Kako bi to izgledalo kada bi se videlo?

a. Isolation:

i. Antikor agreement at Belgrade

ii. CIP (consent for design solution) for concrete section

b. Curbstone:

i. Procurement

ii. MAR (new test report with current date)

iii. Site crew started on 19.09.2023

c. Service Pipes for Utilities

i. Procurement

ii. MAR

d. Span construction and post-tensioning of remaining sections (Freyssinet): 1000 ton jack to be on
site on 02.10.2023

e. Drainage Works: Proposals collected [Pimex – Grandpipe], further communication to be followed

f. Guardrails & Handrails (Unipromet agreement signed, advance payment), Handrail Design (CIP)