You are on page 1of 8

ORGALIME SI 14

GENERAL CONDITIONS
for the
SUPPLY AND INSTALLATION OF MECHANICAL, ELECTRICAL AND ELECTRONIC PRODUCTS
Brussels, January 2014

PREAMBLE DRAWINGS AND TECHNICAL INFORMATION


1. These General Conditions shall apply when the parties 4. All drawings and technical documents relating to the Works
agree In Writing or otherwise thereto. Any modifications of or submitted by one party to the other, prior or subsequent to the
deviations from them must be agreed In Writing. formation of the Contract, shall remain the property of the submitting
party.

DEFINITIONS Drawings, technical documents or other technical information


2. In these General Conditions the following terms shall have received by one party shall not, without the consent of the other
the meanings hereunder assigned to them: party, be used for any other purpose than that for which they were
provided. They may not, without the consent of the submitting
- “Contract”: the agreement In Writing between the
party, otherwise be used or copied, reproduced, transmitted or
parties concerning delivery and performance of the Works and
communicated to a third party.
all appendices, including agreed amendments and additions In
Writing to the said documents;
5. The Contractor shall, not later than at the date of taking-
- “Contract Price”: the payment to be made for the Works.
over, provide free of charge information and drawings which are
If installation is to be carried out on a time basis and has not been
necessary to permit the Purchaser to commission, operate and
completed, the Contract Price for the purposes of Clauses 21, 43,
maintain the Works. Such information and drawings shall be
44 and 51 shall be the price for the Plant with the addition of 10
supplied in the number of copies agreed upon or at least one
per cent or of any other percentage that may have been agreed by
copy of each. The Contractor shall not be obliged to provide
the parties;
manufacturing drawings for the Plant or for spare parts.
- “Gross Negligence”: an act or omission implying either
a failure to pay due regard to serious consequences, which a
TESTS BEFORE SHIPMENT
conscientious contracting party would normally foresee as likely
to ensue, or a deliberate disregard of the consequences of such 6. Tests before shipment of the Plant provided for in the
an act or omission; Contract shall, unless otherwise agreed, be carried out at the
place of manufacture during normal working hours.
- “In Writing”: communication by document signed by
both parties or by letter, fax, electronic mail and by such other If the Contract does not specify the technical requirements,
means as are agreed by the parties; the tests shall be carried out in accordance with general practice
in the appropriate branch of industry concerned in the country of
- “Plant”: the machinery, apparatus, materials, articles,
manufacture.
documentation, software and other products to be supplied by
the Contractor under the Contract;
7. The Contractor shall notify the Purchaser In Writing of these
- “Site”: the place where the Plant is to be installed,
tests in sufficient time to permit the Purchaser to be represented
including as much of the surrounding area as is necessary for
at the tests. If the Purchaser is not represented, the test report
unloading, storage and internal transport of the Plant and
shall be sent to the Purchaser and shall be accepted as accurate.
installation equipment;

- “Works”: the Plant, installation of the Plant and any other


8. If the tests show the Plant not to be in accordance with
work to be carried out by the Contractor under the Contract. If the
the Contract, the Contractor shall without delay remedy any
Works shall according to the Contract be taken over by separate
deficiencies in order to ensure that the Plant complies with the
sections intended to be used independently from each other,
Contract. New tests shall then be carried out at the Purchaser’s
these Conditions shall apply to each section separately. The term
request, unless the deficiency was insignificant.
“Works” shall then refer to the section in question.

9. The Contractor shall bear all costs for tests before shipment
PRODUCT INFORMATION
of the Plant. The Purchaser shall however bear all travelling and
3. All information and data contained in general product living expenses for his representatives in connection with such
documentation and price lists shall be binding only to the extent tests.
that they are by reference In Writing expressly included in the
Contract.

Licensed for electronic use by Voortman Steel Machinery; Licence N° 11/19/06 ORGALIME
PREPARATORY WORK AND WORKING CONDITIONS f) he has made available to the Contractor free of charge
10. The Contractor shall in good time provide drawings necessary storage facilities, providing protection against theft and
showing the manner in which the Plant is to be installed, together deterioration of the Plant, the tools and equipment required for
with all information required for preparing suitable foundations, for installation and the personal effects of the Contractor’s personnel;
providing access for the Plant and any necessary equipment to g) the access routes to the Site are suitable for the required
the Site and for making all necessary connections to the Works. transport of the Plant and the Contractor’s equipment.

11. The Purchaser shall in good time undertake preparatory 15. Upon the Contractor’s request in good time, the Purchaser
work to ensure that the conditions necessary for installation of shall make available to the Contractor, free of charge, such
the Plant and for the correct operation of the Works are fulfilled. labour and operators as may be specified in the Contract or as
This shall not apply to preparatory work which according to the may reasonably be required for the purpose of the Contract. The
Contract shall be performed by the Contractor. persons made available by the Purchaser under this clause shall
provide their own tools. The Contractor shall not be liable for such
12. The preparatory work referred to in Clause 11 shall be labour provided by the Purchaser or for any acts or omissions of
carried out by the Purchaser in accordance with the drawings the persons concerned.
and information provided by the Contractor under Clause 10.
In any case the Purchaser shall ensure that the foundations are 16. If the Contractor so requires, the Purchaser shall give all
structurally sound. If the Purchaser is responsible for transporting necessary assistance required for the import and re-export of
the Plant to the Site, he shall ensure that the Plant is on the Site the Contractor’s equipment and tools, including assistance with
before the agreed date for starting the installation work. customs formalities. The assistance as such shall be provided
free of charge.
13. If an error or omission in the drawings or information referred
to in Clause 10 is discovered by the Contractor or notified to him 17. The Purchaser shall give all necessary assistance to
In Writing before expiry of the period referred to in Clause 59, ensure that the Contractor’s personnel obtain, in good time, visas
the costs of any necessary remedial work shall be borne by the and any official entry, exit or work permits and (if necessary) tax
Contractor. certificates required in the Purchaser’s country, as well as access
to the Site. The assistance as such shall be provided free of
14. The Purchaser shall ensure that: charge.

a) the Contractor’s personnel are able to start work in


accordance with the agreed time schedule and to work during 18. The parties shall, no later than when the Contractor gives
normal working hours. Provided that the Purchaser has been notice that the Plant is ready for dispatch from the place of
given notice In Writing in reasonable time, work may be performed manufacture, each appoint a representative In Writing to act on
outside normal working hours to the extent deemed necessary by their behalf during the work on the Site.
the Contractor; The representatives shall be present on or near the Site
b) he has, in good time before installation is started, informed during working hours. Unless otherwise specified in the Contract,
the Contractor In Writing of all relevant safety regulations in force the representatives shall be authorised to act on behalf of their
at the Site. Installation shall not be carried out in unhealthy or respective party in all matters concerning the installation work.
dangerous surroundings. All the necessary safety and precautionary Wherever these General Conditions stipulate that a notice shall
measures shall have been taken before installation is started and be given In Writing, the representative shall always be authorised
shall be maintained; to receive such notice on behalf of the party he represents.

c) the Contractor’s personnel are able to obtain suitable and


convenient board and lodging in the neighbourhood of the Site PURCHASER’S DEFAULT
and have access to internationally acceptable hygiene facilities 19. If the Purchaser anticipates that he will be unable to fulfil
and medical services; in time his obligations necessary for carrying out installation,
d) he has made available to the Contractor free of charge at including complying with the conditions specified in Clauses 11,
the proper time on the Site all necessary cranes, lifting equipment 12 and 14-17, he shall forthwith notify the Contractor In Writing,
and equipment for transport on the Site, auxiliary tools, machinery, stating the reason and, if possible, the time when he will be able
materials and supplies (including fuel, oils, grease and other to carry out his obligations.
materials, gas, water, electricity, steam, compressed air, heating,
lighting, etc.), as well as the measuring and testing instruments 20. Without prejudice to the Contractor’s rights under Clause 21,
of the Purchaser available on the Site. The Contractor shall if the Purchaser fails to fulfil, correctly and in time, his obligations
specify In Writing his requirements concerning such cranes, lifting necessary for carrying out installation, including to comply with
equipment, measuring and testing instruments and equipment for the conditions specified in Clauses 11, 12 and 14-17, the following
transport on the Site at the latest one month before the agreed shall apply:
date for starting the installation work;
a) The Contractor may at his own discretion choose to
e) he has made available to the Contractor free of charge carry out or employ a third party to carry out the Purchaser’s
sufficient offices on the Site, equipped with telephone and access obligations or otherwise take such measures as are appropriate
to the Internet; under the circumstances in order to avoid or alleviate the effects
of the Purchaser’s default.

2
Licensed for electronic use by Voortman Steel Machinery; Licence N° 11/19/06 ORGALIME
b) The Contractor may suspend in whole or in part his shall notify the Purchaser In Writing whether and how the variation
performance of the Contract. He shall forthwith notify the Purchaser can be carried out, stating the resulting alteration to the Contract
In Writing of such suspension. Price, the time for taking-over and other terms of the Contract.

c) If the Plant has not yet been delivered to the Site, the The Contractor shall also give such notice to the Purchaser
Contractor shall arrange for storage of the Plant at the Purchaser’s when variations are required as a result of changes in laws,
risk. The Contractor shall also, if the Purchaser so requires, insure regulations and rules referred to in Clause 22.
the Plant.

d) The Purchaser shall pay any part of the Contract Price 28. If taking-over is delayed as a result of disagreement between
which, but for the default, would have become due. the parties on the consequences of variations, the Purchaser shall
pay any part of the Contract Price which would have become due
e) The Purchaser shall reimburse the Contractor for any
if taking-over had not been delayed.
costs not covered by Clause 47 or 48, which are reasonably
incurred by the Contractor as a result of measures under a), b) or
c) of this Clause. 29. Save as provided in Clause 23, the Contractor shall not
be obliged to carry out variations requested by the Purchaser
until the parties have agreed on how the variations will affect the
21. If taking-over is prevented by the Purchaser’s default as
Contract Price, the time for taking-over and other terms of the
referred to in Clause 20 and this is not due to any such circumstance
Contract.
as mentioned in Clause 73, the Contractor may also by notice In
Writing require the Purchaser to remedy his default within a final
reasonable period. PASSING OF RISK
If, for any reason which is not attributable to the Contractor, 30. The risk of loss of or damage to the Plant shall pass to the
the Purchaser fails to remedy his default within such period, the Purchaser in accordance with any agreed trade term, which shall
Contractor may by notice In Writing terminate the Contract in whole be construed in accordance with the INCOTERMS® in force at
or in part. The Contractor shall then be entitled to compensation for the date of formation of the Contract. If no trade term has been
the loss he suffers by reason of the Purchaser’s default, including specifically agreed, delivery of the Plant shall be Free Carrier
any consequential and indirect loss. The compensation shall not (FCA) at the place named by the Contractor.
exceed that part of the Contract Price which is attributable to that Any risk of loss of or damage to the Works not covered by
part of the Works in respect of which the Contract is terminated. the first paragraph of this Clause shall pass to the Purchaser on
taking-over of the Works.
LOCAL LAWS AND REGULATIONS Any loss of or damage to the Plant and Works after the risk
22. The Contractor shall ensure that the Works are carried out has passed to the Purchaser shall be at the risk of the Purchaser,
and are in accordance with any laws, regulations and rules which unless such loss or damage results from the Contractor’s negligence.
are applicable to the Works. If required by the Contractor, the
Purchaser shall provide the relevant information on these laws,
TAKING-OVER TESTS
regulations and rules In Writing.
31. When installation has been completed taking-over tests
shall, unless otherwise agreed, be carried out to determine
23. The Contractor shall carry out any variation work necessary whether the Works are as required for taking-over according to
to comply with changes in laws, regulations and rules, referred to in the Contract.
Clause 22, or in their generally accepted interpretation, occurring
The Contractor shall notify the Purchaser In Writing that
between the date of submission of the tender and taking-over.
the Works are ready for taking-over. He shall in this notice give a
The Purchaser shall bear the extra costs and other consequences
date for taking-over tests, giving the Purchaser sufficient time to
resulting from such changes, including variation work.
prepare for and be represented at these tests.

The Purchaser shall bear all costs of taking-over tests. The


24. If the parties are unable to agree on the extra costs and
Contractor shall however bear all costs relating to his personnel
other consequences of changes in laws, regulations and rules,
and his other representatives.
referred to in Clause 22, the Contractor shall be compensated for
any variation work on a time basis.
32. The Purchaser shall provide free of charge any power,
lubricants, water, fuel, raw materials and other materials required
VARIATIONS
for the taking-over tests and for final adjustments in preparing for
25. Subject to the provisions of Clause 29, the Purchaser is these tests. He shall also install free of charge any equipment and
entitled to request variations to the scope, design and construction provide any labour or other assistance necessary for carrying out
of the Works until the Works have been taken over. The Contractor the taking-over tests.
may suggest such variations In Writing.

33. If, after having been notified in accordance with Clause


26. Requests for variations shall be submitted to the Contractor 31, the Purchaser fails to fulfil his obligations under Clause 32
In Writing and shall contain an exact description of the variation. or otherwise prevents the taking-over tests from being carried
out, the tests shall be regarded as having been satisfactorily
27. As soon as possible after receipt of a request for a variation or completed at the starting date for taking-over tests stated in the
after having himself made a proposal for a variation, the Contractor Contractor’s notice.

3
Licensed for electronic use by Voortman Steel Machinery; Licence N° 11/19/06 ORGALIME
34. The taking-over tests shall be carried out during normal he shall forthwith notify the Purchaser thereof In Writing, stating
working hours. If the Contract does not specify the technical the reason and, if possible, the time when taking-over can be
requirements, the tests shall be carried out in accordance with expected.
general practice in the appropriate branch of industry concerned If the Contractor fails to give such notice, the Purchaser
in the Purchaser’s country. shall be entitled to compensation for any additional costs which
he incurs and which he could have avoided had he received such
35. The Contractor shall prepare a report of the taking-over notice.
tests. This report shall be sent to the Purchaser. If the Purchaser
has not been represented at the taking-over tests after having
42. The Contractor shall be entitled to an extension of the time
been notified in accordance with Clause 31, the test report shall
for taking-over if delay occurs:
be accepted as accurate.
a) because of any of the circumstances referred to in
Clause 73, or
36. If the taking-over tests show the Works not to be in
b) as a result of variation work under Clause 23, or
accordance with the Contract, the Contractor shall without delay
remedy the deficiencies. If the Purchaser so requires In Writing c) as a result of variations under Clauses 25-29, or
without delay, new tests shall be carried out in accordance with d) as a result of suspension under Clauses 20, 51 or 76, or
Clauses 31-35. This shall not apply when the deficiency was
e) by an act or omission on the part of the Purchaser or any
insignificant.
other circumstances attributable to the Purchaser.

The extension shall be as necessary having regard to all


TAKING-OVER the relevant circumstances. This provision applies regardless of
37. Taking-over of the Works shall be considered to take place: whether the reason for the delay occurs before or after the agreed
a) when the taking-over tests have been satisfactorily time for taking-over.
completed or are regarded under Clause 33 as having been
satisfactorily completed, or
43. If the Works are not completed at the agreed time for
b) where the parties have agreed not to carry out taking- taking-over, the Purchaser shall be entitled to liquidated damages
over tests, when the Purchaser has received a Contractor’s notice from the date on which taking-over should have taken place.
In Writing that the Works have been completed, provided that the
The liquidated damages shall be payable at a rate of 0.5
Works are as required for taking-over according to the Contract.
per cent of the Contract Price for each commenced week of
Minor deficiencies which do not affect the efficiency of the delay. The liquidated damages shall not exceed 7.5 per cent of
Works shall not prevent taking-over. the Contract Price.
The Contractor’s obligation to install the Plant at the Site If only part of the Works is delayed, the liquidated damages
is fulfilled when the Works are taken over pursuant to this Clause shall be calculated on that part of the Contract Price which is
37, notwithstanding his obligation to remedy any remaining minor attributable to such part of the Works as cannot in consequence
deficiencies. of the delay be used as intended by the parties.

The liquidated damages become due at the Purchaser’s


38. The Purchaser is not entitled to use the Works or any part demand In Writing, but not before taking-over has taken place or
thereof before taking-over. If the Purchaser does so without the the Contract is terminated under Clause 44.
Contractor’s consent In Writing, the Works shall be deemed to
The Purchaser shall forfeit his right to liquidated damages
have been taken over. The Contractor is then relieved of his duty
if he has not lodged a claim In Writing for such damages within six
to carry out taking-over tests.
months after the time when taking-over should have taken place.

39. As soon as the Works have been taken over in accordance


44. If the delay is such that the Purchaser is entitled to
with Clause 37 or 38, the period referred to in Clause 59 shall start
maximum liquidated damages under Clause 43 and if the Works
to run. The Purchaser shall, at the Contractor’s request In Writing,
are still not ready for taking-over, the Purchaser may In Writing
issue a certificate stating when the Works have been taken over.
demand completion of the Works within a final reasonable period
The Purchaser’s failure to issue a certificate shall not affect taking-
which shall not be less than one week.
over according to Clauses 37 and 38.
If the Contractor does not complete the Works within
such final period and this is not due to any circumstance which is
CONTRACTOR’S DELAY
attributable to the Purchaser, then the Purchaser may by notice In
40. If the parties, instead of specifying the date for taking-over, Writing to the Contractor terminate the Contract in respect of such
have specified a period of time within which taking-over shall part of the Works as cannot in consequence of the Contractor’s
take place, such period shall start to run as soon as the Contract failure be used as intended by the parties.
is entered into and all agreed preconditions to be fulfilled by
If the Purchaser terminates the Contract he shall be
the Purchaser have been satisfied, such as official formalities,
entitled to compensation for the loss he suffers as a result of the
payments due at the formation of the Contract and securities.
Contractor’s delay, including any consequential and indirect loss.
The total compensation, including the liquidated damages which
41. If the Contractor anticipates that he will not be able to fulfil
are payable under Clause 43, shall not exceed 15 per cent of that
his obligations for taking-over before or at the time for taking-over,

4
Licensed for electronic use by Voortman Steel Machinery; Licence N° 11/19/06 ORGALIME
part of the Contract Price which is attributable to the part of the and at night shall be charged at special rates. The rates shall be as
Works in respect of which the Contract is terminated. agreed in the Contract or, failing agreement, as normally charged
by the Contractor. Save as otherwise provided, the hourly rates
The Purchaser shall also have the right to terminate the
cover the normal wear and tear of the Contractor’s tools and light
Contract by notice In Writing to the Contractor if it is clear from
equipment;
the circumstances that there will occur a delay in taking-over of
the Works which under Clause 43 would entitle the Purchaser d) time necessarily spent on:
to maximum liquidated damages. In case of termination for this - preparation and formalities incidental to
reason, the Purchaser shall be entitled to maximum liquidated the outward and homeward journeys of the
damages and compensation under the third paragraph of this Contractor’s personnel,
Clause 44. - the outward and homeward journeys and other
journeys to which the personnel are entitled in
45. Liquidated damages under Clause 43 and termination of accordance with current law, regulations or
the Contract with limited compensation under Clause 44 shall be collective agreements in the Contractor’s
the only remedies available to the Purchaser in case of delay on country,
the part of the Contractor. All other claims against the Contractor - daily travel of the Contractor’s personnel
based on such delay shall be excluded, except where the between lodgings and the Site, if it exceeds half
Contractor has been guilty of Gross Negligence. an hour each way and there are no suitable
lodgings closer to the Site,
PAYMENT - waiting when work is prevented by
46. Unless otherwise agreed, payment shall be made within 30 circumstances which are not attributable to the
days after the date of the invoice as follows: Contractor;

a) when installation is carried out on a time basis: e) any expenses incurred by the Contractor in accordance
with the Contract in connection with the provision of equipment
- one third of the agreed price for the Plant at the
by him, including where appropriate a charge for the use of the
formation of the Contract,
Contractor’s own heavy equipment;
- one third when the Contractor notifies the
Purchaser that the Plant or the essential part f) any taxes or dues levied on the invoice and payable by
of it is ready for dispatch from the place of the Contractor in the country where installation takes place;
manufacture and g) any costs which could not reasonably be foreseen by
- the final third on arrival of the Plant at the Site. the Contractor and are caused by a circumstance which is not
attributable to the Contractor;
Payment for installation shall be made against monthly
invoices. h) any extra costs resulting from the applicability of mandatory
rules of the Purchaser’s country in the social field;
b) when installation is included in the lump sum Contract
Price: i) any costs, expenses and time spent resulting from extra
- 30 per cent of the Contract Price at the work which is not attributable to the Contractor.
formation of the Contract,
If these costs are time-related, they shall be charged at the
- 30 per cent when the Contractor notifies the rates referred to in this Clause 47 under c.
Purchaser that the Plant or the essential part
of it is ready for dispatch from the place of
48. When installation is to be carried out for a lump sum, the
manufacture,
Contract Price shall be deemed to include all the items mentioned
- 30 per cent on arrival of the Plant at the Site,
in Clause 47, a) through e). Any items mentioned in Clause 47,
- the remaining part of the Contract Price on f) through i), shall be deemed to be excluded from the Contract
taking-over. Price and shall therefore be charged separately. If these costs
are time-related, they shall be charged at the rates referred to in
47. When installation is carried out on a time basis the following Clause 47 under c).
items shall be separately charged:
a) all travelling expenses incurred by the Contractor in 49. If installation is delayed due to a cause which is attributable
respect of his personnel and the transport of their equipment and to the Purchaser, the Purchaser shall compensate the Contractor
personal effects (within reasonable limits) in accordance with the for any resulting additional costs, including but not limited to:
specified method and class of travel where these are specified in
a) waiting time and time spent on extra journeys;
the Contract;
b) costs and extra work resulting from the delay, including
b) cost of board and lodging and other living expenses,
removing, securing and setting up installation equipment;
including any appropriate allowances of the Contractor’s personnel
for each day’s absence from their homes, including non-working c) additional costs, including costs as a result of the
days and holidays. The daily allowances shall be payable even Contractor having to keep his equipment at the Site for a longer
during incapacity caused by sickness or accident; time than expected;

c) the time worked, which shall be calculated by reference d) additional costs for journeys and board and lodging for
to the number of hours certified as worked in the time-sheets the Contractor’s personnel;
signed by the Purchaser. Overtime and work on Sundays, holidays

5
Licensed for electronic use by Voortman Steel Machinery; Licence N° 11/19/06 ORGALIME
e) additional financing costs and costs of insurance; LIABILITY FOR DEFECTS
f) other documented costs incurred by the Contractor as a 55. Pursuant to the provisions of Clauses 56-71, the Contractor
result of changes in the installation programme. shall remedy any defect or nonconformity (hereinafter termed
defect(s)) in the Works resulting from faulty design, materials or
If these costs are time-related, they shall be charged at
workmanship.
the rates referred to in Clause 47 under c).

56. The Contractor shall not be liable for defects arising out
50. Whatever the means of payment used, payment shall not
of materials provided or a design stipulated or specified by the
be deemed to have been effected before the Contractor’s account
Purchaser.
has been irrevocably credited for the amount due.

51. If the Purchaser fails to pay by a stipulated date, the 57. The Contractor shall only be liable for defects which appear
Contractor shall be entitled to interest from the day on which under the conditions of operation provided for in the Contract and
payment was due and to compensation for recovery costs. The under proper use of the Works.
rate of interest shall be as agreed between the parties or otherwise
8 percentage points above the rate of the main refinancing facility 58. The Contractor shall not be liable for defects caused by
of the European Central Bank. The compensation for recovery circumstances which arise after the risk has passed to the Purchaser,
costs shall be 1 per cent of the amount for which interest for late e.g. defects due to faulty maintenance or faulty repair by the
payment becomes due. Purchaser or to alterations carried out without the Contractor’s
In case of late payment and in case the Purchaser fails consent In Writing. The Contractor shall neither be liable for normal
to give an agreed security by the stipulated date the Contractor wear and tear nor for deterioration.
may, after having notified the Purchaser In Writing, suspend his
performance of the Contract until he receives payment or, where 59. The Contractor’s liability shall be limited to defects in the
appropriate, until the Purchaser gives the agreed security. Works which appear within a period of one year from taking-over. If
If the Purchaser has not paid the amount due within three the use of the Works exceeds that which is agreed, this period shall
months, the Contractor shall be entitled to terminate the Contract be reduced proportionately. If taking-over has been delayed for
by notice In Writing to the Purchaser and, in addition to the interest reasons which are attributable to the Purchaser, the Contractor’s
and compensation of recovery costs according to this Clause 51, liability for defects shall not, except as stated in Clause 60, be
to claim compensation for the loss he incurs. Such compensation extended beyond 18 months after delivery of the Plant.
shall not exceed the Contract Price.
60. When a defect in a part of the Works has been remedied,
RETENTION OF TITLE the Contractor shall be liable for defects in the repaired or replaced
52. The Plant shall remain the property of the Contractor until part under the same terms and conditions as those applicable to
paid for in full, including payment for installation of the Plant, to the original Works for a period of one year. For the remaining parts
the extent that such retention of title is valid under the relevant of the Works the period mentioned in Clause 59 shall be extended
law. only by a period equal to the period during which and to the extent
The Purchaser shall at the request of the Contractor assist that the Works could not be used as a result of the defect.
him in taking any measures necessary to protect the Contractor’s
title to the Plant. 61. The Purchaser shall without undue delay notify the Contractor
The retention of title shall not affect the passing of risk In Writing of any defect which appears. Such notice shall under no
under Clause 30. circumstances be given later than two weeks after the expiry of the
period given in Clause 59 or the extended period(s) under Clause
60, where applicable.
LIABILITY FOR DAMAGE TO PROPERTY BEFORE
TAKING-OVER The notice shall contain a description of the defect.

53. The Contractor shall be liable for any damage to the Works If the Purchaser fails to notify the Contractor In Writing of a
which occurs before the risk has passed to the Purchaser. This defect within the time limits set forth in the first paragraph of this
applies irrespective of the cause of the damage, unless the damage Clause, he shall lose his right to have the defect remedied.
has been caused by the Purchaser or anyone for whom he is Where the defect is such that it may cause damage, the
responsible in connection with performance of the Contract. If the Purchaser shall immediately inform the Contractor In Writing. The
Contractor is not liable for the damage to the Works in accordance Purchaser shall bear the risk of damage to the Works resulting
with this Clause, the Purchaser may still require the Contractor to from his failure so to notify. The Purchaser shall take reasonable
remedy the damage, be it at the Purchaser’s cost. measures to minimise damage and shall in that respect comply
with instructions of the Contractor.
54. The Contractor shall be liable for damage to the Purchaser’s
property occurring before taking-over of the Works only if it is 62. On receipt of the notice under Clause 61 the Contractor
proved that such damage was caused by negligence on the part of shall at his own cost remedy the defect without undue delay, as
the Contractor or anyone for whom he is responsible in connection stipulated in Clauses 55-71. The time for remedial work shall be
with the performance of the Contract. The Contractor shall chosen in order not to interfere unnecessarily with the Purchaser’s
however under no circumstances be liable for loss of production, activities.
loss of profit or any other consequential or indirect loss.
Remedial work shall be carried out at the Site, unless
6
Licensed for electronic use by Voortman Steel Machinery; Licence N° 11/19/06 ORGALIME
the Contractor deems it more appropriate, having regard to the is so substantial as to significantly deprive the Purchaser of the
interests of both parties, that the defective part or the Plant is sent benefit of the Contract as regards the Works or a substantial part
to him or a destination specified by him. of it,

Where remedial work is carried out at the Site, Clauses 14- b) the Purchaser may terminate the Contract by notice In
17 and 54 shall apply correspondingly. Writing to the Contractor in respect of such part of the Works as
cannot in consequence of the defect be used as intended by the
If the defect can be remedied by replacement or repair of a
parties. The Purchaser shall then be entitled to compensation for
defective part and if dismantling and re-installation of the part do
his loss, costs and damages up to a maximum of 15 per cent of
not require special knowledge, the Contractor may demand that
that part of the Contract Price which is attributable to the part of
the defective part is sent to him or a destination specified by him.
the Works in respect of which the Contract is terminated.
In such case the Contractor shall have fulfilled his obligations in
respect of the defect when he delivers a duly repaired part or a
part in replacement to the Purchaser. 70. Notwithstanding the provisions of Clauses 55-69 the
Contractor shall not be liable for defects in any part of the Works
for more than one year from the end of the liability period referred
63. The Purchaser shall at his own expense provide access
to in Clause 59 or from the end of any other liability period agreed
to the Works and arrange for any intervention in equipment other
upon by the parties.
than the Works, to the extent that this is necessary to remedy the
defect.
71. Save as stipulated in Clauses 55-70, the Contractor shall
not be liable for defects. This applies to any loss the defect
64. Unless otherwise agreed, necessary transport of the Plant
may cause, including loss of production, loss of profit and other
or parts thereof to and from the Contractor in connection with the
indirect loss. This limitation of the Contractor’s liability shall not
remedying of defects for which the Contractor is liable shall be at
apply if he has been guilty of Gross Negligence.
the risk and expense of the Contractor. The Purchaser shall follow
the Contractor’s instructions regarding such transport.
ALLOCATION OF LIABILITY FOR DAMAGE CAUSED BY
THE WORKS
65. Unless otherwise agreed, the Purchaser shall bear any
additional costs which the Contractor incurs for remedying the 72. The Contractor shall not be liable for any damage to
defect caused by the Works being located in a place other than property caused by the Works after taking-over and whilst the
the Site. Works are in the possession of the Purchaser. Nor shall the
Contractor be liable for any damage to products manufactured by
the Purchaser or to products of which the Purchaser’s products
66. Defective parts which have been replaced shall be made
form a part.
available to the Contractor and shall be his property.
If the Contractor incurs liability towards any third party
for such damage to property as described in the preceding
67. If the Purchaser has given such notice as mentioned in
paragraph, the Purchaser shall indemnify, defend and hold the
Clause 61 and no defect is found for which the Contractor is
Contractor harmless.
liable, the Contractor shall be entitled to compensation for the
costs he incurs as a result of the notice. If a claim for damage as described in this Clause is lodged
by a third party against one of the parties, the latter party shall
forthwith inform the other party thereof In Writing.
68. If the Contractor does not fulfil his obligations under Clause
62, the Purchaser may by notice In Writing fix a final reasonable The Contractor and the Purchaser shall be mutually
period for fulfilment of the Contractor’s obligations, which shall obliged to let themselves be summoned to the court or arbitral
not be less than one week. tribunal examining claims for damages lodged against one of
them on the basis of damage allegedly caused by the Works. The
If the Contractor fails to fulfil his obligations within such final
liability between the Contractor and the Purchaser shall however
period, the Purchaser may himself undertake or employ a third
be settled in accordance with Clause 78.
party to undertake necessary repair work at the risk and expense
of the Contractor. The limitation of the Contractor’s liability in the first
paragraph of this Clause shall not apply where the Contractor has
Where successful repair work has been undertaken by
been guilty of Gross Negligence.
the Purchaser or a third party, reimbursement by the Contractor
of reasonable costs incurred by the Purchaser shall be in full
settlement of the Contractor’s liabilities for the said defect. FORCE MAJEURE
73. Either party shall be entitled to suspend performance of his
69. Where the defect has not been successfully remedied, as obligations under the Contract to the extent that such performance
stipulated under Clause 68: is impeded or made unreasonably onerous by Force Majeure,
meaning any of the following circumstances: industrial disputes
a) the Purchaser shall be entitled to a reduction of the
and any other circumstance beyond the control of the parties,
Contract Price in proportion to the reduced value of the Works,
such as fire, war, extensive military mobilization, insurrection,
provided that under no circumstances shall such reduction
requisition, seizure, embargo, restrictions in the use of power,
exceed 15 per cent of the Contract Price, or, where the defect

7
Licensed for electronic use by Voortman Steel Machinery; Licence N° 11/19/06 ORGALIME
currency and export restrictions, epidemics, natural disasters, ANTICIPATED NON-PERFORMANCE
extreme natural events, terrorist acts and defects or delays in 76. Notwithstanding other provisions in these General
deliveries by sub-contractors caused by any such circumstance Conditions regarding suspension, each party shall be entitled to
referred to in this Clause. suspend the performance of his obligations under the Contract
A circumstance referred to in this Clause, whether where it is clear from the circumstances that the other party is
occurring prior to or after the formation of the Contract, shall give not going to perform his obligations. A party suspending his
a right to suspension only if its effect on the performance of the performance of the Contract shall forthwith notify the other party
Contract could not be foreseen at the time of the formation of the thereof In Writing.
Contract.

CONSEQUENTIAL LOSSES
74. The party claiming to be affected by Force Majeure shall 77. Save as otherwise stated in these General Conditions there
notify the other party In Writing without delay on the intervention shall be no liability on either party towards the other party for loss
and on the cessation of such circumstance. If a party fails to give of production, loss of profit, loss of use, loss of contracts or for
such notice, the other party shall be entitled to compensation for any other consequential or indirect loss whatsoever.
any additional costs which he incurs and which he could have
avoided had he received such notice.
DISPUTES AND APPLICABLE LAW
If Force Majeure prevents the Purchaser from fulfilling his
78. All disputes arising out of or in connection with the
obligations, he shall compensate the Contractor for expenses
Contract shall be finally settled under the Rules of Arbitration of
incurred in securing and protecting the Works.
the International Chamber of Commerce by one or more arbitrators
appointed in accordance with the said Rules.
75. Regardless of what might otherwise follow from these
General Conditions, either party shall be entitled to terminate the
79. The Contract shall be governed by the substantive law of
Contract by notice In Writing to the other party if performance
the Contractor’s country.
of the Contract is suspended under Clause 73 for more than six
months.

This is an Orgalime publication. Orgalime represents the mechanical, electrical, electronic and metalworking industries in Europe.
All rights reserved ©
Editeur responsable : Adrian Harris, Director General
ORGALIME – The European Engineering Industries Association
Diamant Building, Boulevard A Reyers 80, B – 1030 Brussels
Tel: +32 2 706 82 35 – Fax: +32 2 706 82 50 – secretariat@orgalime.org – www.orgalime.org

Licensed for electronic use by Voortman Steel Machinery; Licence N° 11/19/06 ORGALIME

You might also like