Project Management
Engineer
gives notice
–key aspects
Availability of designers, Sub-Clause 5.1

Liability

Engineer inspects, gives instructions,


determines, approves, etc

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 224
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 225
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 226
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 227
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 228
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 229
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 230
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 231
FIDIC Training Module 1
Start
Notice of Commencement Date

Progress of the Actions of the


Contractor Contractor
Commencement of Early Warning, Cl. 8.3 Access to the Site?, Cl.
Execution, Cl. 8.1 2.1
Submission of Notice of Claims, Cl. 20.1 Drawings?, Cl. 1.9
Programme, C. 8.3
Progress Reports, Cl. 4.21 Others

Notice when work is Application for Payment, Interim & Final


ready, Cl. 7.3 Cl. 14 Statements
Agreement as to time and Engineer shall give notice Testing procedure, Cl. 7.4
place for testing, Cl. 7.4 of intention to attend
Contractor shall forward Engineer shall endorse
certified test results certified results
Ready for Tests Notice for Tests, Cl. 9.1 Testing procedure, Cl. 7, 9

Ready for taking-Over Ready for taking-Over

Expiry of Defects Issue of Performance


Notification period Certificate, Cl. 11.9

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 232
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 233
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 234
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 235
FIDIC Training Module 1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 236
FIDIC Training Module 1

Start Notice of Commencement Date

Progress of the Actions of the


Contractor Contractor

Commencement of Early Warning, Cl. 8.3 Access to the Site?, Cl.


Execution, Cl. 8.1 2.1

Submission of Notice of Claims, Cl. 20.1 Employer´s


Programme, C. 8.3 Requirements?, Cl. 1.9 YB

Progress Reports, Cl. 4.21 Others

Notice when work is Application for Payment, Interim & Final


ready, Cl. 7.3 Cl. 14 Statements

Ready for Tests Notice for Tests, Cl. 9.1

Ready for taking-Over Application for taking


Over, Cl. 10.1

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 237
FIDIC Training Module 1

Project Management – key aspects

–! Commencement, Delays and Suspension

Commencement Submission Monthly Ready for


Date of Programme Reports inspection

Ready for Ready


Certificate
Tests Taking Over

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 238
FIDIC Training Module 1
Commencement Date (Yellow Book)

Engineer Contractor

42 days
Commencement Programme
Date
7 days
Letter of
Acceptance
oder Performance
Contract Security
Agreement 28 days

Employer

Access to the site

INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS – WORLD TRADE CENTER – GENEVA – SWITZERLAND – WWW.FIDIC.ORG 239
FIDIC Training Module 1

Completion
Time of Completion for the Works Delay damages

Commencement EOT
Date Up-date

Submission of Engineer
Programme Employer