Elevation Section A - A
88
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Yield Strength of reinforcement ( Fy ) = 414 N/mm2
89
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Clear Cover to Reinforcement ( c ) = 75 mm
Unit Weight of Concrete ( gc ) = 24 KN/m3
Density of retained liquid, ( gw ) = 8.77 KN/m3
a ) Tank side empty and Other side earth + wind pressure, &
b ) Tank side with liquid & Submerged soil pressure & Other side with soil pressure only.
In both of the cases whatever pressure will comes over the wall will be transferred through the one way
load distribution pattern to column and then will ultimately go to ground. So in this case design formula as
per Clause 3.4.4.2 of BS : 8110 ( Part I ) has been used.
a)
Active earth pressure ( Pa ) = g*Ka* Ho1
= 8.8704 KN/m2
Moment at base of wall due to = 1/6 * Pa * Ho12
active earth Pressure ( Ma ) = 3.785 kNm
b)
Wind pressure, ( Qw ) = 0.76 KN/m2, For the top height of (Ho2) = 3.00m
Moment at base of wall due to = Qw * Ho2 * ( Ho1 + Ho2 /2 )
wind pressure ( Mw ) = 7.068 kNm
Converting to eq triangle of same ht which will prodcue the same moment at the base.
0.76
1/2 x Peq x 4.40 x 4.40/3 = 10.853 1
2
Dividing plate into 3 equal part, and designing for the same. 4.82
Calculating moment and shear for each panel using coefficient of BS : 8110 (Part I ) : Table 3.5
90
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Moment coefficient for middle of interior span ( Mcoeffspan ) = 0.07
91
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Moment coefficient for interior supports ( Mcoeffsupport ) = 0.08
Shear coefficient at interior supports ( Scoeffsupport ) = 0.55
a)
Liquid pressure ( Pl ) = gw * H1
= 40.342 KN/m2
Moment at base of wall due to = Pl * H / 6
1
2
b)
Active earth pressure ( Pa ) = Ka*(g-gw)*Ht1
= 4.549 KN/m2
Moment at base of wall due to = Ka*(g-gw)*Ht13 /6
active earth Pressure ( Ma ) = 1.941 kNm
c)
Passive earth pressure ( Pp ) = g*Kp*Ho1 ( Passive pressure for moment
= 0 KN/m 2 calculation has been ignored so
Moment at base of wall due to = 1/6 * Pp * Ho12 as to be on conservative side )
passive earth Pressure ( Mp ) = 0 kNm
d)
Wind pressure, ( Qw ) = 0.76 KN/m2, For the top height of (Ho2) = 3.00m
Moment at base of wall due to = Qw * Ht3 * ( H1 - Ht3 /2 )
wind pressure ( Mw ) = 1.0146 kNm
Moment at base ( M2 ) = Ml + Ma + Mw
- Mp 1 0.76
= 145.228 kNm 15.00
2
Converting to eq triangle of same ht, 30.01
which will prodcue the same moment at the base. 3
45.01
92
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
1/2 x Peq x 4.40 x 4.40/3 = 145.2281 4.55 40.34
93
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Dividing plate into 3 equal part, and designing for the same.
Effective Length of each plate ( Lweff ) = 4 m
Width of each plate ( We ) = 1.466667 m
Calculating moment and shear for each panel using coefficient of BS : 8110 (Part I ) : Table 3.5
Moment coefficient for middle of interior span ( Mcoeffspan ) = 0.07
Moment coefficient for interior supports ( Mcoeffsupport ) = 0.08
Shear coefficient at interior supports ( Scoeffsupport ) = 0.55
z = 0.95 x d
94
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
= 204.25 mm
95
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
From the above required Astreq1 = 1503.36 mm2/m Max of Ast1, Ast2 & Ast3
Provide Min Reinforcement As Dist. Steel, As per table 3.25 of BS : 8110 ( Part - I )
Distribution steel, Adist = 0.13 % of Area of concrete
= 0.13 x 1000 x 300 / 100
= 390 mm2/m
96
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
3.5 Check For Shear :
( Sample calculation for panel 3 )
Maximum allowable crack width = 0.3 mm (Per BS 8110-2 : 1985 clause 3.2.4)
Where,
acr = Dist from point considered to the surface of the nearest long bar
= Sqrt( S/22+ (c+f/2)2 ) - (f/2)
97
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
= 131.21 mm
S = Spacing of reinforcement
= 200
As = Area of steel
= 2303 mm2
Where,
acr = 131.21 mm
k = Mu / fcu bd2
= 0.085 < 0.156
z = d* [ 0.5 + sqrt ( 0.25 - k/0.9 )] & 0.95 x d
98
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
= 192.21 mm & 204.25 mm
z = 192.21 mm
W2 = 3*acr*em/(1+2*(acr - cmin)/(h-x))
= 0.32 mm > 0.30 mm NOT OK
99
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
100
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Tw
Lf H1
Wc
x A Ht1 Ho1
z Wf Tf
Lf
Plan Section A - A
Here,
Length of footing ( Lf ) = 4.70 m
Width of footing ( Wf ) = 2.70 m
Width of column ( Wc ) = 0.40 m
Length of column ( Lc ) = 0.60 m
Width of wall ( Ww ) = 4.40 m
Length of Wall ( Lw ) = 3.60 m, ( Max wall Length has been Considered )
Top of footing from tank side GL ( Ht1 ) = 1.60 m
Height of liquid from GL ( Ht2 ) = 2.70 m
Free board ( Ht3 ) = 0.30 m
Top of footing from out side GL ( Ho1 ) = 1.60 m
Height of wall from outside GL ( Ho2 ) = 3.00 m
Thickness of footing ( Tf ) = 0.60 m
Height of wall from top of footing ( H1 ) = 4.60 m
Top of wall from bottom of footing ( H ) = 5.20 m
Thickness of wall ( Tw ) = 0.30 m
6.1 BM Calculation :
Case ( a ) :
Wt of column ( Wc ) = gc x Lc x Wc x H1
= 26.496 kN
Wt of wall ( Ww ) = gc x Lw x Ww x Tw Kp = 0
= 114.048 kN
96
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
97
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
= 140.544 kN ... ( 1 )
( Weight of platform
Eccentricity of Wall ( ewall ) = 0.15 m has been neglected )
Active
a)
Calculation of Moment & Shear due to wind and active earth pressure about the base of column.
Wind pressure ( Qw ) = 0.76 KN/m2, For the top ht of ( Ho2 ) = 3m
b)
Moment due to wall eccentricity ( Mwa ) = Ww ewall
= 17.1072 kNm
Passive
c)
Calculation of Moment & Shear due to 2/3 height of passive earth pressure about the base of column.
( Passive pressure has been ignored so as to be on conservative side )
Case ( b ) :
> Here, column is subjected to uniaxial bending moment due to submerged earth
and liquid pressure & compressive load due to self wt as well as weight of wall.
= 140.544 kN ... ( 4 )
Active
98
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
a)
Calculation of Moment & Shear due to wind, liquid and submerged active earth pre about the base of column.
99
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Wind pressure, ( Qw ) = 0.76 kN/m2, For the top ht of ( Ho2 ) = 3m
Pressure due to wind, liquid & = (gw*(H1 - Ht3)+ Ka*(g-gw)*Ht1 + Qw) x (Lw + Wc)
submerged active earth pressure ( Pia ) = 172.08 kN/m2
Shear due to wind, liquid & submerged = (gw*( H1 - Ht3)2/2 + Ka*(g-gw)*Ht12/2 + Qw*Ht3)x(Lw + Wc)
active earth pressure ( Via ) = 339.78 kN
Moment due to wind, liquid & = ( Ka*(g-gw)*Ht13/6 + Qw*Ht3*(Ht3/2+Ht2+Ht1) +
submerged active earth pressure ( Mia ) gw*(H1 - Ht3)3/6) x (Lw + Wc)
= 476.67 kNm
Passive
b)
Calculation of Moment & Shear due passive earth pressure abou the base of column.
c)
Moment due to wall eccentricity ( Mwp ) = Ww ewall
= 17.1072 kNm
Fy = 1.4*Max of ( 1 ) & ( 4 )
= 196.76 kNm
Fx = 1.4*Max of ( 2 ) & ( 5 )
= 352.55 kNm
Mz = 1.4*Max of ( 3 ) & ( 6 )
= 607.82 kNm
FY Fx Fz Mx Mz
MAX 197 353 0 0 608
dtendia = 25 mm
dstirr = 8 mm
100
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Assumed pt% = 2 %
101
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
b = Width of column ( Wc ) Effective width b' = b - c - dstirrups - dtendia/2
= 0.40 m = 0.305 m
h = Length of column ( Lc ) Effective length h' = h - c - dstirrups - dtendia/2
= 0.60 m = 0.505 m
a)
Axial Force & Moment From Case I & II :
N = Maximum Design Axial load ( Wu ) = 196.76 kN ... ( 7 )
Mz = Maximum Design Moment ( Mu ) = 607.82 kNm ... ( 8 )
Mx = Maximum Design Moment ( Mu ) = 0 kNm ... ( 9 )
b)
Moment due to mnimum eccentricity :
c)
Moment due to slenderness :
Effective length ( Le ) = b x Lo
in X direction ( Lex = b x Lox) = 10.12 Un braced < 10 Short Column
in Z direction ( Ley = b x Loz) = 3.45 Braced < 15 Short Column
102
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
103
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Design Moment :
Here, Mx << Mz
Wt of column ( Wc ) = gc x Lc x Wc x H1
= 26.496 kN
Wt of wall ( Ww ) = gc x Lw x Ww x Tw
= 114.048 kN
Soil Cushion ( Ws1 ) = g x Ht1xWf x Lh
272.16 kN
Soil Cushion ( Ws2 ) = g x Ho1 x [(Wf - Wc)*(Lc - Tw) + Wf*Lt]
66.53 kN
Eccentricity of Ws2 in x = [(Wf - Wc)*(Lc - Tw)*(Lt+(Lc-Tw)/2) + Wf*Lt*Lt/2]
direction ( es2 ) [(Wf - Wc)*(Lc - Tw) + Wf*Lt]
104
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
= 0.434 m
Weight of Footing ( Wfo ) = gc*Wf*Lf*Tf
105
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
182.74 kN
Wc
Wl Ww
Here,
Ws1 Ws2 Lt = 0.6
Y Lh = 3.50
Heel Wfo Toe
X Lh Lc Lt
Lf
106
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
107
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Mxr = Max of ( 18 ) & ( 21 )
= 1195.74 kNm
Active
a)
Calculation of Moment & Shear due to wind and active earth pressure about the base of footing.
Wind pressure ( Qw ) = 0.76 kN/m2, For the top ht of ( Ho2 ) = 3m
Passive
b)
Calculation of Moment & Shear due to 2/3 height of passive earth pressure about the base of footing.
Active
a)
Calculation of Moment & Shear due to wind, liquid and active earth pressure about the base of footing.
Wind pressure, ( Qw ) = 0.76 kN/m2, For the top ht of ( Ho2 ) = 3m
Pressure due to wind, liquid & = (gw*(H - Ht3)+ Ka*(g-gw)*(Ht1+Tf )+ Qw) x (Lw + Wc)
submerged earth ( Pia ) = 196.91 kN/m2
Shear due to wind, liquid & submerged = (gw*( H - Ht3) /2 + Ka*(g-gw)*(Ht1+Tf)2/2 + Qw*Ht3)x(Lw+Wc)
2
108
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
109
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Passive
b)
Calculation of Moment & Shear due to 2/3 height of passive earth pressure about the base of footing.
FY FX FZ MX MZ
MAX 886 198 0 0 589
110
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for
WetMain
Crude
Crude
Oil Oil
Tank-21-TK-001
Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
111
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
x Wc Wf H1 z
Lc Water Table
Tf
Lf
Lf
18
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
19
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
In Z direction:
Net Sliding force in Z direction ( Fz ) = 0 KN
FY = 886 KN
Resisting frictional force ( Rz ) = Fy tan(2/3*f )
= 345.9272 KN
F.O.S. against sliding in Z direction = Rz / Fz
= NA
O.K. as value greater than permissible value
In Z direction:
Forces acting at bottom of footing about X
FY = 885.7346 KN
Total overturning moment ( Mxo ) = Mx
= 0 kNm
20
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Restoring Moment ( Mr ) = BF*Lf/2 + Mxr From Case I & II
= 1195.742 kNm
1.35
BF
7.5 Check For Bearing Pressure:
4.7
7.6 Check For Moment And Shear
21
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
1 2 3
36.00 1 2 36.00
P2 P1
8.83 d d
77.58 104.41 ( d = D - 75 - 8 = 517 mm )
90.99 130.77
Factored Pressure Distribution At Salient points Critical Sections For Moment & Shear
22
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Shear at critical section 2: = 114.7934 KN
Shear at critical section 3: = 103.9843 KN
Tensile Reinforcement:
K = Mu / fcubd2 Factore Moment
= 0.028263 < 0.156
Z = d[0.5+Ö(0.25-k/0.9)]
= 500.22 mm &
= 0.95*d
= 491.15 mm
Hence z = 491.15 mm
Ast = M/0.95fyz
= 838.0151 mm2/m
Amin = 0.13% of Area of concrete
= 780 mm2/m
Reqd. Spacing of 16 mm dia bar = 240 mm
Provided Spacing of 16 mm dia bar = 200 mm
Ast,provided = 1005.31 mm2/m
1 2 3
36.00 36.00
1 d
P3 P1 d
130.77
130.77 130.77 130.77
130.77 ( d= D-75-16-8 = 501 mm )
Factored Pressure Distribution At Salient points Critical Sections For Moment & Shear
23
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
24
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
Tensile Reinforcement:
K = Mu / fcubd2 Factore Moment
= 0.011651 < 0.156
Z = d[0.5+Ö(0.25-k/0.9)]
= 494.43 mm &
= 0.95*d
= 475.95 mm
Hence z = 475.95 mm
Ast = M/0.95fyz
= 334.77 mm2/m
Amin = 0.13% of Area of concrete
= 780 mm2/m
Reqd. Spacing of 16 mm dia bar = 258 mm
Provided Spacing of 16 mm dia bar = 200 mm
Ast,provided = 1005.31 mm2/m
UO 1.5d
U1
1.5d
25
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No : 0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By : Mr. Girish Kurnool
26
Client : Kuwait Oil Company
Project : Facility Upgrade and Relocation of Under Ground Process
Job No : JI-180 Doc No : JI-180-000-ECV-CAL-050
Subject : Design of Column Bund Wall Rev No :0
for Main Crude Oil Tank TK - 1526 & Prep. By : Dipak
Test Tank Tk - 1527 Checkd. By :Mr. Girish Kurnool
Appendix - I
EL 100.50 A EL 100.50
400 3600 400 600
300
3000
1600
1600
A 2700 4700
To
T 8 @ 150 mm c/c
T 25 @ 12 Nos
T 16 @ 200 mm c/c
T 16 @ 200 mm c/c
Section B-B
24
( RC Detail Only )
25