03-Nov-21 DAILY PROGRESS REPORT

TIME 06.00 PM

WORKS AT SITE
ITEMS DESCRIPTION

TILING/
1st podium tiles gap filling
Shanti bhai

External Painting/
Ground podium below ramp ceiling painting work.
Bhushan Gore

Internal Painting/
No work.
Awadhraj

Sagar Construction RG garden side drainage gutter cleaning and waterproofing coating work in progress.

Electrical/
RG garden Electrical connection and fittings conceal piping on flooring in progress.
Munna bhai

Plumbing/ Garden drainage pipe fixing from side drain to rainwater outlet & Building no 04 pressure valves
Sattar Bhai cleaning.

Fabrication/
No work.
Nazim Bhai

Aluminium Sliding Work/


No work.
Khan Sahab

RG Garden Garden Grass watering and cement godown debris cleaning.

Tapas Carpenter

SL.NO ISSUE AT SITE DATE OF RESOLVE


1
2
3
4

SL.NO PROGRESS AT SITE TIMELINE

4
NOTES:-
S REPORT

LABOUR REPORT

g work in progress. 2

oring in progress. 2

Building no 04 pressure valves


2

F RESOLVE

TIMELINE