*DAILY PRODUCTION REPORT*


Tuesday, 29 August 2023
*PT. MITRA MULTI INDOMINING JOB SITE PT BUKIT BAIDURI ENERGI*

*I. OVERBURDEN REMOVAL*


*DAILY*
■ Shift I : 15.032 Bcm
■ Shift 2 : 12.880 Bcm
□ Actual Total : 27.912 Bcm

■ Plan : 24.051,31 Bcm


■ Ach % : 116 %

*MONTH TO DATE* 01 August 2023 - 29 August 2023


□ Actual : 776.020 Bcm

■ Plan : 666.737 Bcm


■ Ach % : 116 %

■ Monthly Overburden Removal Plan August 2023 : 714.839 Bcm

*YEAR TO DATE* 01 January 2023 - 29 August 2023


□ Actual : 5.575.903 Bcm
■ Plan : 5.832.733 Bcm
■ Ach % : 96 %

■ Yearly Overburden Removal Plan 2023 : 9.002.977 Bcm

*II. COAL MINING*


*DAILY*
■ Shift I : 1.780,16 Ton
■ Shift 2 : 1.666,56 Ton
□ Actual Total : 3.446,72 Ton
■ Plan : 2.124,12 Ton
■ Ach % : 162 %

*MONTH TO DATE* 01 August 2023 - 29 August 2023


□ Actual : 66.485,83 Ton
■ Plan : 59.087,97 Ton
■ Ach % : 113 %
■ Monthly Coal Mining Plan August 2023 : 63.336,21 Ton

*YEAR TO DATE* 01 January 2023 - 29 August 2023


□ Actual : 480.012,71 Ton
■ Plan : 574.677,82 Ton
■ Ach % : 84 %

■ Yearly Coal Mining Plan 2023 : 821.540,59 Ton

*III. STRIPPING RATIO*


*DAILY*
□ Actual : 8,1
■ Plan : 11,32
■ Ach % : 72 %

*MONTH TO DATE* 01 August 2023 - 29 August 2023


□ Actual : 11,67
■ Plan : 11,28
■ Ach % : -3 %

*YEAR TO DATE* 01 January 2023 - 29 August 2023


□ Actual : 11,62
■ Plan : 10,15
■ Ach % : -14 %

*IV. PROJECT TO DATE*


□ Actual Overburden Removal: 16.459.644 Bcm
□ Actual Coal Mining : 1.171.771,34 Ton
□ Actual SR : 14,05

*V. COAL INVENTORY*


□ Actual Daily Coal Expose : --
■ Plan Daily Coal Expose : 1.955,26 Ton

□ Actual MTD Coal Expose: 68.996,37 Ton


■ Plan MTD Coal Expose : 62.021,32 Ton

□ Actual Coal Inventory (Today) : 6.032,70 Ton


□ Near Coal Expose : --

*VI. WEATHER*
Shift 1 : --
Shift 2 : --
Total : --
*VII. PRODUCTION ISSUE*
Shift 1 (PIT Gold Star)
- OB removal using : 2 X PC400, 5 x Doosan 500 & 2 x Hyundai 850
: 6 x HD Sany, 3 x DT Hino 700, 3 x DT SCANIA P-360, 5 x DT Sany & 30 x
DT Hino FM500
- 07:23 - 07:49 : 1 x HYUNDAI PC850 (EX592) Breakdown Pin bucket Loose
- 06:00 - 18:00 : 1 x KOMATSU PC400 (EX530) Breakdown Starting motor problem
- 06:30 - 08:30 : 1 x DOOSAN 500 (TMEX-012) Breakdown Main Pump Abnormal
- 09:20 - 18:00 : 1 x DOOSAN 500 (TMEX-012) Breakdown Low Power
- 11:28 - 11:36 : 1 x DOOSAN 500 (TMEX-011) Maintenance Mechanic
- 06:00 - 18:00 : 1 x DOOSAN 500 (TMEX-004) Breakdown Engine Overheat
- 06:30 - 07:00 : 1 x DOOSAN 500 (TMEX-003) Breakdown Can't Start
- 06:00 - 18:00 : 1 x KOMATSU PC300 (TMEX-007) Breakdown Tapped Roller Valve Lose
- 06:00 - 18:00 : 1 x KOMATSU D375 (TMDZ-008) Breakdown Eror Transmisi
- 06:00 - 18:00 : 1 x KOMATSU D85SS (TMDZ-007) Breakdown transmision abnormal
- 17:20 - 18:00 : 1 x KOMATSU D85SS (TMDZ-005) Breakdown broken right pole
- 06:00 - 18:00 : 1 x KOMATSU D85SS (TMDZ-001) Breakdown Low Power - Compressi
- Coal Getting using : 1 x PC300-8M0
: 16 x DT Hino FM500
- Dusty at Coal Hauling Road, coal hauling activities wasn't optimal due to reduced visibility

Shift 2 (PIT Gold Star)


- OB removal using : 2 X PC400, 5 x Doosan 500 & 2 x Hyundai 850
: 6 x HD Sany, 3 x DT Hino 700, 3 x DT SCANIA P-360, 5 x DT Sany & 28 x
DT Hino FM500
- 02:34 - 03:01 : 1 x HYUNDAI PC850 (EX583) Breakdown Worn out tooth bucket
- 18:00 - 06:00 : 1 x KOMATSU PC400 (EX530) Breakdown Starting motor problem
- 01:31 - 02:09 : 1 x KOMATSU PC400 (EX616) Breakdown Pin bucket Loose
- 18:00 - 06:00 : 1 x DOOSAN 500 (TMEX-012) Breakdown main pump abnormal

- 02:39 - 06:00 : 1 x DOOSAN 500 (TMEX-011) Breakdown Problem On Radiator


- 18:00 - 06:00 : 1 x DOOSAN 500 (TMEX-004) Breakdown Engine Overheat
- 18:00 - 06:00 : 1 x KOMATSU PC300 (TMEX-007) Breakdown Tapped Roller Valve Lose
- 18:00 - 19:40 : 1 x Hitachi PC200 (TMEX-008) Breakdown Maintenance
- 18:00 - 06:00 : 1 x KOMATSU D375 (TMDZ-008) Breakdown Eror Transmisi
- 18:00 - 06:00 : 1 x KOMATSU D85SS (TMDZ-007) Breakdown transmision abnormal
- 18:00 - 06:00 : 1 x KOMATSU D85SS (TMDZ-001) Breakdown Low Power - Compressi
- Coal Getting using : 1 x PC300-8M0
: 16 x DT Hino FM500
- Dusty at Coal Hauling Road, coal hauling activities wasn't optimal due to reduced visibility