D'INTAN TRADE SDN. BHD ace
LOT 2152, JALAN TOK KENALI WAKAF STAN, KUBANG A
Kwan
1561296.) 16150 KOTA BHARU, KELANTAN CSR/4D/2020/SM-066
Ter 0764500 FO. F650
SITE MEMO
CENTRAL SPINE ROAD (CSR), PAKEJ 4 : KG. RELONG KE RAUB.
SEKSYEN 4D : KUALA DONG KE KG. TANAH BERCANGKUL
TO :T &T Konsult Sdn Bhd Date : 17-11-2020
ATTN :lr. Shaari bin Mohd
cc. WpP JKR Ir. Nasrollah bin Mohamad , DTSB HQ, File
SUBJECT: Method of Statement - Surface Drainage
Hereby the Method of Statement for Surface Drainage as per JKR Standard Road Specification
for Road Works for your further review and approval.
Thank you
Prepared by : + —
BDU ALIN BIN ABDUL HAN ——$§$
mn PENGURUS PROJEK
Name:
y TRADE SDN BHD
Company: DINTAN ‘Company
Date Date
\F-4->010D'INTAN TRADE SDN. BHD
LOT 2152, JALAN TOK KENALI WAKAF STAN, KUBANG KERIAN,
16150 KOTA BHARU, KELANTAN
(561296-M) Tel 09-7643500 Fax : 09-7646500
CENTRAL SPINE ROAD (CSR)
PAKEJ 4: KG. RELONG KE RAUB.
SEKSYEN 4D : KUALA DONG KE KG. TANAH BERCANGKUL
METHOD OF STATEMENT FOR
SURFACE DRAINAGE
IMPORTANT :
The information contained herein is the propriety of D'Intan Trade Sdn. Bhd.
The holder agrees to following
Not to be produced, revealed, published, or distributed in whole or any portion of it without
authorization and to maintain this document in confidence.
This approval shall not relieve the Contractor of his full responsibility to the contractual requirement
of the works carried out. $.0/S.0.R shall have full authority to review this approval based on the
actual site condition.
Prepared By Reviewed By =
oe UL HAMID
Name ‘QURRATU MAILAA BT. NASARUDDIN Name PENGURUS PROJEK
Company aac Company D’INTAN TRADE SON BHO
Date DP INTAN TRADE SON BHD Date:
‘Approved By "agreed By
Name Name
Company Company
Date DateDOCUMENT REF : D'INTAN TRADE SDN BHD
CENTRAL SPINE ROAD PAKEJ 4: KG. RELONG KE
RAUB, SEKSYEN 4D: KUALA DONG KE KG. TANAH
SECTION
BERCANGKUL
‘CONTRACT/SPECIFICATION REF: PROJECT WORK: METHOD STATEMENT | OTHER REFERENCES
JKR/IP/CA/T/2019/42 METHOD STATEMENT FOR SURFACE DRAINAGE
METHOD STATEMENT SURFACE DRAINAGE
CONTENTS
1.0 Objective
2.0 References
3.0 Equipments, Machineries and Manpower
4.0 Construction Methodology
5.0 Quality Control Procedure
6.0 Environmental, Health and Safety Plan
7.0 Emergency Response Plan
REV:0 ISSUE: METHOD STATEMENT FOR SURFACE ORAINAGE PAGE 10F 4DOCUMENT REF: D'INTAN TRADE SDN BHD. SECTION +
CENTRAL SPINE ROAD PAKEJ 4: KG, RELONG KE
RAUB, SEKSYEN 40: KUALA DONG KE KG. TANAH
BERCANGKUL
‘CONTRACT/SPECIFICATION REF: |, pROJECT WORK: METHOD STATEMENT | OTHER REFERENCES :
sKR/IP/CI/T/2019/42 METHOD STATEMENT FOR SURFACE DRAINAGE
METHOD STATEMENT [SURFACE DRAINAGE
1.0 OBJECTIVE
1.1 To ensure that works are carried out in accordance with the specifications and
drawing.
1.2. To ensure routine inspection is carried out.
1.3. To eliminate/minimize errors and poor quality of work.
2.0 REFERENCES
2.1 Construction drawing no
2.1.1 KPKR/J/R/060953/P4/DR/SD/(01-13) - Drainage Standard Details
2.1.2 KPKR/I/R/060953/P4/S4D/DR/LA/(01-20) - Drainage Layout Plan
CH 314000 - CH 44+661.984
2.2 JKR Standard specification for road works :Section 3:
3.0 EQUIPMENTS, MACHINERIES AND MANPOWER
3.1. Excavators/ Backhoe complete with slings
3.2 Tipper/ Dump Trucks
3.3 Calibrated surveying equipment
3.4 Proctor Test apparatus
3.5. Mobile crane complete with concrete skips
3.6 Poker vibrator complete with petrol engines
nage Works
REV:0 ISSUE: METHOD STATEMENT FOR SURFACE DRAINAGE
PAGE20F 4DOCUMENT REF D'INTAN TRADE SDN BHD SECTION
‘CENTRAL SPINE ROAD PAKEJ 4: KG, RELONG KE
RAUB, SEKSYEN 40: KUALA DONG KE KG. TANAH
BERCANGKUL
CCONTRACT/SPECIFICATION REF: PROJECT WORK: METHOD STATEMENT | OTHER REFERENCES
IKR/IP/CA/T/2019/42 METHOD STATEMENT FOR SURFACE DRAINAGE
METHOD STATEMENT ‘SURFACE DRAINAGE
4.0 CONSTRUCTION METHODOLOGY
4.1 To carry out survey and setting out works in order to identify the required extend of
surface drain alignment, length, and invert levels.
4.2 Keeping to the specified line and gradient, the surface drain should be excavated as per
construction drawing. Refer dwg
43. Excavated surface drain trench should be cleared from any form of unsuitable
materials/ debrics,
4.4. Reinforced with steel wire fabrics to ms should be placed along the surface drain
alignment prior to concreting works.
45. Concrete works shall be carry out using concrete Grade 20/20 as per construction
drawing. Refer dwg
5.0 QUALITY CONTROL PROCEDURE
5.1 The work shall be carried out in accordance with the Quality Control Procedure.
6.0 ENVIRONMENTAL, HEALTH AND SAFETY PLAN
6.1 The work shall be carried out in accordance with the Environment, Health, and
Safety Plan.
6.2. All workers are required to wear Personnel Protective Equipment (PPE)
i.e. safety helmets, safety boots and safety vest when working at roadside within
reserve.
6.3. Barriers will be located at the work area to avoid public from entering the site if
required.
REV:0 ISSUE; METHOD STATEMENT FOR SURFACE ORAINAGE PAGE 3.OF 4DOCUMENT REF : D'INTAN TRADE SDN BHD. SECTION
CENTRAL SPINE ROAD PAKEJ 4: KG. RELONG KE
RAUB, SEKSYEN 4D: KUALA DONG KE KG. TANAH
BERCANGKUL
‘CONTRACT/SPECIFICATION REF: PROJECT WORK : METHOD STATEMENT | OTHER REFERENCES
JKR/IP/CS/T/2019/42 METHOD STATEMENT FOR SURFACE DRAINAGE
METHOD STATEMENT ‘SURFACE DRAINAGE
7.0 EMERGENCY RESPONSE PLAN
7.1 The work shall be carried out in accordance with the emergency response plan
when health and safety of worker are threatened,
7.2 The plan will be used to manage emergency incident to protect life, the
environment, property, and restore the condition to normal condition in the
shortest possible time.
REV:0 ISSUE: METHOD STATEMENT FOR SURFACE DRAINAGE PAGE 4.0F 4