Professional Documents
Culture Documents
RD5700011F en 1079035 47010 48
RD5700011F en 1079035 47010 48
Shift No 4459075 Service No. 04335559 Date of Works 22/09/23 Night Weekend
Shift Location TGA Day of the Week FRIDAY
Job Description TGA (TONKIN GAP) ASP Customer Name TONKIN GAP ALLIANCE
Map Ref Distance Duration Full Customer Contact TONKIN GAP ALLIANCE
Plant to Supply Product Job Number 17060748 Phone No 08 9200 2500
Shift Plan Layer Product Short Description Blinder Type Mass Depth (mm) Surface Area (M2)
(Tonnes) Preparation
Asphalt Area (M2)
Tokin Gap 3 6287J3A20 7MM GRAN SMA 50B TO BE DEFINED 750.00 50.00 6000.00 6000.00
Alliance PMB SAS
Shift Plan Material Being Removed Length(M) Width(M) Area Depth(mm) Volume(M3) Volume Hours A Hours B
(Tonnes) Rate Rate
Profiling
Dump Site
Material Removed Location Quantity (Loads) Distance (Kms) Removal
Labour (Includes internal and external employees via agencies) – Excludes subcontractor First Hour Data
Start 06:00 Finish 16:30 Planned Start
Lunch .50 Total 10.00 Planned worked hours (include all travel time) Actual Start
Crew 287 170616 Asphalt Crew 3 (WA) Delay
Amend / Complete the labour table below where actual work deviates from the original shift plan
Address People On Site Int / Planned Planned Planned Planned Actual Actual Actual Actual Additional
Book Number Ext Start Finish Lunch Total Start Finish Lunch Total Allowances
1125354 1 Supervisor Sal EMP 06:00 16:30 .50 10.00
1125357 1 Project Engineer Sal EMP 06:00 16:30 .50 10.00
1125363 1 Project Manager Sal EMP 06:00 16:30 .50 10.00
1051681 Jones, Ryan EMP 06:00 16:30 .50 10.00
1127256 Klein, Jason EMP 06:00 16:30 .50 10.00
1088070 Phillips, Stuart EMP 06:00 16:30 .50 10.00
1138123 Heslington, Matthew EMP 06:00 16:30 .50 10.00
1038537 Watson, Jerome EMP 06:00 16:30 .50 10.00
1038533 Swan, Rory EMP 06:00 16:30 .50 10.00
9009440 1 ASP Protech L2 EXT 06:00 16:30 .50 10.00
9009442 1 ASP Protech L3 EXT 06:00 16:30 .50 10.00
1155227 Harahsheh, Raaid EMP 06:00 16:30 .50 10.00
1138648 Bosworth, Ronan EMP 06:00 16:30 .50 10.00
1105852 Hackett, Neville EMP 06:00 16:30 .50 10.00
9009441 2 ASP Protech L2 EXT 06:00 16:30 .50 10.00
Plant (Includes internal and externally hired leased plant(Dry hire only) – Excludes subcontractor
Internal
Start 06:00 Hours equipment available on site Site Establishment
Field Report : Asphalt Page 2 of 6
Finish 16:30 (Internal and long term lease) Float Moves
Equipment Type Unit Number Planned Planned Planned Actual Actual Actual Break Actual
Start Finish Total Start Finish Hours Down Total
Hours
Trailer - Tag Along TB003 06:00 16:30 10.50
Profiler/Cold Milling Machine PR014 06:00 16:30 10.50
Tack Coater TC006 06:00 16:30 10.50
Truck Medium Single Axle ≥ 8t TM088 06:00 16:30 10.50
ROLLER HAMM HD+90 VO RT101 06:00 16:30 10.50
ROLLER HAMM HD14VV RT134 06:00 16:30 10.50
RUBBER TYRED ROLLER RR204 06:00 16:30 10.50
SKIDSTEER SS137 06:00 16:30 10.50
MATERIAL TRANSFER VEHICLE MT021 06:00 16:30 10.50
PAVER ASPHALT PA140 06:00 16:30 10.50
PAVER PA126 06:00 16:30 10.50
External
Equipment Type Description Hire Company PO No. Qty. Start Finish Total B/D Docket
Hours No.
Sherrin Roller HD70 RA08046 06:30 17:00 10.50
Miscellaneous Items
Item Description Quantity
Subcontractors Excluding dry hire of equipment (Amend details below when actual work deviates from original plan)
External Asphalt Crew Contractor Name PO Number No. Of People Start Finish Total Tonnes Area (M2) Docket No.
Laid
Subcontractors Excluding dry hire of equipment (Amend details below when actual work deviates from original plan)
External Profiling Crew Contractor Name PO Number No. Of Start Finish Total Docket No.
People
Plant Hire (Inc. Driver) Contractor Name PO Number No. Of People Start Finish Total Docket No.
Field Report : Asphalt Page 3 of 6
Plant Hire (Inc. Driver) Contractor Name PO Number No. Of People Start Finish Total Docket No.
Traffic Control Contractor Name PO Number No. Of People Start Finish Total After No. No. Docket No.
Care Arrow Var.
Signs Boards Msg.
Boards
Other Subcontract Service PO Number No. Of People Start Finish Total Service Type Docket No.
Driver / Company Name Rego No. Truck Id No. Travel To Site Hours To Be Paid Additional
Hours Kms Start Finish Total
Field Report : Asphalt Page 4 of 6
Location
Machine No.
Site Map
Comments
Float move
In Intermediate
Work Description Key CH-Chases Pa - Patch Mill – Mill M/F – Mill and Fill 00 – Hot Spot Removal
Material Being Removed Key AC – Asphalt BC – Base Course TAR – Tar SG – Subgrade/Spoil
Field Report : Asphalt Page 5 of 6
Customer Name
Site Conditions
Customer Signature
Summary Of Works
1 2 3 4 5 6 7
Street Name
Chainage Start
Chainage End
Pavement Layer
Mix Type
Blinder Type
Mix Description
Tonnes Laid
Depth (mm)
Area(M2)
RPM
Was Anyone Injured? (If yes, details, name, etc.) All Contractor Dockets Attached?
Foreman's comments
Foreman's signature
Foreman's name
Supervisor's Name
Reviewed by
Date Reviewed