You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/233624381

A case study on the post-construction deformation of concrete face rockfill


dams

Article  in  Canadian Geotechnical Journal · June 2008


DOI: 10.1139/T08-020

CITATIONS READS
35 2,517

2 authors, including:

Myoung-Soo Won
Kunsan National University
43 PUBLICATIONS   462 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Numerical and field test verifications for the deformation behavior of geotextile tubes considering 1D and areal strain View project

Derivation of design charts based on the two-dimensional structural analysis of geotextile tubes View project

All content following this page was uploaded by Myoung-Soo Won on 21 May 2014.

The user has requested enhancement of the downloaded file.


845

A case study on the post-construction


deformation of concrete face rockfill dams
Myoung-Soo Won and You-Seong Kim

Abstract: Concrete face rockfill dams (CFRDs) are considered to be fundamentally safe, especially against leakage, and
to be a low-cost alternative at many sites. Their design is based on empirical experiences rather than theory. The present
paper describes post-construction deformation and leakage using 27 CFRD case studies. The analysis shows that deforma-
tion normal to the face slab is larger than the post-construction crest settlement when the dam height exceeds 100 m and
that the long-term leakage rate increases rapidly when the dam height exceeds 125 m.
Key words: CFRD, dam, rockfill, crest settlement, concrete face slab, leakage.
Résumé : On considère que les barrages en enrochements avec face amont en béton (« CFRD ») possède une sécurité fon-
damentale, particulièrement contre les fuites et ont été une alternative à bon marché pour plusieurs sites, de plus leur
conception est basée sur des expériences empiriques plutôt que sur la théorie. Le présent article décrit la déformation après
construction, et les fuites au moyen de 27 études de cas de CFRD. L’analyse montre que la déformation normale à la face
de la dalle est plus grande que le tassement de la crête après construction lorsque la hauteur du barrage dépasse 100 m, et
le taux de fuites à long terme augmente rapidement lorsque la hauteur du barrage excède 125 m.
Mots-clés : CFRD, barrage, enrochement, tassement de la crête, dalle de la face en béton, fuites.
[Traduit par la Rédaction]

Introduction Cooke 1987). Fitzpatrick et al. (1985) developed two mod-


uli based on the observed deformation behavior of rockfill
during construction and on first filling, for the assessment
A rockfill dam rendered waterproof by concrete slabs on of the deformation behavior of rockfill. Hunter and Fell
the upstream slope surface instead of by a central earth (2003), using a database of case studies that included
core is called a concrete face rockfill dam (CFRD). Con- 35 CFRDs, gathered good quality monitoring records and
crete face rockfill dams have become increasingly popular construction material data to estimate the modulus of com-
in many parts of the world during recent decades (Sherard pacted rockfill in dams — based on the particle size, the
and Cooke 1987, Khalid et al. 1990, Uddin and Gazetas unconfined compressive strength of the rock, the compac-
1995, Xing et al. 2006) due to their advantages (such as tion effect, the valley shape effect, and the applied vertical
cost-effectiveness and great suitability at many sites) over stress — to predict the internal vertical displacement in
central earth core dams. However, the design of the CFRD close proximity to the embankment centerline during con-
is still largely empirical and is based on past experiences struction and the face slab deformation on first filling.
rather than theory. Cooke (1984) has described how CFRD Clements (1984), Sherard and Cooke (1987), Hunter and
design has evolved through a process that is more evolu- Fell (2003), and Hunter (2003) have suggested empirical
tionary than revolutionary, wherein engineering progress predictive methods for the post-construction deformation
came about principally as a consequence of cautious trial based on the historical deformation curves for similar em-
and error. Current design trends and the construction and bankment types. Hunter (2003) presented a guideline to
performance records of many recent dams can be found in predict embankment deformation behavior during construc-
the proceedings of a 1985 American Society of Civil Engi- tion, first filling, and post-construction using a database of
neers (ASCE) symposium (Cooke and Sherard 1985) and in 36 CFRDs. There are a few studies that use the case data
an accompanying issue of the ASCE Journal of Geotechni- from many CFRDs to compare the long-term post-
cal Engineering (Cooke and Sherard 1987, Sherard and construction crest settlement with the crest settlement on
first filling of the reservoir; the long-term deformation with
Received 21 February 2007. Accepted 10 January 2008. first filling deformation normal to the face slab; the crest
Published on the NRC Research Press Web site at cgj.nrc.ca on settlement with the deformation normal to the face slab;
18 June 2008.
and the relationship of leakage and dam height (Sherard
M.-S. Won.1 Department of Civil Engineering, Kunsan National and Cooke 1987, Hunter 2003). To understand the general
University, San 68, Miryong-dong, Kunsan, Jeollabuk-do, 573- post-construction deformation behavior of CFRDs, the
701, Republic of Korea. present study analyzes and describes the crest settlement
Y.-S. Kim. Department of Civil Engineering, Chonbuk National and deformation normal to the face slab, the strain in the
University, 664-14 Deokjin-dong 1Ga, Deokjin-ku, Jeonju, face slab, and the leakage on first filling and during long-
Jeollabuk-do, 561-756, Republic of Korea.
term post-construction using the database produced by
1Corresponding author (e-mail: wondain@kunsan.ac.kr). Hunter (2003) and other references.

Can. Geotech. J. 45: 845–852 (2008) doi:10.1139/T08-020 # 2008 NRC Canada


846 Can. Geotech. J. Vol. 45, 2008

Table 1. Case studies information on concrete face rockfill dams (data from Hunter 2003).

Year Height, Length, Foundation (soil/


No. Name Location Completed H (m) L (m) rock) Rockfill source Particle shape
1 Aguamilpa Mexico 1993 185.5 475 Rock-gravels in Dredged alluvium Rounded
part of river
section
2 Alto Anchicaya Columbia 1974 140 260 Gravels in river Hornfels A
section
3 Bastyan Australia 1983 75 430 Rock Rhyolite (SW to FR) A
4 Cethana Australia 1971 110 213 Rock Quartzite, quarried A
5 Cheongsong(Lower) Korea 2004 62 300 Rock Granite A
6 Cheongsong(Upper) Korea 2004 90 400 Rock Green sandstone A
7 Crtotty Australia 1991 83 240 Rock Gravels Rounded
8 Foz Do Areia Brazil 1979 160 828 Rock Mix basalt, basaltic breccia A
9 Golillas Columbia 1978 125 107 Rock Gravels, unprocessed Rounded
10 Ita Brazil 1999 125 880 Rock Breccia and basalt A
11 Kangaroo Creek Australia 1969 60 178 Rock, some Schist A to subangular
gravels
12 Kotmale Sri Lanka 1984 90 560 Rock Charnockitic/gneissic A
13 Little Para Australia 1977 53 225 Rock Dolomitic siltstone A, elongated?
14 Mackintosh Australia 1981 75 465 Weathered rock Greywacke, some slate A, elongated
15 Mangrove Creek Australia 1981 80 380 Rock Siltstone, sandstone A to subangular?
16 Miryang Korea 2001 89 535 Rock Andesite —
17 Murchison Australia 1982 94 200 Rock Rhyolite (SW to FR) A
18 Namgang Korea 1999 34 1126 Rock, some Gneiss —
gravels
19 Reece Australia 1986 122 374 Gravels in river Dolerite A
section
20 Salvajina Columbia 1984 148 362 Rock and soil, Natural gravels (zone 3A), Rounded(3A)
gravels in river weak sandstone and silt- A?(3B)
section stone (3B)
21 Segredo Brazil 1972 145 720 Rock Basalt (<5% basaltic breccia) A
22 Shiroro Nigeria 1983 125 560 Rock Granite A
23 Tianshengqiao-1 China 1999 178 1168 Rock Limestone and mudstone A
24 Tullabardine Australia 1979 25 214 Rock Greywacke, some slate A, elongated
25 White Spur Australia 1989 43 146 Rock Quarried tuff – SW to FR A
26 Winneke Australia 1978 85 1050 Rock SW to FR siltstone, quarried A
27 Xingo Brazil 1993 140 850 Rock, gravels in Granite gneiss A
lower river bed
Note: A, angular; M, medium; VH, very high; TS, total settlement; SFF, settlement on first filling; TD, total deformation; DFF, deformation on first
240 MPa; high, 20–70 MPa; medium, 6–20 MPa. ?, not sure.

Concrete face rockfill dam (CFRD) zoning Fig. 1. Zone designations for concrete face rockfill dam (CFRD) of
sound rockfill (Cooke and Sherard 1987).
Figure 1 shows the typical zoning of a CFRD (Cooke and
Sherard 1987). As shown in Fig. 1, there are three main
CFRD zones: (i) the concrete face slab (zone 1), which is
impervious; (ii) zone 2 for the filter or transition zone di-
rectly under the concrete slab; and (iii) the main rockfill
(zone 3). Compacted impervious soil (zone 1) is necessary
for defence, to seal cracks or joint openings.
The areas closer to the upstream than the downstream on
each layer contain smaller average-sized rock and more
quarry fines rockfill. The maximum rock sizes at zone 3C
and zone 2 are approximately less than 1500 and 150 mm,
respectively.

Post-construction crest settlement


Clements (1984) reviewed whether or not empirical equa-
tions could accurately assess the post-construction crest set-
tlement and deflections of 68 rockill dams. He found that
# 2008 NRC Canada
Won and Kim 847

Post-construction
Deformation normal to
Crest settlement face slab Leakage (L/s)
Intact rock strength Period surveyed TS TS SFF SFF SFF/ TD DFF DFF/TD
classification (year) (mm) (%) (mm) (%) TS (%) (mm) (mm) (%) Max. rate Long-term
VH 0.4–~5.7 307 0.185 222 0.133 72 320 — — FF 200 160

VH 0.11–10.3 153 0.109 15 0.011 10 160 130 81 FF 1800 —

VH 0.2–7.5 50 0.066 15 0.020 30 68 — — FF 10 5


VH 0–28.6 137 0.124 46 0.043 34 170 — — 70 7.5
High to VH 0~3.2 67 0.112 — — — — — — FF 43 1.5
VH 0~3.3 117 0.130 — — — — — — FF 43 10
VH 0–8.5 55 0.066 16 0.019 29 46 — — 45 32.5
High to VH 0–11 328 0.205 73 0.046 22 780 620 79 FF 240 70
VH 0.46–6.4 52 0.042 20 0.016 38 160 — — FF 1080 385
High(?) to VH 0–4 — — 461 0.369 — — — — FF 1732 200
M to high 0–26 116 0.193 26 0.043 22 — — — 11 2.5

High to VH 0–2.46 255 0.283 96 0.107 38 98 — — <10 —


M 0–22.6 152 0.288 22 0.042 14 — — — 19.2 —
M to high 0–20.6 333 0.444 99 0.132 30 228 173 76 FF 21 9
High 0.67–15 287 0.359 — — — — — — FF 5.6 2.5
— 3 — — — — — — — — 77 9
VH 0.08–17.6 104 0.111 9 0.010 9 77 28 36 FF 3.5 2
— 5 — — — — — — — — 51 4

VH 0.12–15 221 0.181 85 0.070 38 264 215 81 FF 12 1

VH (zone 3A) M? 0.33–0.75 90 0.061 — — — 55 — — 74 —


(zone 3B)

High to VH 0.4–2.5 229 0.158 200 0.138 87 340 — — FF 390 45


VH 0–1.8 166 0.133 — — — 90 — — FF 1800 100
M to VH 0.05–5 >926 >0.52 >926 >0.52 — — 1 380 — FF 200 70
High 0–12.8 19 0.076 2 0.010 11 — — — 2 0.75
VH 0.04–5.9 58 0.135 7 0.016 12 38 15 39 FF 7 2
High 0.17–16.2 270 0.244 105 0.124 39 160 145 91 FF 58 13
M to VH(?) 1.0–6.2 526 0.376 302 0.216 57 510 290 57 200 140

filling; FF, first filling. Classification of unconfined compressive strength of intact rock used in rockfills. Extremely high, > 240 MPa; very high, 70–

they may be prone to large errors because of the existing ment height, etc. According to Hunter (2003), significantly
empirical equations based on simple empirical relationships greater crest settlements are evident for the dumped rockfills
of the displacement with height or time. He proposed an al- compared with compacted rockfills; for embankments con-
ternative approach, using only the deformation curves of ex- structed of medium to high intact strength rockfill, the total
isting dams with similar characteristics to the dam under magnitude of settlement at 10 years is, on average, approxi-
construction instead of empirical equations. Sherard and mately twice that of very high strength rockfills. The long-
Cooke (1987) compared the post-construction crest settle- term rate of crest settlement (on a log scale) for medium to
ment from CFRDs composed of dumped and compacted high strength rockfills is proportional to the increasing em-
rockfill and observed that the crest settlement of dumped bankment height, but the effect of the embankment height
rockfill is 5–8 times greater than for compacted rockfill in is probably not as significant for the compacted very high
3–30 years. Sherard and Cooke (1987) expected that the strength rockfill cases.
crest settlement for a modern compacted CFRD with a Table 1 is mainly taken from the database for compacted
height of 100 m will generally be about 10–15 cm in 5 years, CFRDs in Hunter (2003). Figures 2 and 3, respectively,
and 15–25 cm in 100 years. This coincides with the range of show the total post-construction crest settlement after at
crest settlement of compacted CFRDs (0%–0.25% of dam least 10 years and on first filling, and the ratio of the crest
height) proposed by Clements (1984). Hunter (2003) re- settlement on first filling to the long-term settlement. The
ported that the post-construction crest settlement is signifi- serial numbers in Figs. 2 and 3 indicate the number of the
cantly affected by the method of placement (dumped versus dam shown in Table 1. Medium (M), High, and very high
compacted), the intact strength of the rockfill, the embank- (VH) indicate the intact rock strength used in the rockfill.
# 2008 NRC Canada
848 Can. Geotech. J. Vol. 45, 2008

Fig. 2. Post-construction crest settlements on first filling and after Fig. 3. Crest settlement on first filling to total crest settlement ra-
at least 10 years. tio. FF, first filling; M, medium; VH, very high.

The ranges of the strength and definition of M, High, and voir filling (Pinto et al. 1985). The crest settlement (max)
VH are given in Table 1. The ratio of total long-term crest and slab deflection (max) in Fig. 7 are the crest settlement
settlement to embankment height is usually lower than 0.3% and slab deformation normal to the face slab at the point of
of the dam height in Fig. 2. However, the magnitude of maximum deformation. The response of the rockfill to the
long-term post-crest settlement for embankments constructed water load is rather fast, and the evolution of the deforma-
of very high strength rockfill in Fig. 2 appeared to be tions with time is somewhat obscured by the history of the
0.1%~0.2% of dam height, and embankments constructed of impounding, as shown in Fig. 7 (Pinto et al. 1985).
medium to high intact rockfill were 0.1%~0.45% of dam Figure 8 shows the dam heights versus the total long-term
height. According to Clements (1984) and Sherard and post-construction crest settlements and the total long-term
Cooke (1987), the range of post-construction crest settle- deformations normal to the face slab. The post-crest settle-
ment of compacted CFRDs is 0%~0.25% of dam height. ment and the deformation normal to the face slab are gener-
Therefore, the range of post-construction crest settlement ally similar to each other, and they are smaller than 0.5% of
suggested by Sherard and Cooke (1987) and Clements the dam height. One of the interesting phenomena is that the
(1984) shows a good agreement in the case analyses using crest settlement is larger than the deformation normal to the
rockfill with very high intact strength, but it has a trend that face slab when the dam height is less than 100 m, and the
underestimated crest settlement in the cases using rockfill deformation normal to the face slab is larger than the crest
with medium to high intact strength. Figure 3 shows that ap- settlement when the dam height is greater than 100 m. This
proximately 10%–40% of the total long-term crest settle- phenomenon may be caused by the side slope (about
ment occurred during the first filling. Figure 4 presents a 1.4H:1V), that is, the length of the concrete face slab is in-
typical example of the effect of the first filling (Hunter and creasing with the dam height in the proportion of 1.72 to 1.
Fell 2003). Figures 2–4 show the water load on first filling,
which has a significant effect on the crest settlement.
Strain in the face slab
Deformation normal to face slab Figures 9 and 10, respectively, show the dam face strain
contours at the end of construction and the changes due to
Figures 5 and 6 show the deformation normal to the face the water load at Salvajina Dam. Normal tension zones de-
slab on CFRDs at least 10 years after construction and on veloped in the downslope and horizontal direction on the
first filling (data from Table 1). Like the post-construction upper part of the face slab and close to the abutment at the
crest settlement, the total magnitude of the deformation nor- end of construction (Hacelas et al. 1987). The maximum
mal to the face slab is a little greater at embankments con- compressive strain is in the downslope direction, and is
structed of medium to high intact strength rockfill than that equal to 400 mm, which mobilizes only 42% of the concrete
of very high strength rockfill, and is probably not in propor- compressive strength (Hacelas et al. 1987). The change in
tion to the dam heights. Approximately 80% of the total the dam face strains due to the water load is shown in
long-term deformation normal to the face slab occurred dur- Fig. 10. The strain in the face slab is significantly affected
ing the first filling as shown in Fig. 6. This means that most by the water load, and tension zones caused by the water
deformation occurs during the first filling, and it is signifi- load are developed near the toe, the crest, and the abut-
cantly affected by the water load rather than the crest settle- ments.
ment. It may cause cracks in the concrete face slab, as most Table 2 shows the measured maximum slab strains due to
deformation normal to the face slab occurs during the first the water load (Fitzpatrick et al. 1985). The strains in Ta-
filling. ble 2 show a similar pattern to one another. The maximum
Figure 7 shows the embankment deformations after reser- compressive strains (100–380 mm) are near the center of the
# 2008 NRC Canada
Won and Kim 849

Fig. 4. Post-construction crest settlement of Bastyan Dam (Hunter and Fell 2003).

Fig. 5. Deformations normal to face slab on first filling and after at Fig. 6. Ratio of deformation normal to face slab on first filling to
least 10 years. long-term deformation.

face slab and the maximum tensile strains (25–140 mm) ap- lost water, and may have an impact on the function of the
pear near the toe. Tensile strains in the face slab on reser- reservoir or dam. As shown in Table 1, the maximum leak-
voir filling are indicated near the toe and near the age at a CFRD generally occurs on the first filling because
abutments. According to Fitzpatrick (1986), the failure range of large deformations at the joints or cracks in the face slab
for concrete is between 1000 mm for rapid loading and due to the water load. According to Sherard and Cooke
3000 mm for gradual loading, and the maximum compres- (1987), for most reservoirs on rivers of any significant size,
sive strain in Cethana after 10 years is 400 mm. Therefore, a leakage of a few tens of litres per second has negligible
it is known that strains that occur in the face slab are safe. economic value. Figure 11 shows the relationship of long-
term leakage versus dam heights. As shown in Table 1, the
Leakage time period of the long-term leakage rate is generally given
Sherard and Cooke (1987) showed that leakage emerging in years after the end of first filling.
downstream of a CFRD has a fundamentally different signif- The long-term leakage rate in cases of dam heights less
icance from leaks through dams with earth cores because than 122 m is reasonable at less than 10 L/s, except for the
there is no possibility of earth core erosion and no potential Crotty and Winneke Dams, but the in the cases of dam
threat to the dam safety. Not only Sherard and Cooke heights higher than 125 m the leakage rate rapidly increases
(1987), but also many others (Amaya and Marulanda 1985, between 45 and 200 L/s. Typical CFRDs, which are higher
Arrau et al. 1985, Leps et al. 1985, Millet et al. 1985, than 125 m, such as Alto Anchicaya at 140 m (Materon
Hunter 2003, Freitas 2005, Freitas and Cruz 2007, Keming 1985); Foz Do Areia at 160 m (Pinto et al. 1985); Golillas
et al. 2007), have reported that leakage at a CFRD mainly at 125 m (Amaya and Marulanda 1985); New Exchequerat
emerges through perimeter joints, cracks in the concrete 145 m (Leps et al. 1985); and Shiroroat 125 m (Bodtman
face slab, and joints on abutments, but that this leakage has and Wyatt 1985) have all experienced some leakage prob-
posed no threat to the safety and stability of the dam. How- lems, and in general have needed to repair face slab joints
ever, significant leakage has an economic impact in terms of during the first filling. In Barra Grande (185 m) and Campos
# 2008 NRC Canada
850 Can. Geotech. J. Vol. 45, 2008

Fig. 7. Foz Do Areia Dam deformation after reservoir filling (Pinto et al. 1985).

Fig. 8. Total post-construction crest settlement and total deforma- Fig. 9. Salvajina Dam: concrete face strains at the end of construc-
tion normal to face slab. tion (Hacelas et al. 1987).

Novos (202 m), both recently built in Brazil in 2005, maxi-


mum leakages were recorded 1284 and 1300 L/s, respec-
tively, during first reservoir impounding as a result of the
cracks and slab rupture phenomenon (Freitas and Cruz
2007). After repair work such as drilling and grouting, and mal to the face slab are significantly affected by the first
dumping silt sandy material over joint areas, the leakage filling of the water load. Most deformation normal to
range in both Barra Grande and Campos Novos was 600 to face slab occurred during the first filling.
1000 L/s depending on reservoir water level (Freitas and (2) The range of post-construction crest settlement suggested
Cruz 2007). From these experiences, it can be concluded by Sherard and Cooke (1987) and Clements (1984) had
that CFRDs higher than 125 m may have some problem good agreement in the cases using rockfill with very
with leakage during, as well as after, the first filling. Per- high intact strength, but it had a trend that underesti-
haps, this phenomenon is caused by face slab deformations mated crest settlement in the cases using rockfill with
resulting from the water load. medium to high intact strength.
(3) The magnitude of the long-term post-construction crest
Conclusions settlement is similar to the deformation normal to the
face slab. There is a trend showing that the crest settle-
The present paper has carried out case studies on aspects ment is larger than the deformation normal to the face
of compacted CFRDs, such as post-construction deforma- slab when the dam height is less than 100 m, whereas it
tions and leakage, and has reached the following conclu- is smaller when the dam heights exceed 100 m.
sions.
(4) The maximum compressive strains and the maximum
(1) Post-construction crest settlement and deformation nor- tensile strains in the slab caused by the water load on
# 2008 NRC Canada
Won and Kim 851

Fig. 10. Salvajina Dam: concrete face strains due to water load it rapidly increases to 45–200 L/s when the dam height
(Hacelas et al. 1987). exceeds 125 m.

References
Amaya, F., and Marulanda, A. 1985. Golillas dam: design, con-
struction and performance. In Proceedings of the 2nd Sympo-
sium on Concrete Face Rockfill Dams: Design, Construction
and Performance. Detroit, Mich., October 1985. Edited by J.B.
Cooke and J.L. Sherard. American Society of Civil Engineers
(ASCE), New York, pp. 98–120.
Arrau, L., Ibarra, I., and Noguera, G. 1985. Performance of CO-
GOTI dam under seismic loading. In Proceedings of the 2nd
Symposium on Concrete Face Rockfill Dams: Design, Construc-
tion and Performance. Detroit, Mich., October 1985. Edited by
J.B. Cooke and J.L. Sherard. American Society of Civil Engi-
neers (ASCE), New York, pp. 1–14.
Bodtman, W.L., and Wyatt, J.D. 1985. Design and performance of
Shiroro rockfill dam. In Proceedings of the 2nd Symposium on
Concrete Face Rockfill Dams: Design, Construction and Perfor-
mance. Detroit, Mich., October 1985. Edited by J.B. Cooke and
J.L. Sherard. American Society of Civil Engineers (ASCE), New
York, pp. 231–251.
Clements, R.P. 1984. Post-construction deformation of rockfill
dams. Journal of Geotechnical Engineering, 110: 821–840.
Cooke, J.B. 1984. Progress in rockfill dams. Journal of Geotechni-
Table 2. Maximum face strains due to water load (modified from cal Engineering, 110: 1383–1414.
Fitzpatrick et al. 1985). Cooke, J.B., and Sherard, J.L. 1985. In Proceedings of the 2nd
Symposium on Concrete Face Rockfill Dams: Design, Construc-
Concrete strain (mm) tion, and Performance. Detroit, Mich., October 1985. American
Down slope direction Horizontal direction Society of Civil Engineers (ASCE), New York. pp. 1–658.
Cooke, J.B., and Sherard, J.L. 1987. Concrete face rockfill dam: II
Dam Tensile Compressive Tensile Compressive
Design. Journal of Geotechnical Engineering, 113: 1113–1133.
Cethana 251 3003 — 3803 Fitzpatrick, M.D. 1986. Discussion of progress in rockfill dams.
Mackintosh 1001 3003 106 3003 Journal of Geotechnical Engineering, 112: 221–223.
Murchison 1401 1003 356 703 Fitzpatrick, M.D., Cole, B.A., Kinstler, F.L., and Knoop, B.P.
Note: Typical view of upstream face. Subscripts 1, 3, 6 represent the 1985. Design of concrete-faced rockfill dams. In Proceedings of
approximate location of observation. the Symposium on Concrete Face Rockfill Dams: Design, Con-
struction and Performance. Detroit, Mich., October 1985. Edited
Fig. 11. Long-term leakage versus dam heights. by J.B. Cooke and J.L. Sherard. American Society of Civil En-
gineers (ASCE), New York, pp. 410–434.
Freitas, M.S., Jr. 2005. Deformations and cracking in concrete face
rockfill dams. In Proceedings of the Symposium on 20 years for
Chinese CFRD Construction. Yichang, China, September 2005.
pp. 169–176.
Freitas, M.S., Jr., and Cruz, P.T. 2007. Unpredicted cracks and rup-
tures at face slab in CFRDs – reparing works and treatment. In
Proceedings of the Workshop on High Dam Know-how, Yi-
chang, China, pp. 75–90.
Hacelas, J.E., Ramirez, C.A., and Regalado, G. 1987. Discussion of
design of concrete-faced rockfill dams. Journal of Geotechnical
Engineering, 113: 1182–1187.
Hunter, G.J. 2003. The pre- and post-failure deformation behavior
of soil slopes. Ph.D. thesis, University of New South Wales,
Sydney, Australia.
Hunter, G., and Fell, R. 2003. Rockfill modulus and settlement of
concrete face rockfill dams. Journal of Geotechnical and Geoen-
vironmental Engineering, 129(10): 909–917. doi:10.1061/
(ASCE)1090-0241(2003)129:10(909).
Keming, C., Zhongping, and Caichangguang, 2007. Design re-
first filling are found near the center and toe of the con- search for very high CFRD. In Proceedings of the Workshop on
crete face slab, respectively. High Dam Know-how, Yichang, China, pp. 18–35.
(5) The long-term leakage rate at a CFRD is generally less Khalid, S., Singh, B., Nayak, G.C., and Jain, O.P. 1990. Nonlinear
than 10 L/s when the dam height is less than 122 m, but analysis of concrete face rockfill dam. Journal of Geotechnical

# 2008 NRC Canada


852 Can. Geotech. J. Vol. 45, 2008

Engineering, 116(5): 822–837. doi:10.1061/(ASCE)0733- Pinto, N.L.D.S., Marques Filho, P.L., and Maurer, E. 1985. Foz do
9410(1990)116:5(822). Areia dam-design, construction, and behavior. In Proceedings of
Leps, T.M., Cashatt, C.A., and Janopaul, R.N. 1985. New Exche- the Symposium on Concrete Face Rockfill Dams: Design, Con-
quer Dam, California. In Proceedings of the 2nd Symposium on struction and Performance. Detroit, Mich., October 1985. Amer-
Concrete Face Rockfill Dams: Design, Construction and Perfor- ican Society of Civil Engineers (ASCE), New York, pp. 173–
mance. Detroit, Mich., October 1985. American Society of Civil 191.
Engineers (ASCE), New York, pp. 15–26. Sherard, J.L., and Cooke, J.B. 1987. Concrete-face rockfill dam: I.
Materon, B. 1985. Alto Anchicaya dam: ten years performance. In Assessment. Journal of Geotechnical Engineering, 113: 1096–
Proceedings of the 2nd Symposium on Concrete Face Rockfill 1112.
Dams: Design, Construction and Performance. Detroit, Mich., Uddin, N., and Gazetas, G. 1995. Dynamic response of concrete-
October 1985. American Society of Civil Engineers (ASCE), faced rockfill dams to strong seismic excitation. Journal of Geo-
New York, pp. 73–87. technical Engineering, 121(2): 185–197. doi:10.1061/(ASCE)
Millet, J.C., Louis, F., and Robert, F. 1985. Design, construction & 0733-9410(1995)121:2(185).
performance of Fades Dam. In Proceedings of the 2nd Sympo- Xing, H.-F., Gong, X.-Y., Zhou, X.-G., and Fu, H.-F. 2006. Con-
sium on Concrete Face Rockfill Dams: Design, Construction struction of concrete-faced rockfill dams with weak rocks. Jour-
and Performance. Detroit, Mich., October 1985. American So- nal of Geotechnical and Geoenvironmental Engineering, 132(6):
ciety of Civil Engineers (ASCE), New York, pp. 27–39. 778–785. doi:10.1061/(ASCE)1090-0241(2006)132:6(778).

# 2008 NRC Canada

View publication stats

You might also like