road markings, etc) that
are required for the safe and efficient operation of the road network.
4. Liaising with relevant road agencies for appropriate specifications and standards to aid
The two main types of traffic to be designed for are vehicular and pedestrian traffic. The two
main traffic movements to be handled are those at the entrance and those within the site. In
both cases the objective of design would be to provide geometry and physical structure so as
to ensure reasonable flow for all traffic while minimising or eliminating conflict between
The topographical data supplied by the Client have been scrutinized and validated for the
work to be carried out. The survey extent and details are deemed sufficient for undertaking
Since speeds within the site are expected to be low the horizontal alignments are expected to
follow the architectural road layout closely. Any deviations from this layout, where necessary
3. Standard Specification for Road and Bridge Works, (2007), Published by the Ministry of
Road Transport;
4. Standard Details, Road Signs and Marking for Urban and Trunk Roads;
Pavement configurations will be designed according to the GHA Pavement Design Manual
and the AASHTO Pavement Design Methods.
A double seal bitumen surface (10mm on 14mm chipping) will be employed to provide the
needed smooth surface.
Impact Assessment
The Construction of the pavement will impact on the environment positively or negatively.
Selection of pavement materials in conjunction with the geotechnical engineer and the
construction by layer thickness and compactive effort at optimum level will be employed.
The double seal construction will provide pavement smoothness than the conventional single
chip seal. Recent research is increasingly confirming the role of pavement smoothness in
reducing the emissions and fuel consumption of the vehicles that use the road. A full scale
field study conducted by the trucks running on slightly smoother pavements could reduce fuel
Pavement will be designed as Perpetual pavements, designed to last indefinitely with just the
top 25-30mm wearing course needing to be replaced every 10 years or so, significantly
reducing both the maintenance and construction costs and the need for new materials
Further assessment of the positive and negative social, physical and biological impacts of the
project will be done by a desk study of similarly implemented projects and social
consultations.
Mitigation measures for significant negative impacts would be identified so as to achieve one
of the following:
method or materials
provision of amenities
costed. A Bill of Quantities will be prepared as prescribed by the Civil Engineering Standard
Method of Measurement (CESMM) document. In developing rates build up, all the factors
(equipment, labour, overheads, profit, etc) will be considered in order to arrive at realistic
rates. A market survey will be conducted as well as consultation with industry players in
order to obtain realistic rates. Rates will be compared with those of some recent similar
tenders.
Development and Management Investment Model, (HDM-4), for the economic analysis and
evaluation of the Project for the 20 years following the completion of the construction of the
road. The economic evaluation would be carried out for both "with" and "without" project
cases.
The Consultant is aware that the Road Deterioration sub-model is one of the sensitive models
in the HDM-4 Model. In this regard, a calibrated model will be used to predict the behaviour
of the road.
Economic costs
Economic benefits
In accordance with the TOR, The economic cost and benefits of the project will be evaluated
for the calculation of the Net Present Value (NPV), Economic Internal Rate of Return (EIRR)
and Benefit/Cost Ratio. Benefits will be calculated based on savings in vehicle operating cost
and time. Other non-quantifiable costs and benefits will also be listed. Groups that benefit
and cost accrued will be identified. Staging and Implementation for the project will also be
With the inception phase of the work completed, we are confident that within the following
Executive Summary
Background &Introduction
Geometric Designs
Pavement Design
Working Drawings
Cross-sections
Aside the following documents no previous design report has been provided by the client:
Proposed site layout drawing showing the proposed location of the buildings and
associated infrastructure;
It is therefore difficult to understand the criteria used to develop the road layout shown in the
given drawings.
7.0 APPENDIX
Figure 1. Volume Count Locations (In Red) for Proxy Site.