ACTIVITY TIME (WEEKS) PREDECESSOR

PLANNING 2 -
DEMOLITION 1 A
ELECTRICAL 2 B
PLUMBING 3 B
FRAMING 2 C,D
PAINT 1 E
FIXTURES 2 F
CLEANING 2 G
FLOORING 1 G
TRIM 1 H,I

Compute the earliest activity time, latest activity time, and the slack time.