PENAMBANGAN LPPBJ
TAHUN 2023
(SEPTEMBER-DESEMBER)
OUTLINE
• Estimasi Cadangan
• Target Produksi
• Rencana Jam Kerja
• Peta Rencana Penambangan LOM
• Kebutuhan Peralatan Pertambangan
• Rencana Produksi
• Sequence Penambangan
• Kebutuhan Tenaga Kerja
• Struktur Organisasi
ESTIMASI CADANGAN
Pit LPPBJ
Overburden
# Tahun Bulan Coal (MT) SR
(BCM)
1 September 75,000 25,000 3.00
2 October 150,000 50,000 3.00
2023
3 November 150,000 50,000 3.00
4 December 150,000 50,000 3.00
5 January 150,000 50,000 3.00
6 February 150,000 50,000 3.00
7 March 150,000 50,000 3.00
8 April 150,000 50,000 3.00
9 May 150,000 50,000 3.00
10 2024 June 150,000 50,000 3.00
11 July 150,000 50,000 3.00
12 August 150,000 50,000 3.00
13 September 150,000 50,000 3.00
14 October 150,000 50,000 3.00
15 November 55,724 18,575 3.00
Total 2,080,724 693,575 3.00
RENCANA JAM KERJA
Note:
Perhitungan berdasarkan kapasitas peralatan
SEQUENCE PENAMBANGAN
Desember(Tahun 2023)
KEBUTUHAN TENAGA KERJA
September-Desember(Tahun 2023)
DESKRIPSI QTY. DESKRIPSI QTY.
September-Desember(Tahun 2023)
PROJECT MANAGER
MECHANIC HEAVY EQUIPMENT ADMIN HSE STAFF HR MINE ANALYST GL. PRODUCTION
MECHANIC DUMP TRUCK CREW HSE STAFF FINANCE & ACCOUNTING GEOLOGIST DUMP MAN
BUILDER
SECURITY