SESI 3
PIT OPTIMIZATION BASED ON BESR
Project Valuation DATA COLLECTION TO BE VERIFIED
FLOW CHART LEGAL ASPECT
• IUP STATUS
• AKTAPERUSAHAAN
• IPPKH

DOCUMENT
• EXPLORATION REPORT
• FS
• RESOURCE & RESERVE STATEMENT
• GEOTECHNICAL REPORT

TECHNICAL
RAW DATA –DRILLING RECONCILE
INCLUDE:
• COLLAR.
• LITHOLOGY ( LOGGING)
• QUALITY
PROJECT SOFTWARE
GEOLOGICAL MODEL
TOPOGRAPHY
MINE DESIGN

SOURCE:
INTERNALSOP FIRST UP 2
CONSULTANTS
FLOW CHART PROCESS

FIRST UP 3
CONSULTANTS
WHY PIT OPTIMIZATION?

Source:
Perhapi Workshop KCMI 2018 FIRST UP 4
CONSULTANTS
Source:
Perhapi Workshop KCMI 2018 FIRST UP 5
CONSULTANTS
Source:
Perhapi Workshop KCMI 2018 FIRST UP 6
CONSULTANTS
BESR concept
• BESR adalah Perbandingan nisbah kupas (Striping Ratio) pada titik tertentu
dimana harga jual sama dengan ongkos produksi (titik impas).
• Penentuan BESR berdasarkan Incremental Strip Ratio (bukan kumulatif SR)
dalam penentuan batas pit ekonomis.
• Incremental SR >> Accumulative SR

Misal : BESR adalah di SR 8, maka diketahui accumulative SR adalah SR 6

• Nilai BESR (incremental SR) digunakan sebagai dasar dalam pembuatan Pit
Optimasi

FIRST UP
CONSULTANTS
FIRST UP
CONSULTANTS

THANK YOU