MANAGEMENT
MANAGEMENT
PLANNINNG 2 -
DEMOLITION 1 A
ELECTRICAL 2 B
PLUMBING 3 B
FRAMING C, D
PAINT 1 E
FIXTURES 2 F
CLEANING 2 G
1 G
1 H, I
=17 WEEKS
NETWORK
2(C) 2(H)
DIAGRAM
ELECTRICAL CLEANING
1(B)
TRIM
DEMOLITION
PLANNING
FIXTURES
PAINT
FRAMING 1(J)
2(A)
2(G)
1(F)
PLUMBING 2(E)
FLOORING
3(D)
1(I)
CRITICAL PATH
A-B-D-E-F-G-H-J=14 WEEKS
1 2 3 4 5 6 7 8 9 10 11 12 13 14
PLANNNING
DEMOLITION
ELECTRICAL
PLUMBING
FRAMING
PAINT
FIXTURES
CLEANING
FLOORING
TRIM