I. HIGHWAY ALIGNMENT

a. Remaining Structure’s Construction: 3 Box Culverts, 10 Pipe Culverts

i. Pipe culverts’ construction, start from chainage near Sava Bridge and towards Kuzmin
Interchange

b. Provision of Material and Embankment Construction

c. Resource Planning & Allocation

d. Toll Plazas: Design, Schedule, Market Research, MAR

e. Relocation of Utilities: Check electricity pole near to M7 structure. Agreement for remaining scope.

f. Provision of Embankment Material: Balkan GP, Rapid, LA, Eagle City, Vimil [Increase of
Quantities; New Rates]

II. M5 (BOSUT RIVER BRIDGE)

a. Delivery of Bearings.

b. Pre-cast beam production.