Professional Documents
Culture Documents
Analysis of Rates
Introduction
While filling the tender if a contractor wants to quote the rate of a particular item,
first he has to work out the rate. The procedure for working out the rate of an item
is known as rate analysis. For example, he wants the rate of R.C.C. slab, from
experience or by other means (drawing etc.) he works out the quantities of
materials, that are how many bags of cement, aggregates and steel is required for
the slab. Along with the materials he also calculates how many labours are
required to complete the work in stipulated time and then adds his percentage of
profit. At the same time he keeps other factors also, which can influence his work,
in mind and arrives at a figure for each item and quote it in tender which is the
rate for that particular item at that place in that particular condition and time.
Following factors should be taken into to fix up the rates per unit of item
(a) Quantity of materials and cost: It includes cost of transportation charges, sales
tax, insurance charges etc.
(b) Labour cost: The number and wages of different categories of labours,
(skilled, unskilled, semiskilled, should be known per unit of item)
1
(c) Cost of equipment: Operation cost, rent charges etc. for each tool to be used.
The total cost should divide for the whole duration of the work and should be
added to the particular item.
(d) Overhead charges: It includes office rent, depreciation of equipment, postage,
lighting, traveling, telephone bills, small tools etc.
(e) Profit: Generally a profit of 10 % is considered reasonable, but it varies from 8
% for big projects to 15 % for small projects.
GoH = Covers cost of maintaining Head office, staff office space (cost of
owning /Rental) cost of borrowed capital etc.
GoH = R x Dc
Direct cost: This is incurred only when the project is taken up after the work is
awarded.
PoH: project overheads costs are incurred for salary of project manager, office
staff at project site office, communication temporary accommodation etc.
It is also includes insurance premium & compensation etc.
2
For correct estimate of task costs it is necessary that bill of quantities should
precisely be known.
The quantity of the material to be used for a particular task known from the bill of
quantities
Mc = K * Q * Uc + D + ST
Labour cost, L = N * t * Hc + F * t
Task duration:- depends upon quantity of work and nature of work, also on No.
of resources employed.
For each activity, there is a critical resource person/equipment and usually no. of
this critical resource is limited (fixed). For example, in excavation task,
excavators are critical resources and masons are critical resource for brick work.
3
Normally the routine equipments such as concreting mixers or vibrators are not
considered separately but included in the rate of the concrete. For special
equipment to be borrowed from market:
E = N * t * Hc + DAR
Alternatively, the contractor on the basis of his past experiences can change for
equipment on lumpsum basis or as % of other component – Equipment for
excavation: Birr/ m3 of excavation.
Sub- contractors cost: If any activity needs highly specialized services then
the sub- contract would be given for that.