You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/276113470

Causes of Delay in Construction Projects in the Oil and Gas Industry in the Gulf
Cooperation Council Countries: A Case Study

Article in Journal of Management in Engineering · May 2015


DOI: 10.1061/(ASCE)ME.1943-5479.0000248

CITATIONS READS

184 6,628

2 authors, including:

Hamdi Bashir
University of Sharjah
78 PUBLICATIONS 1,036 CITATIONS

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Project Mangement View project

All content following this page was uploaded by Hamdi Bashir on 09 July 2019.

The user has requested enhancement of the downloaded file.


Case Study

Causes of Delay in Construction Projects in the Oil


and Gas Industry in the Gulf Cooperation Council
Countries: A Case Study
Mohammed Ruqaishi 1 and Hamdi A. Bashir 2
Downloaded from ascelibrary.org by IMPERIAL COLLEGE LONDON on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.

Abstract: Several studies investigating the causes of delay in projects in the construction industry have been conducted worldwide. This
study investigates the causes of delay in construction projects in oil and gas processing facilities in Oman and serves as a case study for the
Gulf Cooperation Council (GCC) countries. Using a questionnaire, data were collected from 59 project managers employed in different
organizations in the oil and gas industry in Oman. The survey results showed a high degree of agreement among the perceptions of project
stakeholders, clients, contractors, and consultants on the causes of project delay, and there is no evidence to suggest that the causes of project
delay differ significantly according to organization size or organizational ownership. Moreover, seven factors were identified as the major
causes of project delay. Although six of these identified elements are general factors that can account for delay in any project in any industry,
one of them—poor interaction with vendors in the engineering and procurement stages—is found to be unique to construction projects in the
oil and gas industry. The findings of this study could be of value to organizations that are planning to conduct construction projects for oil and
gas processing facilities in Oman and other nations with similar environments, such as the GCC countries. DOI: 10.1061/(ASCE)ME.1943-
5479.0000248. © 2014 American Society of Civil Engineers.
Author keywords: Delay; Construction projects; Oil and gas industry; Oman.

Introduction technology services, and outsourcing company, project delays and


cost overruns in certain industries, such as oil and gas, could cost
Project delay is one of the most common problems in the construc- companies trillions of dollars in lost investments. Moreover, proj-
tion industry worldwide. For example, Odeyinka and Yusif (1997) ect delays and cost overruns in the oil and gas industry can also
reported that 7 out of 10 projects surveyed in Nigeria suffered hamper the economic development of countries whose economies
delays. According to Assaf and Al-Hejji (2006), 70% of the large are heavily dependent on the lucrative oil and gas sector, such as
construction projects studied in Saudi Arabia experienced average the Gulf Cooperation Council (GCC) countries. Examples of oil
time overruns of between 10 and 30%. Further, Faridi and and gas construction projects include the construction of gas treat-
Al-Sayegh (2006) revealed that 50% of the construction projects ment units, refinery, and petrochemical plants. Although they are
studied in the United Arab Emirates (UAE) encountered delays. similar to projects in any other industry in that all projects require
According to a survey conducted by the U.S. management consult- planning, organization, coordination, and control, oil and gas con-
ing firm Booz Allen Hamilton, the leaders of 10 out of 20 compa- struction projects have some unique characteristics: (1) they use
nies from the United States, Europe, and Asia stated that 40% of high-technology, made-to-order products; (2) since they are usually
their oil and gas construction projects are plagued by significant conducted in remote desert areas, they encounter unique commu-
schedule and cost overruns (McKenna et al. 2006). Sambasivan nication and logistical challenges; (3) they are technically complex
and Soon (2007) reported that 17.3% of the construction projects projects and usually comprise several subprojects, which involve
in Malaysia encountered delays of over three months. In Oman, of the integration of different technical fields (IEA 2006; Dey 2012);
the 40 construction projects that were implemented for a major and (4) they have considerable environmental and social impacts
public organization over the past three years, only 62% were com- (Dey 2012).
pleted within the stipulated time; no formal records are available for
explaining the cause of project delay in Oman.
Apart from its negative impact on project delivery, project delay Literature Review
can cause cost overrun and disputes among project stakeholders
(Aibinu and Jagboro 2002; Sambasivan and Soon 2007). Accord- Since the problem of project delay is contextual, studies have
ing to Accenture, a Boston-based global management consulting, been conducted to investigate this problem in the construction in-
dustry in several countries. These include Nigeria (Mansfield et al.
1
Consulting Engineer, Tebodin & Partner LLC, 24 Azaiba Plaza, Way 1994); Thailand (Ogunlana et al. 1996; Toor and Ogunlana 2008);
61, Al Ma’aridh St., PC 130, Al Athaibah, Muscat, Sultanate of Oman. Hong Kong (Chan and Kumaraswamy 1997; Lo et al. 2006);
2
Associate Professor, Dept. of Industrial Engineering and Management, Indonesia (Kaming et al. 1997); Lebanon (Mezher and Tawil
Univ. of Sharjah, Sharjah, United Arab Emirates (corresponding author).
1998); Saudi Arabia (Al-Khalil and Al-Ghafly 1999; Assaf and
E-mail: hbashir@sharjah.ac.ae
Note. This manuscript was submitted on October 18, 2012; approved on
Al-Hejji 2006); Jordan (Al-Momani 2000; Odeh and Battaineh
July 29, 2013; published online on August 1, 2013. Discussion period open 2002); Ghana (Frimpong et al. 2003); Kuwait (Koushki et al. 2005);
until September 7, 2014; separate discussions must be submitted for indi- UAE (Faridi and Al-Sayegh 2006); Malaysia (Alaghbari et al.
vidual papers. This paper is part of the Journal of Management in Engi- 2007; Sambasivan and Soon 2007); Vietnam (Thuyet et al. 2007;
neering, © ASCE, ISSN 0742-597X/05014017(8)/$25.00. Le-Hoai et al. 2008; Luu et al. 2009); China (Zou et al. 2007);

© ASCE 05014017-1 J. Manage. Eng.

J. Manage. Eng.
Egypt (Abd El-Razek et al. 2008); Canada (Jergeas 2008; Jergeas • There has not been any study to date that investigated the as-
and Ruwanpura 2010); Jordan (Sweis et al. 2008); South Korea sociation between organization size and factors causing project
(Han et al. 2009); Gaza Strip (Enshassi et al. 2009); Zambia (Kaliba delays. Compared to large organizations, small organizations
et al. 2009); Iran (Pourrostam and Ismail 2011; Fallahnejad 2013); are usually short of capital and skilled staff, have little market
Pakistan (Haseeb et al. 2011); and India (Dey 2012). influence, and have only short-term objectives. On the other
Thuyet et al. (2007), Jergeas (2008), Jergeas and Ruwanpura hand, small organizations generally have better internal com-
(2010), Dey (2012), and Fallahnejad (2013) are perhaps the only munication, greater flexibility, and better relationships with
studies that focused on oil and gas construction projects. Thuyet customers (Ahire and Golhar 1996; Haksever 1996; Gulbro
et al. (2007) conducted a survey to identify the risk factors affecting et al. 2000).
oil and gas construction projects in Vietnam. Based on responses • There has not yet been any study that investigated the associa-
from 42 top managers, project managers, functional managers, risk tion between the type of ownership and factors causing project
experts, and project team members, the following five factors were delays. As compared to private organizations, government-
Downloaded from ascelibrary.org by IMPERIAL COLLEGE LONDON on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.

identified as the major causes of project delay: (1) bureaucratic owned organizations are less flexible, have more bureaucratic
government systems and long project approval procedures, (2) poor decision-making processes, and usually lack skilled staff. How-
design, (3) incompetence of project teams, (4) inadequate tendering ever, government-owned organizations usually do not face any
practices, and (5) delay in internal approval processes from the shortage of funds.
owners. It is evident that none of these factors can be considered • There has not been any study investigating the causes of project
unique to oil and gas construction projects; these are general factors delay in Oman.
that could cause delays in any project, regardless of industry.
As part of a large-scale research project for investigating cost
overruns and the front-end planning process of megaprojects in Objectives and Development of Hypotheses
the oil sands of Alberta, Canada, Jergeas (2008) surveyed inter-
national senior project manager ownership, engineering procure- The main objective of this study is to investigate factors that cause
ment, and construction organizations in Canada, the United States, delays in construction projects in oil and gas processing facilities in
the United Kingdom, Norway, Germany, Spain, Chile, India, and Oman, which serves as a case study for the Gulf GCC countries
Australia. Based on the analysis of the survey results, the causes for (Bahrain, Kuwait, Oman, Qatar, Saudi Arabia, and the UAE).
cost and schedule overruns were classified under the following These six countries, along with Iran and Iraq, hold 56 and 40%
of the world’s proven reserves of conventional oil and gas (IEA
three categories: (1) unrealistic or overly optimistic original cost
2013). In addition to sharing common borders, the GCC countries
estimates and schedules; (2) incomplete scope definition or inad-
have relatively similar political systems and share a common lan-
equate front-end loading and poorly completed front-end deliver-
guage, religion, and social values.
ables, including milestone schedule slippage; and (3) inappropriate
This investigation aimed at providing answers to the following
project strategies for the mega–oil sands environment. Jergeas
questions:
and Ruwanpura (2010) expanded the work of Jergeas (2008)
1. Are the causes of project delay perceived significantly dif-
and reclassified the causes of cost and schedule overruns into
ferently by project stakeholders, clients, contractors, and
the following five categories: (1) misplaced optimism, (2) mis-
consultants?
guided objectives, (3) misaligned strategies, (4) misdirected execu-
2. Do the causes of project delay differ significantly according to
tion, and (5) missing links.
organization size?
Dey (2012) proposed an integrated analytical framework for
3. Do the causes of project delay differ significantly according to
project risk management by conducting a case study on a petroleum
organizational ownership?
oil refinery construction project in central India. In this method, the
4. What are the major causes of delay in construction projects for
risk factors influencing time, cost, and quality were identified by
oil and gas processing facilities in Oman?
project executives using a cause-and-effect diagram for each project
To address the first three research questions, the following three
work package. The identified factors then were compiled by the
null hypotheses were developed:
risk management group to consolidate the list of factors for the en-
• H1: Causes of project delay are not perceived significantly
tire project. The list of factors was classified under five categories:
differently by clients, contractors, and consultants.
(1) technical risks; (2) financial, economic, and political risks;
• H2: Causes of project delay do not differ significantly according
(3) organizational risks; (4) natural hazards; and (5) statutory clear-
to company size.
ance risks. The next major step was to rank the risks using the ana-
• H3: Causes of project cost overrun do not differ significantly
lytic hierarchy process (AHP), which enabled the identification of
according to company ownership.
the major factors influencing time, cost, and quality, including
scope change, engineering and design change, technology, and im-
plementation methodology selection. Methodology
Most recently, Fallahnejad (2013) conducted a survey to iden-
tify and rank the causes of delay in gas pipeline construction proj- This section describes the methodology for investigating the causes
ects in Iran. Based on responses from 23 experts in executions of delay in construction projects in the oil and gas industry in
of oil/gas pipeline projects, it was found that the 10 most important Oman. It focuses on the process of collecting data and the analysis
causes of project delay (from among 44 factors) were related to tools used.
imported materials, unrealistic project duration, client-related ma-
terials, land expropriation, change in orders, contractor selection
Questionnaire Design and Data Collection
methods, payments to contractors, obtaining permits, late delivery
of ordered materials by suppliers, and contractors’ cash flows. For controlling the data collected and facilitating analysis, it was
This brief review of the literature reveals the following: decided to employ a questionnaire with closed-type questions.
• Factors affecting project delay vary from one country to To ensure clarity and completeness of the questionnaire and the
another. applicability of the listed causes, which were identified using a

© ASCE 05014017-2 J. Manage. Eng.

J. Manage. Eng.
50–100 No more than
review of the literature, to the oil and gas construction projects in Employees, 2% 50 Employees,
Oman, a pilot study that included project managers from 10 differ- 5%
ent organizations was conducted. The responses received from
these organizations were used as a guide for refining the question-
naire. The first portion comprised questions regarding the respond- More than 1000
ent’s work experience and organization profile, including the Employees,
number of employees, scope of work, and owner type. The second 44% 101–500
portion was designed to address the main aspect being investigated Employees,
in this study—that is, causes of project delay. In this section, re- 42%
spondents were requested to indicate the level of importance of
44 possible causes of project delay using a 5-point Likert scale
(1 = unimportant, 2 = not very important, 3 = important, 4 = very
Downloaded from ascelibrary.org by IMPERIAL COLLEGE LONDON on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.

important, and 5 = extremely important). Based on the sources of 501–1000


delay, the factors causing project delay listed in the questionnaire Employees, 7%
were classified into eight main groups:
1. Client-related causes; Fig. 1. Response distribution based on organization size
2. Contractor-related causes;
3. Consultant-related causes;
4. Material-related causes;
5. Labor- and equipment-related causes; Joined State-
6. Contract-related causes; Venture, owned,
7. Contract relationship-related causes; and 10% 13%
8. External causes.
A very important step in the data collection process is to select
the sample size. The most effective way to ensure the generality of Public–Private, International,
29% 24%
results is to use a sufficiently large sample. However, in this type of
research, since the size of the population of interest is small, the
sample size can be relatively small as well. In addition to popula- Local Private,
tion size, the sample size depends on factors like minimum accept- 24%
able level of precision and confidence level. In this study, the
sample size was determined based on the most widely used rule
of thumb, “use as many subjects as you can get and you can afford” Fig. 2. Response distribution based on organization owner
(Olejnik 1984). Based on this rule, the questionnaire was sent to a
random sample of 210 project managers of client, contracting, and
consultant organizations in both public and private sectors using
Analysis Tools
multiple sources such as Web-based survey tools, electronic mail,
regular mail, and hand delivery. In order to increase the response To analyze the collected data, the following three nonparametric
rate, respondents were given the option to return either a soft copy statistical tools were used: the reliability test, the Kruskal-Wallis
or hard copy of the completed survey questionnaire. A total of 59 test, and the median. The reliability of the questionnaire was tested
respondents (27 from client organizations, 13 from consultant or- using Cronbach’s alpha, a coefficient of reliability. The Kruskal-
ganizations, and 19 from contracting organizations) returned the Wallis test was used for testing the null hypotheses, and the median
questionnaire, representing a 28% response rate. Unfortunately, was used for ranking purposes.
obtaining a larger sample size was not possible in this study. This Cronbach’s alpha is a measure of internal consistency; that is, it
has always been a problem in this type of research. For example, measures how closely related a set of items are as a group. A high
the sample sizes in Thuyet et al. (2007) and Fallahnejad (2013) Cronbach’s alpha is often used as evidence that the items measure
were 42 and 23, respectively. Thus, the sample size of the study an underlying construct. Cronbach’s alpha (α) is defined as
presented in this paper compares favorably with those reported  Pk 2 
in earlier relevant studies. k j¼1 σUj
α¼ 1− ð1Þ
Figs. 1 and 2 present organization size and owner type in 1−k σ2X
the sample distribution. As shown in Fig. 1, the responses were
received from companies of different sizes—that is, 5% of the where k is the number of questions; σ2Uj is the variance of scores on
responses were received from organizations with 50 or fewer em- each question; and σ2X is the total variance of overall scores.
ployees, 2% from organizations with 50 to 100 employees, 42% The Kruskal-Wallis test is one of the most appropriate tests for
from organizations with 101 to 500 employees, 7% from organi- analyzing Likert-scale responses and situations where the normal-
zations with 501 to 1,000 employees, and 44% from organizations ity assumption is unjustified (Montgomery 2005). The technique
with more than 1,000 employees. It is worth noting that organiza- tests the null hypothesis that the treatments (e.g., project stakehold-
tion size can be classified in different ways; however, the number ers) are identical against the alternative hypothesis that some of the
of employees is the most widely used classification. The sample treatments are different. In this technique, all the observations are
distribution by owner type is summarized in Fig. 2; 13% of the ranked in ascending order, with the average rank given to any value
responses were received from state-owned organizations, 29% from that results in a tie; then, the test statistic (KW) is computed
jointly owned public-private organizations, 24% from local pri- using Eq. (2)
vately owned organizations, 24% from international organizations, 12 Xm
and 10% from organizations that are joint ventures between inter- KW ¼ n R̄2 − 3ðN þ 1Þ ð2Þ
NðN þ 1Þ i¼1 i i
national and local private organizations.

© ASCE 05014017-3 J. Manage. Eng.

J. Manage. Eng.
where m is the number of treatments; ni is the number of obser- Poor Site Management and Supervision by
vations in the ith treatment; N is the total number of observations; Contractors
and Ri is the average of the ranks in the ith treatment.
Poor site management and supervision by contractors also has been
identified as one of the major causes of project delay in other studies,
Results and Discussion such as Faridi and Al-Sayegh (2006), Sambasivan and Soon (2007),
and Pourrostam and Ismail (2011). According to Mohamed and
This section presents the analysis of survey responses on the factors Anumba (2006), poor site management can cause not only delays,
that cause project delay in the following three areas: but also defects, disputes, and cost overruns. This problem can be over-
• Reliability testing; come by recruiting qualified site managers for running site operations
• Hypothesis testing; and efficiently and maintaining an acceptable level of quality, allocating an
• Major causes of project delay. optimal number of workers per supervisor, and ensuring that the super-
Downloaded from ascelibrary.org by IMPERIAL COLLEGE LONDON on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.

visors’ authority matches their responsibilities. Site management can


Reliability Testing also be improved through an integration of knowledge management
processes (Mohamed and Anumba 2006). Knowledge management
The questionnaire reliability was tested using Cronbach’s alpha, is defined by Davenport (1994) as “the process of capturing, distrib-
and the computed coefficient value was 0.964. This value was con- uting, and effectively using knowledge.” Other possible remedies for
sidered acceptable because it exceeded the minimum acceptable resolving the problem of poor site management and supervision can
level of 0.7 (Nunnally and Bernstein 1994). be found in previous studies, particularly Andersson et al. (1996).

Hypothesis Testing
Problems with Subcontractors
To perform the three hypothesis tests, the primary data collected
from the second part of the questionnaire were analyzed from the The involvement of subcontractors in construction projects is
perspective of project stakeholders, organization size, and organi- common, particularly in large projects. The results of this study
zational ownership using the Kruskal-Wallis test. show that problems with subcontractors is one of the major
The Kruskal-Wallis test was conducted for testing the hypoth- causes of project delay, and this finding is consistent with that
esis that the causes of project delay are not perceived significantly of Sambasivan and Soon (2007) and Fallahnejad (2013). Problems
differently by the following three project stakeholders: clients, con- with subcontractors can be minimized by implementing a careful
tractors, and consultants (H1). As shown in Table 1, the Kruskal- selection process of qualified subcontractors that considers not
Wallis test suggests that significant differences (at the 0.01 level only cost, but also quality, safety, and environmental aspects. It is
of significance) in the perceptions of the three stakeholders exist also recommended by Enshassi et al. (2012) to select contactors
for only the following four causes: (1) poor understanding of the according to their previous experience, reputation, and capabilities
scope of work during tendering, (2) poor management of contrac- in terms of labor, equipment, and machinery. For the selection pro-
tors’ schedules, (3) shortage of equipment, and (4) mistakes and cess, using AHP as a decision support system is recommended
discrepancies in the contract document. The finding that significant (Manoharan 2005). Moreover, subcontractors should be involved
differences in perception existed only for 4 out of 44 causes indi- in the initial stages of the project through a balanced flow of in-
cates relative agreement among the three stakeholders regarding the formation between them and the main contactor (Enshassi et al.
causes of project delay. 2012). Most important, it is highly recommended that the contrac-
To explore whether the causes of delay differed according tor regularly monitor the activities of each subcontractor and indi-
to organization size (H2), the Kruskal-Wallis test was conducted. cate any evidence of schedule overrun (Proctor 1996).
As shown in Table 1, at the 0.01 level of significance, there is no
evidence to suggest that the causes of project delay differ due to
organization size. The test also was conducted to test whether Inadequate Planning and Scheduling of Project by
the causes of project delay are perceived significantly differently Contractors
depending on organizational ownership (H3). As shown in Table 1,
at the 0.01 level of significance, there is no evidence to suggest that Previous literature (e.g., Assaf and Al-Hejji 2006; Sambasivan and
there is an association between causes of project delay and organi- Soon 2007) also has determined inadequate planning and schedul-
zational ownership. ing of projects by contractors as one of the most important causes of
project delay. This problem can be overcome by implementing tech-
Major Causes of Project Delay niques for managing projects with planning and scheduling soft-
ware packages, as well as by improving the communication of
Based on the responses from all the respondents, the median was schedule control data between construction site management and
computed for each factor. As shown in Table 2, the following fac- field supervision (Kratt 1989). Moreover, contractors should estab-
tors had the highest median score (4.0) and thus were considered lish a dedicated team for planning and follow-up of pending issues.
the major causes of project delay in the oil and gas industry in
Oman: poor site management and supervision by contractors; prob-
lems with subcontractors; inadequate planning and scheduling of Poor Management of Contractors’ Schedules
the project by contractors; poor management of contractors’ sched-
ules; delay in delivery of materials; lack of effective communica- Sambasivan and Soon (2007) also identified poor management of
tion among project stakeholders; and poor interaction with vendors contractors’ schedules as a major cause of project delay. Apart from
in the engineering and procurement stages. According to the sound planning and monitoring, a requirement for effective manage-
Kruskal-Wallis test results shown here, out of these seven major ment of contractor schedules is that the roles, responsibilities, and
causes, significant differences in the perceptions of project stake- communication channels among project stakeholders are clearly
holders exist only for “poor management of contractor’s schedule.” defined and documented. Rahman and Kumaraswamy (2005)

© ASCE 05014017-4 J. Manage. Eng.

J. Manage. Eng.
Table 1. Comparison by Project Stakeholders, Organization Size, and Owner
p-values of the Kruskal-Wallis tests
Comparison Comparison by Comparison by
by project organization organizational
Causes of delays stakeholders size ownership
Client-related causes
Delays in project financing and making payment for completed work 0.503 0.856 0.265
Client interfaces and change requests 0.318 0.211 0.795
Slow decision making by client 0.052 0.448 0.025
Unrealistic contract duration and imposition of requirements 0.118 0.554 0.620
Poor definition of subsurface input data 0.987 0.659 0.787
Downloaded from ascelibrary.org by IMPERIAL COLLEGE LONDON on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.

Reengineering of different units caused by poor basic design package 0.155 0.324 0.907
Poorly defined or vague scope of work 0.135 0.329 0.152
Complications in the tendering process 0.315 0.400 0.160
Contractor-related causes
Poor understanding of scope of work during tendering 0.001 0.783 0.017
Difficulties in project financing 0.029 0.942 0.037
Poor site management and supervision 0.014 0.550 0.036
Problems with subcontractors 0.053 0.889 0.195
Inappropriate construction methods implemented 0.052 0.138 0.162
Inadequate planning and scheduling of project 0.010 0.845 0.035
Rework due to errors during construction 0.341 0.556 0.452
Inadequate experience of contractor 0.077 0.767 0.025
Unfamiliarity with government regulations and laws 0.245 0.618 0.164
Consultant-related causes
Delay in preparation and approval of drawings during construction work 0.624 0.725 0.294
Delay in conducting inspection and testing 0.804 0.519 0.750
Inadequate quality assurance/control 0.055 0.257 0.172
Lack of ownership in the project 0.515 0.355 0.516
Poor management of contractor’s schedule 0.004 0.837 0.014
Material-related causes
Change in material type during construction caused by poor quality of materials 0.160 0.392 0.140
Delay in delivery of materials 0.293 0.317 0.163
Labor and equipment-related causes
Shortage of labor (including engineers) 0.120 0.756 0.104
Low labor productivity 0.306 0.780 0.297
Shortage of equipment 0.003 0.832 0.010
Low efficiency of equipment 0.016 0.914 0.061
Contract-related causes
Mistakes and discrepancies in the contract document 0.002 0.441 0.021
Inadequate project duration defined in the original contract 0.256 0.669 0.614
Poor definition of payment milestones/distribution of cash flow 0.396 0.803 0.381
Inadequate delay penalties/poor incentives 0.522 0.356 0.436
Conflicts among joint owners of the project (for joint-venture projects) 0.337 0.784 0.215
Contract relationship-related causes
Major disputes and negotiation 0.360 0.794 0.538
Inappropriate overall organization structure linked to the project 0.451 0.425 0.839
Lack of effective communication among project stakeholders 0.014 0.259 0.026
Poor definition of interfaces resulting in scope creep 0.084 0.349 0.045
Poor interaction with vendors in the engineering and procurement stages 0.020 0.451 0.073
External causes
Effect of hot weather on construction activities 0.453 0.766 0.491
Unforeseen weather conditions 0.765 0.396 0.360
Effect of social and cultural factors 0.830 0.793 0.032
Problems with neighbors 0.033 0.183 0.015
Changes in government regulations and laws 0.617 0.626 0.439
Changes in market conditions 0.077 0.802 0.123

suggested that establishing a team that includes owners, consultants, Soon (2007), and Zou et al. (2007) also identified this as a cause
contractors, subcontractors, and suppliers might improve the man- of project delay. Although this factor could delay any construction
agement of contractors’ schedules. project, it is compounded in oil and gas projects by transportation
problems due to the remote location of construction sites with little
or no transport infrastructure and by complications in project buy-
Delay in Delivery of Materials out management because most of the materials required for these
types of projects are usually imported from overseas. To deal
Delay in the supply of materials is identified as another important with these two issues effectively, it is highly recommended that
cause of project delay. Frimpong et al. (2003), Sambasivan and a management group be formed specifically for logistics planning

© ASCE 05014017-5 J. Manage. Eng.

J. Manage. Eng.
Table 2. Median Scores (Heimer et al. 1978) and that an appropriate management buyout
Causes of delay Median system be developed (Hu et al. 2008).
Client-related causes
Delays in project financing and making payment 2
for completed work
Lack of Effective Communication among Project
Client interfaces and change requests 3 Stakeholders
Slow decision making by client 3
Unrealistic contract duration and imposition of 3 Undoubtedly, effective communication among project stake-
requirements holders is crucial for project success. Consistent with the findings
Poor definition of subsurface input data 3 of Sambasivan and Soon (2007), Oman’s oil and gas construction
Reengineering of different units caused by poor 3 projects suffer from poor communication among project stakehold-
basic design package ers. This communication problem invariably leads to rework, and
Downloaded from ascelibrary.org by IMPERIAL COLLEGE LONDON on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.

Poorly defined or vague scope of work 3 thus project delay. Therefore, in order to minimize the risk of
Complications in the tendering process 3 project delay, it is imperative to establish appropriate formal com-
Contractor-related causes munication channels among all project stakeholders during the
Poor understanding of scope of work during 3 conceptual phase. It is also recommended that informal communi-
tendering
cation channels be established since they enable easier information
Difficulties in project financing by contractor 3
Poor site management and supervision by 4 flow within a shorter span of time (Al-Rawas and Easterbrook
contractor 1996; Bassi et al. 2012).
Problems with subcontractors 4
Inappropriate construction methods implemented 3
by contractor Poor Interaction with Vendors in the Engineering
Inadequate planning and scheduling of project by 4 and Procurement Stages
contractor
Rework due to errors during construction 3 Poor interaction with vendors in the engineering and procurement
Inadequate experience of contractor 3 stages has not been identified as a major cause of project delay
Unfamiliarity with government regulations and laws 3 in any previous study. Therefore, this factor could be considered
Consultant-related causes unique to construction projects in the oil and gas industry. Since the
Delay in preparation and approval of drawings 3
oil and gas industry is characterized by the use of high-technology,
during construction work
Delay in performing inspection and testing 3 made-to-order products, the involvement of vendors in the initial
Inadequate quality assurance/control 3 stages of the project is necessary to overcome this problem. This
Lack of ownership in the project 3 is because such involvement enables the identification of require-
Poor management of contractor’s schedule 4 ments and resolution of technical issues at an early stage, thereby
Material-related causes avoiding any negative impacts on cost and schedule at a subsequent
Change in material type during construction caused 3 stage in the project.
by poor quality of materials
Delay in delivery of materials 4
Labor- and equipment-related causes Conclusion
Shortage of labor 3
Low labor productivity 3 Project delay is one of the most common problems in the construc-
Shortage of equipment 3
tion industry worldwide. The literature review in this paper re-
Low efficiency of equipment 3
Contract-related causes
vealed that although considerable research has been conducted
Mistakes and discrepancies in contract document 3 to investigate the causes of project delay in the construction indus-
Inadequate project duration defined in original 3 try worldwide, only five studies have focused on oil and gas con-
contract struction projects to identify these causes thus far. Furthermore, no
Poor definition of payment milestones/distribution 3 study has investigated this issue in any of the GCC countries.
of cash flow Using a questionnaire, data were collected from 59 managers of
Inadequate delay penalties/poor incentives 3 construction projects for oil and gas processing facilities in Oman,
Conflicts among joint owners of the project (for 3 which served as a case study for the GCG countries in the present
joint-venture projects) research. The analysis of survey responses showed that there is a
Contract relationship-related causes high degree of agreement among the perceptions of project stake-
Major disputes and negotiation 3
holders, clients, contractors, and consultants on the causes of proj-
Inappropriate overall organization structure linked 3
to the project
ect delay, and there is no evidence to suggest that the causes of
Lack of effective communication among project 4 project delay differ significantly according to organization size or
stakeholders organizational ownership.
Poor definition of interfaces causing scope creep 3 The results also revealed that the following seven major factors
Poor interaction with vendors in the engineering 4 are responsible for project delay: (1) poor site management and
and procurement stages supervision by contractors, (2) problems with subcontractors,
External causes (3) inadequate planning and scheduling of projects by contractors,
Effect of hot weather on construction activities 3 (4) poor management of contractors’ schedules, (5) delay in deliv-
Unforeseen weather conditions 2 ery of materials, (6) lack of effective communication among project
Effect of social and cultural factors 2 stakeholders, and (7) poor interaction with vendors in the engineer-
Problems with neighbors 2
ing and procurement stages.
Changes in government regulations and laws 2
The first six factors are considered general factors that could
Changes in market conditions 3
affect any type of project, whereas the last one, “poor interaction

© ASCE 05014017-6 J. Manage. Eng.

J. Manage. Eng.
with vendors in the engineering and procurement stages,” is spe- Haksever, C. (1996). “Total quality management in the small business
cific to the oil and gas industry, as construction projects in this environment.” Bus. Horizons, 39(2), 33–41.
industry are characterized by the use of high-technology, made- Han, S. H., Yun, S., Kim, H., Kwak, Y. H., Park, H. K., and Lee,
to-order products. S. H. (2009). “Analyzing schedule delay of mega project: Lessons
learned from Korea train express.” IEEE Trans. Eng. Manage.,
Although this research was conducted to identify the major
56(2), 243–256.
causes of delays in construction projects for oil and gas processing Haseeb, M., Xinhai-Lu, Bibi, Maloof-ud-Dyian, A., and Rabbani, W.
facilities in Oman, the results are likely to be applicable to construc- (2011). “Problems of projects and effects of delays in the construc-
tion projects implemented in any of the GCC countries. tion industry of Pakistan.” Australian J. Bus. Manage. Res., 1(5),
Last but not least, although the sample size used in this 41–50.
study compares favorably with those in earlier studies, additional Heimer, J. A., Bryan, L. A., and Weeks, J. D. (1978). “Logistics problems
empirical studies are necessary for validating the generality of in developing remote oil fields—A case history from Prudhoe Bay.”
these results. J. Petrol. Technol., 30(6), 851–859.
Downloaded from ascelibrary.org by IMPERIAL COLLEGE LONDON on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.

Hu, J., Ren, Z., and Shen, L. (2008). “Impacts of overseas management
structures on project buyout management: Case studies of Chinese
international contractors.” J. Constr. Eng. Manage., 10.1061/(ASCE)
References 0733-9364(2008)134:11(864), 864–875.
International Energy Agency (IEA). (2006). World energy outlook, Paris.
Abd El-Razek, M., Bassioni, H., and Mobarak, A. (2008). “Causes of delay
in building construction projects in Egypt.” J. Constr. Eng. Manage., International Energy Agency (IEA). (2013). World energy outlook, Paris.
10.1061/(ASCE)0733-9364(2008)134:11(831), 831–841. Jergeas, G. (2008). “Analysis of the front-end loading of Alberta mega oil
Ahire, S. L., and Golhar, D. Y. (1996). “Quality management in large versus sands projects.” Proj. Manage. J., 39(4), 95–104.
small firms.” J. Small Bus. Manage., 34(2), 1–13. Jergeas, G., and Ruwanpura, J. (2010). “Why cost and schedule overruns
Aibinu, A. A., and Jagboro, G. O. (2002). “The effects of construction de- on mega oil sands projects?” Pract. Period Struct. Des. Constr.,
lays on project delivery in the Nigerian construction industry.” Int. J. 10.1061/(ASCE)SC.1943-5576.0000024, 40–43.
Proj. Manage., 20(8), 593–599. Kaliba, C., Muya, M., and Mumba, K. (2009). “Cost escalation and
Alaghbari, W., Kadir, M., Salim, A., and Ernawati, S. (2007). “The sig- schedule delays in road construction projects in Zambia.” Int. J. Proj.
nificant factors causing delay of building construction projects in Manage., 27(5), 522–531.
Malaysia.” Eng. Construct. Architect. Manage., 14(2), 192–206. Kaming, P. F., Olomolaiye, P. O., Holt, G. D., and Harris, F. C. (1997).
Al-Khalil, M. I., and Al-Ghafly, M. A. (1999). “Delay in public utility “Factors influencing construction time and cost overruns on high-rise
projects in Saudi Arabia.” Int. J. Proj. Manage., 17(2), 101–106. projects in Indonesia.” Constr. Manage. Econ., 15(1), 83–94.
Al-Momani, A. H. (2000). “Construction delay: A quantitative analysis.” Koushki, P. A., Al-Rashid, K., and Kartam, N. (2005). “Delays and cost
Int. J. Proj. Manage., 18(1), 51–59. increases in the construction of private residential projects in Kuwait.”
Al-Rawas, A., and Easterbrook, S. (1996). “Communication problems in Constr. Manage. Econ., 23(3), 285–294.
requirements engineering: A field study.” Proc., 1st Westminster Kratt, T. J. (1989). “Poor communication of schedule and cost control data
Conf. Prof. Aware. Software Eng., Royal Society, Westminster Univ., between construction site management and field supervision improved
London. by the weekly cost and schedule meeting for direct labor supervisors.”
Andersson, C. A., Miles, D., and Ward, J. (1996). Site management hand- Proc., 1st Const. Cong., ASCE, San Francisco, CA.
book, International Labor Office, Geneva. Le-Hoai, L., Lee, Y. D., and Lee, J. Y. (2008). “Delay and cost overruns in
Assaf, S. A., and Al-Hejji, S. (2006). “Causes of delay in large construction Vietnam large construction projects: A comparison with other selected
projects.” Int. J. Proj. Manage., 24(4), 349–357. countries.” KSCE J. Civ. Eng., 12(6), 367–377.
Bassi, A., Howard, R., Geneletti, D., and Ferrari, S. (2012). “UK and Italian Lo, T. Y., Fung, I. W. H., and Tung, K. C. F. (2006). “Construction delays
EIA systems: A comparative study on management practice and perfor- in Hong Kong civil engineering projects.” J. Constr. Eng. Manage.,
mance in the construction industry.” Environ. Impact Assess. Rev., 34, 10.1061/(ASCE)0733-9364(2006)132:6(636), 636–649.
1–11. Luu, V. T., Kim, S., Tuan, N. V., and Ogunlana, S. O. (2009). “Quantifying
Chan, D., and Kumaraswamy, M. (1997). “A comparative study of causes schedule risk in construction projects using Bayesian belief networks.”
of time overruns in Hong Kong construction projects.” Int. J. Proj. Int. J. Proj. Manage., 27(1), 39–50.
Manage., 15(1), 55–63. Manoharan, R. (2005). “Subcontractor selection method using analytic
Davenport, T. H. (1994). “Saving ITU’s soul: Human-centered information hierarchy process.” M.Sc. thesis, Univ. Teknologi Malaysia, Johor,
management.” Harvard Bus. Rev., 72(2), 54–62. Malaysia.
Dey, P. K. (2012). “Project risk management using multiple criteria Mansfield, N. R., Ugwu, O. O., and Doran, T. (1994). “Causes of delay and
decision-making technique and decision tree analysis: A case study cost overruns in Nigerian construction projects.” Int. J. Proj. Manage.,
of Indian oil refinery.” Prod. Plann. Contr. Manage. Oper., 12(12), 12(4), 254–260.
903–921. McKenna, M. G., Wilczynski, H., and VanDerSchee, D. (2006). Capital
Enshassi, A., Al-Najjar, J., and Kumaraswamy, M. (2009). “Delays and project execution in the oil and gas industry, Booz Allen Hamilton,
cost overruns in construction projects in the Gaza Strip.” J. Fin. Houston.
Manage. Prop. Constr., 14(2), 126–151. Mezher, T. M., and Tawil, W. (1998). “Causes of delays in the construc-
Enshassi, A., Arain, F., and Tayeh, B. (2012). “Major causes of problems tion industry in Lebanon.” Eng. Construct. Architect. Manage., 5(3),
between contractors and subcontractors in the Gaza Strip.” J. Fin. 352–360.
Manage. Prop. Constr., 17(1), 92–112. Mohamed, S. F., and Anumba, C. J. (2006). “Potential for improving
Fallahnejad, M. H. (2013). “Delay causes in Iran gas pipeline projects.” site management practices though knowledge management.” Constr.
Int. J. Proj. Manage., 31(1), 136–146. Innov., 6(4), 232–249.
Faridi, A. S., and Al-Sayegh, S. M. (2006). “Significant factors causing Montgomery, D. C. (2005). Design and analysis of experiments, Wiley,
delay in the UAE construction industry.” Constr. Manage. Econ., New York.
24(11), 1167–1176. Nunnally, J. C., and Bernstein, I. H. (1994). Psychometric theory,
Frimpong, Y., Oluwoye, J., and Crawford, L. (2003). “Causes of delay and McGraw-Hill, New York.
cost overrun in construction of ground water projects in a developing Odeh, A. M., and Battaineh, H. T. (2002). “Causes of construction delay:
countries: Ghana as a case study.” Int. J. Proj. Manage., 21(5), Traditional contracts.” Int. J. Proj. Manage., 20(1), 67–73.
321–326. Odeyinka, H. A., and Yusif, A. (1997). “The causes and effects of construc-
Gulbro, R. D., Shonesy, L., and Dreyfus, P. (2000). “Are small manufac- tion delays on completion cost of housing projects in Nigeria.” J. Fin.
turers failing the quality test?” Ind. Manage. Data Syst., 100(2), 76–80. Manage. Property Constr., 2(3), 31–44.

© ASCE 05014017-7 J. Manage. Eng.

J. Manage. Eng.
Ogunlana, S., Promkuntong, K., and Jearkjirm, V. (1996). “Construction Sambasivan, M., and Soon, Y. W. (2007). “Causes and effects of delays in
delays in a fast-growing economy: Comparing Thailand with other Malaysian construction industry.” Int. J. Proj. Manage., 25(5), 517–526.
economies.” Int. J. Proj. Manage., 14(1), 37–45. Sweis, G., Sweis, R., Abu Hammad, A., Shboul, A. (2008). “Delays in
Olejnik, S. F. (1984). “Planning educational research: Determining the nec- construction projects: The case of Jordan.” Int. J. Proj. Manage.,
essary sample size.” J. Exp. Educ., 53(1), 40–48. 26(4), 665–674.
Pourrostam, T., and Ismail, A. (2011). “Significant factors causing and ef- Thuyet, N. V., Ogunlana, S. O., and Dey, P. K. (2007). “Risk management
fects of delay in Iranian construction projects.” Aust. J. Basic Appl. Sci., in oil and gas construction projects in Vietnam.” Int. J. Energy Sector
5(7), 450–456. Manage., 1(2), 175–194.
Proctor, J. R. (1996). “Golden rule of contractor-subcontractor relations.” Toor, S., and Ogunlana, S. (2008). “Problems causing delays in major
Pract. Period Struct. Des. Constr., 10.1061/(ASCE)1084-0680(1996) construction projects in Thailand.” Constr. Manage. Econ., 26(4),
1:1(12), 12–14. 395–408.
Rahman, M., and Kumaraswamy, M. (2005). “Assembling integrated Zou, P. X. W., Zhang, G., and Wang, J. (2007). “Understanding the key
project teams for joint risk management.” Constr. Manage. Econ., risks in construction project management in China.” Int. J. Proj.
Downloaded from ascelibrary.org by IMPERIAL COLLEGE LONDON on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.

23(4), 365–375. Manage., 25(6), 610–614.

© ASCE 05014017-8 J. Manage. Eng.

View publication stats J. Manage. Eng.

You might also like