You are on page 1of 3

ID ID Task Task Name Duration Start Finish 2020 2021 2022

Mode H2 H1 H2 H1 H2 H1
1 1 Contract PT327 608 days Thu 2/1/20 Tue 3/5/22
2 2 Letter of Award 1 day Thu 2/1/20 Fri 3/1/20
3 3 Preliminaries 60 days Thu 2/1/20 Thu 26/3/20
4 4 Topographical Survey/ SIP/ DIP 21 days Fri 3/1/20 Mon 3/2/20
5 5 Cable Detection 30 days Fri 3/1/20 Fri 14/2/20
6 6 ECM Design and Submission 45 days Fri 3/1/20 Fri 6/3/20
7 7 Physical site survey and 60 days Fri 3/1/20 Fri 27/3/20
investigation (Trial Holes)
8 8 Design Drawing and Materials 60 days Fri 3/1/20 Fri 27/3/20
Submission
9 9 Submission of Conceptual 21 days Fri 3/1/20 Mon 3/2/20
Design AIP
10 10 Submission of Preliminary Design30 days Mon 3/2/20 Mon 16/3/20
11 11 Submission of Clearance to 21 days Tue 17/3/20 Wed 15/4/20
Techincal Agencies and Relevant
Authorities
12 12 Submission of Final Design to 21 days Thu 16/4/20 Fri 15/5/20
LTA/ SMRT
13 13 BCA Application for Permit to 21 days Fri 15/5/20 Mon 15/6/20
Commence Works
14 14 Materials submission to LTA and 21 days Fri 15/5/20 Mon 15/6/20
approval
15 15 Physical Works 400 days Tue 16/6/20 Tue 28/12/21
16 16 Bus Parking 365 days Tue 16/6/20 Tue 9/11/21
17 17 Site Clearance 60 days Tue 16/6/20 Tue 8/9/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Programme.mpp
Summary Manual Summary Rollup Progress
Date: Wed 12/6/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID ID Task Task Name Duration Start Finish 2020 2021 2022
Mode H2 H1 H2 H1 H2 H1
18 18 Construction of Drain 120 days Thu 16/7/20 Thu 31/12/20
19 19 Construction of Kerb 120 days Mon 3/8/20 Mon 18/1/21
20 20 Construction of Semi Rigid 90 days Fri 18/9/20 Fri 22/1/21
Pavement
21 21 Construction of Motorcycle 45 days Sat 21/11/20 Fri 22/1/21
Parking Lots
22 22 Thermoplastic Painting and 30 days Fri 11/12/20 Fri 22/1/21
Other Signage
23 23 Facilities 250 days Sat 23/1/21 Fri 7/1/22
24 24 Construction of Foundation 90 days Sat 23/1/21 Fri 28/5/21
25 25 Intallation of Safety Bollards 30 days Sat 29/5/21 Fri 9/7/21
26 26 Casting of Slab 60 days Sat 10/7/21 Fri 1/10/21
27 27 Installation of Steel Sturctures 120 days Sat 2/10/21 Fri 18/3/22
28 28 Installation of Roof 60 days Fri 19/3/21 Fri 11/6/21
29 29 Construction of facilities room 90 days Sat 12/6/21 Fri 15/10/21
30 30 Architectural Works and others 90 days Sat 16/10/21 Fri 18/2/22
31 31 Electrical Works 180 days Sat 15/5/21 Fri 21/1/22
32 32 LV Main Swtichboard, Sub 90 days Sat 15/5/21 Fri 17/9/21
Switchboards, DB, Power Points
33 33 Light System incld cabling and 90 days Sat 18/9/21 Fri 21/1/22
ducting
34 34 Equipotential System, LPS, EPS 90 days Sat 18/9/21 Fri 21/1/22
35 35 Telecome System, CCTV 90 days Thu 9/9/21 Thu 13/1/22
36 36 Mechanical Works 180 days Thu 15/4/21 Thu 23/12/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Programme.mpp
Summary Manual Summary Rollup Progress
Date: Wed 12/6/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID ID Task Task Name Duration Start Finish 2020 2021 2022
Mode H2 H1 H2 H1 H2 H1
37 37 Airconditioning, Ducting 150 days Thu 15/4/21 Thu 11/11/21
38 38 Mechanical Ventilation System 120 days Thu 15/4/21 Thu 30/9/21
39 39 Plumbing and Sanitary Works 180 days Mon 15/3/21Mon 22/11/21
40 40 TOP & CSC 115 days Mon 22/11/21Mon 2/5/22
41 41 As Built Drawings 60 days Tue 23/11/21Tue 15/2/22
42 42 BCA TOP 60 days Tue 23/11/21Tue 15/2/22
43 43 BCA CSC 60 days Wed 15/12/21Wed 9/3/22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Programme.mpp
Summary Manual Summary Rollup Progress
Date: Wed 12/6/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3

You might also like