No ORIGINAL DESIGN

1 HVAC SYSTEM WORK


Isolation fo AHU : Rockwool Material, Motor IE3 (maker York), TB2 class
HVAC Control BMS use PC Central, include squencing chiller
Chilled Water Pump use existing, 17mH not enough
2 GENERAL HVAC SYSTEM
AC Unit Inverter Type
Duct Material : BJLS + Insulation
Accessories Duct : Grille, Diffuser, FAL maker trox
Accessories Duct in Tobacco Build use swirl (SWL )
Balancing valve and Motorized at Chiller

Accessories AHU : PIBCV


Accessories AHU : FJ
Accessories AHU : GV
3 FIRE FIGHTING SYSTEM WORK
Sprinkler sway bracing

TOTAL MECHANICAL
B ELECTRICAL
1 TRAFO
TRAFO 1250KVA, DRY TYPE
2 BUSDUCT
Trafo to LVMDB use Busduct Cu 2000A
3 MV Cable
Cable from PLN to MVMDB N2XSY 3x(1C-120mm2)
Cable from MVMDB to Trafo N2XSY 3x(1C-120mm2)
4 Genset Cable
Cable From GCP to LVMDB NYY 4x4C-95mm2 + NYA 2x 95mm2

TOTAL ELECTRICAL
TOTAL MECHANICAL & ELECTRICAL
COST BALANCE (IDR)
VE

Isolation fo AHU : PU Material, Motor IE1, non TB class, change local maker (Aicool) 182,060,000
HVAC Control use HMI local control, delete squencing chiller 193,200,000
Chilled Water Pump proposes new pump, 32mH (82,740,000)

Change Non-Inverter Type 19,180,000


Duct Material : PU 338,360,000
Acc Duct : Grille, Diffuser, FAL change lokal brand 49,580,000
Accessories Duct in Tobacco Build use swirl (SWL ) change to grille/diffuser. 80,980,000
Delete Balancing valve and Motorized at Chiller change to reverse return pipe for chiller since
the Chiller Capacity is same 30,630,000

Accessories AHU : PIBCV change to Motorized 19,650,000


Accessories AHU : FJ-->deleted 5,040,000
Accessories AHU : GV-->reduced 12,700,000

Change normal support

33,950,000

TOTAL MECHANICAL 882,590,000

TRAFO 1250KVA, OIL TYPE 203,270,000

Change to Cable 4x4(1C-300mm2) + Cable Rack W800 35,880,000

Change to Aluminium Cable NA2XSY 3x(1C-120mm2) 60,010,000


Change to Aluminium Cable NA2XSY 3x(1C-120mm2) 18,750,000

Change to Aluminium Cable NA2XY 5x4(1C-95mm2) + NYA 2x 95mm2 114,140,000

TOTAL ELECTRICAL 432,050,000


MECHANICAL & ELECTRICAL 1,314,640,000
CONSULTANT FEED BACK

Sway bracings are still needed. The function of sway


bracing cannot be replaced by using only normal support.
The advice from the consultant is not to use UL/FM
standard sway bracing such as Caddy or Toldo brands, just
use hand made fabrication sway bracing and the required
number of sway bracing is only 8 nos.