You are on page 1of 2

2. Refer to the diagram below for the installation location which is exposed to strong wind.

nd. (C) If there are obstacles on both the intake and discharge For indoor unit refrigerant piping installation, refer to the installation instruction
5. REFRIGERANT INSTALLATION manual that comes with that indoor unit.
If a strong wind of more than 5 m/sec blows to the area directly in front of the discharge, the outdoor unit’s air flow is reduced Pattern 1 If there is an obstacle that is higher than the unit on the intake side. (There is no limit to the height of the obstacle
F614942 Do not reuse existing piping, install new piping.
and the outflow may re-enter (short circuit) causing the following outcome: above the discharge.)
ENGLISH

1. Precautions during refrigerant installation.


“Reduced capacity”, “Increased frost formation during heating” or “Operation stopped due to increased pressure”. If the upper part is open 1 For separate installation location 2 For multiple units (more than 2 units)
INSTALLATION INSTRUCTIONS Should an exceptionally strong wind blow to the area directly in front of the discharge of the outdoor unit; there is the risk of
Use clean pipes with no dust inside.
The pipe may corrode with the presence of fluorine dust which will adversely affect the refrigerant piping system due to
damage due to the fan’s high-speed reverse rotation.
OUTDOOR UNIT If the direction of the prevailing wind is known when operating the unit, place the unit at an appropriate angle to the wind’s
n an
deterioration of the refrigerant oil, etc.
This unit is specifically for R410A. Ensure to adhere to the following items and install accordingly:
direction so that the discharge faces towards a building or a wall. th
a th
e • Use pipe cutters and flaring tools which are specially designed
e
or 0 or 200
HP MODEL NAME Air Intake M 10 M for use with R410A. Front panel
REFRIGERANT 2.5 HP U-60P
Wall / Standing outer wall
• When connecting with flaring tools, coat the flare section with
R410A 3 HP
4 HP
U-71P
U-100P an
th
a n
ether-based oil.
• Ensure to use flare nuts supplied with the unit when connecting
Strong wind th e
5 HP U-125P e or 500 this unit.
or 00
6 HP U-140P If there are obstacles above the unit M 3 M
• Only for storing or for open pipes.
1 For separate installation location

More than
500 • Set the lower limit of the allowable pipe length to 7.5m.
Intake side than
Less

1000
Refer to the indoor unit installation instruction manual for the indoor unit installation. • The dimensions for H, A and L are shown in the following If the pipe is shorter than 7.5m, the refrigerant may become Rear
direction
Strong wind table. overfilled and a problem such as abnormal high pressure could
Note: Ensure to hand over this installation instruction manual to the person performing the installation and inform
the customer to keep it properly stored. L A occur.
0 < L 1/2 H 300 Rear piping
Selecting the location for installation and service. L H an 2. The local pipes can protrude from any four directions.
panel
1/2H < L H 500 th
This product uses refrigerant series R410A with the design pressure of 3.8 MPa. e
3. If installing at locations prone to snowfall, install the unit as high as possible with suitable roofing which shelters the unit from or 200 Make holes in the pipe panel for the pipes to penetrate it and lay Front Sideways
H<L Install a pedestal or mount so that L H M
Refer to the caution items listed in “5. Refrigerant installation” for the installation of the refrigerant piping and maintain strict the pipes accordingly. direction direction
control concerning the prevention of mixing impurities (water and mineral oils such as Suniso oils) with R410A. snow.
• Cover the bottom part of the pedestal or mount so that • It is recommended to apply additional substance to the cut area Downward Front piping
4. Avoid installing the unit in locations where there are petroleum products (such as machine oil), saline content (such as coastal Mounting screws for direction
The indoor unit to be connected must be R410A compatible and be sure to check the catalogue, etc. for available models. air does not go through it. panel
areas), sulphurous gas and where high frequency noise is generated. for anti-rust protection. the front panel
The product may not operation properly if connected to other indoor units. 00
5. Place the indoor and outdoor unit, power cords and indoor/outdoor unit connection cables at a minimum distance of 1 meter or n5 Ensure to install pipe panels to prevent rain water from getting into
2 For multiple units (up to 2 units) s tha
more away from televisions and radios. This is to avoid interference to picture and/or sound. Les the unit.

More than
• The dimensions for H, A and L are shown in the following Putty or heat
Close the gap at the pipe connected area with putty or heat

1000
Precautions in terms of safety (However, depending on the electromagnetic waves, noise interference may still occur even with the 1 meter separation.) table. insulator (locally
6. For restaurants and kitchens, avoid installing at locations which draws oil and steam. insulator (locally supplied). supplied)
L A • If an insect or small animal enters the outdoor unit, there is the
Carry out installation work with reliability after thorough reading of this “Precaution in terms of safety”. Plastic parts can deteriorate from droplets of oil and steam or it can cause falling parts or water leakage.
0 < L 1/2 H 500 risk of shorting in the product electronic casing.
7. Avoid installing at the location where cutting oil mist or iron powder is present. L H
Precautions shown here are differentiated between Warnings and Cautions . Those that have much chances for leading 1/2H < L H 750 an [Remove the front panel] Piping
8. If there is an immense voltage fluctuation due to the location’s problem, ensure to split the power supply. th
e
to significant result such as fatality or serious injury if wrong installation would have been carried out are listed compiling them
9. When installing the product in a place where it will be affected by typhoon or strong wind such as wind blowing between buildings, H<L Install a pedestal or mount so that L H or 200 (1) Remove the 2 mounting screws.
M
especially into the column of Warnings . including the rooftop of a building and a place where there is no building in surroundings, fix the product with an overturn • Cover the bottom part of the pedestal or mount so that (2) Slide the front panel using your hands downwards to release Prevention measures to avoid small
However, even in the case of items which are listed in the column of Cautions , such items also have a chance for leading prevention wire, etc. air does not bypass it. the pawls. animals from entering
to significant result depending on the situations. • A limit of only 2 units can be installed. Then remove by pulling the panel towards you.
In either case, important descriptions regarding the safety are listed, then observe them without fail.
As to indications with illustration Precautions when operating the 3-way valve for piping installation
This mark means “Caution” or “Warning”. This mark means “Earth”. Pattern 2 If there is an obstacle that is higher than the unit on the discharge side. (There is no limit to the height of the
obstacle above the discharge.) Do not open the 3-way valve until the piping installation is completed.
After installation work has been completed, do not only make sure that the unit is free from any abnormal condition through the • It is closed during shipment.
If the upper part is open
execution of try run but also explain how to use and how to perform maintenance of this unit to the customer according to the • During installation the side panel may warp if only the flare nut is loosened and tightened with a torque wrench. As a
1 For separate installation location 2 For multiple units (more than 2 units)
instruction manual. result, always be sure to secure to the hexagonal part of the 3-way valve with a spanner, or other tool.
In addition, request the customer to keep this manual for installation work together with instruction manual. Refer to the following table for the tightening torque of the 3-way valve flare nuts.
• If the nuts are over tightened, they may cause the flares to break or leak.
Warnings Warnings 10. Ensure to assign several people or use a mechanical lift, etc. to transport the unit. Do not add additional force to the valve’s cover.

0
e
or 0

20
The appliance must be installed by technician, who takes into Must not use other parts except original optional parts described in M n 10 • Using spanners on the cover or valve itself (other than the hexagonal parts) may cause gas leakage.

na
account the requirements given by ISO 5149 or eventual equivalent catalog and manual. a

th
t h Avoid using spanners on the cover or parts other than the hexagonal part of the valve.

e
requirements.

or
Once installation work is completed, check that there are no

M
refrigerant gas in the room that can come into contact with sparks 3. SELECTING THE LOCATION When installing multiple units, allow enough space in between the units and the e
or 0
As to installation, request the distributor or vendor to perform it. M n 30 Valve shaft
Imperfection in installation caused by that having been carried or flames from a fan heater, stove or kitchen range, which will cause FOR INSTALLATION SERVICE side of the building.
(unit: mm) t h a Service port
out by the customer himself may lead to water leakage, electric toxic gases to be generated.

an re
Valve cap

0
50
(A) If there are obstacles at the intake 500

th Mo
shock, fire, etc.
When performing piping work do not mix air except for specified an
If the upper part is open s th Hexagonal part
Carry out the installation work with reliability according to this manual refrigerant (R410A) in refrigeration cycle. It causes capacity down, If there are obstacles above the unit Les of the valve
for installation work. and risk of explosion and injury due to high tension inside the 1 For separate installation location 1 For separate installation location
Imperfection in installation leads to water leakage, electric shock, refrigerant cycle. • Only if there are obstacles at the • If there are obstacles on both sides • The dimensions for H, A and L are shown in the following Spanner
fire, etc.
Earth
intake table. (Secure) Torque

More than
Carry out the installation work with reliability on the place that can This equipment must be properly earthed. wrench
A

1000
bear the weight of this unit sufficiently. Insufficient strength leads to Flare nut
Earth line must not be connected to gas pipe, water
injury due to falling of the unit. pipe, lightning rod and telephone. L H 100
Otherwise, it may cause electrical shock in case the equipment H<L Install a pedestal or mount so that L H
Carry out predetermined installation work in preparation for strong th Mo 00
wind such as typhoon, earthquake. Imperfection in installation work breakdown or has leakage current. 0 an re • Cover the bottom part of the pedestal or mount so that air n5
10 50 ha 00
an n st n5

n
may lead to accidents arisen from overturn, etc. Provide a power outlet exclusively for each unit, and full disconnection 0 does not go through it. a s tha

0 a
th th Mo th Le

10 th
e an re e s During the cooling mode operation under low ambient pressure, the low
means having a contact separation in all poles must be incorporated or or 00 Les

e
The unit must be installed in accordance with applicable national

or
M 20 M 3 pressure side of the valve can be prone to freezing. Secure the flare nut
in the fixed wiring in accordance with the wiring rules. 2 For multiple units (up to 2 units)

M
and local regulations. 0
Any electrical work should only be carried out by qualified technician Installation of Earth Leakage Current Breaker • The dimensions for H, A and L are shown in the following (shared gas side / liquid side) section of the valve with a silicone sealing
and use exclusive circuits without fail. This equipment must be installed with earth leakage current breaker. table. agent to prevent this from occurring. Silicone sealing agent
2 For multiple units (more than 2 units)

More than
Presence of insufficient capacity in power circuit or imperfection in Otherwise, it may cause electrical shock and fire in case the (Ensure not to leave any holes)
• If there are obstacles on both sides

1000
execution leads to electric shock, fire, etc. equipment breakdown or has leakage current.
A
L H 200 [3-way valve operation method] • Use an Allen wrench (Size 4 mm or 6 mm).
Wiring shall be connected securely using specified cables and fix Do not add or replace refrigerant other than specified type.
them securely so that external force of the cables may not transfer It may cause product damage, burst and injury etc. H<L Install a pedestal or mount so that L H Direction to open
to the terminal connection section. • Cover the bottom part of the pedestal or mount so that air
Imperfect connection and fixing leads to fire, etc. Cautions
does not bypass it.
Do not install the unit at the place where the possibility of inflammable Opening : Open the cover and turn the Allen wrench counter-clockwise until it stops.

an re
0
• A limit of only 2 units can be installed.

50
If installing inside a small room, measures should be taken to prevent

th Mo
gas leakage exists. If such gas leakages should arise and the gas Closing : Open the cover and turn the Allen wrench clockwise until it stops.
refrigerant levels from building up to critical concentrations in the Mo
builds up around the unit, such situation may lead to ignition. re
event of a refrigerant leak occurring. Please discuss with the place of tha
purchase for advice on what measures may be necessary to prevent Drain piping should be made to ensure secure drainage according to Mo n1 (D) Stacking installation setup
the manual for installation work and carry out the thermal insulation re 00 • Stack up to 2 tiers.
critical concentrations being exceeded. If the refrigerant leaks and tha 0
to prevent the occurrence of condensation. n1 • A dimension of approximately 400 mm is required for the second tier outdoor unit’s drain pipe and space for maintenance of

n
reaches critical concentration levels, there is the danger that death

0 a
0
20 th
from suffocation may result. Imperfection in piping work leads to water leakage and may cause e the first tier outdoor unit.
Precautions for handling the valve cap
or
the house and property, etc. to become wet. • Close A section (the space between the upper and lower level outdoor units) so the outtake air does not bypass it. Valve size Tightening torque
M

Securely attach the protective covers for the outdoor unit connection
Position the indoor unit and outdoor unit, power cords and indoor/ Ensure not to scratch the inner surface of the valve or the end of the 20.6N•m~28.4N•m
cables and power cord so that they do not lift up after installation.
outdoor unit connection cables in a way so that they are at least 1 1 If there are obstacles at the discharge 2 If there are obstacles at the intake ø9.52
If the covers are not properly attached and installed, the terminal valve shaft. (2.1kgf•m~2.8kgf•m)
meter away from televisions and radios.
connections may overheat, and fire or electric shock may result. • Once adjustments to the valve are completed, ensure to tighten the 48.0N•m~59.8N•m

400
This is to avoid problems such as interference with picture and/or ø15.88
th Mo

400
Switch off all supplies before accessing any electrical part. sound. (However, note that depending on the electromagnetic wave an re A section valve cap according to the prescribed torque. (4.8kgf•m~6.0kgf•m)
20 A section
conditions, interference may still occur even if the separation distance 0
If refrigerant gas escapes during installation, ventilate the affected is more than 1 meter.)
area. If the refrigerant gas comes into contact with sparks or naked
flames, it will cause toxic gases to be generated.
When fixing the product with an overturn prevention wire, care should Precautions for handling the service ports Tightening torque
be taken to choose a place where no one trips over the fixing wire. If there are obstacles above the unit
1 For separate installation location Use a push-rod with a charge hose. 10.7N•m~14.7N•m
Improper fixing of screw may cause leakage current and electrical • Do not touch the air inlet or the sharp aluminum fins of the 2 For multiple units (more than 2 units)
shock. • Only if there are obstacles at the • If there are obstacles on the intake and • If there are obstacles on both sides • Once adjustments to the valve are completed, ensure to tighten the (1.1kgf•m~1.5kgf•m)
outdoor unit. You may get injured. e
Do not clean inside the indoor and outdoor units by users. Engage • Do not sit or step on the unit, you may fall down accidentally. intake the other side or 00 20
0 valve cap according to the prescribed torque.
M n5
a an
More than 1000

authorized dealer or specialist for cleaning. t h th


• Do not stick any object into the FAN CASE.
More than 1000

More than 1000


or
In case of malfunction of this appliance, do not repair by yourself. 500 M
You may be injured and the unit may be damaged. 500 than Precautions for connecting the pipes
Contact to the sales dealer or service dealer for a repair.
ss th
an Less n 50
0 (E) For multiple row installation (on the roof, etc.)
Le tha
Less 1 For one row installation setup 2 For multiple units (more than 2 units) Ensure that the pipes do not come into contact with the compressor’s Piping Caulking treatment, etc.
During pump-down operation must stop the compressor before disconnecting the piping installation. bolts or exterior panel.
M
(Disconnecting the refrigerant piping, while the compressor is operating with the 2-way valve and 3-way valve opened, leads to or There is a risk of condensation from the 3-way valve coming out between
air intake and an abnormal high pressure in the refrigerant cycle which can cause an explosion and/or injury). 10 e th
n th Mo 00 an the insulation material and the indoor unit’s piping when you install the Insulation
a an re e
During installation, ensure that the refrigerant piping is installed before operating the compressor. th or 0 outdoor unit above then the indoor unit. Ensure to caulk the connection
Warning M n 10 material
n

e 50
or 00
0 a

(Do not install the refrigerant piping while the compressor is operating with the 2-way valve and 3-way valve opened, as this 0
20 th

M 1 th Mo a parts.
0 a

th Mo t h
e

20 th

leads to air intake and an abnormal high pressure in the refrigerant cycle which may cause an explosion and/or injury). an re
or

an re
e

20
M

an
or

0 20
th an
M

0 e th
or 000 • The dimensions for H, A and L are shown e
or 000 han
M 1 M 2 t Precautions for insulation installation Maximum temperature limit of gas or liquid piping exceeds 120 °C
in the following table. e
1. ACCESSORIES SUPPLIED WITH OUTDOOR UNIT an or 0
e
th M 40 In high humidity environment, reinforce the insulation material for the refrigerant piping. Failure to do so may result in
(B) If there are obstacles at the discharge e or 200 A
condensation on the surface of the insulation material.
M
The following parts are supplied as accessories with each outdoor unit. Check that all accessory parts are present before or 0
If the upper part is open 1 For separate installation location 2 For multiple units (more than 2 units) M n 30 L H 200 a n
Use materials with good heat-resistant properties as the heat insulator for the pipes. Ensure to insulate both the gas side
installing the outdoor unit. a th
t h H<L Installation not possible e
or 0 and liquid side pipes.
0 M 50
Part name Q’ty Diagram Application Part name Q’ty Diagram Application 00 50 If the pipes are not adequately insulated, condensation and water leakages may occur.
n3 an
• The above mentioned distance is required for optimal unit performance.
t ha th Allow as much space as possible in order to obtain the best performance from the units. Ensure that the current insulation covers the pipes up to the unit’s connecting part.
Protective For protecting electrical Installation re e
2 This manual Mo or If the piping is exposed , it may cause condensation or burn (when touch the pipe).
bushing wires Instruction M
For tying electrical wires
Banding strap 4 4. TRANSPORT AND INSTALL THE OUTDOOR UNIT
together Precautions for flare nut installation
Transporting Dimensions when adding flare nuts and the tightening torque
If there are obstacles above the unit 1 For separate installation location 2 For multiple units (more than 2 units) 1. Transport the outdoor unit in its original packaging as close as possible to the installation location.
00 500 2. In the event that the unit needs to be lifted or suspended, use a rope or belt and use cloth or wood as padding to avoid damaging Piping size Tightening torque Flare section dimensions A Flare configuration
an 5
More than 1000

than
More than

th
Less Less the unit.
1000

14.2N•m ~ 17.2N•m
2. SELECT THE OUTDOOR UNIT INSTALLATION LOCATION 3. Use the side handles to carry the unit and be careful not to touch the fan with your hand or ø 6.35 (1.4kgf•m ~ 1.7kgf•m)
8.7 ~ 9.1
any objects.

±1°
32.7N•m ~ 39.9N•m

90° ± 2°
Installation

Less than 25
ø 9.52 12.8 ~ 13.2

45°
Be careful when picking up and moving the indoor and outdoor units. Get a partner to help, and bend your 0 1. Read the “Select the outdoor unit installation location” thoroughly before installing the outdoor (3.3kgf•m ~ 4.0kgf•m)
knees when lifting to reduce strain on your back. Sharp edges or thin aluminum fins on the air conditioner can 50
n unit. 49.5N•m ~ 60.3N•m
Warning cut your fingers. tha ø 12.7 16.2 ~ 16.6
e 2. When installing to a concrete or solid surface, use M10 or a W 3/8 bolts and nuts to secure Anchor bolt length (5.0kgf•m ~ 6.0kgf•m)
or the unit. Ensure that it installed upright on a horizontal plane. (Use an anchor bolt for the
M
300 installation as shown in the diagram below.) 68.0N•m ~ 75.5N•m
1. Install the unit once you have checked that the installation location matches the following conditions. ø 15.88 19.3 ~ 19.7
an 3. Avoid installing on the slanted roof. (Unit: mm) (6.8kgf•m ~ 7.6kgf•m)
A location with sufficient ventilation. th
e
Possibly a location that is sheltered from rain or direct sunlight and is well-ventilated so that hot and cool air does not build or 4. In the even where the roof is at risk of receiving oscillations 220 200 160 321 After piping connection has completed, ensure there is no gas leakage.
M
up. or vibrations, secure the unit with a seismic isolating mount

39

10
or vibration absorbing rubber. When tightening the flare nut, coat the flares (inner surface only) with refrigerant oil
A location where the area around the discharge is not exposed to animals or plants which could adversely affect the release 5. The drain water will be discharged from the unit during heating
of hot or cool air from the unit. on the flares Application for ether-based oil

(Anchor pitch)
or defrosting operation mode. 130
A location where the discharge and operation noise will not be a nuisance to the neighbours. Firstly, screw in 3-4 turns by hand.

380.5
Select an appropriate location with good drainage system. (In the winter,
A location that can support the product’s weight or vibrations and secured for horizontal installation wherever possible. there is risk of slipping due to freezing, and depending on the installation Ensure not to get oil on the screw part.
A location that does not obstruct the air discharge or intake. set up there is risk of drain water running overhead.) Refrigerant oil used is ether-based.
A location where there is no danger of flammable or corrosive gas leaks. Please consult us if installing drain elbows. Once the piping connections are completed, perform leakage inspection using nitrogen
A location that provides space for installation and service. gas.

19.5
A location that allows the pipe and cable length fixture for internal and external connections. In cold regions (where the outdoor temperature can drop to below 0˚ 170 620 150
for 2 to 3 consecutive days), the drain water may freeze and may (Anchor pitch)
prevent the fan from operating. For this case, do not use the drain
elbow. Anchor bolt position
6. VACUUM PURGING Use nitrogen gas for the leak tightness test. OUTDOOR UNIT/3-PHASE MODEL OUTDOOR UNIT/SINGLE-PHASE MODEL Test Run Procedure
Using flammable gas can cause an explosion. If there are duplicated system addresses, or if the settings for the Nos. of the indoor units are not consistent, an alarm will
Once the piping connections are completed, perform Power supply (220/230/240V~) Power supply (380/400/415V 3N~) Power supply (220/230/240V~) Power supply (220/230/240V~) Indoor unit occur and the system will not start.
Indoor unit
Switch the power supply ON both indoor and outdoor unit.
leakage inspection using nitrogen gas (leak tightness test) Outdoor unit Short-circuit CHK pin on the outdoor main PCB.
using the 3-way valve for the outdoor unit and then close Circuit breaker Circuit breaker Circuit breaker Circuit breaker
Do not remove CHK pin until test run is completed.
it. Pressure
meter 3-way Earth
Switch Switch Earth Switch Switch Removing CHK pin stops test run.
(Test the pressure with 3.8 MPa) Short-circuit RUN pin on the outdoor main PCB for one second or longer.
valve
Ensure to use a vacuum pump (with a back-flow prevention Branch pipe
Factory setting is cooling operation mode and cooling operation test run starts.

Outdoor unit
device) for inside the refrigerant system. L1 L If heating operation starts, short-circuit both right side and centre of the MODE pin (centre and COOL) continuously.
Vacuuming process will take place after the leak test. L L2 L N Ensure to conduct a test run. In addition, be sure to run the cooling operation test run for at least 20 minutes before starting
N Control cable L3 N Control cable the heating operation test run.
SG SG Main pipe
Nitrogen Refrigerant Vacuum Indoor unit N Earth
To conduct heating operation test run, short-circuit left side and centre of the MODE pin (centre and HEAT) continuously.
meter pump
U1 U1 (TWIN type)
Removing CHK pin’s and MODE pin's short-circuit stops test run.
SG
U2 SG
Earth U2 For the test run using remote control unit, please see installation manual included with the remote control unit.
R1 R1
R2 U1 R2 U1
2 1
U2 2 1
U2 Indoor unit
Indoor unit
Indoor unit
Indoor unit Wired remote Outdoor unit Indoor unit Wired remote Outdoor unit
controller controller
7. REGARDING REFRIGERANT FILLING

Precautions during refrigerant filling This equipment complies with EN/IEC 31000-3-12 provided that the short-circuit power Ssc is greater than or equals to 2 kVA at
the interface point between the user’s supply and the public system. It is the responsibility of the installer or user of the equipment Branch pipe

Outdoor unit
Ensure to fill only with liquid refrigerant when refilling. If using cylinders as shown in the bottom left diagram; without
to ensure; by consultation with the distribution network operator if necessary that the equipment is connected only to supply with a
If gas refrigerant is filled, the refrigerant composition will a siphon tube inside, turn it upside down and use it.
short-circuit power Ssc greater than or equals to 2 kVA.
not be balanced and will cause abnormal operation. (It is recommended to use the manifold with the side glass.)
Ssc : Short circuit power Main pipe
Liquid refrigerant Gas refrigerant SG : Shows the earth for the shielded cable. (TRIPLE type)
Liquid refrigerant

Cylinder with Siphon tube Maximum electric 1 2


Not possible Model name Power supply
a siphon tube Possible current Control cable Ssc Indoor unit
Cylinder Cylinder Indoor unit
U-60PE1E5 220/230/240V~ 18A 0.75mm² 4050 kVA
Indoor unit
U-71PE1E5 220/230/240V~ 18A 0.75mm² 4050 kVA Indoor unit
Use tools that are designed specifically for R410A, for pressure resistance and to prevent mixing impurities.
Fill the refrigerant from the 3-way valve’s service port on the liquid-side. U-71PE1E8 380/400/415V 3N~ 7A 0.75mm² 3
For filling and replacing all refrigerant (For refilling due to a leak) U-100PE1E5 220/230/240V~ 25A 0.75mm² 6000 kVA
For refilling refrigerant, first collect all residual refrigerant and after vacuum dehydration using the vacuum pump. Refill the U-125PE1E5 220/230/240V~ 28A 0.75mm² 6000 kVA Pipe branch 2 Pipe branch 2
refrigerant according to the prescribed amount stated on the placard affixed to this unit. U-140PE1E5 220/230/240V~ 30A 0.75mm² 6000 kVA
Precautions after the pipes’ connection have completed U-100PE1E8 380/400/415V 3N~ 9A 0.75mm² 3
Ensure to open the 3-way valve after completing the piping installation, leak test and vacuuming. If it is closed during U-125PE1E8 380/400/415V 3N~ 10A 0.75mm² 3 Pipe branch 1

Outdoor unit
operation, it can lead to compressor failure. Outdoor main PCB
U-140PE1E8 380/400/415V 3N~ 11A 0.75mm² 3
3 Models U-71PE1E8, U-100PE1E8, U-125PE1E8 and U-140PE1E8 are intended for professional use.
Main pipe
Consult with the supply utility for permission of electrical connection.
Charging with refrigerant (DOUBLE TWIN type)
Electrical work should be handled by Certificated Electrical work personnel by following “Technical standard of electric installation”
At the time of shipment from the factory, this unit is charged with enough refrigerant for an equivalent pipe length of 30m. and “Regulated regulations of nation”. CHK pin
If the equivalent pipe length used will be 30m or less, no additional charging will be necessary. Adjust wire size, length, earth leakage breaker, and fuse capacity according to each country’s Wiring regulations. • Use the main pipe to gain any rise or fall required for the pipes.
If the equivalent pipe length will be between 30 and 50/75m, charge with additional refrigerant according to the equivalent If capacity of power supply circuit and enforcement are not enough, it can causes the electric shock and a fire. • The number of bends should be 8 or less in a single system, and 15 or less overall.
length given in the table below.
• Branch pipes should be positioned horizontally.
For standard type NOTE
Use the standard power supply cables for Europe (such as H05RN-F or H07RN-F which conforms to CENELEC (HAR) rating RUN pin MODE pin
Additional charging amount Equivalent length Minimum length specifications) or use the cables based on IEC standard. (245 IEC57, 245 IEC66)
U-60/71P 50g/m 50m 5m Refrigerant charging
1 Use a shielded cable for the control cable. Overall extension less than 500m *MODE pin: factory setting is cooling operation mode.
U-100/125/140P 50g/m 75m 5m For the twin connection, the amount of refrigerant required for pipe length 30m has been included in this unit at the factory
while that required for pipe length 20m has been included for the triple/double-twin connections.
Pump down operation For the shield part of the shielded cable, twist the end out, crimp it with a No additional charge is required for the first 30m pipe length in the case of the twin connection and for the first 20m in the case
Please refer to the service manual for pump down method. round terminal, and connect it to the SG screw.
Crimp the round terminal
of the triple/double-twin connections. The amount of included refrigerant for each model is listed on NAME PLATE.
11. CHECKS AFTER INSTALLATION HAVE COMPLETED
After crimping it with a round terminal, wrap it with insulating tape so there Make additional charges by adding up pipe length in an order of main pipe (L)  branch pipe (La  Lb  Lc wide diameter) Check the following items after completing installation.
are no spaces and adjust it so the shield part does not touch any live parts. and then selecting the amount of refrigerant corresponding to the remaining (after 30m for the twin connection and after 20m Is there a short circuit with the intake air flow?
for the triple/double-twin connections) liquid side pipe diameter and pipe length from the below table. Is the insulation secure? (Refrigerant piping)
Be sure that the shield part of the shielded cable does
Are there any errors with the wiring?
Caution not touch the terminal block or any live parts. Wrap it well with insulating
Failure to do so may lead to electric shock or fire. Shield part tape so there are no spaces. Liquid pipe diameter Addition amount of refrigerant [g/m] Are the terminal screws loose? Tightening torque (Unit: N•m {kgf•m})
8. ELECTRICAL WIRING M4… 1.57-1.96 {0.16-0.2}, M5... 1.96-2.45 {0.2-0.25}.
ø6.35 20
Is the drain water flowing smoothly?
The units must be connected to the supply cables for fixed wiring by qualified technician.
Feed the power source to the unit via a distribution switch board designed for this purpose, the switch should ø9.52 50 Is the insulation material properly installed?
disconnected all poles with a contact separation of at least 3 mm. Is the earth wire securely connected?
9. TWIN, TRIPLE AND DOUBLE TWIN TYPE CONNECTIONS Is the front panel and the indoor unit air conditioner firmly fixed and was the installation completed without any leakage
When the supply cable is damaged, it must be replaced by qualified technician.
from the refrigerant?
Be sure to install a current leakage breaker, main switch and fuse to the main power supply, otherwise electric Two, three or four indoor units can be operated simultaneously with a single remote control unit.
Are the indoor and outdoor units secured firmly installed with bolts at secured locations?
Warning shocks may result. Note that individual operation is not possible. Wiring
Be sure to connect the unit to secure earth connection. Master unit and slave unit can be set automatically in twin and triple system. Power supply Power supply Power supply
If the earthing work is not carried out properly, electric shocks may result. No address setting is necessary. (220/230/240V~) (220/230/240V~) (380/400/415V 3N~)
Applicable “TWIN” and “TRIPLE” combination table.
Wiring shall be connected securely by using specified cables and fix them securely so that external force of Circuit breaker Circuit breaker Circuit breaker
the cables may not transfer to the terminal connection section. Switch Switch Switch 12. REGARDING DELIVERY TO THE CUSTOMER
Imperfect connection and fixing leads to fire, etc. Outdoor unit 71 Type 100 Type 125 Type 140 Type Earth Earth Earth Earth
Request the customer to review the instruction manual and explain the operating method for the product.
Ensure to connect the electrical cable connections and clamp the wires securely to the terminal connections using cord clamps In addition, it is also recommended that regular inspection checks are agreed upon for maintenance.
U-71 U-100 U-125 U-140 L L1
L L L L Controll
TWIN

so that no undue force is placed on the wires (power source cable, indoor/outdoor connection cables, earth lead wire). N L2
combination N N N N cable L3 User inspection places • Filter and grill cleaning
Do not install a phase advance capacitor for power factor improvement. (It does not improve the power factor and will cause Controll Controll Controll
S-36 S-36 S-50 S-50 S-60 S-60 S-71 S-71 cable cable cable Earth N • Exterior cleaning
abnormal overheating.) U1 U1 U1 U1
Do not bind the excess cables together and place them inside this unit. U2 U2 U2 U2 Earth Serviceman inspection • Check the operating status
R1 R1 R1 R1 Outdoor unit places • Clean the drain pan or things related to the water discharge
Protect the electrical cable with the protective bushing provided so that the cables do no get damaged on the knock hole or R2 R2 R2 R2 U1
U2 • Heat exchanger cleaning
U-100 U-125 U-140
TRIPLE

etched portions. If there is space between the electrical cables and the protective bushing occurs, seal it accordingly.
Tie the cables with the provided binding strap so that they do not touch the compressor and the pipes. combination ______ Indoor unit Wired remote Outdoor unit
Indoor unit Indoor unit Indoor unit
When setting up the cables, inside of unit install properly so that the front panel will not lift up. Make sure that front panel mount S-36 S-36 S-36 S-45 S-45 S-45 S-50 S-50 S-50 controller
correctly. (TRIPLE type) Refer to the installation instruction manual provided with the indoor unit for the specifications on
Use a round type terminal with an insulation sleeve for connecting to the terminal block. (DOUBLE TWIN type) the indoor unit installation.
DOUBLE TWIN

Use the appropriate screwdriver for tightening the terminal screws.


Small sized screwdriver damages the head of the screw and Control U-125 SG : Shows the earth for the shielded cable.
terminal block Power supply
cannot tighten it properly. combination ______ ______ ______
terminal block
There is risk of damaging the screw if the terminal screw is over Insulate the S-36 S-36 S-36 S-36
tightened. Tighten with the appropriate torque. terminal section with
insulation sleeves. Earth lead wire
Screw diameter name Tightening torque N•m (kgf•m) SG
Cord clamp 10. PRECAUTIONS REGARDING TEST RUN
M4 1.57 ~ 1.96 (0.16 ~ 0.2)
Piping Connections
M5 1.96 ~ 2.45 (0.2 ~ 0.25) Cord clamp
Check Before Test Run
The following table shows the pipe diameter.
Direction to pull out wires (Branch pipe kit should be used) Content check
Firmly secure the power supply
cable, the internal/external Power supply cable Is the wire set up and connected as described in the instructions? Check for any phase
Back direction connections and earth wire.
Outdoor unit main pipe Indoor unit combination Indoor/outdoor connection wire sequence.
Branch pipe diameter Earth wire Are the wire connection’s screws loose?
Front direction diameter (mm) S-36 S-45 S-50 S-60 S-71
Sideways direction Tie the insulation pipes so that the Is the open and close device / leakage breaker installed?
power supply cable, control wires, Tying band
and earth lead wire do not come into Liquid side ø6.35 ø6.35 ø6.35 ø9.52 ø9.52 Is the power supply cable’s thickness and length appropriately measured as described
Seal wiring holes after wiring using included protection bush. (Standard Liquid side : ø9.52
contact with the compressor and/or accessories) in the instructions?
(other holes are for connecting conduit pipe) the exposed pipes.
Gas side : ø15.88 Gas side ø12.7 ø12.7 ø12.7 ø15.88 ø15.88 Is it earthed (grounded)?
Earth lead wire set up Check that the insulation resistant value is more than 1 MΩ.
TWIN, DOUBLE TWIN CZ-P155BK1 Use the 500 V mega-testers to measure the insulation.
Branch pipe kit (option)
TRIPLE CZ-P3HPC2 Do not use the mega-tester for any other circuit except for voltage of 220-240V or
The earth lead wire shall be longer than other lead wires as shown in the figure for electrical safety in
380-415V.
case it slips out of the cord from the anchorage. Are the wire connections for the indoor/outdoor units connected as described in the
The following table shows the equivalent pipe lengths and height differences. instructions? Are there any looped wires?
Was the “N-phase” surely connected when connecting the power supply wire on the
three-phase model?
SYMBOLS If N-phase is not connected, only the fan may repeat turning ON/OFF without the
SPEC
Be sure to connect the wires correctly to terminal board with TWIN TRIPLE DOUBLE TWIN compressor operating. In that case, check if there is any problem with N-phase
connecting the crimp type ring terminal to the wires. U-60/71P : 50m connection.
Total pipe length L+La+Lb L+La+Lb+Lc L+La+Lb+Lc+Ld+Le+Lf
If connecting two separate wires to a single crimped terminal, U-100/125/140P : 75m
La+Lc or La+Ld or Lb+Le Refrigerant pipe Is the piping installed as described in the instructions?
place the two crimped terminal wires together as shown in Maximum branch pipe length La or Lb La or Lb or Lc Less than 15m
or Lb+Lf Are the pipes sizes appropriate?
Fig. A. (If the arrangement shown in Fig. B is used, poor contacts
Fig. A (OK) Fig. B (not OK) La > Lb > Lc Lb+Lf  MAX Does the pipe’s length adhere to the specifications?
or contact damage may result.) La > Lb La - Lb La+Lc  MIN
Maximum branch pipe length difference Less than 10m Is the branch pipe slant being appropriately done as described in the instructions?
La - Lb Lb - Lc (Lb + Lf) - (La + Lc) Was vacuum removal sufficiently carried out?
La - Lc
Was the leak tightness test carried out with nitrogen gas? Use the testing pressure of
_____ _____ Lb > La
Maximum pipe length difference of branch pipe 1 (DOUBLE TWIN) Less than 10m 3.8 MPa.
Lb - La
Ld > Lc Is the piping insulation material appropriately installed? (Insulation material is necessary
_____ _____ Lf > Le for both gas and liquid piping.)
Maximum pipe length difference of branch pipe 2 (DOUBLE TWIN) Less than 10m
Ld - Lc Is the 3-way valve for the liquid side and gas side open?
Lf - Le
Height Outdoor located higher installation H1 Less than 30m Always be sure to use a properly insulated tool to operate the short-circuit pin on the circuit board. (Do not use your finger.)
difference Outdoor located lower installation H1 Less than 15m Never switch the power supply ON until the installation has completed.
H2 or H3 or H4 or Supply electrical current through all indoor units and check the voltage.
Height difference between indoor units H2 H2 or H3 or H4 Less than 0.5m
H5 or H6 or H7 Supply electrical current through all the outdoor units and check each inter-phase voltage.
Before the test run, ensure to check that the 3-way valve is open. Operating while the valve is closed causes the compressor
to fail.
F614942 1
PRINTED IN CHINA