CONTROL DE COSTOS BASE PAVIMENTOS HORMIGON

TOTAL MAT+esp MO COSTO AVANCE AVANCE COSTO COSTO PRE COSTO PRE UTILIDAD /
Fecha EQUIPOS $ 4,790 TOTAL M2 M3 UNI UNI TOTAL PERDIDA
SUBTOTAL SEMANAL 2,709,181 3,334,559 893,741 6,937,481 3,570 536 12,955 3,955,739 - 2,981,742
SUBTOTAL SEMANAL 1,459,940 - 141,669 1,601,609 - - - - 1,601,609
SUBTOTAL SEMANAL 1,457,198 4,248,059 - 5,705,258 4,548 682 8,363 5,039,411 - 665,846
SUBTOTAL SEMANAL 952,750 16,450,909 90,681 17,494,340 17,612 2,642 6,622 19,515,475 2,021,135
SUBTOTAL SEMANAL 1,470,581 5,053,211 147,546 6,671,338 5,410 812 8,221 5,994,551 - 676,788
SUBTOTAL SEMANAL 1,527,329 4,950,465 76,317 6,554,111 5,300 795 8,244 5,872,665 - 681,446

19-Abr 256,135 - 22,895 279,030 - - 7,387 $0 - 279,030


20-Abr 323,295 - 35,615 358,910 - - 7,387 $0 - 358,910
21-Abr 270,537 - 270,537 - - 7,387 $0 - 270,537
22-Abr 575,950 - 30,621 606,571 - - 7,387 $0 - 606,571
23-Abr 419,214 - 20,351 439,565 - - 7,387 $0 - 439,565
24-Abr 78,903 6,071,325 6,150,228 6,500 975 7,387 $ 7,202,325 1,052,097
25-Abr - - - - - 7,387 $0 -

SUBTOTAL SEMANAL 1,924,033 6,071,325 109,482 8,104,840 6,500 975 8,313 7,202,325 - 902,515

26-Abr 242,421 - 22,895 265,316 - - 7,387 $0 - 265,316


27-Abr 223,271 - 35,615 258,886 - - 7,387 $0 - 258,886
28-Abr 432,762 - 33,118 465,880 - - 7,387 $0 - 465,880
29-Abr 209,853 - 30,621 240,474 - - 7,387 $0 - 240,474
30-Abr 362,498 - 20,351 382,849 - - 7,387 $0 - 382,849
01-May 36,343 3,736,200 3,772,543 4,000 600 7,387 $ 4,432,200 659,657
02-May - - - - - 7,387 $0 -

SUBTOTAL SEMANAL 1,507,148 3,736,200 142,600 5,385,948 4,000 600 8,977 4,432,200 - 953,748

03-May 354,903 - 354,903 - - 7,387 $0 - 354,903


04-May 376,499 - 376,499 - - 7,387 $0 - 376,499
05-May 321,075 - 321,075 - - 7,387 $0 - 321,075
06-May 263,880 - 263,880 - - 7,387 $0 - 263,880
07-May 505,303 - 505,303 - - 7,387 $0 - 505,303
08-May 233,691 3,798,454 4,032,145 4,067 610 7,387 $ 4,506,052 473,907
09-May - - - - - 7,387 $0 -

SUBTOTAL SEMANAL 2,055,351 3,798,454 - 5,853,806 4,067 610 9,596 4,506,052 - 1,347,754

TOTAL 15,063,512 47,643,182 1,602,036 64,308,730 51,007 7,651 8,405 56,518,417 - 7,790,313

Datos por M2 $/m3 $/m3 $/m3


Reales 1,969 6,227 209
Presupuesto 1,546 5,603 263

PROYECCIÓN ECONOMICA
Cantidad Precio [$] Valor [$]
(a) Total Según Propuesta m3 21,218 7,387.00 156,739,589
(b) Avance Antes del Control m3 9,406 7,387.00 69,480,652
(c) Avance Con Control m3 7,651 8,405.20 64,308,730
(d) Obra por Ejecutar m3 4,161 8,405.20 34,977,693
Proyección de Resultado= (a)-(b)-(c)-(d) 27742.9 -12,027,485