LAMPIRAN BERITA ACARA NEGOSIASI BIAYA SWAKELOLA

NOMOR :
KEGIATAN PENYUSUNAN DOKUMEN MASTERPLAN DRAINASE T.A. 2020

RENCANA ANGGARAN BIAYA (RAB) HASIL NEGOSIASI


SKPD : BAPPEDA KAB. MUNA
KEGIATAN : PENYUSUNAN DOKUMEN MASTERPLAN DRAINASE
LOKASI : KAB. MUNA
SUMBER DANA : APBD 2020
THN. ANGGARAN : 2020
WAKTU PELAKSANAAN : 60 (ENAM PULUH HARI KALENDER)

A. REKAPITUASI
No. URAIAN BIAYA (Rp)

I BIAYA LANSUNG PERSONIL Rp 94,880,000

II BIAYA LANSUNG NON PERSONIL Rp 152,120,000

JUMLAH RP 247,000,000

DIBULATKAN Rp 247,000,000

Terbilang: (Dua Ratus Empat Puluh Tujuh Juta Rupiah)

B. RINCIAN ANGGARAN BIAYA

NO PROFESI/KEAHLIAN VOLUME RINCIAN BIAYA TOTAL BIAYA

I. BIAYA LANGSUNG PERSONIL


A BIAYA LAYANAN KEAHLIAN
I Tenaga Ahli
1 Kordinator Team (Ahli Sipil) 160 Jam 1.0 Org x @ 50,000 = 8,000,000
2 Tenaga Ahli Perencanaan Wilayah 160 Jam 1.0 Org x @ 40,000 = 6,400,000
3 Tenaga Ahli Sipil Pengairan 160 Jam 1.0 Org x @ 40,000 = 6,400,000
4 Tenaga Ahli Sipil Struktur 160 Jam 1.0 Org x @ 40,000 = 6,400,000
5 Tenaga Ahli Gis (S1. Geografi/Sipil Geodesi) 160 Jam 1.0 Org x @ 40,000 = 6,400,000

II Tenaga Penunjang
1 Pembantu Lapangan 1 (Drafter/Operator CAD/CADMap) 45.0 Hari 2.0 Org x @ 80,000 = 7,200,000
2 Pembantu Lapangan 2 (Drafter/Operator GIS dan Pemetaan) 30.0 Hari 2.0 Org x @ 80,000 = 4,800,000
3 Operator Computer/ pembuat laporan 1.0 Keg 3.0 Org x @ 1,520,000 = 4,560,000
4 Bendahara/Keuangan/Admistrasi 1.0 Keg 1.0 Org x @ 1,520,000 = 1,520,000
5 Pembantu Lapangan 3 (Surveyor Teknis) 30 Hari 18.0 Org x @ 80,000 = 43,200,000
Jumlah Biaya Lansung Personil 94,880,000

II. BIAYA LANGSUNG NON PERSONIL

NO URAIAN Volume RINCIAN BIAYA TOTAL BIAYA

A BIAYA OPERASIONAL
1 Biaya Transportasi Kendari - Raha/Raha - Kendari
a Ketua Tim 1.0 0rg 6.0 exp x @ 250,000 = 1,500,000
b Anggota/Tenaga Ahli 4.0 0rg 4.0 exp x @ 250,000 = 4,000,000
c Surveyor 10.0 0rg 2.0 exp x @ 250,000 = 5,000,000
2 Biaya Komunikasi + Paket Data Internet
a Ketua Tim 1.0 0rg 2.0 bulan x @ 350,000 = 700,000
b Anggota/Tenaga Ahli 4.0 0rg 2.0 bulan x @ 350,000 = 2,800,000
c Surveyor 18.0 0rg 2.0 bulan x @ 150,000 = 5,400,000
3 Akomodasi TIM
a Ketua Tim 1.0 0rg 2.0 bulan x @ 350,000 = 700,000
b Anggota 4.0 0rg 2.0 bulan x @ 350,000 = 2,800,000
c Surveyor 18.0 0rg 2.0 bulan x @ 200,000 = 7,200,000
B BAHAN HABIS PAKAI (ATK)
a Belanja ATK (Kertas A3, Kertas A4 & F4, Kertas Foto, Alat Tulis, Map, Tinta) 1.0 Paket 1,680,000 = 1,680,000
b Penggadaan/Penjilitan Laporan & Album Peta 15.0 Bh 250,000 = 3,750,000
c Dokumen Elektronik ( CD + Caver + Box ) 10.0 Bh 50,000 = 500,000
C BIAYA SEWA
1 Sewa Kendaraan Roda Empat 2.0 Bln 1.0 Unit x @ 9,500,000 = 19,000,000
2 Sewa Kendaraan Roda Dua 1.5 Bln 3.0 Unit x @ 3,500,000 = 15,750,000
3 Sewa GPS 1.5 Bln 2.0 Unit x @ 750,000 = 2,250,000
4 Sewa Printer A3 1.0 Bln 1.0 Unit x @ 600,000 = 600,000
5 Sewa Rumah/Tempat Nginap Surveyor & Peneliti 2.0 Bln 1.0 Unit x @ 1,500,000 = 3,000,000
D BIAYA RAPAT, SEMINAR
a Rapat Persiapan 1.0 Keg x @ 2,400,000 = 2,400,000
b Rapat Teknis Operasional 1.0 keg x @ 2,400,000 = 2,400,000
c Rapat Evaluasi Data 1.0 Keg x @ 2,400,000 = 2,400,000
d Rapat Penyusunan Laporan 1.0 Keg x @ 2,400,000 = 2,400,000
e Seminar & Prosentase di SKPD 1.0 Kali x @ 9,500,000 = 9,500,000
E PENGOLAHAN & PELAPORAN
a Survey/Penyelusuran data kondisi existing drainase, sungai & pesisir 20 Hari 18.0 0rg x @ 85,000 = 30,600,000
c Survey Pengembangan & Penataan sistem drainase 11 Hari 18.0 0rg x @ 85,000 = 16,830,000
d Tabulasi dan Imput Data 1.0 Paket x @ 2,000,000 = 2,000,000
e Analisis dan Finalisasi Data 1.0 Paket x @ 2,000,000 = 2,000,000
f Penyusunan Laporan 1.0 Paket x @ 1,460,000 = 1,460,000
g Penyusunan Dok. Keuangan 1.0 Paket x @ 3,500,000 = 3,500,000
Jumlah Biaya Lansung Non Personil 152,120,000

Diperiksa/Disetujui Oleh : Raha, Oktober 2020


Pejabat Pembuat Komitmen Di Siapkan Oleh :
Ketua Tim Pelaksana/Penanggung
Jawab Kegiatan

Samran, ST
NIP. 19770602 201407 1 001 La Welendo, ST.,MT.
NIP. 196812312005011007

Mengetahui :
Kepala Badan Perencanaan Pembangunan Daerah Kab.
Muna
selaku Pengguna Anggaran

Drs. La Mahi, M.Si.


NIP. 196312311993031115
LAMPIRAN BERITA ACARA NEGOSIASI BIAYA SWAKELOLA
NOMOR :
KEGIATAN PENYUSUNAN DOKUMEN MASTERPLAN DRAINASE T.A. 2020

RENCANA ANGGARAN BIAYA (RAB) HASIL NEGOSIASI


SKPD : BAPPEDA KAB. MUNA
KEGIATAN : PENYUSUNAN DOKUMEN MASTERPLAN DRAINASE
LOKASI : KAB. MUNA
SUMBER DANA : APBD 2020
THN. ANGGARAN : 2020
WAKTU PELAKSANAAN : 30 (TIGA PULUH HARI) KALENDER

A. REKAPITUASI
No. URAIAN BIAYA (Rp)

I BIAYA LANSUNG PERSONIL Rp 78,900,000

II BIAYA LANSUNG NON PERSONIL Rp 168,100,000

JUMLAH RP 247,000,000

DIBULATKAN Rp 247,000,000

Terbilang: (Dua Ratus Empat Puluh Tujuh Juta Rupiah)

B. RINCIAN ANGGARAN BIAYA

NO PROFESI/KEAHLIAN VOLUME RINCIAN BIAYA TOTAL BIAYA

I. BIAYA LANGSUNG PERSONIL


A BIAYA LAYANAN KEAHLIAN
I Tenaga Ahli
1 Kordinator Team (Ahli Sipil) 80 Jam 1.0 Org x @ 50,000 = 4,000,000
2 Tenaga Ahli Perencanaan Wilayah 80 Jam 1.0 Org x @ 40,000 = 3,200,000
3 Tenaga Ahli Sipil Pengairan 80 Jam 1.0 Org x @ 40,000 = 3,200,000
4 Tenaga Ahli Sipil Struktur 80 Jam 1.0 Org x @ 40,000 = 3,200,000
5 Tenaga Ahli Gis (S1. Geografi/Sipil Geodesi) 80 Jam 1.0 Org x @ 40,000 = 3,200,000

II Tenaga Penunjang
1 Pembantu Lapangan 1 (Drafter/Operator CAD/CADMap) 27.0 Hari 4.0 Org x @ 80,000 = 8,640,000
2 Pembantu Lapangan 2 (Drafter/Operator GIS dan Pemetaan) 27.0 Hari 3.0 Org x @ 80,000 = 6,480,000
3 Pembantu Lapangan 3 (Op. Computer pembuat laporan & lap. keuangan) 27.0 Keg 4.0 Org x @ 80,000 = 8,640,000
4 Bendahara/Keuangan/Admistrasi 1.0 Keg 1.0 Org x @ 1,540,000 = 1,540,000
5 Pembantu Lapangan 4 (Surveyor Teknis) 23 Hari 20.0 Org x @ 80,000 = 36,800,000
Jumlah Biaya Lansung Personil 78,900,000

II. BIAYA LANGSUNG NON PERSONIL

NO URAIAN Volume RINCIAN BIAYA TOTAL BIAYA

A BIAYA OPERASIONAL
1 Biaya Perjalanan/Transportasi Kendari - Raha/Raha - Kendari
a Ketua Tim 1.0 0rg 6.0 exp x @ 250,000 = 1,500,000
b Anggota/Tenaga Ahli 4.0 0rg 4.0 exp x @ 250,000 = 4,000,000
c Surveyor 12.0 0rg 2.0 exp x @ 250,000 = 6,000,000
2 Biaya Komunikasi + Paket Data Internet
a Ketua Tim 1.0 0rg 1.0 bulan x @ 350,000 = 350,000
b Anggota/Tenaga Ahli 4.0 0rg 1.0 bulan x @ 350,000 = 1,400,000
c Surveyor 20.0 0rg 1.0 bulan x @ 200,000 = 4,000,000
3 Biaya Survey, Pengambilan data, Identifikasi dan inventarisasi
a Survey/Penyelusuran data kondisi existing drainase, sungai & pesisir 23 Hari 10.0 0rg x @ 90,000 = 20,700,000
b Survey topografi zona/wilayah terpilih 20 Hari 4.0 0rg x @ 100,000 = 8,000,000
c Survey Inventarisasi & Identufikasi lokasi titik rawan banjir & genangan 3 Hari 1.0 0rg x @ 90,000 = 270,000
d Survey Pengembangan & Penataan sistem drainase 23 Hari 5.0 0rg x @ 90,000 = 10,350,000
e Pengadaan data curah hujan 5 -10 tahun terakhir 1.0 Keg x @ 3,000,000 = 3,000,000
f Pengadaan dokumen peta dasar & dokumen sekunder lainnya 1.0 Keg x @ 1,980,000 = 1,980,000
g Pemasangan Patok Beton Bench Mark (BM), Uk 10 x 10 x 100 cm 10.0 Bh x @ 750,000 = 7,500,000
B BAHAN HABIS PAKAI (ATK)
a Belanja ATK (Kertas A3, Kertas A4 & F4, Kertas Foto, Alat Tulis, Map, Tinta) 1.0 Paket 3,500,000 = 3,500,000
b Penggadaan/Penjilitan Laporan Pendahuluan & Laporan Antara 12.0 Bh 125,000 1,500,000
c Penggadaan/Penjilitan Laporan Akhir & Album Peta 15.0 Bh 250,000 = 3,750,000
d Dokumen Elektronik ( CD + Caver + Box ) 10.0 Bh 50,000 = 500,000
C BIAYA SEWA
1 Sewa Kendaraan Roda Empat 1.0 Bln 2.0 Unit x @ 9,500,000 = 19,000,000
2 Sewa Kendaraan Roda Dua 1.0 Bln 5.0 Unit x @ 3,500,000 = 17,500,000
3 Sewa GPS 1.0 Bln 4.0 Unit x @ 750,000 = 3,000,000
4 Sewa Alat Ukur (waterpass) 10.0 Hari 1.0 Unit x @ 750,000 = 7,500,000
5 Sewa Printer A3 1.0 Bln 1.0 Unit x @ 600,000 = 600,000
6 Sewa Rumah/Tempat Nginap Surveyor & Peneliti 1.0 Bln 1.0 Unit x @ 1,500,000 = 1,500,000
D BIAYA RAPAT, SEMINAR
a Rapat Persiapan 1.0 Keg x @ 2,400,000 = 2,400,000
b Rapat Teknis Operasional 1.0 keg x @ 2,400,000 = 2,400,000
c Rapat Evaluasi Data 1.0 Keg x @ 2,400,000 = 2,400,000
d Seminar Pendahuluan dan Seminar Akhir di SKPD 2.0 Kali x @ 9,500,000 = 19,000,000
E PENGOLAHAN DATA & PELAPORAN
a Tabulasi dan Imput Data 1.0 Paket x @ 3,500,000 = 3,500,000
b Analisis dan Finalisasi Data 1.0 Paket x @ 3,500,000 = 3,500,000
c Penyusunan Laporan 1.0 Paket x @ 3,500,000 = 3,500,000
d Penyusunan Dok. Keuangan 1.0 Paket x @ 4,000,000 = 4,000,000
Jumlah Biaya Lansung Non Personil 168,100,000

Diperiksa/Disetujui Oleh : Raha, 19 Nopember 2020


Pejabat Pembuat Komitmen Di Siapkan Oleh :
Ketua Tim Pelaksana/Penanggung
Jawab Kegiatan

Samran, ST
NIP. 19770602 201407 1 001 La Welendo, ST.,MT.
NIP. 196812312005011007

Mengetahui :
Kepala Badan Perencanaan Pembangunan Daerah Kab.
Muna
selaku Pengguna Anggaran

Drs. La Mahi, M.Si.


NIP. 196312311993031115