PRODUCTION REVIEW
Production
Desc.
OB Coal
Plan Monthly 3,901,850.85 375,669.73
Plan Month to Date 3,509,275.91 337,960.84
Actual Month to Date 3,078,471.14 287,837.78
Ach Monthly (%) 78.90% 76.62%
Ach MTD (%) 87.72% 85.17%
Remaining Target 823,379.71 87,831.95
Plan/Days before EOM (3 Days) 274,459.90 29,277.32
Production
Desc.
OB Coal
Plan Yearly 34,225,023.00 3,024,412.00
Plan Year to Date 26,172,041.31 2,476,216.94
Actual Year to Date 25,323,774.26 2,191,066.55
Ach Yearly (%) 73.99% 72.45%
Ach Year to date (%) 96.76% 88.48%
Remaining Target 8,901,248.74 833,345.45
Plan/Days before EOY (64 Days) 139,082.01 13,021.02
M o n t h To d at e R ai n & s l i p p e r y
25.00 Act Rain Act Slippery Forecast Rain Forecast Slippery
20.00
15.00
10.00
5.00
-
Week1 Week2 Week3 Week4 Week5
- 0.00% - 0.00%
Week1 Week3 Week4 Week5 Week1 Week3 Week4 Week5
- 0.00% - 0.00%
Week1 Week2 Week3 Week4 Week5 Week1 Week2 Week3 Week4 Week5
90.00%
200.00 13,500.00
20.00%
88.00%
192,940
293,457
56,015
3509275.90539436 111,606
3,078,471
P la n Q t y U n it PA UA P TY A ct u a l
140,000.00 30%
120,000.00
25%
100,000.00 21%
20%
20%
80,000.00 16%
137,870.16 15%
60,000.00
11%
90,917.38 10%
40,000.00 85,513.99
70,771.67
20,000.00 45,731.57 5%
- 0%
PA Loader Qty Loader Rain PTY Hauler Qty Hauler
Bcm
Problem 1. PA
2. Qty
3. PTY
Akses front to disposal, beberapa spot jalan grade tinggi >8% (Blok 14 - T3). Traffic di T3 crowded.
PA aktual unit support :
1x GD805 PA aktual < 50%, 1x GD705 PA aktual < 50%, sehingga available qty hanya masing-masing 1 unit
D85 PA aktual <70%, sehingga rata-rata qty available hanya kurang lebih 2-3 unit.
Corective 1. Berkoordinasi dg tim Logistik untuk push ketersediaan sparepart yang di perlukan oleh Dept. Plant untuk
Action segera mereadykan Digger & Hauler yang berstatus waiting parts.
3. melakukan penurunan grade jalan yang lebih dari 8%, melakukan penambahan/pengalihan akses
meningkatkan PA unit support khususnya grader & Dozer.
8,550.10
4,677.26
47,343.17
337960.841353336
1,093.05
287,837.88
P la n Q t y U n it PA UA P TY A ct u a l
Pareto Loss Coal Mining
30,000.00 60%
20,000.00 40%
15,000.00 30%
24,449.58
10,000.00 20%
15% 14%
13%
10%
5,000.00 10%
7,415.06 7,119.23 6,332.34
4,806.85
- 0%
No Material Qty Loader PTY Hauler PA Hauler No Operator
5. No Operator
Trend in out operator cukup banyak, ada beberapa man power yang dialihkan ke project SSC
Corective 1. Pembuatan rencana staging plan P1, P2, P3. Memindahkan 2x Big digger dari T1 ke T3.
Action 2. Continue R&M dari Dept. Plant
3. Jalan hauling undulating, maintenance jalan closed tgl 27 Okt. Push repair 2x Grader OB yang PA nya rendah.
4. Continue R&M dari Dept. Plant,
5. Evaluasi pemenuhan Man Power.
Cut Off 28 Okt 2021
PARETO PROBLEM & PICA COAL
Detail No Material
REVIEW PA
PA MONTHLY
MONTHLYOB
OB
TERIMAKASIH