a. Isolation:
b. Curbstone:
i. Procurement
i. Procurement
ii. MAR
d. Span construction and post-tensioning of remaining sections (Freyssinet): 1000 ton jack to be on
site on 02.10.2023
f. Guardrails & Handrails (Unipromet agreement signed, advance payment), Handrail Design (CIP)