WEEKLY MEETING

DIVERSION ROAD – PROJECT

PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST


PRODUKSI ROAD DIVERSION-2
PRODUKSI ROAD DIVERSION-2
Date 5,000 4,554 4,554 4,554
4,554 4,554 4,554
Plan Actual Ach % 4,500 4,254
4-Nov-22 4,254.00 - 0.00% 4,000

5-Nov-22 4,554.00 - 0.00% 3,500


3,000
6-Nov-22 4,554.00 - 0.00%
2,500
7-Nov-22 4,554.00 - 0.00% 2,000
8-Nov-22 4,554.00 - 0.00% 1,500

9-Nov-22 4,554.00 - 0.00% 1,000


500
10-Nov-22 4,554.00 - 0.00% 0 0 0 0 0 0
0 0
TOTAL 31,578.00 - 0.00% 4-Nov-22 5-Nov-22 6-Nov-22 7-Nov-22 8-Nov-22 9-Nov-22 10-Nov-22
AVG 4,511.14 - 0.00% ACTUAL PLAN

PRODUKSI WORKSHOP KM18 PRODUKSI WORKSHOP KM18


Date
7,000
Plan Actual Ach % 6,232 6,232 6,232 6,232 6,232 6,232
5,832
6,000
4-Nov-22 5,832.00 1,309.00 22.45%
5-Nov-22 6,232.00 2,703.00 43.37% 5,000

6-Nov-22 6,232.00 2,380.00 38.19% 4,000

7-Nov-22 6,232.00 1,638.00 26.28% 3,000 2,703


2,380
8-Nov-22 6,232.00 714.00 11.46% 2,000 1,638
1,309
9-Nov-22 6,232.00 - 0.00% 714
1,000
10-Nov-22 6,232.00 - 0.00% 0 0
0
TOTAL 43,224.00 8,744.00 20.23% 4-Nov-22 5-Nov-22 6-Nov-22 7-Nov-22 8-Nov-22 9-Nov-22 10-Nov-22
AVG 6,174.86 1,249.14 20.23%
ACTUAL PLAN

PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST


RAIN HOURS
12.00
9.83
10.00

8.00
6.00 6.45
6.00
5.58

4.00
2 2 2 2 2 2 2
2.00
0.58 0.45
-
-
4-Nov 5-Nov 6-Nov 7-Nov 8-Nov 9-Nov 10-Nov
Actual 5.58 6.00 9.83 - 0.58 6.45 0.45
Plan 2 2 2 2 2 2 2

Desc Rain Slippery Rainfall Freq Rain Hari SLIPPERY HOURS


TOTAL
Plan 14.00 7.00 12.00 11.00
MTD
Actual 28.90 24.63 291.00 10.00 9 10.00

8.00

6.00 5.00
3.50
4.00 2.83 2.30
2.00
1 1 1 1 1 - 1 1 -
-
4-Nov 5-Nov 6-Nov 7-Nov 8-Nov 9-Nov 10-Nov
Actual 11.00 3.50 2.83 2.30 - 5.00 -
Plan 1 1 1 1 1 1 1

PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST


PERIODE : 4-Nov-22 S/D 10-Nov-22
VOLUME VOLUME VOLUME TOTAL SISA
PROGRES PROGRES VOLUME
PROJECT BOQ QTY MINGGU MINGGU SAMPAI PROGRES PROGRES
(%) (%) SISA
LALU INI MINGGU (%) (%)
A. ROAD DIVERSION 2
- LAND CLEARING 118,850.00 M2 118,850.00 100.00% - 0.00% 118,850.00 100.00% -
- CUT 147,054.00 M3 139,204.00 94.66% - 0.00% 139,204.00 94.66% 7,850.00 5.34%
- FILL 92,853.00 M3 77,002.00 82.93% - 0.00% 77,002.00 82.93% 15,851.00 17.07%
- SAFETY BERM 2,000.00 M' 2,000.00 100.00% - 0.00% 2,000.00 100.00% - 0.00%
- CULVERT 88.00 M' 88.00 100.00% - 0.00% 88.00 100.00% - 0.00%
- HEAD WALL 1.00 UNIT 1.00 100.00% - 0.00% 1.00 100.00% - 0.00%

B. INFRASTUCTUR KM-18
- LAND CLEARING 228,516.00 M2 200,190.00 87.60% - 0.00% 200,190.00 87.60% 28,326.00 12.40%
- CUT 636,654.00 M3 395,740.00 62.16% 29,300.00 4.60% 425,040.00 66.76% 211,614.00 33.24%
- FILL 659,509.00 M3 389,724.00 59.09% 18,751.00 2.84% 408,475.00 61.94% 251,034.00 38.06%

PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST


ROAD DIVERSION SEGMEN 2 :

➢ Unit General :
- Exca 20 T (EXXC-30) perapihan tanggul & bahu jalan
➢ Maintenance jalan segmen 1 & pembentukan badan jalan segmen 2:
- Motor Greder (MGKM-007)
- 2 Unit Compactor VBXC-007 & 011
- 1 Unit Buldozer 076

INFRASTRUCTUR KM 18 :

➢ Exca 80 T, 1 Unit (EXXC-51) cut area workshop dari Elv 65.00 ke Elv 63.50
➢ Unit Support :
➢ - 1 Unit Hauller 80 Ton
- 1 Unit Buldozer D8R (BDCT-005)
- 1 Unit Buldozer D85ESS (BDKM-077)
- 1 Unit Exca 20 T (EXXC-005)
- 1 Unit Compactor (VBIR-001)

PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST


POPULASI UNIT PROJECT INFRASTRUKTUR PT.KARUNIA WAHANANUSA

NO. DESCRIPTION UNIT NUMBER QTY LOCATION REMARKS

A Road Diversion Segmen 2


1 Exca 215 EXXC-30 1.00 Road Diversion Ready
2 Buldozer D85ESS BDKM-076 1.00 Road Diversion Ready
3 Compactor XCMG VBXC-007 1.00 Road Diversion Ready
4 Compactor XCMG VBXC-011 1.00 Road Diversion Ready
5 Motor Greder MGKM-007 1.00 Road Diversion Ready
6 Tower Lamp Atlas Copco TLAC-006 1.00 Road Diversion Ready

B Infrastuctur KM-18
1 Exca XE800D EXXC-51 1.00 KM-18 Ready
2 Exca 215 EXXC-005 1.00 KM-18 Ready
Breakdown, Motor Stering,
3 Buldozer Santui BDST-19 1.00 KM-18
Waiting Part at China
4 Buldozer D85ESS BDKM-077 1.00 KM-18 Ready
5 Buldozer D8R BDCT-005 1.00 KM-18 Ready
6 Dump Truck XDR 80 T DTXC-51 1.00 KM-18 Ready
7 Compactor IR VBIR-001 1.00 KM-18 Ready
8 Tower Lamp Atlas Copco TLAC-008 1.00 KM-18 Ready
9 Tower Lamp Atlas Copco TLAC-007 1.00 KM-18 Ready

C Equipment 'Mining Infra


1 Exca XE800D EXXC-50 1.00 Mining Ready
2 Exca XE800D EXXC-52 1.00 Workshop Ready
3 Exca XE800D EXXC-53 1.00 Workshop Ready
4 Exca 490 EXXC-38 1.00 Workshop Ready
5 Exca 215 EXXC-37 1.00 Workshop Ready
Breakdown, Motor Stering,
6 Compactor XCMG VBXC-006 1.00 Workshop
Waiting Part at China
Breakdown, Motor Stering,
7 Compactor XCMG VBXC-009 1.00 Workshop
Waiting Part at China
8 Dump Truck XDR 80 T DTXC-53 1.00 Workshop Ready
9 Dump Truck XDR 80 T DTXC-58 1.00 Workshop Ready
10 Dump Truck XDR 80 T DTXC-65 1.00 Workshop Ready
11 Dump Truck XDR 80 T DTXC-56 1.00 Workshop Ready
12 Dump Truck XDR 80 T DTXC-66 1.00 Workshop Ready
13 Dump Truck XDR 80 T DTXC-52 1.00 Workshop Ready
14 Dump Truck XDR 80 T DTXC-60 1.00 Workshop Ready
Breakdown, Finaldrive, Waiting
15 Dump Truck XDR 80 T DTXC-61 1.00 Workshop
Part at China
16 Dump Truck XDR 80 T DTXC-38 1.00 Mining Ready
17 Dump Truck XDR 80 T DTXC-55 1.00 Mining Ready
18 Dump Truck XDR 80 T DTXC-62 1.00 Mining Ready
19 Dump Truck XDR 80 T DTXC-63 1.00 Mining Ready
20 Dump Truck XDR 80 T DTXC-50 1.00 Mining Ready
21 Dump Truck XDR 80 T DTXC-36 1.00 Sangkulirang Ready
22 Dump Truck XDR 80 T DTXC-37 1.00 Sangkulirang Ready
27 Buldozer Santui BDST-18 1.00 CHR Ready
28 Motor Greder MGXC-016 1.00 Mining Ready
29 Motor Greder MGXC-019 1.00 Mining Ready

PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST


Perubahan cut RL 65 to RL 63.5 – KM 18
PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST
PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST
CH 1 + 475 s\d CH 2 + 400 Sudah
Dilakukan Joint Inspeksi KWN-BT-
KCB
PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST
PT KARUNIA WAHANANUSA site TABANG SAFETY FIRST
WATER MONITORING CONTROL BOX ROAD DIVERSION & PROJECT
FACILITY KM.18