Professional Documents
Culture Documents
SYNOPSIS
With the availability of various pile instrumentation techniques and
numerous publications today, the use of instrumented pile load tests for
monitoring pile performance and investigating on the design parameters in
relation to pile length provision has become very popular in the local piling
industry. The common use of conventional sacrificial cast-in strain gauges and
sleeved rod tell-tales method is generally limited to bored pile application. In
the recent past 5 years, an innovative instrumentation and analysis technique,
called Glostrext method has also been used widely, providing an improved and
practical way for instrumentation application for instrumented load tests. The
Glostrext method is practically suitable for application on all commonly used
local pile types including bored piles, barrettes, micropiles, spun piles and RC
square piles. Key advantages of the Glostrext method include: (i) the method
enables installation of instrumentation after pile installation and thus virtually
eliminates the risk of instrument damage during pile production and
installation, (ii) remarkable potential of allowing a test pile to be constructed
with an efficiency close to a normal working pile due to its post-install nature,
(iii) a useful means in narrowing down the zone for damage identification
when a pile fails in the load test, and (iv) providing an improved method for
determination of pile modulus, an important parameter in the interpretation of
Year 2006
instrumented load test results. Key aspects of instrumented load tests and
recent case histories will be discussed beside comparison of pros and cons on
various pile instrumentation techniques and interpretations. A discussion on
the authors’ proposed more representative loading sequence is also included.
1
Outline
• Introduction
• The need and trends in pile instrumentation
• Case Histories
• References for application of Glostrext Method for bored piles
• References for application of Glostrext Method for precast piles
Introduction :
Main construction control for piles in early years:
• Based on the measurement of set of each pile (driven); and
• A selected small number of non-instrumented static load tests to
verify the Capacity and specified Load- Settlement requirement.
2
Introduction:
Case 1: Case 2: Case 3:
Ideal, Over- Under-
adequate, conservative, provided,
safe and
economical
not
economical
not safe • Pile length design is an “art”
0.0 m Existing GL
• Millions (or billions?) of
Soft
Layer
dollars are wasted every
year due to under-provided
/over-designed foundations
10.0 m
worldwide !
Competent
Soil Strata
Introduction :
For pile instrumentation in general, vw strain gauges and
mechanical tell-tales are installed and cast within the pile to
allow for monitoring of axial loads and movements at various
levels down the pile shaft including the pile toe
• However, the common use of conventional sacrificial cast-in strain gauges and
sleeved rod tell-tales method is generally limited to bored pile application.
History of vibrating wire sensors:
(Recommended Reference: Long Term Monitoring Using VW Sensors by
A.J.Simmonds, The 6th International Conference on Structural Health Monitoring of
Intelligent Infrastructure, Hong Kong, 9-11 December 2013)
• Earliest recorded account: 1888 in Italy by Pietro Cardini ;
• Next is found in US Patent No. 633,471 in 1899;
• 1928 in Russia by Daviddenkoff and in France by Andre Coyne;
• 1930 A. Coyne made first commercial installation of VW sensors at Bromme Dam;
• 1931 Andre Coyne patented a VW Strain Gauge and in 1947 he founded Telemac,
who manufactured vw sonsors in commercial basis.
• Today vw sensors are manufactured in several countries.
3
Introduction :
The Glostrext technology consists of a deformation monitoring
system which uses advanced pneumatically-anchored
extensometers coupled with high-precision spring-loaded
transducers, and a novel analytical technique to monitor loads
and displacements down the shaft and at the toe of piles.
(Recommended References: Aziz, H.M.A. & Lee, S.K. (2006), Krishnan, S. & Lee, S.K.
(2006), Lee, S.K. et al.(2007), Faisal, H.A. & Lee, S.K. (2008, 2010), Liew S.S. et al.(2010)
Chong, YW & Lee, S.K. (2013), in different regional and international conferences)
4
Instrumentation Methods for Cast-in-place Piles
Examples / Illustration of
pile test instrumentation
5
Review of Conventional Methods : Cast-in-place piles
Instrumented Test Bored Pile
Apllied load measured by vw load cells
Pile head
1.
PTop Platform level Installation of vibrating
Verify and back-
calculate Ec Strain Gauges Lev. A wire strain gauge
(VWSG) to the main
reinforcement bar at the
designated level
PB Strain Gauges Lev. B
2.
Tell-tale Extensometer 1 VWSGs and signal
PC Strain Gauges Lev. C
cables & mechanical tell-
tales installed on
reinforcement cage
PD Strain Gauges Lev. D
3.
PE Strain Gauges Lev. E
Signal cables for VWSGs
are led along the rebar s
Tell-tale Extensometer 2
PF Strain Gauges Lev. F with strong ties to the top
Pile toe
Legend:
during lowering of cages
denotes Vibrating Wire Strain Gauges
denotes mechanical tell-tale extensometer 4.
Concreting well beyond
Fig. (a) : Sacrificial cast-in conventional midnight is common
pile instrumentation method
Constraints:
• Long lead time;
• delays the casting of the piles
• Higher risks of forming soft toe
(due to sedimentation at toe)
• very often when there is difficulty
in pile installation (concreting time,
hole collapse..) or due to human
problem, the instruments also get
damaged
• Strain gauges capture only localised
strain measurement.
• Tell-tales performance affected by
rod friction, bowing, eccentricity,
reference beam movement.
• If no direct cut out hole provided in
pile top plate, tell-tale rods often
give erratic readings
• congestion of sleeved pipes/rods.
6
Post-install Glostrext Method for Bored Piles
Instrumented Test Bored Pile
Apllied load measured by vw load cells
Pile head
PTop 2.5" GI/steel pipe fully
Anchored Lev. A
GLOSTREXT Sensor 1
Verify and back-
calculate Ec
accessible for housing
Anchored Lev. B VW extensometer and sensors
GLOSTREXT Sensor 2 PAve(BC)
Anchored Lev. C
Anchored Lev. D
GLOSTREXT Sensor 4
PAve(DE)
Anchored Lev. E
GLOSTREXT Sensor 5 PAve(EF)
Anchored Lev F
GLOSTREXT Sensor 6 PAve(FG)
Anchored Lev. G
Pile toe
Legend:
denotes GLOSTREXT anchored level
denotes GLOSTREXT Vibrating Wire Sensor
1.
Installation of pile as usual like working pile
Fig. (b) : Glostrext instrumentation without instruments during casting (only with
Method access steel/g.i. pipes for housing Glostrext sensors
post-casting of pile)
7
Post-install Glostrext Method for Micropiles
Instrumented Micropile
SPT value, N (blows/30cm)
0 20 40 60 80 100
0.0 m Anchored Lev. A-0 (RL 1663.457 m)
0
0.5 m
1
1.25 m Global Strain Gauge Lev A
22
2 2.0 m Anchored Lev. 1 Extensometer Lev. 1
Micropile
3 31
9
Gra nite, RQD= 81%
9.75 m Global Strain Gauge Lev. D
10
Depth below original ground level (m)
18
Gra nite, RQD= 18%
19
Granite, RQD= 0%
20
21
22
23
24
Legend:
denotes Glostrext anchored level
25
denotes Glostrext Sensor
SI Borehole : BH-1
8
Review of Conventional Methods: Precast piles
For precast driven / jack-in piles, the application of
instrumented full-scale static load tests is far more
challenging than their bored pile counterparts due to
significant difference in method of pile installation.
Therefore, the far lacking driven pile industry is long due for
a better technology to revolutionize the methodology in the
acquisition of design data in a more accurate and reliable
way, to catch up with the evolution in the design methods.
5
Clay
Sandy
spun concrete piles piles:
Clay Strain Gauges Lev. C
20
• By incorporating high
Strain Gauges Lev. D
temperature-resistant strain
25
9
Constraints of Conventional Method
This method is extremely unpopular and difficult to be
routinely applied in project sites due to the following
constraints:
(a) High cost of these temperature-resistant strain gauges;
(b) Tremendous difficulties involved in coordinating the
installation of the strain gauges into pile segments;
(c) Long lead-time is normally required for instrumentation
works, as the instruments have to be pre-assembled and
installed onto the high strength prestressing bar cage
prior to autoclaved heat-cured ‘spin-cast’ production
process of the piles; and
(d) Great uncertainty over the ability of the delicate
instruments to withstand the stresses arising from pile
production and driving processes.
Sandy
the past few decades, by
Clay Strain Gauges Lev. C
20 installing either an
instrumented reinforcement
25
Strain Gauges Lev. D steel cage or an
Sandy
Silt Strain Gauges Lev. E
instrumented pipe, into the
30 Strain Gauges Lev. F hollow core of spun piles
Pile toe at 30.0 m depth
Legends:
followed by cement grout
SI borehole log
denotes Vibrating Wire Strain Gauges infilling
denotes Pile Joint
10
Approximate Instrumentation Method for
Prestressed Spun Concrete Piles
(i) (ii)
(iii) (iv)
Typical installation process of spun pile instrumentation in Approximate Method
Section of instrumented spun pile after cement grout infilling in Approximate Method
11
Shortcomings of Approximate Method
The obvious shortcomings of this approximate method include:
(a) The infilling of cement grout substantially alters the structural
properties of the piles, thus rendering them significantly different
from the actual working spun piles, which are usually not grouted
internally;
(b) The change in strain in the post-grouted core under the applied
loading may not be the same as the change in strain in the
prestressed concrete wall of the pile because of the different
stiffness of the two materials of different mix, strength and age;
(c) Structural shortening measurement of the test piles are not
representative of the actual working piles;
(d) Structural integrity of the original pile cannot be reliably
ascertained, particularly performance of pile joints, during the
static load test; and
(e) Significant time loss due to grout infilling and curing process,
beside the environmental unfriendly nature of this method.
To Datalogger
Glostrext Anchor
Reference :
Glostrext Sensor
Lee, Sieng Kai (2011), “Development and
Connecting Rod, Application of a New Instrumentation
Hose & Signal Cable
Technique for Spun Concrete Piles”. PhD
Thesis, Department of Civil Engineering,
Global Strain Extensometer instrumentation University of Malaya, Kuala Lumpur.
approach for typical spun pile application
12
Glostrext Method for Spun Piles
Glostrext
inside
Glostrext
inside
13
Development of Glostrext Method for Spun Piles
4000
Pile Top Load (kN )
3000
2000
Glostrext
inside
1000 Typical Results
of Laboratory
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Verification
0
Time (hours)
Tests
S3-Global Strain Extensometer Technology
200 S3-Average VWSGs Lev A,B,C
Change in Strain (microstrain)
400
600
800
1000
1200
1400
1600
14
Glostrext Method for Spun Piles
Load transferred (PAve) at mid-
point of each anchored
interval can be calculated as:
Precision
P = ε(Ec Ac )
Transducer for where,
measuring ε= average change in global
displacement,
i.e. distance strain gauge readings;
change between Ac = cross-sectional area of spun
upper and lower pile section;
extensometers.
Accuracy is
Ec = concrete secant modulus in
approx.ly pile section
0.01mm/2 to 5m
corresponding Note:
to 2 to 5 µε For conventional method, tell-tales
are normally limited to 3 nos, but for
Glostrext Method, N levels of
glostrext sensors give N levels/N
pairs of equivalent TT but without
congestion problem, and with more
than 10 times better accuracy And
provide much more information on
finite segmental deformation.
Schematic diagram of typical instrumented spun pile
using Global Strain Extensometer technology
4 RL 0.00 m MLSD
4.5 m
6
6.5 m Glostrext Sensor 1 Global Strain Gauge Lev. A
8
10
Seabed (RL-7.0m) 11.5 m Anchored Lev. A-1 Extensometer Lev. 1
Seabed (RL-7.0m)
12
Hollow core
14
VS-1:
16 Peak=16kPa
Rem=5kPa 16.5 m Glostrext Sensor 2 Global Strain Gauge Lev. B
18
VS-2:
Peak=27kPa Spun pile
Rem=10kPa
20
Silty Clay
21.5 m Anchored Lev. A-2 Extensometer Lev. 2
22
Depth below pile top (m)
VS-3:
Peak=43kPa
24 Rem=13kPa
28 6
28.5 m Anchored Lev. A-3 Extensometer Lev. 3
7
30
7
32
8
33.25 m Glostrext Sensor 4 Global Strain Gauge Lev. D
34 14
Silty Sand
15
36
18
38
19 39.0 m Anchored Lev. A-4 Extensometer Lev. 4
40 21
40.75m Glostrext Sensor 5 Global Strain Gauge Lev. E
27
42
42.5m Anchored Lev. A-5 Extensometer Lev. 5
91
44 43.75m Glostrext Sensor 6 Global Strain Gauge Lev. F
94
45.0 m Anchored Lev. A-6 Extensometer Lev. 6
46 64
15
Glostrext Method for Marine Spun Piles
3
3.55 m Anchored Lev. A-1 Extensometer Lev. 1
4
RL 0.00 m CD
5
Hollow core
6
7 Spun pile
8
8.55 m Glostrext Sensor 2 Global Strain Gauge Lev. B
9
10
11
12
15
0
16
Depth below pile top (m)
17
VS-1:
Peak=14kPa Marine
18 Clay
Rem=4kPa
18.675 m Glostrext Sensor 3 Global Strain Gauge Lev. C
19
20
VS-2:
21 Peak=23kPa
Rem=8k Pa
22
VS-3:
Peak =40k Pa
23 Rem=15k Pa
24
24.3m Anchored Lev. A-3 Extensometer Lev. 3
25
33 142.85
71429
34
136.36
35 36364
Legend:
36
125 denotes Glostrext anchored level
37
denotes Glostrext Sensor
SI Borehole : BH7
16
Glostrext Method for RC Square Piles
Glostrext Sensor
Pile top
Signal Cables,
pressure hole
Datalogger
arrangement for
Jacking System with
Load Cell
RC pile
50mm dia. Hole
Opening (Bottom
instrumented
Plate) & 25mm
with Glostrext
Min. 50mm thk Steel Plate
Trench (Top Plate)
RC Square Pile
17
Glostrext Method for RC Square Piles
Instrumented Pile
SPT value, N (blows/30cm)
0 50 100 150 200
(RL 40.0mm )
0
0.3 m Anchored Lev. A-0
0.8 m Glostrext Sensor 1 Global Strain Gauge Lev. A
1
1.3 m Anchored Lev. 1 Extensometer Lev. 1
3
2
3 5
Clayey Sand
4
4
4.8m Glostrext Sensor 2 Global Strain Gauge Lev. B
5
52mm Ø i.d.
6 12 steel pipe to
house instruments
7
11
8
Sand 8.3 m Anchored Lev. 2 Extensometer Lev. 2
9 13
10
8 RC pile
11
11.3 m Glostrext Sensor 3 Global Strain Gauge Lev. C
12 12
Depth below original ground level (m)
13
12
14
14.3 m Anchored Lev. 3 Extensometer Lev. 3
15 9
Sand Silt
16
12
17
17.3 m Glostrext Sensor 4 Global Strain Gauge Lev. D
18 13
19
15
20
20.3 m Anchored Lev. 4 Extensometer Lev. 4
21 12
27 61
28 Legend:
71 denotes Glostrext anchored level
29
denotes Glostrext Sensor
30 79
SI Borehole : BH9
Case Histories
Recommneded References for application of
Glostrext Method for bored piles
18
Case Histories
Recommended References for application of
Glostrext Method for precast piles
1. Faisal Hj Ali & Lee Sieng Kai (2008). “Recent development in pile
instrumentation technique for prestressed spun concrete piles”.
Geotechnical Engineering Journal, Southeast Asian Geotechnical
Society. Vol. 19.No. 2, pp. 77-86.
2. S.K. Lee, T.K. Lau, A.H. Tan, Faisal Hj. Ali, Y.W. Chong, 2007.
“Recent Development in Pile Instrumentation Technology for
Driven and Jacked-in Prestressed Spun Concrete Piles”, Proceedings
of 16th South East Asian Geotechnical Conference, Kuala Lumpur, pp.
727-734.
3. Krishnan S. & Lee S.K., 2006. “A Novel Approach to the Performance
Evaluation of Driven Prestressed Concrete Piles and Bored Cast-in-
place Piles”. Proceedings of 10th International Conference on Piling
and Deep Foundations, Amsterdam, pp 718-726
19
Discussion on Key Aspects of Instrumented
Load Tests and Interpretations of Results
Quote:
20
(1) Proposed more representative loading sequence
Pile load testing using
Comparison the slow
of required
time for various
maintained load test test
method methods
is the(Fellenius, 1975)
most commonly
adopted method of checking the
performance of piles in Singapore
and the region.
Although several engineering
practices have their own
individual specifications for
maintained load tests, the ICE
Specification for Piling (similarly
adopted in MS 1756:2004,
Source of reference: Professor Bengt H. Fellenius’BS
CP4:2003, Lecture
8004: Note,
1986)“sets out a
One Day Short Cource on Basics of Design of Piled
suitable Foundation”
minimum
Comparison scheme and
of load-
(Organized by GETD, IEM), 14 June 2013 Petaling
limits on theJaya.
rate of movement
movement behavior for test
before next load
methods stage is1975)
(Fellenius, added.
10% 30 minutes
20% 30 minutes
30% 30 minutes
40% 30 minutes
50% 30 minutes
60% 30 minutes
70% 30 minutes
80% 30 minutes
90% 30 minutes
100% 30 minutes
70% 10 minutes
100% Repeat 9 times 10 minutes
110% 30 minutes
120% 30 minutes
130% 30 minutes
140% 30 minutes
150% 30 minutes
160% 30 minutes
170% 30 minutes
180% 30 minutes
190% 30 minutes
200% 12 hours
Go higher if possible -
150% 30 minutes
100% 30 minutes
50% 30 minutes
0% 3 hours
Note:
Limit for the rate of movement of 0.25mm per hour before next load
stage provided the rate is decreasing.
21
(1) Proposed more representative loading sequence
3400
3200
3000
2800
2600
2400
2200
Pile Top Load (kN )
2000
1800
1600
1400
1200
1000
800
600
400
200
0
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38
Load Cell
Versus
Pressure
Gauge for
hydraulic jack
22
(2) Pile top load measurement
Sample calibration
sheet for Vibrating
Wire Load Cell
23
(3) Settlement monitoring
Pile Movement
Monitoring System :
24
(5) Synchronized readings for all insruments
10000
load versus pile top
8000
settlement, pile base
6000
settlement and total
4000
pile shortening for
2000
an instrumented test
0
0 5 10 15 20 25 30 35 40 pile
Pile Top Settlement /Pile Base Settlement /
Total Shortening (mm)
Pile Top Settlement Pile Base Settlement Total Shortening
25
(6) Assessment of Pile Top Settlement / Pile Base
Settlement / Total Shortening
But with Glostrext pile instrumentation, we can identify the embedded structural
damage with the ability to narrow down the probable zone of such structural
failure as shown in this example.
26
(7) Load Transfer Analysis
The load distribution along the shaft and at the base were normally
derived from computations based on the measured changes in strain
gauge readings and pile properties
P = ε (Ec Ac + Es As )
where
ε = average change in strain gauge readings
Ac = cross-sectional area of concrete
Ec = modulus of concrete
As = cross-sectional area of steel reinforcement
Es = Young's Modulus of Elasticity in steel (= 200 kN/mm2)
• Tangent Modulus
The Tangent Modulus is defined as the slope of a line tangent to the stress-strain curve at a point of
interest. Tangent Modulus can have different values depending on the point at which it is determined. For
example, Tangent Modulus is equal to the Young’s Modulus when the point of tangency falls within the
linear range of the stress-strain curve. Outside the linear elastic region, Tangent Modulus is always less
than the Young’s Modulus. Tangent Modulus is mostly used to describe the stiffness of a material in the
plastic range.
27
(7) Load Transfer Analysis
Pile modulus is an important parameter in the interpretation of instrumented load test
results. C.Lam & S.A.Jefferis (2011) identified ten pile modulus determination methods,
of which four are based on laboratory and the remainder on in situ pile instrumentation.
Six of the methods have been used to interpret the modulus of a concrete pile subject to
an axial compression load test. From their review, based on a comparison of the derived
pile loads the secant modulus method was found to be the most satisfactory .
6
8 8
35
y = -5.75E-03x + 2.56E+01 10 10
30 12
12
25 14 14
16 16
20
18 18
15 20 20
y = -0.0026x + 20.909
22 22
10
24 24
Glostrext data VWSGs data From Glostrext Data From VWSGs Data
5 26 26
Linear (Glostrext data) Linear (VWSGs data)
28 28
0
0 200 400 600 800 1000 1200 1400 P= 1448 kN P= 2884 kN P= 4254 kN P= 5538 kN P= 1448 kN P= 2884 kN P= 4254 kN P= 5538 kN
P= 7099 kN P= 8602 kN P= 10068 kN P= 11501 kN P= 7099 kN P= 8602 kN P= 10068 kN P= 11501 kN
Average Axial Segmental Strain ( x 10-6 ) from Lev A P= 12925 kN P= 14238 kN P= 15603 kN P= 17225 kN P= 12925 kN P= 14238 kN P= 15603 kN P= 17225 kN
28
(8) Assessment of Shaft Friction and Endbearing
34000
32000
30000
28000
26000
24000
22000
Pile Top Load (kN )
20000
18000
16000
Weak Soil?
14000
12000
Soft toe ?
10000
8000
Weak Toe?
6000
4000
2000
0
Reference: Shamsher Prakash et al,
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
“Pile (mm)
Pile Top Settlement /Pile Base Settlement / Total Shortening Foundations in
Engineering Practice”
Pile Top Settlement Pile Base Settlement Total Shortening
Reference: CP4:2003
29
(8) Assessment of Shaft Friction and Endbearing
1100 Mobilised Unit Shaft Friction (kN/m2) 20000
Mobilised Unit Shaft Friction ( kN/m2 )
Load ( kN )
600 Lev G to Lev H 8
Lev H to Lev I 10 10000
500
12
400
14
300 16 5000
200 18
100 20
0 22
0
0 5 10 15 20 25 30 35 40 24 0 5 10 15 20 25 30 35 40
Average Movement of Pile between soil stratum ( mm ) 26
Pile Top Settlement (mm)
28
1100 10000 50
Mobilised Unit Shaft Friction ( kN/m2 )
Pb/Ptop ( % )
Lev H to Lev I 6000 30
600
5000 25
500
4000 20
400
300 3000 15
200 2000 10
100 1000 5
0 0 0
0 5 10 15 20 25 30 35 40 0 5 10 15 20 25 30 35 40 0 5 10 15 20 25 30 35 40
Pile Top Settlement (mm) Pile Base Settlement ( mm ) Pile Top Settlement (mm)
Loads ( kN)
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000
0 5838
1
5838
2
3
Depth below platform level (m)
4
5710
5
8
5530
9
10
11
5234
12
4787
13
4272
14
3752
15
16
P= 802 kN P= 1537 kN P= 2271 kN P= 3011 kN P= 3283 kN
P= 3559 kN P= 3820 kN P= 3218 kN P= 4463 kN P= 3607 kN
P= 4997 kN P= 5385 kN P= 5603 kN P= 5838 kN
30
(8) Assessment of Shaft Friction and Endbearing
this is reflected as a
line that flattens out
as an asymptote line
in the load transfer
characteristics plot
16000
14000
12000
10000
8000
6000
4000
2000
0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
Conclusion
• Ultimate test piles are usually tested to 2.5WL or 3.0WL in
present practice (CP4:2003, 7.5.4.4);
• It is meaningful only to instrument an ultimate test pile if it is
brought to and near to its geotechnical failure so that we can
derive the true Ks & Kb values;
• However normal foundation pile design usually err on
conservative side and it is unlikely to fail by testing it with the
normal design length;
• In order to enable a true geotechnical failure, there are 2 ways
out: (1) to shorten the pile length and test it to the usual 3.0WL;
or (2) to increase the max test load to 3.5WL~4.0WL;
• Our personal view is that the 2nd method is more costly and
more risky, should preferably go for the 1st method, with
appropriate and careful instrumentation implementation;
• With committed and co-operative relationship among the
authority, project owner, design/builder, specialist piling
subcontractors, pile suppliers and pile instrumentation and
testing specialists, there is no doubt every party can contribute
towards further improvement of the piling industry;
31
Conclusion
• But undeniably we need incentives and reasonable flexibility to
encourage innovation in this not too glamourous industry.
Thank you.
32