12 Pemasangan & Instalasi Exhaust Fan Modena Cooker Hood BX 6500 5.000 Unit 3,750,000.00 18,750,000.00
A B C
ADHI MORTON.ST
Direktur
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
NAMA KEGIATAN : 0
NAMA PEKERJAAN: 0
LOKASI :0
TH. ANGGARAN :0
Anl. Praktis 10 M2 Bongkaran Rangka Atap Kayu ( Kayu tidak dipakai lagi )
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.00 90,000.00 90,000.00
Mandor Oh 0.05 125,000.00 6,250.00
Jumlah Tenaga Kerja 90,000.00
B Bahan -
Jumlah Harga Bahan -
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 90,000.00
E Overhead & Profit 10% x D 9,000.00
F Harga Satuan Pekerjaan (D+E) 99,000.00
Untuk 1 M2 Bongkaran Rangka Atap Kayu ( Anl.Bongkaran Rangka Atap Kayu / 10 ) 9,900.00
A. 2.2.1.0. 1 m² Pembersihan Lapangan dan Perataan
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 0.100 90,000.00 9,000.00
Mandor Oh 0.005 125,000.00 625.00
Jumlah Tenaga Kerja 9,625.00
B Bahan -
Jumlah Harga Bahan -
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 9,625.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 9,625.00
A.3.2.1.10. Pemasangan 1 m³ Pondasi Siklop, 60% Beton Campuran 1 SP : 2 PB : 3 Kr dan 40% Batu Belah
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 3.400 90,000.00 306,000.00
Tukang Oh 0.850 125,000.00 106,250.00
Kepala Tukang Oh 0.085 150,000.00 12,750.00
Mandor Oh 0.170 125,000.00 21,250.00
Jumlah Tenaga Kerja 446,250.00
B Bahan
Batu Belah M3 0.480 136,630.00 65,582.40
Semen Portland Kg 194.000 1,200.00 232,800.00
Pasir Beton M3 0.312 130,000.00 40,560.00
Kerikil M3 0.468 202,800.00 94,910.40
Besi Beton Kg 126.000 13,800.00 1,738,800.00
Kawat Beton Kg 1.800 17,000.00 30,600.00
Jumlah Harga Bahan 2,203,252.80
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 2,649,502.80
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 2,649,502.80
A.4.4.1.7. Pemasangan 1 m² Dinding Bata Merah (5x11x22) Cm Tebal 1/2 Batu Campuran 1 SP : 2 PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 0.300 90,000.00 27,000.00
Tukang Oh 0.100 125,000.00 12,500.00
Kepala Tukang Oh 0.010 150,000.00 1,500.00
Mandor Oh 0.015 125,000.00 1,875.00
Jumlah Tenaga Kerja 42,875.00
B Bahan
Batu Bata Bh 70.000 1,000.00 70,000.00
Semen Portland Kg 18.950 1,200.00 22,740.00
Pasir Pasang M3 0.038 130,000.00 4,940.00
Jumlah Harga Bahan 97,680.00
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 140,555.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 140,555.00
A.4.4.1.8. Pemasangan 1 m² Dinding Bata Merah (5x11x22) Cm Tebal 1/2 Batu Campuran 1 SP : 3 PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 0.300 90,000.00 27,000.00
Tukang Oh 0.100 125,000.00 12,500.00
Kepala Tukang Oh 0.010 150,000.00 1,500.00
Mandor Oh 0.015 125,000.00 1,875.00
Jumlah Tenaga Kerja 42,875.00
B Bahan
Batu Bata Bh 70.000 1,000.00 70,000.00
Semen Portland Kg 14.370 1,200.00 17,244.00
Pasir Pasang M3 0.040 130,000.00 5,200.00
Jumlah Harga Bahan 92,444.00
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 135,319.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 135,319.00
A.4.4.1.10. Pemasangan 1 m² Dinding Bata Merah (5x11x22) Cm Tebal 1/2 Batu Campuran 1 SP : 5 PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 0.300 90,000.00 27,000.00
Tukang Oh 0.100 125,000.00 12,500.00
Kepala Tukang Oh 0.010 150,000.00 1,500.00
Mandor Oh 0.015 125,000.00 1,875.00
Jumlah Tenaga Kerja 42,875.00
B Bahan
Batu Bata Bh 70.000 1,000.00 70,000.00
Semen Portland Kg 9.680 1,200.00 11,616.00
Pasir Pasang M3 0.045 130,000.00 5,850.00
Jumlah Harga Bahan 87,466.00
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 130,341.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 130,341.00
A.4.4.1.1. Pemasangan 1 m² Dinding Bata Merah (5x11x22) Cm Tebal 1 Batu Campuran 1 SP : 2 PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 0.600 90,000.00 54,000.00
Tukang Oh 0.200 125,000.00 25,000.00
Kepala Tukang Oh 0.020 150,000.00 3,000.00
Mandor Oh 0.030 125,000.00 3,750.00
Jumlah Tenaga Kerja 85,750.00
B Bahan
Batu Bata Bh 140.000 1,000.00 140,000.00
Semen Portland Kg 43.500 1,200.00 52,200.00
Pasir Pasang M3 0.080 130,000.00 10,400.00
Jumlah Harga Bahan 202,600.00
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 288,350.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 288,350.00
A.4.1.1.1. Membuat 1 m³ Beton Mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 247.000 1,200.00 296,400.00
Pasir Beton Kg 869.000 92.86 80,692.86
Kerikil ( Maks 30 mm ) Kg 999.000 150.22 150,072.00
Air Kerja Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 540,064.86
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 737,514.86
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 737,514.86
A.A.4.1.1.4. Membuat 1 m³ Lantai Kerja Beton Mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.200 90,000.00 108,000.00
Tukang Oh 0.200 125,000.00 25,000.00
Kepala Tukang Oh 0.020 150,000.00 3,000.00
Mandor Oh 0.060 125,000.00 7,500.00
Jumlah Tenaga Kerja 143,500.00
B Bahan
Semen Portland Kg 230.000 1,200.00 276,000.00
Pasir Beton Kg 893.000 92.86 82,921.43
Kerikil ( Maks 30 mm ) Kg 1027.000 150.22 154,278.22
Air Kerja Ltr 200.000 60.00 12,000.00
Jumlah Harga Bahan 525,199.65
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 668,699.65
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 668,699.65
A.4.1.1.2. Membuat 1 m³ Beton Site Mix Mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 276.000 1,200.00 331,200.00
Pasir Beton Kg 828.000 92.86 76,885.71
Kerikil ( Maks 30 mm ) Kg 1012.000 174.07 176,162.96
Air Kerja Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 597,148.68
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 794,598.68
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 794,598.68
A.4.1.1.3. Membuat 1 m³ Beton Site Mix Mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 299.000 1,200.00 358,800.00
Pasir Beton Kg 799.000 92.86 74,192.86
Kerikil ( Maks 30 mm ) Kg 1017.000 174.07 177,033.33
Air Kerja Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 622,926.19
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 820,376.19
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 820,376.19
A.A.4.1.1.5. Membuat 1 m³ Beton Site Mix Mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 326.000 1,200.00 391,200.00
Pasir Beton Kg 760.000 92.86 70,571.43
Kerikil ( Maks 30 mm ) Kg 1029.000 174.07 179,122.22
Air Kerja Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 653,793.65
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 851,243.65
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 851,243.65
A.A.4.1.1.6. Membuat 1 m³ Beton Site Mix Mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 352.000 1,200.00 422,400.00
Pasir Beton Kg 731.000 92.86 67,878.57
Kerikil ( Maks 30 mm ) Kg 1031.000 174.07 179,470.37
Air Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 682,648.94
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 880,098.94
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 880,098.94
A.4.1.1.7. Membuat 1 m³ Beton Site Mix Mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 371.000 1,200.00 445,200.00
Pasir Beton Kg 698.000 92.86 64,814.29
Kerikil ( Maks 30 mm ) Kg 1047.000 174.07 182,255.56
Air Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 705,169.84
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 902,619.84
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 902,619.84
A.4.1.1.8. Membuat 1 m³ Beton Site Mix Mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 384.000 1,200.00 460,800.00
Pasir Beton Kg 692.000 92.86 64,257.14
Kerikil ( Maks 30 mm ) Kg 1039.000 174.07 180,862.96
Air Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 718,820.11
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 916,270.11
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 916,270.11
A.4.1.1.9. Membuat 1 m³ Beton Site Mix Mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 406.000 1,200.00 487,200.00
Pasir Beton Kg 684.000 92.86 63,514.29
Kerikil ( Maks 30 mm ) Kg 1026.000 174.07 178,600.00
Air Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 742,214.29
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 939,664.29
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 939,664.29
A.4.1.1.10. Membuat 1 m³ Beton Site Mix Mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.650 90,000.00 148,500.00
Tukang Oh 0.275 125,000.00 34,375.00
Kepala Tukang Oh 0.028 150,000.00 4,200.00
Mandor Oh 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 197,450.00
B Bahan
Semen Portland Kg 413.000 1,200.00 495,600.00
Pasir Beton Kg 681.000 92.86 63,235.71
Kerikil ( Maks 30 mm ) Kg 1021.000 174.07 177,729.63
Air Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 749,465.34
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 946,915.34
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 946,915.34
A.4.1.1.11. Membuat 1 m³ Beton Site Mix Mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 2.100 90,000.00 189,000.00
Tukang Oh 0.350 125,000.00 43,750.00
Kepala Tukang Oh 0.035 150,000.00 5,250.00
Mandor Oh 0.105 125,000.00 13,125.00
Jumlah Tenaga Kerja 251,125.00
B Bahan
Semen Portland Kg 439.000 1,200.00 526,800.00
Pasir Beton Kg 670.000 92.86 62,214.29
Kerikil ( Maks 30 mm ) Kg 1006.000 174.07 175,118.52
Air Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 777,032.80
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 1,028,157.80
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 1,028,157.80
A.4.1.1.12. Membuat 1 m³ Beton Site Mix Mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 2.100 90,000.00 189,000.00
Tukang Oh 0.350 125,000.00 43,750.00
Kepala Tukang Oh 0.035 150,000.00 5,250.00
Mandor Oh 0.105 125,000.00 13,125.00
Jumlah Tenaga Kerja 251,125.00
B Bahan
Semen Portland Kg 448.000 1,200.00 537,600.00
Pasir Beton Kg 667.000 92.86 61,935.71
Kerikil ( Maks 30 mm ) Kg 1000.000 174.07 174,074.07
Air Ltr 215.000 60.00 12,900.00
Jumlah Harga Bahan 786,509.79
C Peralatan -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 1,037,634.79
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 1,037,634.79
A.4.2.1.4. Pembuatan 1 m² pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 1.050 90,000.00 94,500.00
Tukang Oh 1.050 125,000.00 131,250.00
Kepala Tukang Oh 0.105 150,000.00 15,750.00
Mandor Oh 0.052 125,000.00 6,500.00
Jumlah Tenaga Kerja 248,000.00
B Bahan
Besi siku L 30.30.4 Kg 15.000 9,200.28 138,004.25
Besi plat baja Kg 32.800 191,840.28 6,292,361.11
Kawat las Kg 0.050 114,750.00 5,737.50
Jumlah Harga Bahan 6,436,102.86
C Peralatan
0.000 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 6,684,102.86
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 6,684,102.86
A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja Oh 0.040 90,000.00 3,600.00
Tukang Oh 0.020 125,000.00 2,500.00
Kepala Tukang Oh 0.002 150,000.00 300.00
Mandor Oh 0.002 125,000.00 250.00
Jumlah Tenaga Kerja 6,650.00
B Bahan
Kawat las listrik Kg 0.400 114,750.00 45,900.00
Solar Ltr 0.300 5,150.00 1,545.00
Minyak pelumas Ltr 0.040 44,000.00 1,760.00
Jumlah Harga Bahan 49,205.00
C Peralatan
Sewa alat Jam 0.170 64,285.71 10,928.57
Jumlah Harga Peralatan 10,928.57
D Jumlah (A+B+C) 55,855.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 55,855.00
G Untuk 1 Cm Pekerjaan Pengelasan Harga Satuan Pekerjaan F/10 5,585.50
Pemasangan 1 m² Rangka Atap Baja Ringan, Jarak Kuda2 ± 120 Cm, jarak reng ± 35 Cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja OH 0.450 90,000.00 40,500.00
Tukang OH 0.225 125,000.00 28,125.00
Kepala Tukang OH 0.023 150,000.00 3,375.00
Mandor OH 0.002 125,000.00 281.25
Jumlah Tenaga Kerja 72,281.25
B Bahan
C Truss 75 . 40 . 8 . 1 mm Btg 0.659 112,700.00 74,311.56
V Reng 32 . 45 . 5 . 0.6 mm Btg 0.458 45,600.00 20,876.25
Screw Truss Bh 13.225 170.00 2,248.25
Screw Reng Bh 6.241 120.00 748.88
Valley Gutter Lbr 0.011 193,800.00 2,094.98
Dynabolt Bh 0.609 2,120.00 1,291.88
Bracket L Bh 0.700 21,250.00 14,875.00
Jumlah Harga Bahan 116,446.79
C Peralatan
0.000 0.00 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 188,728.04
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 188,728.04
1 m³ Pasang Konstruksi Kuda-Kuda Kayu Kelas II
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja OH 4.000 90,000.00 360,000.00
Tukang OH 12.000 125,000.00 1,500,000.00
Kepala Tukang OH 1.200 150,000.00 180,000.00
Mandor OH 0.200 125,000.00 25,000.00
Jumlah Tenaga Kerja 2,065,000.00
B Bahan
Kayu Kelas II M3 1.100 2,000,000.00 2,200,000.00
Paku Biasa Kg 0.800 17,000.00 13,600.00
Besi Strip Kg 15.000 19,880.00 298,200.00
Jumlah Harga Bahan 2,511,800.00
C Peralatan
0.000 0.00 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 4,576,800.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 4,576,800.00
A.4.6.1.2. Pembuatan Dan Pemasangan 1 m³ Kusen Pintu Dan Kusen Jendela, Kayu Kelas II
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja OH 6.000 90,000.00 540,000.00
Tukang OH 18.000 125,000.00 2,250,000.00
Kepala Tukang OH 1.800 150,000.00 270,000.00
Mandor OH 0.300 125,000.00 37,500.00
Jumlah Tenaga Kerja 3,097,500.00
B Bahan
Kayu Klas II M3 1.200 2,000,000.00 2,400,000.00
Paku 10 cm Kg 1.250 17,000.00 21,250.00
Lem Kayu Kg 1.000 35,100.00 35,100.00
Jumlah Harga Bahan 2,456,350.00
C Peralatan
0.000 0.00 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 5,553,850.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 5,553,850.00
A.4.6.1.5. Pembuatan Dan Pemasangan 1 m² Daun Pintu Panel, Kayu Kelas I Atau II
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja OH 1.000 90,000.00 90,000.00
Tukang OH 3.000 125,000.00 375,000.00
Kepala Tukang OH 0.300 150,000.00 45,000.00
Mandor OH 0.050 125,000.00 6,250.00
Jumlah Tenaga Kerja 516,250.00
B Bahan
Papan Kayu Klas II M3 0.040 2,000,000.00 80,000.00
Lem Kayu Kg 0.500 35,100.00 17,550.00
Jumlah Harga Bahan 97,550.00
C Peralatan
0.000 0.00 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 613,800.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 613,800.00
A.4.6.1.7. Pembuatan Dan Pemasangan 1 m² Pintu Dan Jendela Jalusi, Kayu Kelas I Atau II
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja OH 1.000 90,000.00 90,000.00
Tukang OH 3.000 125,000.00 375,000.00
Kepala Tukang OH 0.300 150,000.00 45,000.00
Mandor OH 0.050 125,000.00 6,250.00
Jumlah Tenaga Kerja 516,250.00
B Bahan
Papan Kayu Klas II M3 0.064 2,000,000.00 128,000.00
Lem Kayu Kg 0.500 35,100.00 17,550.00
Jumlah Harga Bahan 145,550.00
C Peralatan
0.000 0.00 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 661,800.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 661,800.00
A.4.7.1.4. Pengecatan 1 m² Bidang Kayu Baru (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja OH 0.070 90,000.00 6,300.00
Tukang OH 0.009 125,000.00 1,125.00
Kepala Tukang OH 0.006 150,000.00 900.00
Mandor OH 0.030 125,000.00 3,750.00
Jumlah Tenaga Kerja 12,075.00
B Bahan
Cat Menie Kg 0.200 29,900.00 5,980.00
Plamur Kg 0.150 30,600.00 4,590.00
Cat Dasar Kg 0.170 73,400.00 12,478.00
Cat Penutup Kg 0.260 73,400.00 19,084.00
Kuas Bh 0.010 9,180.00 91.80
Pengencer Kg 0.030 36,430.00 1,092.90
Ampelas Lbr 0.200 4,590.00 918.00
Jumlah Harga Bahan 44,234.70
C Peralatan
0.000 0.00 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 56,309.70
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 56,309.70
A.4.7.1.10. Pengecatan 1 m² Dinding Dalan (Interior) Baru - (1 Lapis Plamuur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja OH 0.020 90,000.00 1,800.00
Tukang OH 0.063 125,000.00 7,875.00
Kepala Tukang OH 0.006 150,000.00 945.00
Mandor OH 0.003 125,000.00 375.00
Jumlah Tenaga Kerja 10,995.00
B Bahan
Plamur Kg 0.100 7,220.00 722.00
Cat Dasar Kg 0.100 29,750.00 2,975.00
Cat Penutup Kg 0.260 29,750.00 7,735.00
Jumlah Harga Bahan 11,432.00
C Peralatan
0.000 0.00 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 22,427.00
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 22,427.00
A.4.7.1.10. Pengecatan 1 m² Dinding Luar (Exterior) Baru - (1 Lapis Plamuur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A Tenaga
Pekerja OH 0.020 90,000.00 1,800.00
Tukang OH 0.063 125,000.00 7,875.00
Kepala Tukang OH 0.006 150,000.00 945.00
Mandor OH 0.003 125,000.00 375.00
Jumlah Tenaga Kerja 10,995.00
B Bahan
Plamur Kg 0.100 7,220.00 722.00
Cat Dasar Kg 0.100 40,370.00 4,037.00
Cat Penutup Kg 0.260 40,370.00 10,496.20
Jumlah Harga Bahan 15,255.20
C Peralatan
0.000 0.00 -
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 26,250.20
E Overhead & Profit 0% x D -
F Harga Satuan Pekerjaan (D+E) 26,250.20
B. BAHAN
1 Batu Kali M3 Rp. 200,000.00
2 Batu Gunung M3 Rp. 210,000.00
3 Batu Karang M3 Rp. 127,500.00
4 Batu Belah 20/25 M3 Rp. 136,630.00
5 Batu Pecah 1/2 (Craser) M3 Rp. 235,000.00 174.07 / Kg
6 Batu Pecah 1/3 (Craser) M3 Rp. 235,000.00 174.07 / Kg
7 Batu Pecah 3/5 (Craser) M3 Rp. 235,000.00 174.07 / Kg
8 Batu Pecah 1/2 (Manual) M3 Rp. 235,000.00 174.07 / Kg
9 Batu Pecah 2/3 (Manual) M3 Rp. 235,000.00 174.07 / Kg
10 Batu Pecah 3/5 (Manual) M3 Rp. 235,000.00 174.07 / Kg
11 Batu Pecah 5/7 (Manual) M3 Rp. 235,000.00 174.07 / Kg
12 Kerikil Sungai Ayakan M3 Rp. 202,800.00 150.22 / Kg
13 Batako Lokal (10x15x35) Bh Rp. 2,120.00
14 Batu Bata Ukuran 5 x 11 x 23 Bh Rp. 1,000.00
15 Batu Sikat Hitam Ktg Rp. 212,500.00
16 Batu Andesit Sisir M2 Rp. 229,500.00
17 Batu Koral M2 Rp. 97,750.00
18 Pasir Pasang M3 Rp. 130,000.00 92.86 / Kg
19 Pasir Beton M3 Rp. 130,000.00 92.86 / Kg
20 Pasir Plesteran M3 Rp. 130,000.00
21 Pasir Urug M3 Rp. 130,000.00
22 Tasirtu M3 Rp. 135,000.00
23 Tanah Urug M3 Rp. 115,000.00
24 Tanah Taman M3 Rp. 127,500.00
25 Rumput Gajah Mini M2 Rp. 75,000.00
26 Glass Block 20x20 Bh Rp. 22,500.00
27 Roster 25x25 Bh Rp. 15,600.00
28 Roster 20x40 Bh Rp. 19,500.00
29 Paving Block 5 Cm Bh Rp. 1,600.00
30 Paving Block 9 Cm Bh Rp. 19,500.00
31 Cansteen Beton 20x40 Bh Rp. 17,210.00
32 Cansteen Beton 40x50 Bh Rp. 43,030.00
33 Cansteen Beton 60x45 Bh Rp. 63,110.00
34 Air Kerja Ltr Rp. 60.00
35 Semen Portland ( 50 Kg / Zak ) Zak Rp. 60,000.00 1,200.00 / Kg
36 Semen Warna Kg Rp. 20,400.00
37 Cornis ( 20 Kg / Zak ) Zak Rp. 75,990.00 3,799.50 / Kg
NO URAIAN SATUAN HARGA KETERANGAN
C. SEWA PERALATAN
1 Dump Truck Hari Rp. 500,000.00 71,428.57 / Jam
2 Welding (min.5 jam) Hari Rp. 450,000.00 64,285.71 / Jam
3 Concret Mixer Hari Rp. 350,000.00
4 Concret Pump Standart Hari Rp. 3,500,000.00 500,000.00 / Jam
5 Concret Pump Long Boom Hari Rp. 4,500,000.00 642,857.14 / Jam
6 Concret Vibrator Hari Rp. 250,000.00 35,714.29 / Jam
7 Stamper Hari Rp. 250,000.00
8 Compresor Hari Rp. 200,000.00 28,571.43 / Jam
9 Mesin Bor Hari Rp. 250,000.00 35,714.29 / Jam
10 Rangkaian Pipa GIP Hari Rp. 150,000.00 21,428.57 / Jam
11 Vibrator Ls Rp. 20,000.00
12 Pompa Pengecoran Ls Rp. 15,000.00
13 Alat Bantu Ls Rp. 20,000.00
KELAS A5
Enter the amont
28,080,000.00 8
ratus trilyun
In words
bu rupiah
8 7 6 5 4 3 2 1
2.00 8.00 - 8.00 - - - -
puluh juta ratus puluh ribu ribu ratus puluh rupiah
puluh juta puluh ribu rupiah
#REF! #REF! M3
D. Pekerjaan Plafond
1 Pek. Rangka Plafond Hollow 162.55 162.55 M2
2 Pek. Plafond Kalsiboard 162.55 162.55 M2
3 Pek. Lis Plafond 76.94 76.94 M1
E. Pekerjaan Cat
1 Cat Dinding 992.30 992.30 M2
2 Cat Plafond 162.55 M2
#REF! #REF! 64.983 64.98 M2
JENDELA
PINTU
F. Pekerjaan Peralatan Sanitair
J1 J2
9.3 7.46
NAMA PEKERJAAN :
LOKASI :
TH. ANGGARAN :
LOKASI :
TH. ANGGARAN :
A B C
Dimensi Beton / M¹
No. Uraian Pekerjaan
h b L P
1 Sloof S-1
15 x 20 0.15 0.20 0.03 33.33
0.15 0.20 0.03 33.33
2 Kolom K-1
15 x 25 0.25 0.25 0.06 16.00
0.25 0.25 0.06 16.00
3 Kolom K-P
12 x 12 0.12 0.12 0.01 69.44
0.12 0.12 0.01 69.44
4 Balok BL-1
15 x 20 0.12 0.15 0.02 55.56
0.12 0.15 0.02 55.56
4 Balok Latei
15 x 20 0.15 1.00 0.15 6.67
0.15 0.20 0.03 33.33
5 Plat Beton
0.15 0.20 0.03 33.33
0.15 0.20 0.03 33.33
4 Balok Latei
15 x 20 0.15 0.20 0.03 33.33
0.15 0.20 0.03 33.33
3 Kolom K-1
30 x 30 0.40 0.40 0.16 6.25
Besi Ulir 0.40 0.40 0.16 6.25
4 Kolom Praktis
12 x 12 0.12 0.12 0.01 69.44
0.12 0.12 0.01 69.44
6 Sloof S-1
25 x 35 0.25 0.35 0.09 11.43
0.25 0.35 0.09 11.43
7 Sloof S-2
12 x 20 0.12 0.20 0.02 41.67
0.12 0.20 0.02 41.67
8 Balok B-1
25 x 35 0.25 0.35 0.09 11.43
0.25 0.35 0.09 11.43
9 Balok B-2
15 x 30 0.15 0.30 0.05 22.22
0.15 0.30 0.05 22.22
10 Balok B-3
10 x 50 0.10 0.50 0.05 20.00
0.10 0.50 0.05 20.00
11 Balok Latei 1
12 x 20 0.12 0.20 0.02 41.67
0.12 0.20 0.02 41.67
11 Ringbalok
12 x 20 0.12 0.20 0.02 41.67
0.12 0.20 0.02 41.67
1 Kolom K-1
30 x 30 0.30 0.30 0.09 11.11
Besi Ulir 0.30 0.30 0.09 11.11
2 Kolom Praktis
12 x 12 0.12 0.12 0.01 69.44
0.12 0.12 0.01 69.44
3 Balok B-1
25 x 35 0.25 0.35 0.09 11.43
0.25 0.35 0.09 11.43
3 Balok Latei 1
15 x 20 0.12 0.20 0.02 41.67
0.12 0.20 0.02 41.67
4 Ring Balk
12 x 12 0.12 0.12 0.01 69.44
0.12 0.12 0.01 69.44
9 Balok B-2
15 x 30 0.15 0.30 0.05 22.22
0.15 0.30 0.05 22.22
6 Plat Lantai
T : 12 Cm Lapis Atas 0.12 1.00 0.12 8.33
Lapis Bawah 0.12 1.00 0.12 8.33
Luas
Berat Berat Besi / Total
Bekisting / Jenis Besi Besi Begel / M¹ Jml Besi Pjg Besi
Besi / M M³ Beton
M³
M² Ø (Kg) Jarak M¹ Jumlah Batang M¹ Kg M3
Beton
11.67 10.00 0.617 4.000 133.33 82.200 0.113
8.00 0.395 0.150 6.67 4.000 133.33 52.608
134.808
Beton
16.00 12.00 0.888 4.000 64.00 56.817 #REF!
8.00 0.395 0.150 6.67 6.000 96.00 37.878
94.694
Beton
33.33 12.00 0.888 4.000 277.78 246.600 0.072
8.00 0.395 0.150 6.67 2.533 175.93 69.413
316.013
Beton
15.00 12.00 0.888 4.000 222.22 197.280 0.072
8.00 0.395 0.150 6.67 2.933 162.96 64.299
261.579
Beton
7.67 12.00 0.888 4.000 26.67 23.674 #REF!
8.00 0.395 0.150 6.67 4.000 133.33 52.608
76.282
Beton
11.67 12.00 0.888 4.000 133.33 118.368 #REF!
6.00 0.222 0.150 6.67 4.000 133.33 29.592
147.960
Beton
11.67 12.00 0.888 4.000 133.33 118.368 #REF!
8.00 0.395 0.150 6.67 4.000 133.33 52.608
170.976
Luas
Berat Berat Besi / Total
Bekisting / Jenis Besi Besi Begel / M¹ Jml Besi Pjg Besi
Besi / M M³ Beton
M³
M² Ø (Kg) Jarak M¹ Jumlah Batang M¹ Kg M3
Beton
2.19 16.00 1.578 0.15 20.51 29.33 46.30 0.423
16.00 1.578 0.15 8.67 15.60 24.62
16.00 1.578 0.15 20.51 29.33 46.30
16.00 1.578 0.15 8.67 15.60 24.62
16.00 1.578 0.15 0.45 10 4.50 7.10
148.93
Beton
13.33 16.00 1.578 8.000 88.89 140.288 2.025
8.00 0.395 0.100 10.00 11.000 122.22 48.224
188.512
Beton
10.00 16.00 1.578 8.000 50.00 78.912 7.857
8.00 0.395 0.100 10.00 15.000 93.75 36.990
115.902
Beton
33.33 12.00 0.888 4.000 277.78 246.600 0.582
8.00 0.395 0.150 6.67 2.533 175.93 69.413
316.013
Beton
6.86 14.00 1.208 8.000 91.43 110.477 4.659
8.00 0.395 0.100 10.00 11.000 125.71 49.602
160.079
Beton
13.33 12.00 0.888 4.000 166.67 147.960 0.160
8.00 0.395 0.100 10.00 5.400 225.00 88.776
236.736
Beton
10.86 14.00 1.208 8.000 91.43 110.477 4.659
8.00 0.395 0.100 10.00 11.000 125.71 49.602
160.079
Beton
16.67 14.00 1.208 6.000 133.33 161.112 0.840
8.00 0.395 0.080 12.50 10.000 222.22 87.680
248.792
Beton
22.00 12.00 0.888 5.000 100.00 88.776 0.414
8.00 0.395 0.100 10.00 11.000 220.00 86.803
175.579
Beton
21.67 12.00 0.888 4.000 166.67 147.960 0.366
8.00 0.395 0.100 10.00 5.400 225.00 88.776
236.736
Beton
21.67 12.00 0.888 4.000 166.67 147.960 1.184
8.00 0.395 0.100 10.00 5.400 225.00 88.776
236.736
Beton
8.33 10.00 0.617 0.15 6.67 7.667 63.89 39.388 1.486
10.00 0.617 0.15 13.33 14.333 119.44 73.638
113.025
16.67 12.00 0.888 6.000 133.33 118.368 0.254
8.00 0.395 0.150 6.67 5.333 118.52 46.763
165.131
8.33 10.00 0.617 0.15 6.67 7.667 63.89 39.388 3.650
10.00 0.617 0.15 13.33 14.333 119.44 73.638
113.025
5.390
Beton
13.33 16.00 1.578 8.000 88.89 140.288 6.480
8.00 0.395 0.100 10.00 11.000 122.22 48.224
188.512
Beton
33.33 12.00 0.888 4.000 277.78 246.600 0.288
8.00 0.395 0.150 6.67 2.533 175.93 69.413
316.013
Beton
10.86 14.00 1.208 8.000 91.43 110.477 4.659
8.00 0.395 0.100 10.00 11.000 125.71 49.602
160.079
Beton
21.67 12.00 0.888 4.000 166.67 147.960 0.461
8.00 0.395 0.100 10.00 5.400 225.00 88.776
236.736
Beton
25.00 12.00 0.888 6.000 416.67 369.900 0.374
8.00 0.395 0.100 10.00 3.800 263.89 104.120
474.020
Beton
16.67 14.00 1.208 6.000 133.33 161.112 0.401
8.00 0.395 0.080 12.50 10.000 222.22 87.680
248.792
Beton
8.33 10.00 0.617 0.15 6.67 7.667 63.89 39.388 5.256
10.00 0.617 0.15 13.33 14.333 119.44 73.638
113.025
Beton
10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 2.180
10.00 0.617 0.15 13.33 14.333 143.33 88.365
135.630
Total
Total Besi
Bekisting
M2 Kg
Bakesting Besi
1.316 15.206
Bakesting Besi
#REF! #REF!
Bakesting Besi
2.400 22.753
Bakesting Besi
1.080 18.834
Bakesting Besi
#REF! #REF!
Bakesting Besi
#REF! #REF!
Bakesting Besi
#REF! #REF!
Total
Total Besi
Bekisting
M2 Kg
Bakesting Besi
0.925 62.924
Bakesting Besi
27.000 381.737
Bakesting Besi
78.570 910.642
Bakesting Besi
19.392 183.844
Bakesting Besi
31.950 745.866
Bakesting Besi
2.128 37.783
Bakesting Besi
50.588 745.866
Bakesting Besi
14.003 209.023
Bakesting Besi
9.097 72.602
Bakesting Besi
7.940 86.759
Bakesting Besi
25.662 280.390
Bakesting Besi
12.383 167.955
4.230 41.910
30.417 412.541
47.030 622.407
Bakesting Besi
86.400 1,221.558
Bakesting Besi
9.600 91.012
Bakesting Besi
50.588 745.866
Bakesting Besi
9.984 109.088
Bakesting Besi
9.360 177.473
Bakesting Besi
6.683 99.753
Bakesting Besi
43.800 594.059
Bakesting Besi
21.800 295.673
ENGINEERING ESTIMATE
RINCIAN KUSEN ALUMUNIUM
1 Unit Kusen + Pintu Jendela Aluminium (PJ2)
Harga Jumlah
No Uraian Satuan Koefisien Satuan Harga
(Rp) (Rp)
1 Tenaga + Bahan
Kusen Aluminium M1 19.050 75,636.50 1,440,875.33
Slimar Pintu Aluminium M1 11.140 48,001.50 534,736.71
Kaca Bening 5mm M2 4.770 223,245.00 1,064,878.65
Sealent M1 26.960 10,866.50 292,960.84
Handel Pintu 30cm Set 4.000 189,562.50 758,250.00
Floor Hinges + Patch Fitting Set 1.000 542,312.50 542,312.50
Kunci Pintu Frameles Ex. Dekson Set 2.000 387,275.00 774,550.00
Harga Satuan Pekerjaan 5,408,564.03
2 #REF! 0.22 0.22 0.05 20.66 18.18 10.00 0.617 6.000 123.97 76.426
0.22 0.22 0.05 20.66 - - - -
0.22 0.22 0.05 20.66 6.00 0.222 0.150 6.67 5.200 107.44 23.845
100.270
Beton #REF! 23.845 #REF! #REF!
Besi #REF! 76.426 #REF! #REF!
#REF!
3 Kolom (KP) 11 x 11 cm 0.11 0.11 0.01 82.64 18.18 10.00 0.617 4.000 330.58 203.802
0.11 0.11 0.01 82.64 - - 4.000 330.58 -
0.11 0.11 0.01 82.64 6.00 0.222 0.250 4.00 1.360 112.40 24.945
228.747
Beton #REF! 24.945 #REF! #REF!
Besi #REF! 203.802 #REF! #REF!
#REF!
4 #REF! 0.11 0.11 0.01 82.64 7.44 10.00 0.617 4.000 330.58 203.802
0.11 0.11 0.01 82.64 - - - - -
0.11 0.11 0.01 82.64 6.00 0.222 0.150 6.67 2.267 187.33 41.576
245.377
Beton #REF! 41.576 #REF! #REF!
Besi #REF! 203.802 #REF! #REF!
#REF!
5 Ring Balok 12 x 20 cm 0.12 0.20 0.02 41.67 16.67 10.00 0.617 4.000 166.67 102.750
0.12 0.20 0.02 41.67 - - - - -
0.12 0.20 0.02 41.67 - - - - -
0.12 0.20 0.02 41.67 6.00 0.222 0.150 6.67 3.600 150.00 33.291
136.041
Beton #REF! 33.291 #REF! #REF!
Besi #REF! 102.750 #REF! #REF!
#REF!
6 Ring Balok 11 x 25 cm 0.11 0.25 0.03 36.36 18.18 10.00 0.617 5.000 181.82 112.091
0.11 0.25 0.03 36.36 10.00 0.617 1.000 36.36 22.418
0.11 0.25 0.03 36.36 - - - - -
0.11 0.25 0.03 36.36 6.00 0.222 0.150 6.67 4.133 150.30 33.358
167.867
Beton #REF! 33.358 #REF! #REF!
Besi #REF! 134.509 #REF! #REF!
#REF!
7 Plat Dak T = 10 cm (Elv. + 7,07 mtr) 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 10.00 11.000 110.00 67.815
0.10 1.00 0.10 10.00 10.00 0.617 0.15 13.33 14.333 143.33 88.365
156.180
Beton #REF! - #REF! #REF!
Besi #REF! 156.180 #REF! #REF!
#REF!
8 Plat Meja Beton 7cm 0.07 1.00 0.07 14.29 14.29 10.00 0.617 0.15 6.67 7.667 109.52 67.521
67.521
Beton #REF! - #REF! #REF!
Besi #REF! 67.521 #REF! #REF!
#REF!
3 Pedestal Kolom 30 x 30 cm 0.30 0.30 0.09 11.11 13.33 16.00 1.578 8.000 88.89 140.288 4.356
0.30 0.30 0.09 11.11 - - 8.000 88.89 - 751.137
0.30 0.30 0.09 11.11 8.00 0.395 0.150 6.67 7.333 81.48 32.149 58.080
172.437
4 Pedestal Tangga 15 x 143 cm 0.15 2.03 0.30 3.28 14.32 10.00 0.617 14.000 45.98 28.345 0.163
0.15 2.03 0.30 3.28 - - 8.000 26.27 - 13.994
0.15 2.03 0.30 3.28 10.00 0.617 0.150 6.67 28.400 93.27 57.500 2.334
85.844
5 Balok Sloof 20 x 30 (Type SL 1) 0.20 0.30 0.06 16.67 10.00 14.00 1.208 5.000 83.33 100.695 4.320
0.20 0.30 0.06 16.67 12.00 0.888 2.000 33.33 29.592 733.290
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456 43.200
169.743
6 Balok Sloof 20 x 30 (Type SL 2) 0.20 0.30 0.06 16.67 10.00 14.00 1.208 5.000 83.33 100.695 0.540
0.20 0.30 0.06 16.67 12.00 0.888 2.000 33.33 29.592 91.661
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456 5.400
169.743
7 Balok Sloof 15 x 20 (Type SL 3) 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 0.360
0.15 0.20 0.03 33.33 12.00 0.888 - - - 61.551
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 4.800
170.976
8 Kolom 30 x 30 cm 0.30 0.30 0.09 11.11 13.33 16.00 1.578 8.000 88.89 140.288 8.712
0.30 0.30 0.09 11.11 - - 8.000 88.89 - 1,502.274
0.30 0.30 0.09 11.11 8.00 0.395 0.150 6.67 7.333 81.48 32.149 116.160
172.437
9 Kolom Praktis 11 x 11 cm 0.11 0.11 0.01 82.64 18.18 10.00 0.617 4.000 330.58 203.802 0.127
0.11 0.11 0.01 82.64 - - 8.000 661.16 - 31.175
0.11 0.11 0.01 82.64 6.00 0.222 0.150 6.67 2.267 187.33 41.576 2.310
245.377
10 Balok 15 x 30 cm (Balok Bordes Elv. 4,00 m) 0.15 0.30 0.05 22.22 16.67 12.00 0.888 4.000 88.89 78.912 0.360
0.15 0.30 0.05 22.22 12.00 0.888 2.000 44.44 39.456 59.447
0.15 0.30 0.05 22.22 8.00 0.395 0.150 6.67 5.333 118.52 46.763 6.000
165.131
11 Balok 20 x 40 cm (Elv. 4,00 m) 0.20 0.40 0.08 12.50 12.50 16.00 1.578 5.000 62.50 98.640 8.640
0.20 0.40 0.08 12.50 12.00 0.888 4.000 50.00 44.388 1,548.253
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168 108.000
179.196
12 Balok 30 x 70 cm (Elv. 4,00 m) 0.30 0.70 0.21 4.76 8.10 16.00 1.578 8.000 38.10 60.123 7.560
0.30 0.70 0.21 4.76 19.00 2.226 2.000 9.52 21.196 1,243.900
0.30 0.70 0.21 4.76 14.00 1.208 8.000 38.10 46.032 61.200
0.30 0.70 0.21 4.76 10.00 0.617 0.150 6.67 12.667 60.32 37.186
164.537
13 Plat Lantai Tangga T = 12 cm (Elv. 0,00 s/d 4,00 m) 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513 2.082
0.12 1.00 0.12 8.33 10.00 0.617 0.15 13.33 14.333 119.44 73.638 270.908
130.150 17.346
14 Plat Lantai II T = 12 cm (Elv. 4,00 m) 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513 19.631
0.12 1.00 0.12 8.33 10.00 0.617 0.15 13.33 14.333 119.44 73.638 2,554.949
130.150 163.590
15 Kolom 30 x 30 cm 0.30 0.30 0.09 11.11 13.33 16.00 1.578 8.000 88.89 140.288 5.940
0.30 0.30 0.09 11.11 - - 8.000 88.89 - 1,024.278
0.30 0.30 0.09 11.11 8.00 0.395 0.150 6.67 7.333 81.48 32.149 79.200
172.437
16 Kolom Praktis 11 x 11 cm 0.11 0.11 0.01 82.64 18.18 10.00 0.617 4.000 330.58 203.802 0.459
0.11 0.11 0.01 82.64 - - 8.000 661.16 - 112.587
0.11 0.11 0.01 82.64 6.00 0.222 0.150 6.67 2.267 187.33 41.576 8.342
245.377
17 Ring Balok 15 x 20 cm 0.15 0.20 0.03 33.33 13.33 10.00 0.617 4.000 133.33 82.200 2.248
0.15 0.20 0.03 33.33 - - 4.000 133.33 - 302.994
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 29.968
134.808
18 Ring Balok Ampik 15 x 15 cm 0.15 0.15 0.02 44.44 13.33 10.00 0.617 4.000 177.78 109.600 0.475
0.15 0.15 0.02 44.44 - - 4.000 177.78 - 79.859
0.15 0.15 0.02 44.44 8.00 0.395 0.150 6.67 3.333 148.15 58.453 6.336
168.053
16 Kolom / Balok Beton Septiktank 12/12 0.12 0.12 0.01 69.44 16.67 10.00 0.617 4.000 277.78 171.250 0.459
0.12 0.12 0.01 69.44 - - 8.000 555.56 - 96.490
0.12 0.12 0.01 69.44 6.00 0.222 0.150 6.67 2.533 175.93 39.045 7.647
210.295
27 Plat Beton Septiktank T= 10 Cm 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 -
0.10 1.00 0.10 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 -
94.530 -
4 Pedestal Kolom (Type B) 25 x 40 cm 0.25 0.40 0.10 10.00 13.00 16.00 1.578 8.000 80.00 126.259 5.412
0.25 0.40 0.10 10.00 - - 8.000 80.00 - Berat Besi
0.25 0.40 0.10 10.00 8.00 0.395 0.150 6.67 8.000 80.00 31.565 70.356
157.824
5 Balok Sloof 20 x 30 (Type SL 1) 0.20 0.40 0.08 12.50 10.00 16.00 1.578 6.000 75.00 118.368 13.406
0.20 0.40 0.08 12.50 12.00 0.888 4.000 50.00 44.388 2,789.247
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168 134.064
198.924
13.406 36.168 484.883
14.158 162.756 2,304.365
2,789.247
6 Balok Sloof 20 x 30 (Type SL 2) 0.20 0.40 0.08 12.50 10.00 16.00 1.578 6.000 75.00 118.368 5.240
0.20 0.40 0.08 12.50 12.00 0.888 4.000 50.00 44.388 1,081.423
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168 52.400
198.924
5.240 36.168 189.520
5.480 162.756 891.903
1,081.423
7 Balok Sloof 15 x 20 (Type SL 3) 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 1.082
0.15 0.20 0.03 33.33 - - 4.000 133.33 - 194.550
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 14.424
170.976
1.082 52.608 56.911
1.163 118.368 137.638
194.550
8 Balok Sloof 15 x 15 (Type SL 4) 0.15 0.15 0.02 44.44 13.33 10.00 0.617 4.000 177.78 109.600 0.265
0.15 0.15 0.02 44.44 - - 4.000 177.78 - 39.582
0.15 0.15 0.02 44.44 6.00 0.222 0.150 6.67 3.333 148.15 32.880 3.531
142.480
0.265 32.880 8.707
0.282 109.600 30.874
39.582
9 Kolom 30 x 30 cm 0.15 0.20 0.03 33.33 18.33 12.00 0.888 4.000 133.33 118.368 0.516
0.15 0.20 0.03 33.33 - - - - - 88.224
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 9.460
170.976
10 Kolom Praktis 11 x 11 cm 0.15 0.15 0.02 44.44 13.33 10.00 0.617 4.000 177.78 109.600 1.798
0.15 0.15 0.02 44.44 - - - - - 256.111
0.15 0.15 0.02 44.44 6.00 0.222 0.150 6.67 3.333 148.15 32.880 23.967
142.480
8 Balok Sloof 15 x 15 (Type SL 4) 0.30 0.70 0.21 4.76 6.67 19.00 2.226 2.000 9.52 21.196 -
0.30 0.70 0.21 4.76 16.00 1.578 8.000 38.10 60.123 -
0.30 0.70 0.21 4.76 14.00 1.208 8.000 38.10 46.032 -
0.30 0.70 0.21 4.76 10.00 0.617 0.150 6.67 12.667 60.32 37.186 -
164.537
A. 10,285.983
Poor
1 Plat
Poor Plat 120 x 120 cm 1.20 1.20 1.44 0.69 0.96 12.00 0.888 20.000 13.89 12.330 4.675
1.20 1.20 1.44 0.69 4.52 14.00 1.208 20.000 13.89 16.783 1,141.571
29.113 20.350
Perbuah Poor Plat 120 x 120
Jenis Besi Berat Besi / Panjang Pot Jml Panjang Total Berat Besi
12.00 0.888 1.26 18.000 22.680 20.13
0.213 14.00 1.208 1.46 18.000 26.280 31.76
1.000 51.890 22.000 1,141.571
4.706 244.186
2 Poor Plat Tangga 75 x 203 cm 0.60 1.10 0.66 1.52 0.48 16.00 1.578 20.000 30.30 47.825 0.234
0.60 1.10 0.66 1.52 6.15 16.00 1.578 20.000 30.30 47.825 403.147
95.651 1.305
Perbuah Poor Plat 125 x 125
Jenis Besi Berat Besi / Panjang Pot Jml Panjang Total Berat Besi
12.00 0.888 3.39 20.000 67.800 60.19
0.078 14.00 1.208 3.07 20.000 61.400 74.19
1.000 134.382 3.000
12.821 1,722.849
3 #REF! 0.70 1.10 0.77 1.30 0.56 16.00 1.578 20.000 25.97 40.993 0.118
0.70 1.10 0.77 1.30 4.74 16.00 1.578 20.000 25.97 40.993 49.164
81.986 0.540
Perbuah Poor Plat 75 x 105
Jenis Besi Berat Besi / Panjang Pot Jml Panjang Total Berat Besi
12.00 0.888 2.01 13.000 26.130 23.20
0.118 12.00 0.888 1.95 15.000 29.250 25.97
1.000 49.164 1.000
8.466 416.204
D.
Kolom
1 Pedestal Kolom 30 x 30 cm 0.25 0.25 0.06 16.00 16.00 14.00 1.208 8.000 128.00 154.668 5.412
0.25 0.25 0.06 16.00 - - 8.000 128.00 - 204.994
0.25 0.25 0.06 16.00 8.00 0.395 0.150 6.67 6.000 96.00 37.878 86.592
192.545
5.412 37.878 204.994
- 154.668 -
204.994
1 Balok Sloof 20 x 40 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 5.444
0.15 0.20 0.03 33.33 - - - - - 998.710
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 72.580
170.976
5.444 52.608 286.372
6.018 118.368 712.339
998.710
2 Balok Sloof 20 x 30 0.20 0.30 0.06 16.67 10.00 16.00 1.578 5.000 83.33 131.520 4.692
0.20 0.30 0.06 16.67 10.00 0.617 2.000 33.33 20.550 1,017.255
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456 46.920
191.526
4.692 39.456 185.128
5.472 152.070 832.127
1,017.255
3 Kolom (K1) 15 x 20 cm 0.15 0.20 0.03 33.33 23.33 10.00 0.617 6.000 200.00 123.300 3.132
0.15 0.20 0.03 33.33 - - - - - 1,934.091
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 73.080
175.908
3.132 52.608 164.768
3.672 123.300 452.758
617.526
4 Kolom (K2) 25 x 25 cm 0.25 0.25 0.06 16.00 16.00 14.00 1.208 8.000 128.00 154.668 4.744
0.25 0.25 0.06 16.00 - - - - - 913.387
0.25 0.25 0.06 16.00 8.00 0.395 0.150 6.67 6.000 96.00 37.878 75.900
192.545
5 Kolom (K3) 25 x 60 cm 0.25 0.60 0.15 6.67 11.33 14.00 1.208 12.000 80.00 96.667 3.105
0.25 0.60 0.15 6.67 - - - - - 387.271
0.25 0.60 0.15 6.67 8.00 0.395 0.150 6.67 10.667 71.11 28.058 35.190
124.725
6 Kolom (K4) 15 x 25 cm 0.15 0.25 0.04 26.67 21.33 12.00 0.888 6.000 160.00 142.042 0.236
0.15 0.25 0.04 26.67 - - - - - 13.185
0.15 0.25 0.04 26.67 8.00 0.395 0.150 6.67 4.667 124.44 49.101 5.040
191.142
0.236 49.101 11.600
0.311 142.042 44.210
55.811
9 Ring Balok 15 x 20 cm (Elv. 300 & 400 cm) 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 5.647
0.15 0.20 0.03 33.33 - - - - - 1,029.119
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 75.292
170.976
5.647 52.608 297.072
6.185 118.368 732.047
1,029.119
10 #REF! 0.25 0.25 0.06 16.00 16.00 14.00 1.208 8.000 128.00 154.668 4.744
0.25 0.25 0.06 16.00 - - - - - 913.387
0.25 0.25 0.06 16.00 8.00 0.395 0.150 6.67 6.000 96.00 37.878 75.900
192.545
11 #REF! 0.25 0.60 0.15 6.67 11.33 14.00 1.208 12.000 80.00 96.667 3.105
0.25 0.60 0.15 6.67 - - - - - 387.271
0.25 0.60 0.15 6.67 8.00 0.395 0.150 6.67 10.667 71.11 28.058 35.190
124.725
12 Kolom (K4) 15 x 25 cm 0.15 0.25 0.04 26.67 21.33 12.00 0.888 6.000 160.00 142.042 0.188
0.15 0.25 0.04 26.67 - - - - - 35.839
0.15 0.25 0.04 26.67 8.00 0.395 0.150 6.67 4.667 124.44 49.101 4.000
191.142
13 #REF! 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513 2.962
0.12 1.00 0.12 8.33 12.00 0.888 0.15 13.33 14.333 119.44 106.038 602.932
162.551 24.680
2.962
3.709 162.551 602.932
14 #REF! 0.20 0.40 0.08 12.50 12.50 14.00 1.208 6.000 75.00 90.626 3.744
0.20 0.40 0.08 12.50 16.00 1.578 2.000 25.00 39.456 747.070
0.20 0.40 0.08 12.50 10.00 0.617 2.000 25.00 15.413 46.800
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168
181.662
3.744 36.168 135.413
4.204 145.494 611.657
747.070
16 #REF! 0.12 0.30 0.04 27.78 20.00 14.00 1.208 4.000 111.11 134.260 0.702
0.12 0.30 0.04 27.78 - - 2.000 55.56 - 146.707
0.12 0.30 0.04 27.78 - - 2.000 55.56 - 14.040
0.12 0.30 0.04 27.78 8.00 0.395 0.150 6.67 4.933 137.04 54.069
188.329
0.702 54.069 37.957
0.810 134.260 108.751
146.707
17 #REF! 0.12 0.20 0.02 41.67 21.67 12.00 0.888 4.000 166.67 147.960 0.564
0.12 0.20 0.02 41.67 - - 2.000 83.33 - 133.420
0.12 0.20 0.02 41.67 - - 2.000 83.33 - 12.210
0.12 0.20 0.02 41.67 8.00 0.395 0.150 6.67 3.600 150.00 59.184
207.144
0.564 59.184 33.351
0.676 147.960 100.068
133.420
18 #REF! 0.20 0.40 0.08 12.50 12.50 14.00 1.208 6.000 75.00 90.626 4.032
0.20 0.40 0.08 12.50 16.00 1.578 2.000 25.00 39.456 802.298
0.20 0.40 0.08 12.50 10.00 0.617 2.000 25.00 15.413 50.400
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168
181.662
4.032 36.168 145.829
4.512 145.494 656.469
802.298
19 #REF! 0.15 0.20 0.03 33.33 18.33 12.00 0.888 5.000 166.67 147.960 0.426
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 100.534
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 7.810
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
200.568
0.426 52.608 22.411
0.528 147.960 78.123
100.534
21 #REF! 0.12 0.30 0.04 27.78 20.00 14.00 1.208 4.000 111.11 134.260 0.702
0.12 0.30 0.04 27.78 - - 2.000 55.56 - 146.707
0.12 0.30 0.04 27.78 - - 2.000 55.56 - 14.040
0.12 0.30 0.04 27.78 8.00 0.395 0.150 6.67 4.933 137.04 54.069
188.329
0.702 54.069 37.957
0.810 134.260 108.751
146.707
22 #REF! 0.12 0.20 0.02 41.67 21.67 12.00 0.888 4.000 166.67 147.960 0.564
0.12 0.20 0.02 41.67 - - 2.000 83.33 - 133.420
0.12 0.20 0.02 41.67 - - 2.000 83.33 - 12.210
0.12 0.20 0.02 41.67 8.00 0.395 0.150 6.67 3.600 150.00 59.184
207.144
0.564 59.184 33.351
0.676 147.960 100.068
133.420
23 #REF! 0.15 0.20 0.03 33.33 11.67 12.00 0.888 4.000 133.33 118.368 0.844
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 164.831
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 9.842
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
170.976
0.844 52.608 44.380
1.018 118.368 120.451
164.831
24 #REF! 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 1.161
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 218.034
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 15.480
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
170.976
1.161 52.608 61.078
1.326 118.368 156.956
218.034
26 #REF! 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 1.567
0.10 1.00 0.10 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 214.394
94.530 15.670
1.567
2.268 94.530 214.394
27 #REF! 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 2.234
0.10 1.00 0.10 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 211.180
94.530 22.340
2.234
2.234 94.530 211.180
28 Kolom Praktis 0.12 0.12 0.01 69.44 16.67 10.00 0.617 4.000 277.78 171.250
0.12 0.12 0.01 69.44 - - - - -
0.12 0.12 0.01 69.44 6.00 0.222 0.150 6.67 2.533 175.93 39.045
210.295
29 Kolom 12/37 0.12 0.37 0.04 22.52 22.07 10.00 0.617 6.000 135.14 83.311
0.12 0.37 0.04 22.52 - - - - -
0.12 0.37 0.04 22.52 6.00 0.222 0.150 6.67 5.867 132.13 29.325
112.636
30 Balok Sloof 20 x 40 0.15 0.20 0.03 33.33 13.33 10.00 0.617 4.000 133.33 82.200
0.15 0.20 0.03 33.33 - - - - -
0.15 0.20 0.03 33.33 6.00 0.222 0.150 6.67 4.000 133.33 29.592
111.792
31 Balok Latai 12/12 0.12 0.12 0.01 69.44 16.67 10.00 0.617 4.000 277.78 171.250
0.12 0.12 0.01 69.44 6.00 0.222 0.150 6.67 2.533 175.93 39.045
210.295
32 Balok Latai 12/15 0.12 0.15 0.02 55.56 23.33 10.00 0.617 4.000 222.22 137.000
0.12 0.15 0.02 55.56 6.00 0.222 0.150 6.67 2.933 162.96 36.168
173.168
33 Ring Balok Latai 15/25 0.15 0.25 0.04 26.67 17.33 12.00 0.888 6.000 160.00 142.042
0.15 0.25 0.04 26.67 8.00 0.395 0.150 6.67 4.667 124.44 49.101
191.142
27 Plat 7 cm 0.07 1.00 0.07 14.29 14.29 10.00 0.617 0.15 6.67 7.667 109.52 67.521 -
0.07 1.00 0.07 14.29 10.00 0.617 0.15 6.67 7.667 109.52 67.521 66.667
135.043 -
30 #REF! 0.15 0.20 0.03 33.33 13.33 10.00 0.617 4.000 133.33 82.200
0.15 0.20 0.03 33.33 - - - - -
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
134.808
29 #REF! 0.15 0.20 0.03 33.33 23.33 10.00 0.617 4.000 133.33 82.200
0.15 0.20 0.03 33.33 - - - - -
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
134.808
33 Ring Balok12/20 0.12 0.20 0.02 41.67 21.67 10.00 0.617 5.000 208.33 128.438
0.12 0.20 0.02 41.67 8.00 0.395 0.150 6.67 3.600 150.00 59.184
187.622
33 Ring Balok15/15 0.15 0.15 0.02 44.44 13.33 10.00 0.617 4.000 177.78 109.600
0.15 0.15 0.02 44.44 8.00 0.395 0.150 6.67 3.333 148.15 58.453
168.053
8 Kolom 30 x 30 cm 0.12 0.12 0.01 69.44 16.67 10.00 0.617 4.000 277.78 171.250 8.712
0.12 0.12 0.01 69.44 - - 8.000 555.56 - 1,747.050
0.12 0.12 0.01 69.44 6.00 0.222 0.200 5.00 1.900 131.94 29.284 145.200
200.534
RHITUNGAN KONVERSI BESI
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Besi
Bakesting
Beton 21.120
Besi
Bakesting
Beton 1.440
Besi
Bakesting
Beton 0.560
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
ENGINEERING ESTIMATE
DAFTAR KUANTITAS DAN HARGA
SATUAN KERJA : POLITEKNIK KESEHATAN PALU
PEKERJAAN : PERENCANAAN PEMBANGUNAN GEDUNG KELAS JURUSAN GIZI POLITEKNIK KESEHATAN PALU
KEGIATAN : DUKUNGAN MANAJEMEN DAN PELAKSANAAN TUGAS TEKNIS LAINNYA PADA PROGRAM KESEHATAN
PENGEMBANGAN DAN PEMBERDAYAAN SUMBER DAYA MANUSIA
LOKASI : JL. THALUA KONCI NO.19 MAMBORO
SUMBER DANA : APBN
TH. ANGGARAN : 2017
10 Pengujian Sumur (Pumping Test) Termasuk Recovery 24.000 Jam #REF! #REF!
11 Pengadaan dan Pemasangan Pompa Submersible Depth 70m 1.000 Unit 4,250,000.00 4,250,000.00
Single-Phase :220V 50Hz
RPM n=2850 r/min
Jumlah Section 4.1.1.A #REF!
B. Pekerjaan Ground Reservoar (1 Unit)
1 Galian Tanah 16.817 M3 86,625.00 1,456,755.30
2 Urugan Pasir 5 cm 0.462 M3 184,250.00 85,123.50
3 Lantai Reservoar T = 12 cm
• Lantai Kerja T = 5 cm Beton K.100 0.375 M3 668,699.65 250,762.37
• Beton Site Mix K.200 0.312 M3 880,098.94 274,150.82
• Pembesian 29.541 Kg 16,405.00 484,613.95
4 Sloof 12 x 20 cm
• Beton Site Mix K.200 0.289 M3 880,098.94 254,735.84
• Pembesian 57.163 Kg 16,405.00 937,764.11
5 Kolom 12 x 12 cm
• Beton Site Mix K.200 0.159 M3 880,098.94 139,914.61
• Pembesian 31.880 Kg 16,405.00 522,992.28
6 Ring Balok 12 x 20 cm
• Beton Site Mix K.200 0.289 M3 880,098.94 254,735.84
• Pembesian 57.163 Kg 16,405.00 937,764.11
• Bekisting Balok 2 x Pakai 0.524 M2 141,807.50 74,307.13
7 Dinding Beton T = 12 cm
• Beton Site Mix K.200 1.788 M3 880,098.94 1,573,194.46
• Pembesian 191.329 Kg 16,405.00 3,138,747.65
• Bekisting Batako 20.240 M2 #REF! #REF!
• Bekisting Dinding 2 x Pakai 14.896 M2 138,807.50 2,067,676.52
8 Plat Penutup Beton T = 10 cm
• Beton Site Mix K.200 0.583 M3 880,098.94 513,097.68
• Pembesian 66.549 Kg 16,405.00 1,091,738.31
• Bekisting Plat 2 x Pakai 5.830 M2 149,087.50 869,180.13
9 Water Proofing Coating 2 Lapis (Pelapis Anti Bocor) 22.495 M2 #REF! #REF!
10 Plesteran 1 Pc : 2 Ps (Lantai dan Dinding Sisi Dalam) 22.495 M2 64,743.80 1,456,398.83
11 Acian Semen (Lantai dan Dinding Sisi Dalam) 22.495 M2 37,150.00 835,681.82
12 Pipa Peluap PVC 2" 0.300 M1 84,483.50 25,345.05
13 Pipa Kuras PVC 1" 2.500 M1 52,286.00 130,715.00
14 Box Kontrol Plat Besi 60 x 60 cm 1.000 Ls 250,000.00 250,000.00
14 Tangga Panjat Besi Beton Ø12 5.549 M1 16,405.00 91,023.14
15 Cat Dinding dan Plat Reservoar (Sisi Luar) 4.499 M2 26,250.20 118,098.60
Jumlah Section 4.1.1.A #REF!
C. Pekerjaan Plumbing
C.1 Pekerjaan Plumbing Air Bersih
1 PVC 1" (Jaringan Transmisi Dari Ground Reservoar Ke Pompa Air 78.341 M1 52,286.00 4,096,111.38
Pada Plat Dak )
2 PVC 1" (Jaringan Distribusi Dari Roof Tank Ke Pipa Bagi PVC ¾) 37.044 M1 52,286.00 1,936,882.58
3 PVC ¾" (Jaringan Distribusi Dari PVC 1" Ke Kran Air) 13.200 M1 24,728.50 326,416.20
Jumlah Section 4.1.1.C.1 6,359,410.17
C.2 Pekerjaan Plumbing Air Kotor
1 PVC 3" (Jaringan Pembuangan Dari Closed Ke Septiktank) 13.829 M1 133,326.50 1,843,705.51
2 PVC 2" (Jaringan Pembuangan Dari Floor Drain Ke Sal. Air Hujan) 19.299 M1 84,483.50 1,630,447.07
3 PVC 2" (Jaringan Pembuangan Dari Dak Beton Ke Sal. Air Hujan) 41.712 M1 84,483.50 3,523,975.75
Jumlah Section 4.1.1.C.2 6,998,128.32
C.3 Pekerjaan Saluran Air Hujan
1 Saluran Air Hujan 150,10 m1 (Lihat Gambar Detail)
• Galian Tanah 17.399 M3 70,625.00 1,228,818.99
• Urugan Tanah Kembali Bekas Galian 4.350 M3 23,541.67 102,401.58
• Urugan Pasir 5 Cm 3.002 M3 184,250.00 553,118.50
• Lantai Saluran Beton K.100 3.002 M3 668,699.65 2,007,436.35
• Dinding 1/2 Bata Trasram 1 Pc : 3 Psr 93.956 M2 135,319.00 12,714,065.79
• Plesteran Dinding Trasram 1 Pc : 3 Psr 87.693 M2 62,177.00 5,452,456.57
• Acian 87.693 M2 37,150.00 3,257,776.38
A B C
A B C
JUMLAH HARGA
(Rp)
F
250,000.00
6,990,637.50
4,563,091.50
3,500,000.00
5,000,000.00
20,303,729.00
12,583,008.90
1,048,584.08
782,694.00
815,232.21
67,936.02
50,364.74
72,115.31
6,009.61
25,564.69
10,007,082.25
833,923.52
1,906,176.80
90,298,590.20
8,388,349.75
126,885,632.07
17,397,893.16
5,681,272.23
19,461,577.05
36,020,114.86
11,386,410.00
365,578.10
1,252,312.17
3,704,884.63
1,018,826.38
92,782.08
508,529.91
2,029,063.62
334,516.00
8,851,169.22
33,389,715.95
JUMLAH HARGA
(Rp)
F
16,601,377.00
4,204,305.38
13,750,198.63
7,885,654.08
811,357.18
3,714,720.52
2,726,456.92
539,041.70
1,605,502.60
2,354,175.20
17,676,581.18
83,555,038.40
6,136,960.22
2,232,651.72
1,333,982.20
306,622,648.29
15,152,816.88
57,680,565.38
14,001,060.94
240,698.37
891,686.98
331,199.70
16,086,037.98
28,863,472.47
38,990,471.52
7,640,868.04
19,855,812.58
14,331,319.15
1,474,553.48
4,823,204.94
4,955,039.09
209,648.78
958,982.93
644,955.17
#REF!
49,791,661.46
38,816,399.75
#REF!
1,431,772.46
1,981,050.78
#REF!
1,814,896.28
2,085,421.10
#REF!
1,435,649.37
1,756,144.08
#REF!
25,314,094.20
JUMLAH HARGA
(Rp)
F
20,786,937.47
#REF!
15,625,338.68
15,365,636.75
1,314,449.77
5,150,067.74
4,081,829.62
91,776.72
441,299.61
318,159.31
#REF!
878,514.56
629,625.30
#REF!
1,908,937.38
1,461,184.48
128,204.51
468,776.47
360,758.28
1,241,623.99
4,915,531.14
3,760,734.90
#REF!
125,257,553.22
120,367,284.00
#REF!
7,583,913.38
6,798,390.00
#REF!
10,585,879.10
#REF!
3,281,713.01
8,168,323.76
14,014,225.00
3,042,958.60
1,746,050.00
3,445,175.60
5,976,646.96
14,014,225.00
3,042,958.60
1,746,050.00
722,753.86
1,798,965.21
2,940,005.50
638,373.87
366,299.00
#REF!
14,384,337.10
JUMLAH HARGA
(Rp)
F
29,778,133.42
30,248,930.40
2,740,628.10
7,129,310.10
5,763,287.40
600,227.48
2,044,010.29
1,721,213.00
387,243.53
1,033,915.02
1,110,460.00
156,833.63
422,056.11
449,736.30
424,856.42
1,943,393.45
1,307,011.42
801,594.12
2,923,477.25
1,722,110.28
1,267,022.97
5,126,706.57
4,681,951.87
1,072,858.21
4,390,791.34
3,143,021.43
62,927.07
266,050.53
184,349.75
59,178.46
224,358.70
179,244.68
4,101,291.91
11,623,776.66
12,422,337.00
606,766.47
2,296,404.66
1,837,825.20
1,270,651.40
4,785,476.56
3,848,655.55
5,248,029.99
17,512,178.37
8,890,087.63
#REF!
3,860,672.79
2,215,254.50
2,106,317.29
JUMLAH HARGA
(Rp)
F
3,933,142.35
4,611,276.38
2,002,525.73
1,149,049.50
74,909.44
139,878.97
163,996.25
71,218.18
40,865.00
#REF!
134,622,779.55
81,922,647.35
9,828,926.44
5,686,870.00
#REF!
#REF!
58,457,156.45
8,790,322.24
53,349,078.89
2,667,455.48
16,631,931.66
1,405,691.40
51,632,606.77
85,319.12
289,992.99
387,627.50
193,697,182.51
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
14,155,484.33
19,915,000.36
68,305,404.32
102,375,889.00
#REF!
750,000.00
#REF!
#REF!
JUMLAH HARGA
(Rp)
F
#REF!
#REF!
137,287.50
7,500,000.00
900,000.00
#REF!
70,941,373.84
64,742,405.88
16,508,995.19
55,810,014.06
208,002,788.97
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
11,312,313.36
26,194,612.58
88,927,018.60
1,184,330.27
127,618,274.81
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
4,080,821.60
#REF!
500,000.00
250,000.00
#REF!
#REF!
1,801,040.00
4,705,224.00
1,568,408.00
#REF!
38,250.00
#REF!
1,000,000.00
JUMLAH HARGA
(Rp)
F
#REF!
4,250,000.00
#REF!
1,456,755.30
85,123.50
250,762.37
274,150.82
484,613.95
254,735.84
937,764.11
139,914.61
522,992.28
254,735.84
937,764.11
74,307.13
1,573,194.46
3,138,747.65
#REF!
2,067,676.52
513,097.68
1,091,738.31
869,180.13
#REF!
1,456,398.83
835,681.82
25,345.05
130,715.00
250,000.00
91,023.14
118,098.60
#REF!
4,096,111.38
1,936,882.58
326,416.20
6,359,410.17
1,843,705.51
1,630,447.07
3,523,975.75
6,998,128.32
1,228,818.99
102,401.58
553,118.50
2,007,436.35
12,714,065.79
5,452,456.57
3,257,776.38
JUMLAH HARGA
(Rp)
F
3,136,177.39
5,420,078.15
#REF!
80,088.75
6,674.06
799,464.65
471,799.08
281,894.20
136,891.44
#REF!
1,646,127.50
137,177.29
1,440,832.00
141,394.20
18,375.00
938,481.00
3,056,044.30
#REF!
#REF!
221,339.58
1,074,418.56
641,952.00
50,000.00
#REF!
12,801,800.00
3,500,000.00
2,376,000.00
#REF!
#REF!
#REF!
487,500.00
988,000.00
208,000.00
351,000.00
9,750,000.00
4,095,000.00
#REF!
4,687,500.00
#REF!
#REF!
#REF!
#REF!
#REF!
585,000.00
988,000.00
104,000.00
JUMLAH HARGA
(Rp)
F
380,250.00
11,310,000.00
4,914,000.00
#REF!
4,687,500.00
#REF!
ATAN PALU
RAM KESEHATAN
AH HARGA
20,303,729.00
126,885,632.07
306,622,648.29
#REF!
#REF!
#REF!
193,697,182.51
#REF!
#REF!
#REF!
102,375,889.00
#REF!
208,002,788.97
#REF!
#REF!
#REF!
127,618,274.81
#REF!
#REF!
#REF!
6,359,410.17
6,998,128.32
#REF!
AH HARGA
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
7
na
SE
IAI
BACK UP VOLUME
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PERENCANAAN GEDUNG KANTOR LURAH KULANGO
LOKASI : JL. U. HANGGI NO. 99 KEL. KULANGO
TH. ANGGARAN : 2016
Dimensi Jumlah
No Uraian Pekerjaan
(Bh)
• Bekisting Balok
• Bekisting Balok
9 Balok (BLK 3) 25 x 35 cm (Elv. ± 3,95 mtr) Dimensi Panjang Jumlah
• Beton Ready Mix K.250 Khusus Beton 0.088 7.740 1.000
• Pembesian Khusus Pembesian 0.088 8.560 1.000
• Bekisting Balok
10 Balok (BLK 4) 20 x 30 cm (Elv. ± 2,56 mtr) Dimensi Panjang Jumlah
• Beton Ready Mix K.250 Khusus Beton 0.060 7.740 1.000
• Pembesian Khusus Pembesian 0.060 8.180 1.000
• Bekisting Balok
11 Balok (BLK 4) 20 x 30 cm (Elv. ± 4,00 mtr) Dimensi Panjang Jumlah
• Beton Ready Mix K.250 Khusus Beton 0.060 130.880 1.000
• Pembesian Khusus Pembesian 0.060 145.800 1.000
• Bekisting Balok
12 Balok (BLK 5) 20 x 25 cm (Elv. ± 3,95 mtr) Dimensi Panjang Jumlah
• Beton Ready Mix K.250 Khusus Beton 0.050 93.410 1.000
• Pembesian Khusus Pembesian 0.050 114.378 1.000
• Bekisting Balok
13 Balok (BLK 6) 11 x 25 cm (Elv. ± 2,89 mtr) Dimensi Panjang Jumlah
• Beton Site Mix K.200 Khusus Beton 0.028 54.310 1.000
• Pembesian Khusus Pembesian 0.028 61.201 1.000
• Bekisting Plat
20 Plat Lantai Bordes T = 12 cm (Elv. + 2,56 mtr) Tebal Area Jumlah
• Beton Ready Mix K.250 Khusus Beton 0.120 5.760 2.000
Khusus Beton 0.120 2.820 4.000
• Bekisting Plat
21 Plat Tangga Area Samping Lebar
• Beton Ready Mix K.250 Trap 1 0.870 1.850 2.000
• Pembesian Trap 2 0.470 1.850 2.000
• Bekisting Tangga
22 Plat Sunscren Depan & Sudut T = 8 cm (Elv. + 2,67 mtr) Tebal Area
• Beton Site Mix K.250 Trap 1 0.080 44.77
• Pembesian
• Bekisting Plat
• Plesteran 1 Pc : 2 Ps
• Acian Semen
23 Plat Sunscren Belakang T = 8 cm (Elv. + 2,67 mtr) Tebal Area
• Beton Site Mix K.250 Trap 1 0.080 47.00
• Pembesian
• Bekisting Plat
• Plesteran 1 Pc : 2 Ps
• Acian Semen
24 Plat Sunscren Samping T = 8 cm (Elv. + 2,97 mtr) Tebal Area
• Beton Site Mix K.250 Trap 1 0.080 9.86
• Pembesian
• Bekisting Plat
• Plesteran 1 Pc : 2 Ps
• Acian Semen
• Plesteran 1 Pc : 2 Ps
• Acian Semen
18 Plat Sunscren Samping T = 8 cm (Elv. + 6,50 mtr) Tebal Area Jumlah
• Beton Site Mix K.175 Khusus Beton 0.080 1.100 1.000
• Pembesian
• Bekisting Plat 2 x Pakai
Khusus Pembesian 0.080 1.100 1.000
• Plesteran 1 Pc : 2 Ps
• Acian Semen
Versi II
Luas Datar Derajat
Rangka Atap 617.750 0.866
Atap 632.750 0.866
Lisplang 150.390
Nok 70.000
Jurai Dalam 7.500
Bangunan Timur
Km/Wc 1.930 2.560 1.000
Km/Wc 1.780 2.560 2.000
Depan Lap 1 2.700 2.790 4.000
Depan Lap 2 2.700 0.940 4.000
Samping Kiri 3.180 3.630 2.000
Tengah 3.180 3.630 2.000
Km/Wc 1.550 2.560 2.000
Km/Wc 1.550 2.560 2.000
Samping Kiri 3.180 3.630 1.000
Tangga Lap.1 3.580 1.000 1.000
Tangga Lap.2 1.420 1.000 1.000
Atas Teras Dpn 2.700 0.840 4.000
Atas Teras Dpn 3.650 0.840 1.000
Atas Teras Blk 1.930 0.840 2.000
Atas Teras Sudut 3.700 0.700 1.000
Belakang Lap 1 2.700 2.790 12.000
Belakang Lap 2 2.700 0.940 12.000
Belakang Lap 1 1.780 2.560 2.000
Belakang Lap 2 1.780 0.890 2.000
Bangunan Barat
2 Dinding 1/2 Bata Trasram 1 Pc : 3 Psr (Area Km/Wc) Panjang Tinggi Jml KM/WC
1.780 2.000 1.000 2.000
1.780 2.000 1.000 2.000
1.930 2.000 1.000 2.000
1.000 2.000 1.000 2.000
1.930 2.000 1.000 2.000
3.180 2.000 1.000 2.000
0.770 2.000 1.000 2.000
0.770 2.000 1.000 2.000
1.550 2.000 1.000 2.000
1.550 2.000 1.000 2.000
Total Ukuran
Kusen
1:3
1:5
E. Pekerjaan Cat
1 Cat Dinding Dalam / Interior
Dd Dlam Panjang Tinggi
Kelas 1 37.890 3.420
Kelas 2 37.890 3.420
Kelas 3 37.890 3.420
Kelas 4 37.890 3.420
Area Jumlah
Buangan Pintu 3.800 4.000
Buangan Jendela 2.520 26.000
Bangunan Timur
Depan Atas Realing 3.650 1.100 1.000
Sudut 3.740 1.100 1.000
Sudut Ats Tangga 3.700 0.700 1.000
Sudut Ats Tangga 1.630 0.700 1.000
Depan Lap 1 2.700 2.750 4.000
Depan Lap 2 2.700 0.730 4.000
Balkon Bwh Relling 2.700 0.760 4.000
Balkon Bwh Relling 3.650 0.760 1.000
Tangga Bwh Relling 2.040 0.760 1.000
Balkon Samp Relling 1.740 0.760 2.000
Samping 1.630 0.370 1.000
Vertikal 3.230 3.830 6.000
E. Pekerjaan Cat
1 Cat Dinding Dalam / Interior Dd Dlam Panjang Tinggi
Kelas 1 37.890 3.600
Kelas 2 37.890 3.600
Kelas 3 37.890 3.600
Kelas 4 37.890 3.600
Cat Dinding Dalam (Kotor)
Area Jumlah
Buangan Pintu 3.800 4.000
Buangan Jendela 2.520 26.000
Buangan Kusen
Cat Dinding Dalam (Bersih)
Plat Lantai 10 38.410 1.000 1.000
Plat Sunscren Samping T = 8 cm (Elv. + 6,50 mtr) 1.100 1.000 1.000
Cat Dinding Dalam + Plat Bawah
F. Pekerjaan Khusus
1 Railing Pipa Stainless Steel Ø 2,½" (Lihat Gambar Detail) Panjang Jumlah Vol
• Railing Tangga (Type RT) Panjang Pipa 9.480 1.000 9.480
0.175 10.000 1.750 Aval
11.230 20% 2.246
Las Dia Jml
0.230 16.000 3.680 100.000
0.250
Kg Dia
0.230 0.001 11.230 0.003 7,850.000
2 Aliminium Composite Panel (ACP) - (Lihat Gambar Detail) Panjang Jumlah Vol
3 Tangga Panjat (Lihat Gambar Detail) Sisi Kika 4.730 2.000 9.460
Tempel 0.175 10.000 1.750
Tempel 0.360 11.000 3.960 Aval
15.170 15% 2.276
~ Underlayer / Foam
~ Parquet (Laminated Flooring)
~ Skriting Profile / Plin (1,2 x 10 x 240 cm) 13.050
~ Staircase Nosing 1.150 4.000 1.000
~ Finishing HPL
C. Pekerjaan Plumbing
C.1 Pekerjaan Plumbing Air Bersih
1 PVC 1" (Jaringan Transmisi Dari Ground Reservoar Ke Pompa Air Vol
Pada Plat Dak ) Datar Pada Tanah 31.690 22.140 53.830 Save
Panjat 10.390 10.390 20.780 0.050
74.610 3.731
2 PVC 1" (Jaringan Distribusi Dari Roof Tank Ke Pipa Bagi PVC ¾)
Vol
Turun 1 8.030 9.610 17.640 Save
Turun 2 8.030 9.610 17.640 0.050
35.280 1.764
3 PVC ¾" (Jaringan Distribusi Dari PVC 1" Ke Kran Air) Ttk
Turun 1 8.000 0.750 6.000 Save
Turun 2 8.000 0.750 6.000 0.100
12.000 1.200
C.2 Pekerjaan Plumbing Air Kotor
1 PVC 3" (Jaringan Pembuangan Dari Closed Ke Septiktank)
Vol
Closed 1 7.630 - 7.630 Save
Closed 2 5.540 - 5.540 0.050
13.170 0.659
2 PVC 2" (Jaringan Pembuangan Dari Floor Drain Ke Sal. Air Hujan)
Vol
WC 1 6.940 2.250 9.190 Save
WC 2 6.940 2.250 9.190 0.050
18.380 0.919
3 PVC 2" (Jaringan Pembuangan Dari Dak Beton Ke Sal. Air Hujan)
Vol
Dak 1 9.480 2.000 18.960 Save
Dak 2 9.480 2.000 18.960 0.100
37.920 3.792
• Acian
2 Rabat Beton Sepanjang Saluran Air Hujan
• Urugan Sirtu Dipadatkan 150.100 0.120 0.928
• Beton K. 100 T = 5 cm 150.100 1.080 0.050
3 Grill Saluran Air Hujan (Lht. Gbr. Detail) 26.110
4 Box Peresapan 7 Bh Dimensi Tinggi Jumlah
• Galian Tanah Type 1 ± 0,00 0.360 0.450 4.000
Type 3 ± 0,30 0.360 0.450 2.000
Type 4 ± 0,45 0.360 0.450 1.000
• Acian
• Urugan Kerikil 20 Cm 0.360 0.200 7.000
1.000
17.063
32.500
49.563
726.300
162.200
1.000
1.000
Volume
-
- -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Volume
-
Volume
4.248
Volume
1.828
1.343
1.242
1.289
1.289
1.250
1.172
9.411
Volume
2.353
Volume
0.273
Volume
0.833
Volume
0.208
Volume
0.139
Volume
12.640
1.123
2.160
14.220
19.625
4.590
5.220
1.575
5.220
7.140
1.000
5.580
1.540
4.140
8.800
22.000
1.040
2.320
1.160
20.600
141.693
Volume
35.423
1.792
8.554
10.346
Volume
382.143 325.69
99.129 129.58
481.272
Volume
32.569
12.958
45.527
Volume
4.121
0.295
0.145
0.145
8.366
4.121
4.121
4.121
0.295
0.145
0.145
26.018
Volume
8.496
21.240
2,195.679
70.800
Volume
0.547
1.367
225.839
6.335
Volume
0.139
0.555
123.686
2.080
Volume
9.660 -
12.810
Volume
4.589
6.085
Volume
0.886
1.174
Volume
0.588
0.588
7.296
34.214
41.510
20.480
95.040
115.520
2.345
1.643
4.841
1.927
1.066
3.431
3.160
2.828
2.317
1.625
1.107
0.702
4.841
1.107
0.702
4.841
4.108
2.761
45.352
4.841
3.431
4.841
4.841
17.954
35.908
Volume
16.538
18.572
Volume
0.293
0.329
Volume
17.556
17.556
Volume
8.339
8.339
Volume
1.609
1.609
Volume
0.256
0.256
Volume
16.954
18.686
Volume
0.384
0.487
Volume
0.677
0.749
Volume
0.464
0.491
Volume
7.853
8.748
Volume
4.671 93.410
5.719 114.38
Volume
1.494
1.683
Volume
0.104
0.150
Volume
0.244
0.284
Volume
0.567
0.724
Volume
0.140
0.177
Volume
1.459
1.637
Volume
35.328
9.180
0.361
0.620
1.692
1.260
48.442
58.666
Volume
1.382
1.354
2.736
3.552
Volume
3.219
1.739
4.958
Volume
3.582
Volume
3.760
Volume
0.789
Volume
4.464
11.880
16.344
4.464
11.880
16.344
Volume
1.674
1.440
3.114
1.674
1.440
3.114
Volume
0.682
0.682
Volume
0.440
0.440
Volume
0.178
0.178
Volume
0.194
0.150
0.174
0.518
0.194
0.150
0.174
0.518
Volume
0.911
1.009
Volume
1.488
1.675
Volume
1.219
1.422
Volume
0.072
0.098
Volume
0.070
0.100
Volume
4.818
4.818
Volume
0.713
0.802
Volume
0.835
0.658 1.493
0.934 1.670
0.736
Volume
5.224
0.739
5.963
3.841
2.994
6.835
Volume
2.474
2.474
2.474
Volume
0.088
0.088
0.088
Vol Total
169.649
441.396
611.044
Vol Total
49.550
97.410
146.960
5.120
29.000
64.160
98.280
Vol Total
713.316
730.637
150.390
70.000
7.500
Volume
30.132
10.152
9.114
3.168
4.941
9.114
30.132
10.152
23.087
23.087
7.936
7.936
11.543
3.580
1.420
9.072
3.066
3.242
2.590
90.396
30.456
9.114
3.168
4.941
9.114
90.396
30.456
23.087
23.087
23.087
7.936
7.936
11.543
3.580
1.420
27.216
3.108
2.590
606.094
15.200
3.320
6.920
65.520
1.000
0.680
92.640
7.120
7.120
7.720
4.000
7.720
12.720
3.080
3.080
6.200
6.200
64.960
606.094
92.640
64.960
448.494
896.988
42.901
90.288
14.630
3.762
33.858
4.598
103.246
29.260
279.642
3.080
1.680
0.960
0.540
10.428
4.742
0.847
0.331
22.608
147.702
11.520
11.280
41.317
38.161
4.675
9.440
9.000
22.310
1,389.841
0.104
0.150
Volume
82.410
167.310
0.858
0.948
0.705
0.615
0.668
0.758
0.848
0.938
0.405
0.405
0.405
0.405
1.503
1.593
13.600
14.076
26.300
82.410
82.410
82.410
561.978
Volume
5.900
2.900
2.900
5.900
2.900
2.900
23.400
32.723
27.148
27.148
87.019
0.260
1.300
1.560
68.000
8.420
1.287
2.920
0.760
1.000
2.000
6.000
1.000
5.840
5.050
1.460
1.000
1.000
3.000
2.920
5.080
6.220
1.050
1.000
3.000
1.000
1.000
Volume
328.800
328.800
163.360
148.400
15.480
112.040
439.280
129.584
129.584
129.584
129.584
518.335
15.200
65.520
80.720
437.615
41.317
76.500
3.010
5.170
14.100
10.500
42.969
193.565
631.180
Volume
28.296
11.556
10.175
11.880
4.015
4.114
2.590
1.141
29.700
7.884
8.208
2.774
1.550
2.645
0.603
74.225
84.888
34.668
10.175
32.670
4.070
2.915
89.100
23.652
22.572
2.014
2.812
1.550
0.603
123.709
636.755
15.200
70.560
6.720
92.480
544.275
1,088.550
27.900
13.950
2.325
2.325
2.945
11.160
83.700
9.300
5.580
2.790
28.000
87.600
277.575
95.274
38.410
1.100
1.380
136.163
1,502.288
Volume
83.610
83.610
83.610
83.610
123.220
457.660
Volume
328.800
23.500
50.290
402.590
331.480
109.670
78.050
52.700
571.900
136.404
136.404
136.404
136.404
545.616
15.200
65.520
80.720
464.896
38.410
1.100
504.406
44.088
13.476
6.000
2.246
368.000
92.000
20.276
3.990
6.000
0.665
69.000
17.250
6.003
5.430
6.000
0.905
115.000
28.750
8.170
5.610
6.000
0.935
115.000
28.750
8.441
5.850
6.000
0.975
115.000
28.750
8.802
17.446
6.000
2.908
18.339
187.000
1.669
6.720
61.840
Volume
0.268
0.013
0.014
0.020
0.022
0.337
Volume
21.670
0.690
22.360
13.050
4.600
21.291
18.233
4.558
Vol
15.610
1.091
1.532
18.233
18.233
Vol
16.817
0.462
0.375
0.312
0.375
0.289
0.324
0.159
0.159
0.289
0.324
0.524
1.788
2.429
20.240
14.896
0.583
0.704
4.471
4.471
3.661
3.661
6.230
22.495
78.341
37.044
13.200
13.829
19.299
41.712
Volume
0.653
1.003
1.411
3.620
0.280
0.840
0.515
0.684
0.950
0.315
2.428
0.599
0.627
3.476
17.399
4.350
3.002
3.002
Volume
5.344
8.213
11.550
29.625
2.288
4.500
2.756
3.619
5.025
1.669
12.844
3.169
3.356
93.956
Volume
4.988
7.665
10.780
27.650
2.135
4.200
2.573
3.378
4.690
1.558
11.988
2.958
3.133
87.693
87.693
16.715
8.105
26.110
0.648
0.324
0.162
1.134
0.284
0.252
2.100
1.750
1.750
0.308
5.908
2.730
2.275
2.275
0.308
7.588
0.504
DAFTAR PERHITUNGAN KONVERSI BESI
SATUAN KERJA : POLITEKNIK KESEHATAN PALU
PEKERJAAN : PERENCANAAN PEMBANGUNAN GEDUNG KELAS JURUSAN GIZI POLITEKNIK KESEHATAN PALU
KEGIATAN : DUKUNGAN MANAJEMEN DAN PELAKSANAAN TUGAS TEKNIS LAINNYA PADA PROGRAM KESEHATAN
PENGEMBANGAN DAN PEMBERDAYAAN SUMBER DAYA MANUSIA
LOKASI : JL. THALUA KONCI NO.19 MAMBORO
SUMBER DANA : APBN
TH. ANGGARAN : 2017
4 Poor Plat Tangga (Type D) 75 x 185 cm Poor Plat Tangga (Type D) 75 x 185 cm
Jenis Besi BB / M Pj Pot Jml Pj Total Berat Besi
14.00 1.208 4.85 6.000 29.100 35.16
14.00 1.208 1.84 12.000 22.080 26.68
0.278
1.000 61.843
3.604 222.857 Berat / M3 0.555
1.040 123.686
3.748 2.080
5 Pedestal Kolom (Type K1) 30 x 35 cm 0.30 0.35 0.11 9.52 12.38 16.00 1.578 6.000 57.14 90.185
0.30 0.35 0.11 9.52 14.00 1.208 4.000 38.10 46.032
0.30 0.35 0.11 9.52 8.00 0.395 0.150 6.67 8.000 76.19 30.062
166.279
Beton 9.660 30.062 290.396 9.660
Besi 12.810 136.217 1,744.942 2,035.338
119.600
6 Pedestal Kolom (Type K1.a) 30 x 35 cm 0.30 0.35 0.11 9.52 12.38 14.00 1.208 10.000 95.24 115.080
0.30 0.35 0.11 9.52 - - - - -
0.30 0.35 0.11 9.52 8.00 0.395 0.150 6.67 8.000 76.19 30.062
145.142
Beton 4.589 30.062 137.938 4.589
Besi 6.085 115.080 700.233 838.171
56.810
5 Pedestal Kolom (Type K3) 11 x 50 cm 0.11 0.50 0.06 18.18 22.18 14.00 1.208 4.000 72.73 87.879
0.11 0.50 0.06 18.18 12.00 0.888 4.000 72.73 64.564
0.11 0.50 0.06 18.18 8.00 0.395 0.150 6.67 7.467 135.76 53.565
206.008
Beton 0.886 53.565 47.431 0.886
Besi 1.174 152.444 179.007 226.438
19.642
5 Pedestal Tangga (Type T2) 15 x 185 cm 0.15 1.85 0.28 3.60 14.41 12.00 0.888 26.000 93.69 83.178
0.15 1.85 0.28 3.60 - - 4.000 14.41 -
0.15 1.85 0.28 3.60 12.00 0.888 0.150 6.67 26.000 93.69 83.178
166.355
Beton 0.588 83.178 48.933 0.588
Besi 0.588 83.178 48.933 97.867
8.480
6 Sloof 20 x 35 0.20 0.35 0.07 14.29 10.00 14.00 1.208 5.000 71.43 86.310
0.20 0.35 0.07 14.29 12.00 0.888 4.000 57.14 50.729
0.20 0.35 0.07 14.29 10.00 0.617 0.150 6.67 6.667 95.24 58.714
195.753
Beton 16.538 58.714 970.988 16.538
Besi 18.572 137.039 2,545.048 3,516.036
165.375
7 Sloof 15 x 20 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368
0.15 0.20 0.03 33.33 - - - - -
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
170.976
Beton 0.293 52.608 15.435 0.293
Besi 0.329 118.368 38.919 54.355
3.912
8 #REF! 0.25 0.25 0.06 16.00 16.00 10.00 0.617 8.000 128.00 78.912
0.25 0.25 0.06 16.00 - - - -
0.25 0.25 0.06 16.00 6.00 0.222 0.150 6.67 6.000 96.00 21.306
100.218
Beton 17.556 21.306 374.052 17.556
Besi 17.556 78.912 1,385.379 1,759.431
280.896
9 Kolom (K1.a) 30 x 35 cm 0.30 0.35 0.11 9.52 12.38 14.00 1.208 10.000 95.24 115.080
0.30 0.35 0.11 9.52 - - - - -
0.30 0.35 0.11 9.52 8.00 0.395 0.150 6.67 8.000 76.19 30.062
145.142
Beton 8.339 30.062 250.688 8.339
Besi 8.339 115.080 959.664 1,210.351
103.246
9 Kolom (K3) 11 x 50 cm 0.11 0.50 0.06 18.18 22.18 12.00 0.888 4.000 72.73 64.564
0.11 0.50 0.06 18.18 12.00 0.888 4.000 72.73 64.564
0.11 0.50 0.06 18.18 8.00 0.395 0.150 6.67 7.467 135.76 53.565
182.693
Beton 1.609 53.565 86.201 1.609
Besi 1.609 129.129 207.807 294.008
35.697
10 Kolom (KP) 11 x 11 cm 0.11 0.11 0.01 82.64 18.18 10.00 0.617 4.000 330.58 203.802
0.11 0.11 0.01 82.64 - - 4.000 330.58 -
0.11 0.11 0.01 82.64 6.00 0.222 0.250 4.00 1.360 112.40 24.945
228.747
Beton 0.256 24.945 6.375 0.256
Besi 0.256 203.802 52.082 58.457
4.646
11 Balok (BLK 1) 25 x 55 cm (Elv. ± 4,00 mtr) 0.25 0.55 0.14 7.27 8.07 19.00 2.226 2.000 14.55 32.372
0.25 0.55 0.14 7.27 16.00 1.578 6.000 43.64 68.869
0.25 0.55 0.14 7.27 14.00 1.208 4.000 29.09 35.152
0.25 0.55 0.14 7.27 8.00 0.395 0.150 6.67 10.000 72.73 28.695
165.087
Beton 16.954 28.695 486.492 16.954
Besi 18.686 136.392 2,548.659 3,035.152
136.863
12 Balok (BLK 2) 11 x 55 cm (Elv. ± 4,00 mtr) 0.11 0.55 0.06 16.53 18.18 14.00 1.208 1.000 16.53 19.973
0.11 0.55 0.06 16.53 12.00 0.888 8.000 132.23 117.390
0.11 0.55 0.06 16.53 - - 4.000 66.12 -
0.11 0.55 0.06 16.53 8.00 0.395 0.150 6.67 8.133 134.44 53.043
190.405
Beton 0.384 53.043 20.378 0.384
Besi 0.487 137.362 66.899 87.277
6.985
13 Balok (BLK 3) 25 x 35 cm (Elv. ± 3,95 mtr) 0.25 0.35 0.09 11.43 10.86 16.00 1.578 5.000 57.14 90.185
0.25 0.35 0.09 11.43 14.00 1.208 2.000 22.86 27.619
0.25 0.35 0.09 11.43 - - 4.000 45.71 -
0.25 0.35 0.09 11.43 8.00 0.395 0.150 6.67 7.333 83.81 33.068
150.872
Beton 0.677 33.068 22.395 0.677
Besi 0.749 117.804 88.235 110.631
7.353
14 Balok (BLK 4) 20 x 30 cm (Elv. ± 2,56 mtr) 0.20 0.30 0.06 16.67 13.33 14.00 1.208 7.000 116.67 140.973
0.20 0.30 0.06 16.67 - - 2.000 33.33 -
0.20 0.30 0.06 16.67 - - 4.000 66.67 -
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456
180.429
Beton 0.464 39.456 18.323 0.464
Besi 0.491 140.973 69.190 87.513
6.192
15 Balok (BLK 4) 20 x 30 cm (Elv. ± 4,00 mtr) 0.20 0.30 0.06 16.67 9.33 14.00 1.208 7.000 116.67 140.973
0.20 0.30 0.06 16.67 - - 2.000 33.33 -
0.20 0.30 0.06 16.67 - - 4.000 66.67 -
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456
180.429
Beton 7.853 39.456 309.840 7.853
Besi 8.748 140.973 1,233.232 1,543.072
73.293
16 Balok (BLK 5) 20 x 25 cm (Elv. ± 3,95 mtr) 0.20 0.25 0.05 20.00 11.60 14.00 1.208 4.000 80.00 96.667
0.20 0.25 0.05 20.00 12.00 0.888 2.000 40.00 35.510
0.20 0.25 0.05 20.00 - - 4.000 80.00 -
0.20 0.25 0.05 20.00 8.00 0.395 0.150 6.67 5.333 106.67 42.086
174.264
Beton 4.671 42.086 196.565 4.671
Besi 5.719 132.178 755.910 952.474
54.178
17 Balok (BLK 6) 11 x 25 cm (Elv. ± 2,89 mtr) 0.11 0.25 0.03 36.36 19.27 10.00 0.617 7.000 254.55 156.927
0.11 0.25 0.03 36.36 - - 2.000 72.73 -
0.11 0.25 0.03 36.36 - - 4.000 145.45 -
0.11 0.25 0.03 36.36 6.00 0.222 0.150 6.67 4.133 150.30 33.358
190.286
Beton 1.494 33.358 49.821 1.494
Besi 1.683 156.927 264.111 313.933
28.784
18 Balok (BLK 7) 11 x 30 cm (Elv. ± 3,20 mtr) 0.11 0.30 0.03 30.30 21.52 12.00 0.888 1.000 30.30 26.902
0.11 0.30 0.03 30.30 10.00 0.617 6.000 181.82 112.091
0.11 0.30 0.03 30.30 - - 4.000 121.21 -
0.11 0.30 0.03 30.30 8.00 0.395 0.150 6.67 4.800 145.45 57.391
196.383
Beton 0.104 57.391 5.985 0.104
Besi 0.150 138.993 20.916 26.900
2.244
19 Balok (BLK 7) 11 x 30 cm (Elv. ± 4,00 mtr) 0.11 0.30 0.03 30.30 18.18 12.00 0.888 1.000 30.30 26.902
0.11 0.30 0.03 30.30 10.00 0.617 6.000 181.82 112.091
0.11 0.30 0.03 30.30 - - 4.000 121.21 -
0.11 0.30 0.03 30.30 8.00 0.395 0.150 6.67 4.800 145.45 57.391
196.383
Beton 0.244 57.391 14.015 0.244
Besi 0.284 138.993 39.537 53.552
4.440
20 Balok (BLK 8) 11 x 20 cm (Elv. ± 2,56 mtr) 0.11 0.20 0.02 45.45 18.18 10.00 0.617 4.000 181.82 112.091
0.11 0.20 0.02 45.45 - - - - -
0.11 0.20 0.02 45.45 - - - - -
0.11 0.20 0.02 45.45 8.00 0.395 0.150 6.67 3.467 157.58 62.173
174.264
Beton 0.567 62.173 35.235 0.567
Besi 0.724 112.091 81.128 116.363
10.304
21 Balok (BLK 8) 11 x 20 cm (Elv. ± 4,00 mtr) 0.11 0.20 0.02 45.45 18.18 10.00 0.617 4.000 181.82 112.091
0.11 0.20 0.02 45.45 - - - - -
0.11 0.20 0.02 45.45 - - - - -
0.11 0.20 0.02 45.45 8.00 0.395 0.150 6.67 3.467 157.58 62.173
174.264
Beton 0.140 62.173 8.699 0.140
Besi 0.177 112.091 19.876 28.575
2.544
22 Balok (BL 1) 11 x 15 cm (Elv. ± 2,73 mtr) 0.11 0.15 0.02 60.61 18.18 10.00 0.617 4.000 242.42 149.455
0.11 0.15 0.02 60.61 - - - - -
0.11 0.15 0.02 60.61 - - - - -
0.11 0.15 0.02 60.61 6.00 0.222 0.150 6.67 2.800 169.70 37.663
187.117
Beton 1.459 37.663 54.935 1.459
Besi 1.637 149.455 244.702 299.636
26.520
23 Plat Lantai T = 12 cm (Elv. + 4,00 mtr) 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513
0.12 1.00 0.12 8.33 10.00 0.617 0.15 13.33 14.333 119.44 73.638
130.150
Beton 48.442 - - 48.442
Besi 58.666 130.150 7,635.328 7,635.328
403.680
24 Plat Lantai Bordes T = 12 cm (Elv. + 2,56 mtr) 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513
0.12 1.00 0.12 8.33 10.00 0.617 0.15 13.33 14.333 119.44 73.638
130.150
Beton 2.736 - - 2.736
Besi 3.552 130.150 462.293 462.293
22.800
26 Plat Tangga 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513
0.12 1.00 0.12 8.33 10.00 0.617 0.15 13.33 14.333 119.44 73.638
130.150
Beton 4.958 - - 4.958
Besi 4.958 130.150 645.284 645.284
41.317
27 Plat Sunscren Depan & Sudut T = 8 cm (Elv. + 2,67 mtr) 0.08 1.00 0.08 12.50 12.50 8.00 0.395 0.15 10.00 11.000 137.50 54.252
0.08 1.00 0.08 12.50 10.00 0.617 0.15 10.00 11.000 137.50 84.769
139.021
Beton 3.582 - - 3.582
Besi 3.582 139.021 497.917 497.917
44.770
28 Plat Sunscren Belakang T = 8 cm (Elv. + 2,67 mtr) 0.08 1.00 0.08 12.50 12.50 8.00 0.395 0.15 6.67 7.667 95.83 37.812
0.08 1.00 0.08 12.50 10.00 0.617 0.15 6.67 7.667 95.83 59.081
96.893
Beton 3.760 - - 3.760
Besi 3.760 96.893 364.319 364.319
47.000
29 Plat Sunscren Samping T = 8 cm (Elv. + 2,97 mtr) 0.08 1.00 0.08 12.50 12.50 8.00 0.395 0.15 10.00 11.000 137.50 54.252
0.08 1.00 0.08 12.50 10.00 0.617 0.15 10.00 11.000 137.50 84.769
139.021
Beton 0.789 - - 0.789
Besi 0.789 139.021 109.660 109.660
9.860
30 Kolom (K2) 30 x 30 cm 0.30 0.30 0.09 11.11 13.33 12.00 0.888 8.000 88.89 78.912
0.30 0.30 0.09 11.11 - - - - -
0.30 0.30 0.09 11.11 8.00 0.395 0.150 6.67 7.333 81.48 32.149
111.061
Beton 16.344 32.149 525.449 16.344
Besi 16.344 78.912 1,289.738 1,815.186
217.920
30 Kolom (K2.a) 30 x 30 cm 0.30 0.30 0.09 11.11 13.33 14.00 1.208 8.000 88.89 107.408
0.30 0.30 0.09 11.11 - - - - -
0.30 0.30 0.09 11.11 8.00 0.395 0.150 6.67 7.333 81.48 32.149
139.557
Beton 3.114 32.149 100.113 3.114
Besi 3.114 107.408 334.469 434.582
41.520
31 Kolom (K3) 11 x 50 cm 0.11 0.50 0.06 18.18 18.18 12.00 0.888 8.000 145.45 129.129
0.11 0.50 0.06 18.18 - - - - -
0.11 0.50 0.06 18.18 8.00 0.395 0.150 6.67 7.467 135.76 53.565
182.693
Beton 0.682 53.565 36.531 0.682
Besi 0.682 129.129 88.066 124.597
12.400
31 Kolom (K3.a) 11 x 50 cm 0.11 0.50 0.06 18.18 18.18 10.00 0.617 8.000 145.45 89.673
0.11 0.50 0.06 18.18 - - 4.000 72.73 -
0.11 0.50 0.06 18.18 8.00 0.395 0.150 6.67 7.467 135.76 53.565
143.237
Beton 0.440 53.565 23.568 0.440
Besi 0.440 89.673 39.456 63.024
8.000
32 Kolom (K4) 11 x 30 cm 0.11 0.30 0.03 30.30 18.18 10.00 0.617 6.000 181.82 112.091
0.11 0.30 0.03 30.30 - - 4.000 121.21 -
0.11 0.30 0.03 30.30 6.00 0.222 0.150 6.67 4.800 145.45 32.282
144.373
Beton 0.178 32.282 5.753 0.178
Besi 0.178 112.091 19.975 25.727
3.240
33 Kolom (KP) 11 x 11 cm 0.11 0.11 0.01 82.64 18.18 10.00 0.617 4.000 330.58 203.802
0.11 0.11 0.01 82.64 - - 4.000 330.58 -
0.11 0.11 0.01 82.64 6.00 0.222 0.250 4.00 1.360 112.40 24.945
228.747
Beton 0.518 24.945 12.919 0.518
Besi 0.518 203.802 105.545 118.463
9.416
36 Balok (BLK 4) 20 x 30 cm (Elv. ± 7,12 mtr) 0.20 0.30 0.06 16.67 13.33 14.00 1.208 7.000 116.67 140.973
0.20 0.30 0.06 16.67 - - 2.000 33.33 -
0.20 0.30 0.06 16.67 - - 4.000 66.67 -
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456
180.429
Beton 0.911 39.456 35.937 0.911
Besi 1.009 140.973 142.270 178.206
12.144
36 Balok (BLK 6) 11 x 25 cm (Elv. ± 6,79 mtr) 0.11 0.25 0.03 36.36 22.18 10.00 0.617 7.000 254.55 156.927
0.11 0.25 0.03 36.36 - - 2.000 72.73 -
0.11 0.25 0.03 36.36 - - 4.000 145.45 -
0.11 0.25 0.03 36.36 6.00 0.222 0.150 6.67 4.133 150.30 33.358
190.286
Beton 1.488 33.358 49.652 1.488
Besi 1.675 156.927 262.857 312.509
33.016
37 Balok (BLK 7) 11 x 30 cm (Elv. ± 7,12 mtr) 0.11 0.30 0.03 30.30 18.18 12.00 0.888 1.000 30.30 26.902
0.11 0.30 0.03 30.30 10.00 0.617 6.000 181.82 112.091
0.11 0.30 0.03 30.30 - - 4.000 121.21 -
0.11 0.30 0.03 30.30 8.00 0.395 0.150 6.67 4.800 145.45 57.391
196.383
Beton 1.219 57.391 69.960 1.219
Besi 1.422 138.993 197.689 267.650
22.164
38 Balok (BLK 8) 11 x 20 cm (Elv. ± 7,12 mtr) 0.11 0.20 0.02 45.45 18.18 - - 1.000 45.45 -
0.11 0.20 0.02 45.45 10.00 0.617 5.000 227.27 140.114
0.11 0.20 0.02 45.45 - - 4.000 181.82 -
0.11 0.20 0.02 45.45 6.00 0.222 0.150 6.67 3.467 157.58 34.972
175.086
Beton 0.072 34.972 2.501 0.072
Besi 0.098 140.114 13.717 16.218
1.300
39 Balok (BLK 8) 11 x 20 cm (Elv. ± 7,12 mtr) 0.11 0.20 0.02 45.45 18.18 - - 1.000 45.45 -
0.11 0.20 0.02 45.45 10.00 0.617 4.000 181.82 112.091
0.11 0.20 0.02 45.45 - - 4.000 181.82 -
0.11 0.20 0.02 45.45 6.00 0.222 0.150 6.67 3.467 157.58 34.972
147.063
Beton 0.070 34.972 2.431 0.070
Besi 0.100 112.091 11.245 13.676
1.264
40 Balok (RB ) 11 x 20 cm (Elv. ± 8,00 mtr) 0.11 0.20 0.02 45.45 18.18 - - 1.000 45.45 -
0.11 0.20 0.02 45.45 10.00 0.617 4.000 181.82 112.091
0.11 0.20 0.02 45.45 - - 4.000 181.82 -
0.11 0.20 0.02 45.45 6.00 0.222 0.150 6.67 3.467 157.58 34.972
147.063
Beton 4.818 34.972 168.497 4.818
Besi 4.818 112.091 540.054 708.551
87.600
41 Balok (BL 1) 11 x 15 cm (Elv. ± 6,73 mtr) 0.11 0.15 0.02 60.61 18.18 - - 1.000 60.61 -
0.11 0.15 0.02 60.61 10.00 0.617 4.000 242.42 149.455
0.11 0.15 0.02 60.61 - - 4.000 242.42 -
0.11 0.15 0.02 60.61 6.00 0.222 0.200 5.00 2.100 127.27 28.247
177.701
Beton 0.713 28.247 20.134 0.713
Besi 0.802 149.455 119.848 139.982
12.960
42 Balok dan Plat (BL 2) 11 x 15 cm (Elv. ± 6,73 mtr) 0.11 0.15 0.02 60.61 18.18 - - 1.000 60.61 -
0.11 0.15 0.02 60.61 10.00 0.617 4.000 242.42 149.455
0.11 0.15 0.02 60.61 - - 4.000 242.42 -
0.11 0.15 0.02 60.61 6.00 0.222 0.200 5.00 2.100 127.27 28.247
177.701
Beton 1.493 28.247 42.164 1.493
Besi 1.670 149.455 249.544 291.708
27.140
44 Plat Dak T = 10 cm (Elv. + 7,07 mtr) 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 10.00 11.000 110.00 67.815
0.10 1.00 0.10 10.00 10.00 0.617 0.15 13.33 14.333 143.33 88.365
156.180
Beton 5.963 - - 5.963
Besi 6.835 156.180 1,067.490 1,067.490
59.630
45 Plat Sunscren Depan & Belakang T = 8 cm (Elv. + 6,67 mtr) 0.08 1.00 0.08 12.50 12.50 10.00 0.617 0.15 6.67 7.667 95.83 59.081
0.08 1.00 0.08 12.50 8.00 0.395 0.15 6.67 7.667 95.83 37.812
96.893
Beton 2.474 - - 2.474
Besi 2.474 96.893 239.753 239.753
30.930
46 Plat Sunscren Depan & Belakang T = 8 cm (Elv. + 6,67 mtr) 0.08 1.00 0.08 12.50 12.50 10.00 0.617 0.15 6.67 7.667 95.83 59.081
0.08 1.00 0.08 12.50 8.00 0.395 0.15 6.67 7.667 95.83 37.812
96.893
Beton 0.088 - - 0.088
Besi 0.088 96.893 8.527 8.527
1.100
46 Plat Meja Beton Toilet Wanita T = 8 cm 0.08 1.00 0.08 12.50 12.50 10.00 0.617 0.15 6.67 7.667 95.83 59.081
0.08 1.00 0.08 12.50 10.00 0.617 0.15 6.67 7.667 95.83 59.081
118.163
Beton 0.104 - - 0.104
Besi 0.150 118.163 17.677 17.677
1.300
27 Lantai Reservoar T = 12 cm 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 6.67 7.667 63.89 39.388
Reservor 0.12 1.00 0.12 8.33 10.00 0.617 0.15 6.67 7.667 63.89 39.388
78.775
Beton 0.312 - - 0.312
Besi 0.375 78.775 29.541 29.541
-
7 Sloof 12 x 20 cm 0.12 0.20 0.02 41.67 6.67 10.00 0.617 6.000 250.00 154.125
Reservor 0.12 0.20 0.02 41.67 - - - - -
0.12 0.20 0.02 41.67 6.00 0.222 0.200 5.00 2.700 112.50 24.968
179.093
Beton 0.289 24.968 7.227 0.289
Besi 0.324 154.125 49.937 57.163
1.930
33 Kolom 12 x 12 cm 0.12 0.12 0.01 69.44 - 10.00 0.617 4.000 277.78 171.250
Reservor 0.12 0.12 0.01 69.44 - - - - -
0.12 0.12 0.01 69.44 6.00 0.222 0.200 5.00 1.900 131.94 29.284
200.534
Beton 0.159 29.284 4.655 0.159
Besi 0.159 171.250 27.225 31.880
-
7 Ring Balok 12 x 20 cm 0.12 0.20 0.02 41.67 6.67 10.00 0.617 6.000 250.00 154.125
Reservor 0.12 0.20 0.02 41.67 - - - - -
0.12 0.20 0.02 41.67 6.00 0.222 0.200 5.00 2.700 112.50 24.968
179.093
Beton 0.289 24.968 7.227 0.289
Besi 0.324 154.125 49.937 57.163
-
27 Dinding 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 6.67 7.667 63.89 39.388
Reservor 0.12 1.00 0.12 8.33 10.00 0.617 0.15 6.67 7.667 63.89 39.388
78.775
Beton 1.788 - - 1.788
Besi 2.429 78.775 191.329 191.329
-
46 Plat Penutup Beton T = 10 cm 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265
Reservor 0.10 1.00 0.10 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265
94.530
Beton 0.583 - - 0.583
Besi 0.704 94.530 66.549 66.549
5.830
6 Kg/Btg 6 Mtr
Besi Siku (30.30.2 mm) P = 6m 0.060 0.0020 0.00012 6.000 7,850 5.65 Kg 13,800.000 77,997.60 77,990.000
Besi Siku (40.40.3 mm) P = 6m 0.080 0.0030 0.00024 6.000 7,850 11.30 Kg 13,800.000 155,995.20 155,990.000
Besi Siku (40.40.5 mm) P = 6m 0.080 0.0050 0.0004 6.000 7,850 18.84 Kg 13,800.000 259,992.00 259,990.000
Besi Siku (50.50.4 mm) P = 6m 0.100 0.0040 0.0004 6.000 7,850 18.84 Kg 13,800.000 259,992.00 259,990.000
Besi Siku (50.50.5 mm) P = 6m 0.100 0.0050 0.0005 6.000 7,850 23.55 Kg 13,800.000 324,990.00 324,990.000
Besi □ 20.20.1,2mm P = 6 mm 0.080 0.0012 0.000096 6.000 7,850 4.52 Kg 13,800.000 62,398.08 62,390.000
Besi □ 20.40.1,2mm P = 6 mm 0.120 0.0012 0.000144 6.000 7,850 6.78 Kg 13,800.000 93,597.12 93,590.000
Besi □ 40.40.1,2mm P = 6 mm 0.160 0.0012 0.000192 6.000 7,850 9.04 Kg 13,800.000 124,796.16 124,790.000
Besi □ 40.40.1,4 mm P = 6 mm 0.160 0.0014 0.000224 6.000 7,850 10.55 Kg 13,800.000 145,595.52 145,590.000
Besi □ 20.40.1,8 mm P = 6m 0.120 0.0018 0.000216 6.000 7,850 10.17 Kg 13,800.000 140,395.68 140,390.000
Besi □ 40.40.1,8 mm P = 6m 0.160 0.0018 0.000288 6.000 7,850 13.56 Kg 13,800.000 187,194.24 187,190.000
Besi □ 50.50.1,8 mm P = 6m 0.200 0.0018 0.00036 6.000 7,850 16.96 Kg 13,800.000 233,992.80 233,990.000
Besi □ 40.60.1,8 mm P = 6m 0.120 0.0018 0.000216 6.000 7,850 10.17 Kg 13,800.000 140,395.68 140,390.000
Besi Strip 40.1,8 mm P = 3 0.040 0.0018 0.000072 3.000 7,850 1.70 Kg 13,800.000 23,399.28 23,390.000
Besi Strip 30.1,8 mm P = 3 0.030 0.0018 0.000054 3.000 7,850 1.27 Kg 13,800.000 17,549.46 17,540.000
Besi Strip 20.1,8 mm P = 3 0.020 0.0018 0.000036 3.000 7,850 0.85 Kg 13,800.000 11,699.64 11,690.000
Realing Type R5
Besi □ 20.40.1,2mm P = 6 mm 6.78 6.00 1.13
Besi □ 40.40.1,2mm P = 6 mm 9.04 6.00 1.51
3 Pedestal Kolom 30 x 30 cm 0.30 0.30 0.09 11.11 13.33 16.00 1.578 8.000 88.89 140.288 4.356
0.30 0.30 0.09 11.11 - - 8.000 88.89 - 751.137
0.30 0.30 0.09 11.11 8.00 0.395 0.150 6.67 7.333 81.48 32.149 58.080
172.437
4 Pedestal Tangga 15 x 143 cm 0.15 2.03 0.30 3.28 14.32 10.00 0.617 14.000 45.98 28.345 0.163
0.15 2.03 0.30 3.28 - - 8.000 26.27 - 13.994
0.15 2.03 0.30 3.28 10.00 0.617 0.150 6.67 28.400 93.27 57.500 2.334
85.844
5 Balok Sloof 20 x 30 (Type SL 1) 0.20 0.30 0.06 16.67 10.00 14.00 1.208 5.000 83.33 100.695 4.320
0.20 0.30 0.06 16.67 12.00 0.888 2.000 33.33 29.592 733.290
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456 43.200
169.743
6 Balok Sloof 20 x 30 (Type SL 2) 0.20 0.30 0.06 16.67 10.00 14.00 1.208 5.000 83.33 100.695 0.540
0.20 0.30 0.06 16.67 12.00 0.888 2.000 33.33 29.592 91.661
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456 5.400
169.743
7 Balok Sloof 15 x 20 (Type SL 3) 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 0.360
0.15 0.20 0.03 33.33 12.00 0.888 - - - 61.551
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 4.800
170.976
8 Kolom 30 x 30 cm 0.30 0.30 0.09 11.11 13.33 16.00 1.578 8.000 88.89 140.288 8.712
0.30 0.30 0.09 11.11 - - 8.000 88.89 - 1,502.274
0.30 0.30 0.09 11.11 8.00 0.395 0.150 6.67 7.333 81.48 32.149 116.160
172.437
9 Kolom Praktis 11 x 11 cm 0.11 0.11 0.01 82.64 18.18 10.00 0.617 4.000 330.58 203.802 0.127
0.11 0.11 0.01 82.64 - - 8.000 661.16 - 31.175
0.11 0.11 0.01 82.64 6.00 0.222 0.150 6.67 2.267 187.33 41.576 2.310
245.377
10 Balok 15 x 30 cm (Balok Bordes Elv. 4,00 m) 0.15 0.30 0.05 22.22 16.67 12.00 0.888 4.000 88.89 78.912 0.360
0.15 0.30 0.05 22.22 12.00 0.888 2.000 44.44 39.456 59.447
0.15 0.30 0.05 22.22 8.00 0.395 0.150 6.67 5.333 118.52 46.763 6.000
165.131
11 Balok 20 x 40 cm (Elv. 4,00 m) 0.20 0.40 0.08 12.50 12.50 16.00 1.578 5.000 62.50 98.640 8.640
0.20 0.40 0.08 12.50 12.00 0.888 4.000 50.00 44.388 1,548.253
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168 108.000
179.196
12 Balok 30 x 70 cm (Elv. 4,00 m) 0.30 0.70 0.21 4.76 8.10 16.00 1.578 8.000 38.10 60.123 7.560
0.30 0.70 0.21 4.76 19.00 2.226 2.000 9.52 21.196 1,243.900
0.30 0.70 0.21 4.76 14.00 1.208 8.000 38.10 46.032 61.200
0.30 0.70 0.21 4.76 10.00 0.617 0.150 6.67 12.667 60.32 37.186
164.537
13 Plat Lantai Tangga T = 12 cm (Elv. 0,00 s/d 4,00 m) 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513 2.082
0.12 1.00 0.12 8.33 10.00 0.617 0.15 13.33 14.333 119.44 73.638 270.908
130.150 17.346
14 Plat Lantai II T = 12 cm (Elv. 4,00 m) 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513 19.631
0.12 1.00 0.12 8.33 10.00 0.617 0.15 13.33 14.333 119.44 73.638 2,554.949
130.150 163.590
15 Kolom 30 x 30 cm 0.30 0.30 0.09 11.11 13.33 16.00 1.578 8.000 88.89 140.288 5.940
0.30 0.30 0.09 11.11 - - 8.000 88.89 - 1,024.278
0.30 0.30 0.09 11.11 8.00 0.395 0.150 6.67 7.333 81.48 32.149 79.200
172.437
16 Kolom Praktis 11 x 11 cm 0.11 0.11 0.01 82.64 18.18 10.00 0.617 4.000 330.58 203.802 0.459
0.11 0.11 0.01 82.64 - - 8.000 661.16 - 112.587
0.11 0.11 0.01 82.64 6.00 0.222 0.150 6.67 2.267 187.33 41.576 8.342
245.377
17 Ring Balok 15 x 20 cm 0.15 0.20 0.03 33.33 13.33 10.00 0.617 4.000 133.33 82.200 2.248
0.15 0.20 0.03 33.33 - - 4.000 133.33 - 302.994
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 29.968
134.808
18 Ring Balok Ampik 15 x 15 cm 0.15 0.15 0.02 44.44 13.33 10.00 0.617 4.000 177.78 109.600 0.475
0.15 0.15 0.02 44.44 - - 4.000 177.78 - 79.859
0.15 0.15 0.02 44.44 8.00 0.395 0.150 6.67 3.333 148.15 58.453 6.336
168.053
16 Kolom / Balok Beton Septiktank 12/12 0.12 0.12 0.01 69.44 16.67 10.00 0.617 4.000 277.78 171.250 0.459
0.12 0.12 0.01 69.44 - - 8.000 555.56 - 96.490
0.12 0.12 0.01 69.44 6.00 0.222 0.150 6.67 2.533 175.93 39.045 7.647
210.295
27 Plat Beton Septiktank T= 10 Cm 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 -
0.10 1.00 0.10 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 -
94.530 -
3 Pedestal Kolom 30 x 30 cm 0.25 0.40 0.10 10.00 13.00 16.00 1.578 8.000 80.00 126.259 5.412
0.25 0.40 0.10 10.00 - - 8.000 80.00 - Berat Besi
0.25 0.40 0.10 10.00 8.00 0.395 0.150 6.67 8.000 80.00 31.565 70.356
157.824
4 Pedestal Kolom (Type B) 25 x 40 cm 0.25 0.40 0.10 10.00 13.00 16.00 1.578 8.000 80.00 126.259 5.412
0.25 0.40 0.10 10.00 - - 8.000 80.00 - Berat Besi
0.25 0.40 0.10 10.00 8.00 0.395 0.150 6.67 8.000 80.00 31.565 70.356
157.824
5 Balok Sloof 20 x 30 (Type SL 1) 0.20 0.40 0.08 12.50 10.00 16.00 1.578 6.000 75.00 118.368 13.406
0.20 0.40 0.08 12.50 12.00 0.888 4.000 50.00 44.388 2,789.247
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168 134.064
198.924
13.406 36.168 484.883
14.158 162.756 2,304.365
2,789.247
6 Balok Sloof 20 x 30 (Type SL 2) 0.20 0.40 0.08 12.50 10.00 16.00 1.578 6.000 75.00 118.368 5.240
0.20 0.40 0.08 12.50 12.00 0.888 4.000 50.00 44.388 1,081.423
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168 52.400
198.924
5.240 36.168 189.520
5.480 162.756 891.903
1,081.423
7 Balok Sloof 15 x 20 (Type SL 3) 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 1.082
0.15 0.20 0.03 33.33 - - 4.000 133.33 - 194.550
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 14.424
170.976
1.082 52.608 56.911
1.163 118.368 137.638
194.550
8 Balok Sloof 15 x 15 (Type SL 4) 0.15 0.15 0.02 44.44 13.33 10.00 0.617 4.000 177.78 109.600 0.265
0.15 0.15 0.02 44.44 - - 4.000 177.78 - 39.582
0.15 0.15 0.02 44.44 6.00 0.222 0.150 6.67 3.333 148.15 32.880 3.531
142.480
0.265 32.880 8.707
0.282 109.600 30.874
39.582
9 Kolom 30 x 30 cm 0.15 0.20 0.03 33.33 18.33 12.00 0.888 4.000 133.33 118.368 0.516
0.15 0.20 0.03 33.33 - - - - - 88.224
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 9.460
170.976
10 Kolom Praktis 11 x 11 cm 0.15 0.15 0.02 44.44 13.33 10.00 0.617 4.000 177.78 109.600 1.798
0.15 0.15 0.02 44.44 - - - - - 256.111
0.15 0.15 0.02 44.44 6.00 0.222 0.150 6.67 3.333 148.15 32.880 23.967
142.480
8 Balok Sloof 15 x 15 (Type SL 4) 0.30 0.70 0.21 4.76 6.67 19.00 2.226 2.000 9.52 21.196 -
0.30 0.70 0.21 4.76 16.00 1.578 8.000 38.10 60.123 -
0.30 0.70 0.21 4.76 14.00 1.208 8.000 38.10 46.032 -
0.30 0.70 0.21 4.76 10.00 0.617 0.150 6.67 12.667 60.32 37.186 -
164.537
2 Poor Plat Tangga 75 x 203 cm 0.60 1.10 0.66 1.52 0.48 16.00 1.578 20.000 30.30 47.825 0.234
0.60 1.10 0.66 1.52 6.15 16.00 1.578 20.000 30.30 47.825 403.147
95.651 1.305
Perbuah Poor Plat 125 x 125
Jenis Besi Berat Besi / Panjang Pot Jml Panjang Total Berat Besi
12.00 0.888 3.39 20.000 67.800 60.19
0.078 14.00 1.208 3.07 20.000 61.400 74.19
1.000 134.382 3.000
12.821 1,722.849
3 #REF! 0.70 1.10 0.77 1.30 0.56 16.00 1.578 20.000 25.97 40.993 0.118
0.70 1.10 0.77 1.30 4.74 16.00 1.578 20.000 25.97 40.993 49.164
81.986 0.540
Perbuah Poor Plat 75 x 105
Jenis Besi Berat Besi / Panjang Pot Jml Panjang Total Berat Besi
12.00 0.888 2.01 13.000 26.130 23.20
0.118 12.00 0.888 1.95 15.000 29.250 25.97
1.000 49.164 1.000
8.466 416.204
D.
Kolom
1 Pedestal Kolom 30 x 30 cm 0.25 0.25 0.06 16.00 16.00 14.00 1.208 8.000 128.00 154.668 5.412
0.25 0.25 0.06 16.00 - - 8.000 128.00 - 204.994
0.25 0.25 0.06 16.00 8.00 0.395 0.150 6.67 6.000 96.00 37.878 86.592
192.545
5.412 37.878 204.994
- 154.668 -
204.994
1 Balok Sloof 20 x 40 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 5.444
0.15 0.20 0.03 33.33 - - - - - 998.710
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 72.580
170.976
5.444 52.608 286.372
6.018 118.368 712.339
998.710
2 Balok Sloof 20 x 30 0.20 0.30 0.06 16.67 10.00 16.00 1.578 5.000 83.33 131.520 4.692
0.20 0.30 0.06 16.67 10.00 0.617 2.000 33.33 20.550 1,017.255
0.20 0.30 0.06 16.67 8.00 0.395 0.150 6.67 6.000 100.00 39.456 46.920
191.526
4.692 39.456 185.128
5.472 152.070 832.127
1,017.255
3 Kolom (K1) 15 x 20 cm 0.15 0.20 0.03 33.33 23.33 10.00 0.617 6.000 200.00 123.300 3.132
0.15 0.20 0.03 33.33 - - - - - 1,934.091
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 73.080
175.908
3.132 52.608 164.768
3.672 123.300 452.758
617.526
4 Kolom (K2) 25 x 25 cm 0.25 0.25 0.06 16.00 16.00 14.00 1.208 8.000 128.00 154.668 4.744
0.25 0.25 0.06 16.00 - - - - - 913.387
0.25 0.25 0.06 16.00 8.00 0.395 0.150 6.67 6.000 96.00 37.878 75.900
192.545
5 Kolom (K3) 25 x 60 cm 0.25 0.60 0.15 6.67 11.33 14.00 1.208 12.000 80.00 96.667 3.105
0.25 0.60 0.15 6.67 - - - - - 387.271
0.25 0.60 0.15 6.67 8.00 0.395 0.150 6.67 10.667 71.11 28.058 35.190
124.725
6 Kolom (K4) 15 x 25 cm 0.15 0.25 0.04 26.67 21.33 12.00 0.888 6.000 160.00 142.042 0.236
0.15 0.25 0.04 26.67 - - - - - 13.185
0.15 0.25 0.04 26.67 8.00 0.395 0.150 6.67 4.667 124.44 49.101 5.040
191.142
0.236 49.101 11.600
0.311 142.042 44.210
55.811
9 Ring Balok 15 x 20 cm (Elv. 300 & 400 cm) 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 5.647
0.15 0.20 0.03 33.33 - - - - - 1,029.119
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608 75.292
170.976
5.647 52.608 297.072
6.185 118.368 732.047
1,029.119
10 #REF! 0.25 0.25 0.06 16.00 16.00 14.00 1.208 8.000 128.00 154.668 4.744
0.25 0.25 0.06 16.00 - - - - - 913.387
0.25 0.25 0.06 16.00 8.00 0.395 0.150 6.67 6.000 96.00 37.878 75.900
192.545
11 #REF! 0.25 0.60 0.15 6.67 11.33 14.00 1.208 12.000 80.00 96.667 3.105
0.25 0.60 0.15 6.67 - - - - - 387.271
0.25 0.60 0.15 6.67 8.00 0.395 0.150 6.67 10.667 71.11 28.058 35.190
124.725
12 Kolom (K4) 15 x 25 cm 0.15 0.25 0.04 26.67 21.33 12.00 0.888 6.000 160.00 142.042 0.188
0.15 0.25 0.04 26.67 - - - - - 35.839
0.15 0.25 0.04 26.67 8.00 0.395 0.150 6.67 4.667 124.44 49.101 4.000
191.142
13 #REF! 0.12 1.00 0.12 8.33 8.33 10.00 0.617 0.15 10.00 11.000 91.67 56.513 2.962
0.12 1.00 0.12 8.33 12.00 0.888 0.15 13.33 14.333 119.44 106.038 602.932
162.551 24.680
2.962
3.709 162.551 602.932
14 #REF! 0.20 0.40 0.08 12.50 12.50 14.00 1.208 6.000 75.00 90.626 3.744
0.20 0.40 0.08 12.50 16.00 1.578 2.000 25.00 39.456 747.070
0.20 0.40 0.08 12.50 10.00 0.617 2.000 25.00 15.413 46.800
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168
181.662
3.744 36.168 135.413
4.204 145.494 611.657
747.070
16 #REF! 0.12 0.30 0.04 27.78 20.00 14.00 1.208 4.000 111.11 134.260 0.702
0.12 0.30 0.04 27.78 - - 2.000 55.56 - 146.707
0.12 0.30 0.04 27.78 - - 2.000 55.56 - 14.040
0.12 0.30 0.04 27.78 8.00 0.395 0.150 6.67 4.933 137.04 54.069
188.329
0.702 54.069 37.957
0.810 134.260 108.751
146.707
17 #REF! 0.12 0.20 0.02 41.67 21.67 12.00 0.888 4.000 166.67 147.960 0.564
0.12 0.20 0.02 41.67 - - 2.000 83.33 - 133.420
0.12 0.20 0.02 41.67 - - 2.000 83.33 - 12.210
0.12 0.20 0.02 41.67 8.00 0.395 0.150 6.67 3.600 150.00 59.184
207.144
0.564 59.184 33.351
0.676 147.960 100.068
133.420
18 #REF! 0.20 0.40 0.08 12.50 12.50 14.00 1.208 6.000 75.00 90.626 4.032
0.20 0.40 0.08 12.50 16.00 1.578 2.000 25.00 39.456 802.298
0.20 0.40 0.08 12.50 10.00 0.617 2.000 25.00 15.413 50.400
0.20 0.40 0.08 12.50 8.00 0.395 0.150 6.67 7.333 91.67 36.168
181.662
4.032 36.168 145.829
4.512 145.494 656.469
802.298
19 #REF! 0.15 0.20 0.03 33.33 18.33 12.00 0.888 5.000 166.67 147.960 0.426
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 100.534
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 7.810
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
200.568
0.426 52.608 22.411
0.528 147.960 78.123
100.534
21 #REF! 0.12 0.30 0.04 27.78 20.00 14.00 1.208 4.000 111.11 134.260 0.702
0.12 0.30 0.04 27.78 - - 2.000 55.56 - 146.707
0.12 0.30 0.04 27.78 - - 2.000 55.56 - 14.040
0.12 0.30 0.04 27.78 8.00 0.395 0.150 6.67 4.933 137.04 54.069
188.329
0.702 54.069 37.957
0.810 134.260 108.751
146.707
22 #REF! 0.12 0.20 0.02 41.67 21.67 12.00 0.888 4.000 166.67 147.960 0.564
0.12 0.20 0.02 41.67 - - 2.000 83.33 - 133.420
0.12 0.20 0.02 41.67 - - 2.000 83.33 - 12.210
0.12 0.20 0.02 41.67 8.00 0.395 0.150 6.67 3.600 150.00 59.184
207.144
0.564 59.184 33.351
0.676 147.960 100.068
133.420
23 #REF! 0.15 0.20 0.03 33.33 11.67 12.00 0.888 4.000 133.33 118.368 0.844
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 164.831
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 9.842
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
170.976
0.844 52.608 44.380
1.018 118.368 120.451
164.831
24 #REF! 0.15 0.20 0.03 33.33 13.33 12.00 0.888 4.000 133.33 118.368 1.161
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 218.034
0.15 0.20 0.03 33.33 - - 2.000 66.67 - 15.480
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
170.976
1.161 52.608 61.078
1.326 118.368 156.956
218.034
26 #REF! 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 1.567
0.10 1.00 0.10 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 214.394
94.530 15.670
1.567
2.268 94.530 214.394
27 #REF! 0.10 1.00 0.10 10.00 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 2.234
0.10 1.00 0.10 10.00 10.00 0.617 0.15 6.67 7.667 76.67 47.265 211.180
94.530 22.340
2.234
2.234 94.530 211.180
28 Kolom Praktis 0.12 0.12 0.01 69.44 16.67 10.00 0.617 4.000 277.78 171.250
0.12 0.12 0.01 69.44 - - - - -
0.12 0.12 0.01 69.44 6.00 0.222 0.150 6.67 2.533 175.93 39.045
210.295
29 Kolom 12/37 0.12 0.37 0.04 22.52 22.07 10.00 0.617 6.000 135.14 83.311
0.12 0.37 0.04 22.52 - - - - -
0.12 0.37 0.04 22.52 6.00 0.222 0.150 6.67 5.867 132.13 29.325
112.636
30 Balok Sloof 20 x 40 0.15 0.20 0.03 33.33 13.33 10.00 0.617 4.000 133.33 82.200
0.15 0.20 0.03 33.33 - - - - -
0.15 0.20 0.03 33.33 6.00 0.222 0.150 6.67 4.000 133.33 29.592
111.792
31 Balok Latai 12/12 0.12 0.12 0.01 69.44 16.67 10.00 0.617 4.000 277.78 171.250
0.12 0.12 0.01 69.44 6.00 0.222 0.150 6.67 2.533 175.93 39.045
210.295
32 Balok Latai 12/15 0.12 0.15 0.02 55.56 23.33 10.00 0.617 4.000 222.22 137.000
0.12 0.15 0.02 55.56 6.00 0.222 0.150 6.67 2.933 162.96 36.168
173.168
33 Ring Balok Latai 15/25 0.15 0.25 0.04 26.67 17.33 12.00 0.888 6.000 160.00 142.042
0.15 0.25 0.04 26.67 8.00 0.395 0.150 6.67 4.667 124.44 49.101
191.142
27 Plat 7 cm 0.07 1.00 0.07 14.29 14.29 10.00 0.617 0.15 6.67 7.667 109.52 67.521 -
0.07 1.00 0.07 14.29 10.00 0.617 0.15 6.67 7.667 109.52 67.521 66.667
135.043 -
30 #REF! 0.15 0.20 0.03 33.33 13.33 10.00 0.617 4.000 133.33 82.200
0.15 0.20 0.03 33.33 - - - - -
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
134.808
29 #REF! 0.15 0.20 0.03 33.33 23.33 10.00 0.617 4.000 133.33 82.200
0.15 0.20 0.03 33.33 - - - - -
0.15 0.20 0.03 33.33 8.00 0.395 0.150 6.67 4.000 133.33 52.608
134.808
33 Ring Balok12/20 0.12 0.20 0.02 41.67 21.67 10.00 0.617 5.000 208.33 128.438
0.12 0.20 0.02 41.67 8.00 0.395 0.150 6.67 3.600 150.00 59.184
187.622
33 Ring Balok15/15 0.15 0.15 0.02 44.44 13.33 10.00 0.617 4.000 177.78 109.600
0.15 0.15 0.02 44.44 8.00 0.395 0.150 6.67 3.333 148.15 58.453
168.053
8 Kolom 30 x 30 cm 0.12 0.12 0.01 69.44 16.67 10.00 0.617 4.000 277.78 171.250 8.712
0.12 0.12 0.01 69.44 - - 8.000 555.56 - 1,747.050
0.12 0.12 0.01 69.44 6.00 0.222 0.200 5.00 1.900 131.94 29.284 145.200
200.534
RHITUNGAN KONVERSI BESI
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Besi
Bakesting
Beton 21.120
Besi
Bakesting
Beton 1.440
Besi
Bakesting
Beton 0.560
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Beton
Besi
Bakesting
Bakesting
BesiTotal
Total
M² Kg
Beton
Besi
Bakesting
ENGINEERING ESTIMATE
HARGA SATUAN UPAH, BAHAN & PERALATAN
B. BAHAN
1 Pasir Urug M3 Rp. 170,000.00
2 Tasirtu M3 Rp. 167,000.00
3 Tanah Urug M3 Rp. 106,250.00
4 Tanah Taman M3 Rp. 255,000.00
5 Pasir Pasang (Lokal) M3 Rp. 170,000.00
6 Pasir Beton (Lokal) M3 Rp. 148,750.00 Rp 106.25 / Kg
7 Pasir Pasang / Beton (Toli-Toli) M3 Rp. 320,000.00 Rp 228.57 / Kg
8 Batu pecah 2 - 3 cm lokal M3 Rp. 255,000.00 Rp 188.89 / Kg
9 Batu pecah 3 - 5 cm Lokal M3 Rp. 255,000.00 Rp 188.89 / Kg
10 Kerikil Sungai Ayakan M3 Rp. 170,000.00 Rp 125.93 / Kg
11 Batu Kali M3 Rp. 170,000.00
11 Batu Gunung M3 Rp. 191,250.00
12 Batu Bata Ukuran 5 x 11 x 23 Bh Rp. 950.00
13 Batako H. 10 Bh Rp. 4,463.00
14 Roster Ukuran 12 x 20 x 20 Bh Rp. 25,500.00
15 Batu Karang M3 Rp. 175,000.00
16 Batu Koral Ktg Rp. 275,000.00
17 Cansteen Beton Bh Rp. 17,500.00
18 Gorong - gorong Ø 40 Cm P = 1 m Bh Rp. 175,000.00
19 Grass Block Beton 25 x 25 Bh Rp. 7,500.00
20 Paving Block 5 Cm (6 Sisi) Bh Rp. 3,570.00
21 Air Kerja Ltr Rp. 80.00
22 Semen Portland (50 Kg) Zak Rp. 92,200.00 Rp 1,844.00 / Kg
23 SemenWarna 20 Kg Zak Rp. 28,688.00 Rp 1,434.40 Kg
24 Nat / Mortar Flex Kg Rp. 18,700.00
25 Floor Hardener 5 kg Kg Rp. 70,000.00 Rp 14,000.00 Kg
26 TCT Colour Bond Stell M2 Rp. 89,400.00
27 Genteng Metal Zincalume 0,800 x 0,770 = T = 0,20 mm Lbr Rp. 30,000.00
28 Genteng Metal Zincalume 0,800 x 0,770 = T = 0,35 mm Lbr Rp. 85,000.00
29 Nok Metal T = 0,35 TCT Warna Lbr Rp. 35,000.00
30 Nok Genteng Metal Zincalume Lbr Rp. 35,000.00
31 Seng Plat BJLS 20 L = 40 cm M1 Rp. 49,500.00
32 Talang PVC Btg Rp. 112,000.00
33 Lisplank GRC 0,8 x 30 P= 4 m Lbr Rp. 115,000.00 Rp 28,750.00 /M1
34 Seng Gelombang BJLS 20 Lbr Rp. 42,350.00
35 Kayu Kelas I M3 Rp. 2,860,000.00
36 Kayu Klas II M3 Rp. 1,700,000.00
37 Kayu Klas III M3 Rp. 1,300,000.00
38 Handrail Kayu Klas III Btg Rp. 150,000.00
39 Dolken Kayu Galam Ø 8 - 10 P = 4 m Btg Rp. 6,050.00
40 Bambu Ø 5 - 10 Btg Rp. 6,050.00
41 Formite Bh Rp. 5,000.00
42 Tali Ijuk Kg Rp. 12,500.00
43 Ijuk M3 Rp. 75,000.00
C. SEWA PERALATAN
1 Dump Truck Hari Rp. 500,000.00 Rp 71,428.57 / Jam
2 Welding (min.5 jam) Hari Rp. 450,000.00 Rp 64,285.71 / Jam
3 Concret Mixer Hari Rp. 350,000.00
4 Concret Vibrator Hari Rp. 300,000.00
5 Stamper Hari Rp. 300,000.00
6 Compresor Hari Rp. 200,000.00 Rp 28,571.43 / Jam
7 Vibrator Ls Rp. 20,000.00
8 Pompa Pengecoran Ls Rp. 15,000.00
9 Alat Bantu Ls Rp. 20,000.00
ENGINEERING ESTIMATE
REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PERENCANAAN GEDUNG KANTOR LURAH KULANGO
LOKASI : JL. U. HANGGI NO. 99 KEL. KULANGO
TH. ANGGARAN : 2016
Buol, 2016
Dibuat :
Muslih, ST
Team Leader
ENGINEERING ESTIMATE
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN PERSIAPAN
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PERENCANAAN GEDUNG KANTOR LURAH
LOKASI : KULANGO
JL. U. HANGGI NO. 99 KEL. KULANGO
TH. ANGGARAN : 2016
3 Pedestal Kolom 30 x 30 cm
• Beton Site Mix K.200 4.356 M3 880,098.94 3,833,710.99
• Pembesian 751.137 Kg 16,405.00 12,322,402.88
• Bekisting Kolom (2 x Pakai) 58.080 M2 138,807.50 8,061,939.60
5 Kolom 30 x 30 cm
• Beton Site Mix K.200 8.712 M3 880,098.94 7,667,421.98
• Pembesian 1,502.274 Kg 16,405.00 24,644,805.76
• Bekisting Kolom (2 x Pakai) 116.160 M2 138,807.50 16,123,879.20
6 Kolom Praktis 11 x 11 cm
• Beton Site Mix K.125 0.127 M3 794,598.68 100,953.76
• Pembesian 31.175 Kg 16,405.00 511,428.70
• Bekisting Kolom (2 x Pakai) 2.310 M 2
138,807.50 320,645.33
2 Kolom Praktis 11 x 11 cm
• Beton Site Mix K.125 0.459 M3 794,598.68 364,587.30
• Pembesian 112.587 Kg 16,405.00 1,846,988.21
• Bekisting Kolom (2 x Pakai) 8.342 M2 138,807.50 1,157,987.69
3 Ring Balok 15 x 20 cm
• Beton Site Mix K.200 2.248 M3 880,098.94 1,978,110.38
• Pembesian 302.994 Kg 16,405.00 4,970,624.13
• Bekisting Balok 29.968 M2 283,615.00 8,499,374.32