ACTIVITY TIME(WEEKS) PREDECESSOR

PLANNINNG 2 -

DEMOLITION 1 A

ELECTRICAL 2 B

PLUMBING 3 B

FRAMING C, D

PAINT 1 E

FIXTURES 2 F

CLEANING 2 G

1 G

1 H, I

=17 WEEKS
NETWORK
2(C) 2(H)
DIAGRAM

ELECTRICAL CLEANING

1(B)

TRIM
DEMOLITION
PLANNING
FIXTURES
PAINT
FRAMING 1(J)
2(A)
2(G)
1(F)
PLUMBING 2(E)
FLOORING

3(D)
1(I)

CRITICAL PATH
A-B-D-E-F-G-H-J=14 WEEKS
1 2 3 4 5 6 7 8 9 10 11 12 13 14
PLANNNING
DEMOLITION
ELECTRICAL
PLUMBING
FRAMING
PAINT
FIXTURES
CLEANING
FLOORING
TRIM