MBAZG523 PROJECT MANAGEMENT EC 3M MAY 23

Q1

Q2
Q3

Q4
MBAZG539 DATA VISUALIZATION AND COMM EC 3R MAY 23

Qtext :
With reference to the following figure, what is the problem that the visualization is facing? How would you
solve it? (5 Marks)
Qtext :
What purpose does Quick Table Calculation serve in tableau? Give 3 types of Quick Table Calculation
that is possible in Tableau. (5 marks)

Qtext :
What does bin mean in Tableau? How do you create bins? (5 Marks)

Qtext :
How are parameters different from filters in Tableau? (5 Marks)

Qtext :
Suppose there a table is spread around in 6 pages in a pdf file. Can you use Tableau to access
this table and visualize? If yes, give the steps involved. (5 marks)

Qtext :
What do you understand by the term “Use Data Interpreter” in Tableau? Give example of two use
cases when this feature can be used, explain how? (10 Marks)

Qtext :
What is implicit and explicit measures in Power BI? How is it related to calculated field in
Tableau? How do you create an explicit measure in Tableau? (10 marks)
MBAZG523 PROJECT MANAGEMENT EC 2R MAR 23

Qtext :
The network below represents a project being analyzed by Critical Path Methods. Activity
durations are indicated on the network. (2+1+2+3=8 M)

(a) Identify the activities on the critical path.


(b) What is the duration of the critical path?
(c) Calculate the amount of slack time at activity H.
(d) If activity I were delayed by ten time units, what would be the impact on the project duration?

Qtext :
An entrepreneur is considering investing in a project to manufacture a new brand of soap with
an initial investment of Rs. 10,00,000. Other relevant data is given below.

Calculate the NPV and discounted payback if the minimum expected rate of return is 10% and
inflation is 4%. (4+6=10 M)
Qtext :
A network consists of the following list. Times are given in weeks. [3+2+2+5=12 M]

a. Draw the network diagram.


b. Calculate the expected duration and variance of each activity.
c. Calculate the expected duration and variance of the critical path.
d. Calculate the probability that the project will be completed in less than 28 weeks.

MBAZG539 DATA VISUALIZATION AND COMM EC 2R MAR 23

Qtext :
What is a calculated field in Tableau? How do you create it? (5 marks)

Qtext :
What is a story and dashboard in Tableau? Explain. – (5 Marks)
Qtext :
What do you understand by Hierarchical field in Tableau? – (5 Marks)

Qtext :
What are Measures and Dimensions? (5 marks)

Qtext :
Creating a foreground and background in a visualization satisfies which Visual Perception
Theory? Explain why? (5 marks)

Qtext :
What are the different datatypes in Tableau? (5 marks)