You are on page 1of 1

Est Tot.

May June
No. Description
Day 11 12 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6
PIPE & PIPE RACK ANALYSIS
OXYGEN SUPPLAY PT. TIMAH

First Submission Detail Schedule

A. Preparation
- Collecting Data & Literature 2
- Work Method / Work Detail Proposal 2 E1 E1
- Product List and Detail Schedule 2 E1 E1

B. Pipe Stress Manual Calculation


- Pipe Thickness & Allowable Working Pressure Calculation 2 E1 E1
- Allowable Pipe Span Calculation 2 E1 E1
- Reaction Force in Support Design 2 E1 E1

C. Pipe Rack Design

Preparation & Collect Data


- Preliminary Pipe Rack Layout 1 E2
- Pipe Rack Basic Design

GET Contract
Section B 1 E2
Section B1 1 E2
Section A & C E2
1
Section D E2
- Pipe Rack Analysis (Use STAAD.Pro) 2 E2 E2
- Analysis Report 1 E2
- Pipe Rack Design Drawing (Include BOQ)
Section B 3 D D D
Section B1 2 D D
Section A D
1
Section C D
Section D 1 D

D. Pipe Stress Analysis


- Modeling 4 E1 E1 E1 E1
- Run Analysis 2 E1 E1
- Pipe Stress Report 2 E1 E1

Total Days For Pipe Stress 14


Total Days For Pipe Rack 14
Extra Speed Sch

FIRGA SENA ENGINERING


Note :
1. E = Engineer
2. D = Drafter
Ivan R. Nurhamsah