Professional Documents
Culture Documents
Analysis of delays in Tanzanian construction industry: transaction cost economics (TCE) and
structural equation modelling (SEM) approach
Murali Sambasivan T.J. Deepak Ali Nasoor Salim Venishri Ponniah
Article information:
To cite this document:
Murali Sambasivan T.J. Deepak Ali Nasoor Salim Venishri Ponniah , (2017)," Analysis of delays in Tanzanian construction industry:
transaction cost economics (TCE) and structural equation modelling (SEM) approach ", Engineering, Construction and Architectural
Management , Vol. 24 Iss 2 pp. -
Permanent link to this document:
http://dx.doi.org/10.1108/ECAM-09-2015-0145
Downloaded on: 08 February 2017, At: 07:11 (PT)
References: this document contains references to 0 other documents.
To copy this document: permissions@emeraldinsight.com
The fulltext of this document has been downloaded 2 times since 2017*
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
Access to this document was granted through an Emerald subscription provided by emerald-srm:173272 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald for Authors service
information about how to choose which publication to write for and submission guidelines are available for all. Please
visit www.emeraldinsight.com/authors for more information.
About Emerald www.emeraldinsight.com
Emerald is a global publisher linking research and practice to the benefit of society. The company manages a portfolio of
more than 290 journals and over 2,350 books and book series volumes, as well as providing an extensive range of online
products and additional customer resources and services.
Emerald is both COUNTER 4 and TRANSFER compliant. The organization is a partner of the Committee on Publication Ethics (COPE)
and also works with Portico and the LOCKSS initiative for digital archive preservation.
Introduction
A time overrun of 10% to 30% on 70% of the construction projects is not uncommon (Assaf and
Al-Hejji, 2006). Delays in projects usually result in either extension or acceleration of the
project and these results in additional cost. According to Marzouk and El-Rasa (2014), delay is
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
defined as “an act or event which extends required time to perform or complete work of the
contract and manifests itself as additional days of work.” (p. 49). Identifying the causes and
effects of delays in the construction industry in different parts of the world has been the passion
of researchers and practitioners. In fact, many researchers have addressed the issue of
identifying the causes and/or effects of delays in the construction industry in different countries
(For example, Assaf and Al-Hejji, 2006 (Saudi Arabia); Kasimu and Abubakar, 2012 (Nigeria);
Marzouk and El-Rasas, 2014 (Egypt); Alaghbari et al., 2007 and Sambasivan and Soon, 2007
(Malaysia)). Few researchers have analyzed the relationships between the causes and effects of
delays using simple correlation (for example, Sambasivan and Yoon, 2007) and regression (for
example, Aibinu and Jagboro, 2002; Parikh and Joshi, 2013). These simple approaches fall short
of revealing the complete relationships between the causes and effects of delays and inter-
relationships within the effects of delays. For example, among the effects of delays, time
overrun leads to cost overrun (Aibinu and Jagboro, 2002), cost and time overruns often lead to
disputes. Another significant problem in using correlations for understanding relationships is the
al. (2005), these issues can lead to wrong interpretation of results. It is essential for the project
managers to understand all the links between causes and effects of delays in order to make
effective decisions to reduce delays in project completion. In this research, the use of a more
sophisticated tool, namely, SEM to analyze the complex relationships is demonstrated. The
possibility of handling complex dependencies is regarded as one of the main advantages of using
SEM (Quereshi and Kang, 2014). SEM is not new to research related to project management.
However, the current study is one of the initial studies that use SEM to study the relationships
Earlier researchers have relied on the empirical results to understand the links between
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
the causes and effects of delays (For example, Assaf and Al-Hejji, 2006; Kasimu and Abubakar,
2012; Sambasivan and Soon, 2007). These researchers have failed to establish the theoretical
underpinnings that can be used to establish the links. The theoretical foundations of a field
describe and inform the practice and provide the primary means to guide future developments
(Garrison, 2000). A few scholars have attempted to use TCE and Game Theory (GT) to
(Peckiene, Komarovska, and Ustinovicius, 2013; Walker and Wing, 2001; Winch, 1982). There
is a dearth of research in explaining the relationships through a theoretical lens between causes
and effects of delays and this is a significant gap that is addressed in this research.
The setting for the study is Tanzanian Construction Industry (TCI). TCI is said to be in
the fifth position among all sectors contributing 8% of the GDP and employing 10% of the
workforce in Tanzania. In recent years, Tanzanian government has set aside 13% of the budget
for infrastructure expenditure. A study by Kikwasi (2012) has identified the following causes
and effects of delays in TCI: (1) causes – design changes, delays in payments to contractors,
information delays, poor project management, funding problems and disagreements on the
amounts of work done and (2) effects – time overrun, cost overrun, disputes, and other negative
impacts. The problem with this study is the small sample size of 40 respondents and there are no
other studies available. Kikwasi’s study has not considered the relationship between the cause
and effect factors. The current study considers 31 causes of delays whereas Kikwasi’s study
considered 21 causes. The huge volume and complexity of projects in TCI pose a great
industry. The current study is timely since TCI is poised for a spectacular growth.
The causes of delays considered in this research are: (1) client related, (2) contractor
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
related, (3) consultant related, (4) material related, (5) labor and equipment related, (6) contract
and relationship related, and (7) external factors. The effects of delays considered in this
research are: (1) cost overrun, (2) dispute, (3) arbitration, (4) litigation, and (5) abandonment. A
few researchers have studied these factors (Aibinu and Jagboro, 2002; Kikwasi, 2013;
Sambasivan and Yoon, 2007). As indicated earlier, their analyses are too narrow. The basic
objectives of this research are: (1) to explain the relationship between causes and effects of
delays by applying TCE as a theoretical foundation, (2) to demonstrate the application of SEM in
uncovering the complex relationships between and causes and effects of delays.
Literature review
One of the initial studies on the application of SEM in project management is by Molenaar,
Washington, and Diekman (2000). They have studied the fundamental factors that impact
contract disputes between clients and contractors. The authors argue that final set of structural
equations provides insight into the interaction of the variables that is not apparent with other
approaches like correlation and regression. Zulu (2007) has used SEM to study the relationship
between project management and project performance. Specifically, Zulu has studied the direct
and indirect effects of project leadership, project team, project policy and strategy, project
Zhang and Zeng (2013) have developed an engineering project management evaluation
model. In order to identify the critical factors that can be used to evaluate the performance, the
authors have used SEM. Memon, Rahman, Aziz, and Abdullah (2012) have used SEM to reveal
the relationships between four resource-related factors and cost overrun in the construction
industry in Malaysia. The factors or latent constructs that have been considered in their paper
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
are: (1) machinery related, (2) finance related, (3) manpower related and (4) material related.
They argue that SEM functionality is better than other multivariate techniques such as multiple
regression, path analysis and factor analysis in analyzing the cause–effect relations between
latent constructs.
Chen, Zhang, Liu, and Mo (2012) have studied the interrelationships between the critical
success factors of construction projects in Taiwan. They have argued that understanding the
interrelationships by the project managers is essential to ensure a project’s success. Cho, Hong,
and Hyun (2009) have analyzed the effects of project characteristics on project performance in
Korea using SEM. Qureshi and Kang (2014) have analyzed, using SEM, the organizational
framework for sustainable project portfolio selection based on SEM. In the last few years, SEM
has been popular among project management researchers to analyze various issues related to
project management. In spite of promising increase in the application of SEM, there are many
more interesting issues such as, understanding the inter-relationships between and within causes
and effects of delays in construction project management that can be effectively addressed using
In general, the literature is replete with research on causes and effects of delays in the
construction industry in different countries (For example, Alaghbari et al., 2007; Assaf and Al-
Hejji, 2006; Frimpong, Oluwoye, and Crawford, 2003; Alinaitwe, Apolot, and Tindiwensi,
2013). In fact, Ramanathan, Narayanan, and Idrus (2012) have identified 15 published research
papers on causes and/or effects of delays between 1997 and 2010. The current research
highlights few research papers from the extant literature. Chan and Kumaraswamy’s (1997)
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
research on factors causing delays in the Hong Kong construction industry is considered to be
one of the early significant works. Aibinu and Jagboro (2002) defined delays in construction
industry as situation whereby the contractor and the project owner jointly or individually
contribute to the non-completion of the project within the original or the stipulated or agreed
contract period.
Assaf and Al-Hejji (2006) have defined delays as a time overrun either beyond
completion date specified in a contract or beyond the date that parties agreed upon for the
delivery of a project. Sambasivan and Soon (2007) have analyzed the delays in the Malaysian
construction industry and have identified 10 most important causes of delay from a list of 28
factors and six effects of delays. They have also established bi-variate relationships between the
A most recent survey concerning delays in Nigeria by Kasimu and Abubakar (2012)
reveal that out of 43 factors that cause delays, four important factors are: (1) lack of interest by
the stakeholder, (2) blacklist by authorities, (3) waste of money and time and (4) decline of
reputation. Kikwasi (2012) has studied the delays in TCI and has identified 21 causes and 14
effects of delays. Alinaitwe et al. (2013) have investigated the causes of delays and their effects
on cost overruns in the Ugandan construction industry. The literature review vindicates the stand
of the authors that there is no dearth of studies related to causes and effects of delays in the
construction industry and the number of studies is continuously growing. What is lacking is the
theoretical foundation and comprehensive analysis using an appropriate tool. In this research,
we attempt to fill these gaps. Table 1 summarizes the relevant studies carried out between 1995
and the current study. The table clearly shows the span of work done in the analysis of delays in
construction industry.
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
The current research attempts to explain the link between the causes and effects of delays in the
construction industry based on TCE. The origin of transaction costs can be traced back to
Richard Coase’s seminal work on the nature of the firm. However, it was Williamson (1981)
who carried the work further to explain the economics of organizations. According to
Williamson (1989), TCE focuses on the organization of transactions that occur whenever a good
or service is transferred from a provider to a user. The transactions occurring inside the
organization can include costs such as managing and monitoring, procuring inputs and capital
equipment and the transactions occurring outside the organization can include costs such as
search and information cost, bargaining cost, and policing and enforcement costs. The
rationality, and opportunistic behavior (Williamson, 1996). TCE uses a contractual approach to
the study of economic organizations. According to Williamson (1998: p. 548), TCE is “central
to the study of organizations through assessing how their governance structures serve to
economize on these transaction costs.” TCE has been subjected to severe criticisms because of
its treatment of human behavior as ‘opportunistic’ and for being ad hoc. Klein and Shelanski
(1996) have refuted the criticisms and have provided empirical evidence to support the logic of
organization described by TCE. The authors have shown a range of applications of TCE
including vertical integration, complex contracts and hybrid modes of organizations, transfer
temporary structures can be classified as hybrid modes of organizations. TCE has been one of
the most influential theories in the study of organizations because of the empirical studies that it
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
construction industry.
According to Li, Arditi, and Wang (2014), researchers do agree that the concept of transaction
costs is not universally accepted by all participants in the construction industry. But at the same
time, researchers have argued that the parties involved in the construction project must
understand the existence and importance of transaction costs. A few researchers have attempted
to explain the process of project management and the relevant transaction costs in construction
industry using TCE. We discuss a few examples that are appropriate to this study. (1) Walker
and Wing (1999) have used TCE (in combination with project management theory) to explain
the structuring and management of project organizations. They have identified the transaction
costs incurred by the owner of the project from start to finish. They have listed down various
activities in a project that lead to transaction costs. The transaction costs listed are: cost of
establishing project organization structure, in-house client costs, cost of coordination between
relationships, costs of negotiations, cost of monitoring agreements and contracts, and costs
related disputes, litigation, and arbitration; (2) Li et al. (2014) have discussed the transaction
costs incurred by construction owners. According to the authors, the transaction paradigm in
construction industry has been dealt by many researchers to address project organization and
measurement of transaction costs. They break the transaction costs into two categories: pre-
contract and post-contract. According to them, pre-contract transaction costs are: cost of market
negotiation, and cost of day-to-day pre-contract management. The post-contract costs are: cost
of day-to-day contract administration, cost of administering claims and change orders, cost of
dispute resolution, and incentive payments. Li et al. (2014) have stated very clearly that during
the construction phase questionable decisions and actions can lead to disagreements, conflicts,
disputes, arbitration, change orders, and claims and these problems can lead to increase in
transaction costs; and (3) Rajeh, Tookey, and Rotimi (2015) have demonstrated the way to
estimate transaction costs in the construction procurement. They have stated that TCE offers a
mechanism to understand unseen costs associated with pre- and post-contract work. According
to them, pre-contract includes information gathering and procurement and post-contract includes
contract administration and enforcement. They have argued that transaction costs are highly
significant in the overall cost of construction. Based on the studies linking TCE and construction
industry, we argue that the factors that the causes of delay, discussed in this research, can lead to
increase in transaction costs. The increase in transaction costs, in turn, can lead to cost overrun,
According to Dubois and Gadde (2002), construction is a project-based activity in which time,
quality, and budget are for an individual project and the relationships between the stakeholders
(clients, contractors, consultants, and suppliers) are established on a short-term basis. Winch
(1989) argues that the nature of construction projects gives rise to temporary coalitions of firms
(a firm can represent a client, a contractor, a consultant, or a supplier) with divergent economic
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
and social interest. According to TCE, the nature of coalition often leads to transaction costs
incurred by the firms (Williamson, 1996). In the construction industry, search and information
costs may relate to costs associated in finding the appropriate contractors, consultants and
suppliers; bargaining costs are the costs associated with drawing up the required contractual
agreement between the parties that transact; policing and enforcement costs are the costs
associated with ensuring that each party adheres to the terms of contract. The next logical
question is: What are the important determinants of transaction costs in the construction
industry?
delays and undesirable effects: uncertainty, limited rationality, and opportunistic behavior
(Winch, 1989). Uncertainties can stem from task, nature, organization, and contract. Because of
its unique nature, each project has distinctive set of problems related to tasks which leads to task
uncertainty. The weather and other acts of nature can introduce a new dimension of uncertainty
and this temporary structure can generate tensions that lead to uncertainty. Organizational
uncertainty increases with increase in project size. Typically, in a construction activity many
firms are involved (client, contractor, consultant, and suppliers). Therefore, contractual
mechanisms have to be in place for effective governance of the projects. Two of the main
contents of contracts are estimation of time and cost. Unfortunately, the estimates are not exact
construction business it is difficult to (1) foresee and specify all issues in the contract and (2)
between firms. Therefore, the transaction costs tend to be high. Opportunistic behavior in the
construction industry can be due to limited duration of project, temporary coalition of firms with
specific economic and social interest, uncertainty and limited rationality. Collaboration
(temporary or otherwise) between firms such as in a construction project can fail because of
opportunistic hazards as each firm involved in the project tries to maximize its own interest
instead of collaborative interest (Park and Ungson, 2001). D’Alpaos, Moretto, Valbonesi, and
Vergalli (2013) highlight the case of opportunistic behavior of suppliers in public procurement
that eventually led to time overruns in public works and construction in Italy.
The causes of delays (constructs) highlighted in this research are: client related,
contractor related, consultant related, material related, labor and equipment related, contract
related, contract relationship related, and external. These factors are the result of uncertainty,
limited rationality, and opportunistic behavior (Winch, 1989). The causes of delays result in cost
overrun, disputes, arbitration, litigation, and complete abandonment (Sambasivan and Soon,
2007). A recent study by Lua, Zhang, and Pan (2014) has identified 13 hidden transaction costs
arising out of disputes. Disputes can arise because of time and/or cost overruns. Alinaitwe et al.
(2013) have identified the causes of delays that can lead to cost overruns because of the increase
in transaction costs in the Ugandan construction industry. After assimilating the evidences based
on TCE, the current research concludes that the causes of delays impact the effects of delays
through increase in transaction costs. Figure 1 gives the initial framework used in this research.
H1: Causes of delays in the construction industry have impact on the effects of delays.
Methodology
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
This study was conducted using the survey method. A questionnaire was developed to assess the
perceptions of clients, consultants, and contractors on the relative importance of causes and
effects of delay in TCI. Since one of the coauthors had links in TCI, the questionnaire was sent
to (Construction) Contractor Registration Board (CRB) in Tanzania to vet and verify the
relevance of causes and effects of delays in TCI. After the factors were agreed upon by the
researchers and CRB, 400 questionnaires were distributed to 50 clients, 200 consultants and 150
contractors. There were 6000 firms registered with CRB. The sampling frame was provided by
CRB. The questionnaire was divided into three parts: (1) background information of the
respondents, (2) causes of delays, and (3) effects of delays (Odeh and Battineh, 2002;
The cause of delays were: (1) client-related (4 observed variables) – this indicates the
problems caused by clients/owners due to financial and payment difficulties, interference, slow
observed variables) – this indicates the problems caused by contractors and sub-contractors due
errors, and inadequate experience; (3) consultant-related (4 observed variables) – this indicates
problems caused by consultants due to contracts, preparation of approval of drawings, quality
assurance, and test and inspection; (4) material-related (4 observed variables) – this indicates
problems due to poor quality and shortage of material; (5) labor and equipment-related (4
observed variables) – this indicates problems due to shortage in labor supply, poor labor
productivity, shortage in equipment availability, and equipment failure; (6) contract and
relationship due to change orders and mistakes or discrepancies in contract document, major
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
disputes and negotiations, inappropriate structure, and lack of communication between parties;
and (7) external-related (4 observed variables) – this includes problems caused by external
factors such as weather condition, regulatory changes, community, and unforeseen site condition
(Sambasivan and Yoon, 2007: p. 520). A 4-point Likert scale ranging from 1 (strongly disagree)
The third part of the questionnaire had the effects of delays. They were: (1) cost overrun,
(2) disputes, (3) litigation, (4) arbitration, and (5) abandonment. A 5-point Likert scale ranging
from 1 (never) to 5 (always) was used to capture the significance of ‘effect’ factors of delay.
Relative importance index (RII) developed by Kometa, Olomolaiye, and Harris (1994)
has been used to determine the relative importance of causes and effects of delays. RII has been
calculated based on the responses from three stakeholders: clients, contractors, and consultants.
The four point scale (1—strongly disagree, 2—disagree, 3—agree, and 4—strongly agree) was
used to compute RII for each cause of delay and a five point scale (1—never, 2—rarely, 3—
1 to 5 for effects of delays), A is the highest weight (4 for cause and 5 for effect) and N is the
total number of respondents. The ranking of different factors was done based on RII. An overall
ranking was developed by combining the responses of all the respondents (Sambasivan and
Soon, 2007). A similar ranking procedure was adopted for the effects of delays.
Choice of SEM
SEM is a multi-variate statistical technique that is used for analyzing the relationships between
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
latent constructs (or variables) and manifest (observed) variables in a model. Latent constructs
are the variables of interest and which cannot be measured directly. Manifest variables are the
variables that are observed and measured directly by the researcher. These manifest variables
are used to measure latent constructs (Qureshi and Kang, 2014). Many multi-variate techniques
such as multiple regression and linear models allow only a single relationship between
independent and dependent constructs. SEM allows (1) multiple dependent constructs, (2)
relationships between independent and dependent constructs, and (3) inter-relationships within
independent constructs and dependent constructs. In essence, SEM solves multiple regression
equations simultaneously. The possibility of modelling complex dependencies make SEM the
Measures
A questionnaire was constructed with three sections. Section I captured the demographic
information. Section II contained the causes of delays (construct and observed variables) and
Section III the effects of delays. As indicated earlier, causes of delays were captured using a 4-
point Likert scale and effects of delays were captured using a 5-point Likert scale. A high score
on causes indicates that the factor plays a stronger role in causing delays. A high score on the
effects indicates that the consequence of the factor is significant. The items under each factors
were adapted from Odeh and Battineh (2002) and Sambasivan and Soon (2007). Table 2 gives
Results
Descriptive Statistics
Out of 400 questionnaires that were distributed, 308 were returned (21 from clients, 157 from
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
consultants and 130 from contractors). Since one of the coauthors had links in TCI, the response
rate was high (77.5%). The characteristics of the respondents were: (1) 24% were from
government, 72% were from private, and 4% were from regulatory firms; (2) 68% were project
manager/director/managing director of firms; and (3) 46% had more than 10 years of experience
and 71% had more than 6 years of experience in the construction industry.
The relative importance index, RII, was computed for each cause and was used to rank the
causes. The ranking was then used to identify the most significant factors of delay in TCI.
Based on the ranking, major problems plaguing TCI are: (1) inability of the clients to make
payments on time to contractors, consultants, and suppliers – the inability to pay sets a chain
reaction and subsequently leads to a host of other problems such as disputes, arbitration, and
litigation; (2) inability of contractors to plan effectively – this inability demonstrates the lack of
experience and skills of contractors; (3) inability to get the material delivered on time – this
problem may be linked to the inability to pay by the clients and/or the suppliers may have
inadequate resources to supply on time. TCI imports most of the important materials such as
steel and cement because of the poor quality of material from the local manufacturers; (4)
unforeseen site conditions may be due to natural causes such as floods. Another reason for this
condition is the quality of manpower/professionals not being available in adequate numbers; and
(5) inability on the part of contractors to manage the site – this problem may be due to
inadequate experience of contractors to execute construction projects on time. There have been
cases where some contractors have refused to appoint experienced project managers. Table 2
gives the RII for all causes of delays. The results of this study (with 31 causes) are more
comprehensive compared to the results obtained by the study by Kikwasi (2012) (with 21
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
causes). To recap, the study by Kikwasi has identified the following important cause factors
poor project management, funding problems and disagreements on the amounts of work done.
The calculation of RII for the effects of delays in TCI were done as explained in the
previous section. The ranking of effects was done using the RII scores and the information is
given in Table 3. Based on the ranking, the effects were in the following order in TCI: (1) Cost
overrun, (2) Disputes, (3) arbitration, (4) litigation, (5) total abandonment. The correlations
SEM results
In order to test the measurement model, the procedure based on Confirmatory Factor Analysis
(CFA) as suggested by Hair et al. (2010) was used. Specifically, the following were tested: (1) if
the factor loading of items (observed variables) on each construct was greater than 0.5. While
running CFA, we treated the five effects of delays under one construct since each effect had only
one observed variable; (2) if the composite reliability of each construct was greater than 0.7; and
(3) if the Average Variance Extracted (AVE) of each construct was greater than 0.5. The results
are given in Table 5. The results indicate that all the three conditions are met. This table also
provides the correlation between the constructs. The fit statistics of measurement model are: chi-
square/degrees of freedom = 2.034 (threshold < 3.0), Root mean square error of approximation
(RMSEA) = 0.058 (threshold < 0.08), Normed Fit Index (NFI) = 0.990, Comparative fit index
(CFI) = 0.995, Goodness of fit index (GFI) = 0.959 (threshold for all fit indices > 0.9), and Root
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
The hypothesis was tested by running the structural model using Lisrel 9.1. The structural model
was built as follows based on the literature and correlation table: (1) all the causes of delays were
allowed to link with all the effects of delays and (2) effects of delays were allowed to be inter-
related. In the final run of the model, we included only the relationships that were significant.
The fit statistics of the model are: chi-square/degrees of freedom = 2.068 (threshold < 3.0), Root
mean square error of approximation (RMSEA) = 0.059 (threshold < 0.08), Normed Fit Index
(NFI) = 0.994, Comparative fit index (CFI) = 0.997, Goodness of fit index (GFI) = 0.974
(threshold for all fit indices > 0.9), and Root mean error residual (RMR) = 0.0125 (threshold <
0.08). The final framework with significant positive relationships (significant level = 0.05) are
given in Figure 2. The interesting relationships between various factors are given in the
following paragraphs.
The following are the significant relationships: (1) Client-related cause with litigation (β = 0.279,
p-value = 0.007); (2) Contractor-related cause with cost overrun (β = -0.689, p-value = 0.030);
(3) Consultant-related cause with cost overrun (β = 0.619, p-value = 0.016), arbitration (β =
0.432, p-value = 0.009), and abandonment (β = 0.445, p-value = 0.020); (4) Material-related
cause with cost overrun (β = 0.477, p-value = 0.024); (5) Labor and equipment-related cause
with disputes (β = -0.223, p-value = 0.000) and litigation (β = -0.332, p-value = 0.001); (6)
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
Contract and relationship-related cause with cost overrun (β = -0.726, p-value = 0.000),
arbitration (β = -0.585, p-value = 0.000), and abandonment (β = -0.829, p-value = 0.001); and (7)
external-related cause with abandonment (β = 0.497, p-value = 0.000). There are a few negative
coefficients that require explanation. For example, the cost overrun has significant positive
contract and relationship-related have significant negative coefficients. Based on these, we can
conclude that in TCI the consultant-related and material-related causes more often lead to cost
overrun but the contractor-related and contract and relationship-related seldom lead to cost
overrun. In summary, out of seven causes considered in this study only four causes (client-
related, consultant-related, material-related, and external related) have been found to have impact
The following are the significant relationships: (1) Cost overrun with disputes (β = 0.590, p-
value = 0.000) and arbitration (β = 0.130, p-value = 0.013); (3) Disputes with litigation (β =
0.227, p-value = 0.000), arbitration (β = 0.541, p-value = 0.000), and abandonment (β = 0.179, p-
value = 0.004); (4) Arbitration with litigation (β = 0.599, p-value = 0.000) and abandonment (β =
0.283, p-value = 0.001); and (5) Litigation with abandonment (β = 0.283, p-value = 0.000).
Discussions
In this research, a theoretical foundation using TCE to explain the link between the causes and
effects of delays in the construction industry has been developed. Earlier studies have argued the
relevance of TCE in the construction industry but have not explained how TCE can be used to
understand the impact of causes on effects of delays. This gap has been filled by recognizing the
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
role of transaction costs in providing the required explanation. Specifically, it is argued that
nature of coalition between the firms (clients, contractors, consultants, and suppliers) lead to
uncertainty, bounded rationality, and opportunistic behavior (Williamson, 1996). These lead to
the effects such as cost overrun, disputes, arbitration, litigation, and abandonment through
The current research has studied TCI and identified 31 different causes of delays
(observed variables) that are grouped under seven constructs and six effects of delays. Based on
RII, the ten most important causes of delays are: (1) client-related factor – lack of finance and
payment of completed works (Rank 1); (2) contractor-related factors – improper planning (Rank
2) and site management (Rank 5); (3) material-related factor – on-time delivery of material
(Rank 3); (4) external-related factor – unforeseen site condition (Rank 4); (5) consultant-related
factors – waiting for approval of tests and inspection (Rank 6) and preparation and approval of
drawings (Rank 8); (6) contract and relationship-related factor – lack of communication between
parties (Rank 7); and (7) labor and equipment-related factor – lack of appropriate skills (Rank 9)
and equipment availability (Rank 10). The five important effects of delays, based on RII, are:
cost overrun (Rank 1), (2) disputes (Rank 2), (3) arbitration (Rank 3), (4) litigation (Rank 4), and
The current research has also studied the ‘complete’ set of relationships between causes
and effects of delays at the construct level in TCI. The SEM has been used to study the complex
set of relationships between the various constructs. The hypothesis is supported and the
interesting findings on the effects of delays are: (1) incidence of cost overrun can be explained
by consultant-related and material-related causes (R2 = 0.164); (2) cost overrun factors are
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
important to explaining the disputes (R2 = 0.475); (3) consultant-related factors, cost overrun and
disputes are significant to explaining arbitration (R2 = 0.541); (4) client-related, disputes, and
arbitration factors are keys to explaining litigation (R2 = 0.653); and (5) incidence of
A summary of factors that impact effects of delays is given in Table 6. At this juncture, it
is useful to recall the warning given by Tu et al. (2005) regarding the problems posed by
They have argued that lack of consideration can lead to misinterpretation and erroneous results.
The correlations given in Table 3 indicate that there is a strong evidence of multi-collinearity
effects due to strong correlation between explanatory variables (causes of delays). Besides, our
analysis shows that effects of delays are correlated. Therefore, our contention is that modelling
complex dependencies between and within causes and effects of delays are significant to
understand the relationships. Related to TCI, the findings from the current research are more
comprehensive than the findings by Kikwasi (2012). The major points of departure in the
current research are: (1) a sample size of 308 respondents compared to 40 used by Kikwasi
(2012) and (2) in-depth statistical analyses of relationships using SEM compared to descriptive
statistics by Kikwasi (2012). The analyses used in the current research provide findings that can
help in reducing the effects of delays by controlling the appropriate causes of delays.
What are the important messages conveyed by this research? First, TCE can be used as a
theoretical lens to explain the links between and within causes and effects of delays. Earlier
researchers have depended on the empirical results to understand the links between the factors
(Assaf and Al-Hejji, 2006; Kasimu and Abubakar, 2012; Sambasivan and Soon, 2007). Second,
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
use of multi-variate tools such as SEM (covariance-based or partial least squares-based) are
needed to understand the complex relationships between various factors. Interpretations based
on such analysis are more accurate. Earlier researchers have used simple tools like correlation
and regression that can be subjected to inaccurate results because of collinearity and multi-
collinearity effects (Assaf and Al-Hejji, 2006; Kasimu and Abubakar, 2012; Sambasivan and
Soon, 2007). The empirical results of the current study are based on the data obtained from TCI.
It is believed that the procedure used in this research can be used to study the construction
industry in any country. The recommended actions can then be based on such ‘complete’
analysis. Third, the specific recommendations to TCI are: (1) consultant-related and material-
related causes are critical to explaining the incidence of cost overrun in a project. The results
indicate that waiting for approval of tests and inspection and preparation and approval and
factors of delay. These factors can lead to increase in transaction costs and therefore, cost
overrun. It is the duty of consultants to ensure that all the approvals are obtained on time and the
project managers must make sure that materials (from international and/or local suppliers) arrive
on time to avoid escalation of costs; (2) cost overrun is critical to explaining the incidence of
disputes. Disputes between the parties (clients, contractors, consultants, and suppliers) escalate
if there is increase in costs of the project; (3) client-related factor, disputes, and arbitration lead
to litigation. The results also suggest that problems of finance and payments on time coupled
with other effects of delays lead to litigation; and (5) consultant-related and external-related
causes, disputes, litigation, and arbitration result in abandonment of projects. The analysis of
How can the results of this study be generalized? (1) The establishment of TCE as a
theoretical foundation can enable researchers in any country to link the causes and effects of
delays. (2) The use of a tool such as SEM can enable the researchers and practitioners to see the
complete landscape of relationships between and within causes and effects of delays. (3) The
effects of delays and their rankings are consistent with studies conducted in other countries
(Aibinu and Odeyinka, 2006; Kalibu et al., 2009; Kikwasi, 2012; Sambasivan and Soon, 2007).
It is proposed that such a similar study in any country can use the effect factors considered in this
study. The inter-relationships between the effects of delays can be different in different
countries. According to the current study, (ii) cost overrun results in disputes and arbitration, (ii)
disputes result in litigation, arbitration, and abandonment, (iii) arbitration results in litigation and
abandonment, and (iv) litigation results in abandonment. (4) The causes of delays can be
country-dependent. This study has identified 31 causes and the findings from other studies
indicate that many of these causes are observed in other countries. For example, the top-ranked
factors that are common across studies are: difficulty in making payments, improper planning,
poor project management, site conditions and management, and material related problems.
Insert Table 6
Conclusions
The current study has argued the role of TCE in the construction-industry literature in explaining
the impact of causes on effects of delays. Specifically, it has been shown that increase in
transaction costs due to uncertainty, limited rationality, and opportunistic behavior play a crucial
role in explaining the impact. The application of SEM in analyzing the complex relationships
between causes and effects of delays has been demonstrated. Analyzing and understanding the
relationships can help stakeholders reduce the incidences of delays in the construction industry.
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
These two new developments are the important contributions of this study to the body of
The important findings of this study related to the effects of delays are: (1) cost overrun
can be explained by consultant-related, material-related and time overrun factors (R2 = 0.164);
(3) disputes can be explained by cost overrun (R2 = 0.475); (4) arbitration can be explained by
consultant-related, cost overrun, and dispute factors (R2 = 0.541); (5) litigation can be explained
by client-related, disputes, and arbitration factors (R2 = 0.653); and (6) abandonment can be
0.472).
involved in TCI have been provided. Specific recommendations made to different project
players to avoid delays and related problems in projects are: (1) clients must release payments on
time; (2) project managers must ensure that (i) staff with right skills are employed in the project,
(ii) suppliers provide the input materials (including equipment) on time, and (iii) the project is
well governed through regular communication between the stakeholders; (3) consultants must
ensure that preparation and approval of drawings, tests, and inspection procedures are obtained
on time; and (4) contractors must manage the day-to-day operations in the project sites
efficiently. The researchers and practitioners in other parts of the world can use the approach
outlined in this study to better understand and deal with delays in the construction industry. This
research is not without limitations. First, the number of respondents from clients is very low
compared to the number from consultants and contractors. Second, this study is a cross-sectional
study. As such, the relationship between causes and effects of delays must be treated with
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
caution.
References
Abd El-Razek, M., Bassioni, H., and Mobarak, A., (2008), “Causes of Delay in Building
Construction Projects in Egypt”, Journal of Construction Engineering Management,
134(11), 831–841.
Aibinu A.A., Jagboro G.O., (2002), “The effects of construction delays on project delivery in
Nigerian construction industry”, International Journal of Project Management 20, 593-
599.
Aibinu, A., Odeyinka, A. (2006), “Construction delays and their causative factors in Nigeria”,
Journal of Construction Engineering and Management, 132(7), 667-677.
Alaghbari, W., Kadir, M. R. R., Salim, A., Ernawati., (2007), “The significant factors causing
delay of construction projects in Malaysia”, Engineering, Construction, and
Architectural Management, 14(2), 192-206.
Alinaitwe, H., Apolot, R., Tindiwensi, D., (2013), “Investigation into the Causes of Delays and
Cost Overruns in Uganda's Public Sector Construction Projects”, Journal of Construction
in Developing Countries, 18(2), 33–47.
Assaf, S. A., Al-Khalil, M., Al-Hazmi, M. (1995), “Causes of delay in large building
construction projects”, Journal of Management in Engineering, 11(2), 45-50.
Assaf, S. A., Al-Hejji. S., (2006), “Causes of delay in large construction projects”, International
Journal of Project Management, 24(4), 349–57.
Chan, D. W. M., Kumaraswamy, M. M., (1997), “A comparative study of causes of time
overruns in Hong Kong construction projects”, International Journal of Project
Management, 15(1), 55-63.
Chen, Y., Zhang, Y., Liu, J., and Mo, P. (2012), “Interrelationships among Critical Success
Factors of Construction Projects Based on the Structural Equation Model”, Journal of
Management Engineering, 28(3), 243–251.
Cho, K. M., Hong, T. H., Hyun, C. T., (2009), “Effect of project characteristics on project
performance in construction projects based on structural equation model”, Expert Systems
with Applications: An International Journal, 36(7), 10461-10470.
D’Alpaos, C., Moretto, M., Valbonesi, P., Vergalli, S., (2013), “Time overruns as opportunistic
behavior in public procurement”, Journal of Economics, 110(1), 25-43.
Dubois, A., Gadde, L. E., (2002), “The construction industry as a loosely coupled system:
implications for productivity and innovation”, Construction Management and Economics,
20(7), 621-631.
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
Frimpong, Y., Oluwoye, J., Crawford, L., (2003), “Causes of delay and cost overruns in
construction of groundwater projects in developing countries: Ghana as a case study”,
International Journal of Project Management, 21 (5), 321-326.
Hair, J.F., Black, B., Babin, B., Anderson, R., Tatham, R. L., (2010), Multivariate Data Analysis,
Pearson International, New York, NY.
Kaliba, C., Muya, M., Mumba, K. (2009), “Cost escalation and schedule delays in road
construction projects in Zambia”, International Journal of Project Management, 27, 522-
531.
Kasimu, M. A., Abubakar, I. D., (2012), “Causes of delay in Nigerian construction industry”,
Interdisciplinary Journal of Contemporary Research in Business, 4 (2), 758-794.
Khalili-Damghani, K., Tavana, M., (2014), “A Comprehensive Framework for Sustainable
Project Portfolio Selection Based on Structural Equation Modeling”, Project
Management Journal, 45, 83–97.
Kikwasi, G. J., (2012), “Causes and effects of delays and disruptions in construction projects in
Tanzania”, Australasian Journal of Construction Economics and Building, Conference
Series, 1(2), 52-59.
Klein, P. G., Shelanski, H. A., (1996), “Transaction cost economics in practice: applications and
evidence”, Journal of Market Focused Management, 1, 281-300.
Kometa, S. T., Olomolaiye, P. O., Harris, F. C. (1994), “Attributes of UK construction clients
influencing project consultants’ performance”, Construction Management Economics, 12,
433-443.
Li, A., Arditi, D., Wang, Z. (2014), “Transaction costs incurred by construction owners”,
Engineering, Construction, and Architectural Management, 21(4), 444-458.
Lua, W., Zhang, L., Pan, J., (2014), “Identification and analyses of hidden transaction costs in
project dispute resolutions”, International Journal of Project Management, in press.
Marzouk, M. M., El-Rasas, T. I. (2014), “Analyzing delay causes in Egyptian construction
projects”, Journal of Advanced Research, 5(1), 49-55.
Memon, A. H., Rahman I. A., Aziz, A. A. A., Abdullah, N. H. (2012), “Using Structural
Equation Modelling to Assess Effects of Construction Resource Related Factors on Cost
Overrun”, World Applied Sciences Journal 20 (Mathematical Applications in
Engineering): 06-15, 2012.
Molenaar, K., Washington, S., Diekmann, J. (2000), “Structural Equation Model of Construction
Contract Dispute Potential”, Journal of Construction Engineering Management, 126(4),
268–277.
Nguyen, D. L., Ogunlana, S., Quang, T., Lam, K. C. (2004), “Large construction projects in
developing countries: a case study from Vietnam”, International Journal of Project
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
Williamson, O. E., (1996), The Mechanisms of Governance, New York, Oxford University Press.
Williamson, O. E., (2007), “Transaction cost economics: an introduction. Economics discussion
papers”, discussion paper 2007-3. Can be accessed at: http://www.economics-
ejournal.org/economics/discussionpapers.
Winch, G., (1989), “The construction firm and the construction project: a transaction cost
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
reputation.
Kikwasi (2012) Design changes, delays in Time overrun, Descriptive
payment to contractors, cost overrun, statistics
Tanzania information delays, funding disputes, and
problems, poor project other negative
management, compensation impacts
issues and disagreement on
the valuation of work done
Memon et al. Machinery, material, Cost overrun SEM
(2013) finance, manpower
Malaysia
Alinaitwe, Delayed Payments, Cost and time Descriptive
Apolot, and material, labor/equipment, overruns statistics and rank
Tindiwensi Scope changes, project correlation
(2013) management, external,
contractor, client, contract,
Uganda and contractual
relationships
Current study Client, contractor, Time overrun, Descriptive
consultant, material, cost overrun, statistics and SEM
Tanzania labor/equipment, contract, dispute,
contractual relationships, arbitration,
and external litigation, and
abandonment
Table 1. Summary of literature review
S/N HYPOTHESIZED CAUSES PERCENTAGE OF RESPONDENTS SCORING RANKING OF CAUSES
1 C lient R e lat ed C ause s 4 3 2 1 R II RANK
1 finance and payment of co mpleted wo rks 54.5 35.5 8.7 1.3 0.861 1
2 o wner interference 12.3 53.2 26.1 8.4 0.669 28
2 C o ntra ct o r R elat ed C a us es
4 waiting for approval o f tests and inspection 40.3 33.2 22.9 3.5 0.773 6
6 C o ntra ct R e la te d C ause s
5 inappro priate o verall organizatio nal structure linking 20.3 50.3 26.5 2.9 0.713 21
6 lack of communication between the parties 37.7 40.6 18.1 3.5 0.77 7
Total
34.80 21.90 14.80 4.500 0.477 5
abandonment
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
CO DI AR LI TA
Cost overrun
1.00
(CO)
Dispute (DI) 0.653 1.00
Arbitratio
0.555 0.702 1.00
n (AR)
Litigatio
0.516 0.670 0.784 1.00
n (LI)
Total
Abandonmen 0.388 0.520 0.611 0.595 1.00
t (TA)
Table 3. RII scores, ranking of ‘effect’ factors, and correlation between effect factors
1 2 3 4 5 6 7 8 9 10 11 12
1 1.00
2 0.979 1.00
10 -0.393 -0.418 -0.379 -0.406 -0.407 -0.431 -0.421 0.555 0.702 1.00
11 -0.357 -0.395 -0.361 -0.384 -0.401 -0.406 -0.416 0.516 0.670 0.784 1.00
12 -0.185 -0.222 -0.165 -0.201 -0.201 -0.233 -0.188 0.388 0.520 0.611 0.595 1.00
Contract- 0.903 – 0.970 0.865 0.969 0.983 0.971 0.963 0.966 1.00
related (5 0.949
items)
External- 0.886 – 0.960 0.859 0.940 0.951 0.951 0.945 0.946 0.955 1.00
related (4 0.964
items)
Client-related
Contractor- related
External-related Arbitration
Complete abandonment
0.619
0.497
0.2790.432 0.445
Downloaded by University of Newcastle At 07:11 08 February 2017 (PT)
R2=0.475 R2=0.643
Litigation
Disputes 0.236