POC-M1.

2-RA-148
PENTA-OCEAN CONSTRUCTION CO. LTD.
Revision: C
PROCUREMENT OF POWER PLANT AND PORT FACILITIES UNDER MATARBARI ULTRA SUPER Sheet: Page 7 of 14
CRITICAL COAL-FIRED POWER PROJECT PACKAGE 1.2 Date: 20th Aug 2023

Risk Assessment – Transportation

Initial Risk Residual Risk Owner (Action Officer)


Possible Accident / Level Risk Level
Additional Risk
No Work Activity Hazard Ill Health & Existing Risk Control Follow-
Control
Persons-at-Risk S L R S L R Name Designation up
Period
1.1 Use passenger Uneven ground, Soft -Fatality or Bodily Ensure the driver hold 5 2 10 Ensure safety 5 1 5
vehicle for ground, Foggy weather, injury due to vehicle valid driving licence and (M) devices like reverse (M)
transfer staff/ Heavy rain, Blind spot collision or hits he must be competent & alarm, horn; side
worker inside pedestrians /road authorized/appointed mirrors are in good
the project user or animals driver to drive the Working conditions
-Property damage vehicles.
due to vehicle
collision or topple According to BRTA the Proper maintenance
minimum age of driver is the vehicle
18 years and maximum
65 years old. Arrange refresher
training for driver.
Less than 21years old
can’t drive medium or Ensure driver health
heavy motor vehicle. condition fit for
drive.
Before start driver must
check vehicle, condition Adhere to POC
and update daily pre- Traffic Management
operational check list plan.

Blood alcohol content


when driving is 0.0

Drivers and passengers


will wear seat belts.
POC-M1.2-RA-148
PENTA-OCEAN CONSTRUCTION CO. LTD.
Revision: C
PROCUREMENT OF POWER PLANT AND PORT FACILITIES UNDER MATARBARI ULTRA SUPER Sheet: Page 8 of 14
CRITICAL COAL-FIRED POWER PROJECT PACKAGE 1.2 Date: 20th Aug 2023

Risk Assessment – Transportation

Initial Risk Residual Risk Owner (Action Officer)


Possible Accident / Level Risk Level
Additional Risk
No Work Activity Hazard Ill Health & Existing Risk Control Follow-
Control
Persons-at-Risk S L R S L R Name Designation up
Period
1.1 Use passenger Uneven ground, Soft -Fatality or Bodily Follow the project speed 5 2 10 Follow the seating 5 1 5
vehicle for ground, Foggy weather, injury due to vehicle limit Maximum 15 km/h (M) passenger capacity, (M)
transfer staff/ Heavy rain, Blind spot collision or hits don’t over load
worker inside pedestrians /road Follow banksman
the project user or animals instruction On the hazard/spot
-Property damage light during heavy
Beware of pedestrians
due to vehicle rain/foggy weather
(Specially kids while drive
collision or topple
at south beach) and
Install the yellow
oncoming vehicle
stick to identify the
Ensure the access is safe vehicle of lower
for drive place

Don’t use phone while Provide Fire


driving Extinguisher for fire
emergency
Don’t carry passenger and
heavy material’s together

Before reversing must


check mirrors and over
driver shoulder. If driver
can’t see behind the
vehicle, walk around and
check there are no
obstructions

Ensure reverse alarm are


in working condition
POC-M1.2-RA-148
PENTA-OCEAN CONSTRUCTION CO. LTD.
Revision: C
PROCUREMENT OF POWER PLANT AND PORT FACILITIES UNDER MATARBARI ULTRA SUPER Sheet: Page 9 of 14
CRITICAL COAL-FIRED POWER PROJECT PACKAGE 1.2 Date: 20th Aug 2023

Risk Assessment – Transportation

Initial Risk Residual Risk Owner (Action Officer)


Possible Accident / Level Risk Level
Additional Risk
No Work Activity Hazard Ill Health & Existing Risk Control Follow-
Control
Persons-at-Risk S L R S L R Name Designation up
Period
1.2 Use passenger Uneven ground, Soft -Fatality or Bodily Instate of land transport 5 2 10 Proper maintenance 5 1 5
vehicle for ground, Foggy weather, injury due to vehicle use boat specially from (M) the vehicle (M)
transfer staff/ Heavy rain, Blind spot collision or hits Project to Bodorkhali or
worker outside pedestrians /road Cox’bazar. Arrange refresher
the project user or animals training for driver.
-Property damage Instate of land transport
due to vehicle use Air transport. Ensure driver health
collision or topple condition fit for
Ensure the driver hold drive.
valid Bangladeshi driving
licence and he must be On the hazard/spot
competent & light during heavy
authorized/appointed rain/foggy weather
driver to drive the
vehicles. Adhere to POC
Traffic Management
Before start driver must plan.
ensure the vehicle is free
from defect & update the
daily checklist.

The driver to be thorough


for the slow driving
especially when passing
inside the village, narrow
or crowded road. The
front passenger as guide
to driver.

Drivers and passengers


will wear seat belts.
POC-M1.2-RA-148
PENTA-OCEAN CONSTRUCTION CO. LTD.
Revision: C
PROCUREMENT OF POWER PLANT AND PORT FACILITIES UNDER MATARBARI ULTRA SUPER Sheet: Page 10 of 14
CRITICAL COAL-FIRED POWER PROJECT PACKAGE 1.2 Date: 20th Aug 2023

Risk Assessment – Transportation

Initial Risk Residual Risk Owner (Action Officer)


Possible Accident / Level Risk Level
Additional Risk
No Work Activity Hazard Ill Health & Existing Risk Control Follow-
Control
Persons-at-Risk S L R S L R Name Designation up
Period
1.2 Use passenger Uneven ground, Soft -Fatality or Bodily Assigned additional driver 5 2 10
vehicle for ground, Foggy weather, injury due to vehicle for ambulance or any (M)
transfer staff/ Heavy rain, Blind spot collision or hits vehicle which going to
worker outside pedestrians /road long hours driving
the project user or animals (Dhaka)

-Property damage Beware of pedestrians


due to vehicle (Specially kids) or
collision or topple oncoming vehicle

Beware of animals

Don’t use phone while


driving

Don’t carry passenger and


heavy material’s together

Provide Fire Extinguisher


for fire emergency

Ensure reverse alarm are


in working condition

Extra precaution on poor


visibility such as heavy
rain, foggy weather.

Provide First Aid box.


POC-M1.2-RA-148
PENTA-OCEAN CONSTRUCTION CO. LTD.
Revision: C
PROCUREMENT OF POWER PLANT AND PORT FACILITIES UNDER MATARBARI ULTRA SUPER Sheet: Page 11 of 14
CRITICAL COAL-FIRED POWER PROJECT PACKAGE 1.2 Date: 20th Aug 2023

Risk Assessment – Transportation

Initial Risk Residual Risk Owner (Action Officer)


Possible Accident / Level Risk Level
Additional Risk
No Work Activity Hazard Ill Health & Existing Risk Control Follow-
Control
Persons-at-Risk S L R S L R Name Designation up
Period
1.3 Movement of Uneven ground, Soft Injury or even fatality Operator must be 5 2 10 Ensure safety 5 1 5 Site On-going
Machinery and ground, Foggy weather, to the drivers or road appointed and qualified to (M) devices like rotating (M) Engineer/
Vehicle (using Heavy rain, Blind spot user and cause operate the machine and light, reverse alarm, Supervisor
site access properly damage. vehicle. horn; side mirrors
road) are in good Working Machinery
Adhere to 15 km/hr site conditions, Operator
speed limit.
Fire extinguisher
Adhere to POC Traffic Standby.
Management plan.
Banksman or Traffic
Driver or operate to use Controller must
only designated traffic guide and give
route. proper signal to the
machinery/vehicle.
Stop at any junction and
ensure no other vehicle or Extra precaution on
person crossing. poor visibility such
as heavy rain.
Always stop and ensure Further reduce the
traffic is clear before speed limit
crossing of junctions. (Spot/Hazard light
on).

Always keep a safe


distance away from
shoulder.
POC-M1.2-RA-148
PENTA-OCEAN CONSTRUCTION CO. LTD.
Revision: C
PROCUREMENT OF POWER PLANT AND PORT FACILITIES UNDER MATARBARI ULTRA SUPER Sheet: Page 12 of 14
CRITICAL COAL-FIRED POWER PROJECT PACKAGE 1.2 Date: 20th Aug 2023

Risk Assessment – Transportation

Initial Risk Residual Risk Owner (Action Officer)


Possible Accident / Level Risk Level
Additional Risk
No Work Activity Hazard Ill Health & Existing Risk Control Follow-
Control
Persons-at-Risk S L R S L R Name Designation up
Period
1.3 Movement of Uneven ground, Soft Severe injury to Banks man should be 5 2 10 Establish safe work 5 1 5 Site On-going
Machinery and ground working personnel station in a position (M) procedure (M) Engineer/
Vehicle (using where operators can Supervisor
site access Damage to property easily see. Operators must
road) and machinery. follow the banks Lifting
Only authorized persons man signal Supervisor
who are involved in the
work activity are allowed Machinery
Banks man must
in the area. Operator
appropriate flag
(e.g. use his red flag
for stop, and green
for go)

Banksman must use


whistle and must be
visible to give clear
signals to the
operators.

1.4 Movement and Machinery hits worker Severe injury or Before reversing must 5 2 10 Practicing safe 5 1 5 Site On-going
reversing of or other equipment fatality to banks man check mirrors and over (M) working procedures. (M) Engineer/
machinery and others in the driver shoulder. If driver Supervisor
vicinity can’t see behind the Pre-plan activities
vehicle, walk around and Provide barricade, Machinery
check there are no cons and signage in Operator
obstructions the area
POC-M1.2-RA-148
PENTA-OCEAN CONSTRUCTION CO. LTD.
Revision: C
PROCUREMENT OF POWER PLANT AND PORT FACILITIES UNDER MATARBARI ULTRA SUPER Sheet: Page 13 of 14
CRITICAL COAL-FIRED POWER PROJECT PACKAGE 1.2 Date: 20th Aug 2023

Risk Assessment – Transportation

Initial Risk Residual Risk Owner (Action Officer)


Possible Accident / Level Risk Level
Additional Risk
No Work Activity Hazard Ill Health & Existing Risk Control Follow-
Control
Persons-at-Risk S L R S L R Name Designation up
Period
1.4 Movement and Machinery hits worker Damage to property Banksman to give 5 2 10 Operators must 5 1 5 Site On-going
reversing of or other equipment and machinery. clear/proper signals (M) follow the (M) Engineer/
machinery banksman signal. Supervisor
Make sure the
Machinery
machineries working area
Operator
should have sufficient safe
distance from slope
shoulder.
Due to Overloading of Topple and Bodily Check the tyre condition 4 2 8
vehicles explosion of injuries to workers by operator/mechanic (M)
over-inflated tyre
Ensure the capacity of
loads and close monitor
by supervisor

Driver to advise
acceptable load for
transport.
1.5 Manpower Refer to: Mitigation Plan / Prevention Guidelines Against Spread of COVID-19
welfare during
pandemic/Third
party