Professional Documents
Culture Documents
Crown MLCP MEP DBR R0 - 13.09.23
Crown MLCP MEP DBR R0 - 13.09.23
PROJECT
CLIENT
Page 1 of 67
MEP DBR
DOCUMENT CONTROL
REVISION
DATE SERVICE REMARKS
NUMBER
Page 2 of 67
MEP DBR
Contents
SECTION I : GENERAL............................................................................................. 5
1. PREAMBLE ................................................................................................................................. 5
2. PROJECT DESCRIPTION .......................................................................................................... 5
Page 3 of 67
MEP DBR
Page 4 of 67
MEP DBR
SECTION I : GENERAL
1. PREAMBLE
The intent of this report is to give an overview of MEPF (Mechanical, Electrical, Plumbing and
Fire Fighting) services designed by LEAD Consultancy & Engineering Services (India) Pvt. Ltd,
Bengaluru, herein after referred as LCES in this document, for the proposed project of MLCP
building of Lodha Taloja, Navi Mumbai
2. PROJECT DESCRIPTION
Project consists single building with G+12 upper floors structure with terrace. Latest architectural floor
plans received dt. 05.09.2023 have been used for DBR preparation. Following is the ground floor plan
of the building.
Page 5 of 67
MEP DBR
Page 6 of 67
MEP DBR
1. HVAC OBJECTIVES
The objective is to create a thermally controlled, clean environment within the space of a building
envelope by providing energy-efficient HVAC system. The objective is that the HVAC system
designed and built is economical, energy efficient, simple and flexible with regard to its operation &
maintenance.
The design is based on the inputs from the Client, Architects, the entire design team, and as per the
requirements of applicable codes, standards and best practices of good engineering design.
The DBR is based on the latest architectural drawing shared through mail dt.05.09.2023.
It is to be noted that this report on The HVAC system proposal is for concept information only. The
concept report aims to set the direction for further detail design development, collating all comments
from the client / architects prior to acceptance and sign-off.
2. SCOPE OF WORKS
Parking general ventilation
Parking smoke management
Mechanical ventilation of utility rooms
Mechanical ventilation of toilets
Air conditioning of retail areas, FCC on the ground floor
Stair / lift well / lift lobby pressurization as per NBC-2016
Page 7 of 67
MEP DBR
Apart from the specific equipment standards and specifications, the following broad certifying agency /
standards have been considered while designing the HVAC system.
NBC-2016
ASHRAE 90.1 – Energy Standard for Buildings (2016)
ASHRAE 62.1 – Ventilation for Acceptable Indoor Air Quality (2016)
ASHRAE 52.1 – Air Filters
ASHRAE 55 - Thermal Comfort Conditions for Human Occupancy
AMCA – Fans
SMACNA – Duct Construction Standards.
ECBC – Energy Conservation Building code.
ASHRAE Handbooks – Design Principals
NFPA – 90 A for Installation of Air Conditioning and Ventilation Systems
4. BASIS OF DESIGN
Location - Mumbai
Latitude - 19.089 Lat ° N
Altitude: - 11 meters (36 Feet)
Daily Temp. Range - 05 °C (09 °F)
0.4% and 99.6% Design data values have been considered for Cooling and Heating system
design as applicable.
Page 8 of 67
MEP DBR
Design Parameters:
Glass U-value : 5.5 W/(m2.K), SHGC: 0.81 (As per previous DBR reference)
Wall U-value : 0.36 Btu / Hr Sq.ft °F (Assumed, need to confirm by client)
Partition U-value : 0.36 Btu / Hr Sq.ft °F (Assumed, need to confirm by client)
Roof U-value : 0.40 Btu / Hr Sq.ft °F (Assumed, need to confirm by client)
Lighting Loads-Retail : 1.0 W/Sqft (As per previous DBR reference)
Equipment Loads-Retail : 3.0 W/Sqft (As per previous DBR reference)
Occupancy- Office/Retail : 66 Sqft/Person (Assumed as per previous experience)
i. RETAIL AREAS
For ground floor retail shops, DX split ACs have been planned. The outdoor units shall be planned on
the chajja provided on the first floor. The power cabling and the refrigerant piping will be taken out
from the retail shops through appropriate slab and wall openings to finally connect it to the 1st floor
ODUs. Dedicated fresh air system is not envisaged for the retail shops. The infiltration through the
door openings shall meet the fresh air requirements, as all retail shops are abutting external wall/door.
Based on the previous experiences and instructions from the Lodha team, it is observed that sizing
the AC capacities on area basis (180 sqft/TR), gives the results slightly higher than the HAP
calculations. The same approach shall be adopted for sizing the AC capacities for ground floor retails.
The condensate drain water pipe shall be terminated inside the available individual retail toilets or the
drain point.
The condensate drain water pipe shall be terminated inside the available drain point.
Page 9 of 67
MEP DBR
The condensate drain water pipe shall be terminated inside the available drain point.
6. VENTILATION - TOILETS
Each toilet is designed with minimum 10 ACPH air flow rate as per NBC-2016.
8. VENTILATION - PARKING
Natural ventilation shall be envisaged for car parking at all the floor levels of MLCP building as per
NBC-2016, as the entire area is exposed to the ambient from all directions. To achieve this, minimum
2.5% of the floor car parks area will be provided as wall openings spread evenly around the building
perimeter.
Page 10 of 67
MEP DBR
9. VENTILATION - CORRIDOR
Since the corridor formed by the retail shops, is not enclosed at its both entrance ends, same is
considered under natural ventilation.
Page 11 of 67
MEP DBR
As the building height is more than 30 meters (34 meters), as per NBC-2016 Clauses 4.4.2.5 table-6,
all these project staircases shall be either pressurized or cross ventilated. An abstract of the NBC-
2016 clause is attached below for reference.
As it evident from the architectural layouts that cross ventilation of these three staircases (with
external walls) are not possible hence pressurization as per NBC-2016 has been considered. The
pressurisation fans shall be located on the terrace. To avoid over pressurization (above 50 Pascals) in
the staircases, pressure relief dampers shall be incorporated.
As it can be seen from the staircase ST-3 layout, the lift lobby is difficult to provide with active
pressurization system since lobby is not enclosed at all the levels, hence as per above mentioned
table-6 from NBC-2016, the liftwell shall be considered for pressurization. The infiltration air coming
from the gaps of staircase ST-3 door and Lift doors shall result in certain amount of positive pressure
inside the lift lobby compared to the parking areas.
Page 12 of 67
MEP DBR
As mentioned in the above section, the two liftwells of the MLCP building shall be pressurized. The
fans shall be located on the terrace, integrated with fire alarm system.
All the pressurization fans at the terrace level shall be provided with bird mesh. The fan units and the
starter panels shall be planned with the weather protection hoods/canopy.
The parking floors' natural ventilation will serve as a passive method of managing and dispersing the
smoke and fire produced.
v. CORRIDOR
The corridor' natural ventilation will serve as a passive method of managing and dispersing the smoke
and fire produced.
Following tables provides the summary of battery limits of the buyer's ( End customer) and Builder's
scope of works.
Page 14 of 67
MEP DBR
Page 15 of 67
MEP DBR
Design Considerations
Load matrix
HT Breakers
HT Metering yard
HT panels
HT Cables
Transformers
Generators & Synchronizing Panel
LT Switchgears, Bus ducts, Cables and end terminations
Short circuit study for precise selection of switchgears
Voltage drop calculation for precise selection of cables & bus ducts
UPS systems and battery backup
Transient voltages
Automation and monitoring - optional
Selection of Lighting for common areas as per lighting simulation & for Retails as per
architect/ ID team.
Emergency Lighting
General power for common areas
Earthing system
Lightning protection system
DG fuel system shall be from Day tank.
5. DESIGN CONSIDERATION
Primary Voltage system would be 11KV, 3 Phase, 3 wire, 50Hz (fault level considered is
350MVA).
Power requirement is approximate for CROWN MLCP 785 kVA / 707 kW seen from the load
matrix/ load list.
Secondary voltage system 415 V, 50 Hz, 3 Phase, 4 Wire.
Incoming HT power – based on feasibility single input from distinct upstream substations of
M/s. MSEDCL . In case M/s. MSEDCL gives sanction only for a single feed, RMU can be
utilized as a loop in loop out or in place of RMU single module HT breaker can be installed.
However, it can be concluded upon receipt of a feasibility report from M/s. MSEDCL.
11kV Ring main unit.
HT power connectivity using XLPE (E) – Aluminum conductor cables – 11KV to withstand
fault levels as per M/s. MSEDCL prescription.
Conventional Transformers – Dry type – with off-load tap changer (OCTC) and high efficient
copper-wound type to ensure low losses as per M/s. MSEDCL prescription. The Transformer
will be N configuration as per M/s. MSEDCL requirement.
Feeder Breakers and Transformer Feeding HT breakers with numerical relays for protection.
Secondary connections using Aluminium armoured cables to suit site conditions between
Transformer & Feeder Pillar/ Main Panel.
Page 16 of 67
MEP DBR
Form-3b, IP4X/5X switchboards for power distribution with breakers of suitable kA levels.
Standby LT Diesel Generators –back up for common load of Crown MLCP tower.
Emergency lighting loads – 10-15% of Lighting is catered through inverters for common area
lighting
Sizing of cables to restrict voltage drop <5% up to end point.
Transient voltage suppression using TVSS and SPD’s in different distribution levels.
All light fitting shall be of LED type with drivers, along with dimmable ballasts where dimming
is required.
Lighting lux level (refer matrix for lighting in different areas).
Earthing system as per IS code and IEEE.
Lightning protection systems as per the codes and standard practice.
Closure of electrical and LV shafts with fire retardant materials to avoid fire entering to the
other floors.
Closure of equipment’s wall crossing using fire seal material.
Page 17 of 67
MEP DBR
Load
Description Summary Unit
CASA
Crown MLCP TCL 1873 kW
Crown MLCP MDL 707 kW
Transformer Load in kVA @ 0.9 PF 786 kVA
Transformer Capacity with 85 % loading 924 kVA
TRANSFORMER CAPACITY
1Nos. 1000KVA
SELECTION : -
Page 18 of 67
MEP DBR
Load
DG Load for common area (CCrown
Summary Unit
MLCP)
CASA
DG Load in Kw 603 kW
DG Load in kVA @ 0.8 PF 754 kVA
DG Capacity with 90 % loading 837 kVA
8. GRID POWER
It is intended to bring in 11 KV HT Power to the proposed facility from distinct upstream Power
stations/ Network of M/s. MSEDCL.
It is Planned to opt 1 No's of Ring main unit for the proposed project and each Ring main
unit has 2 No’s of Load break switch as incomer & 1 no's of Vacuum circuit Breaker as
outgoing.
HT cable shall be laid in RCC trench/DWC HDPE pipes and chambers or on Cable trays
and Route marker shall be installed at regular intervals of 25-30 meters.
The Incoming & Outgoing Breaker selection and cable sizing for HT Installation will be
designed based on system fault level (in MVA) confirmation by M/s. MSEDCL.
The RMU will be located indoor at the substation as per the prescription of M/s. MSEDCL.
10. HT CABLES
Based on MSEDCL feasibility study and recommendation HT cable size will be considered. The cable
selection will be based on fault level and current carrying capacity. Distance between upstream
substation and the proposed facility is also a key factor to size cable based on voltage drop. Cable
current carrying capacity need to be de rated based on manufacturers recommendations since the
cable will be laid underground. HT cables are laid in trench/Buried though Hume pipes or on cable
trays. The same shall be as per MSEDCL & installed by builder.
Page 19 of 67
MEP DBR
Battery charger is provided inbuilt in HT panel. The purpose of the battery is to have the reliable
power required for operation of switchgear and trip circuits.
Battery voltage shall be of 110 Volts DC 12.0 Emergency Stop Button - Optional
Emergency stop button shall be provided for isolation of HT power during fire or emergency. The
feasible location for the emergency push button shall be as per MSEDCL approvals/inputs. Same
shall be provided by builder.
12. TRANSFORMER
Transformers envisaged is of oil / dry type with below-mentioned configuration
Since the transformers are indoor, dry type and outdoor oil type transformers are proposed
considering the following parameters. (Transformer is in Supply Company (MSEDCL) Scope Need to
Confirm Type of transformer With Supply Company (MSEDCL))
Greater energy efficiency with lower losses as per ECBC for dry type / IS 1180 oil type.
Lower sound level
Smaller footprint
Much longer operating life, ease of maintainability and repairability
TRANSFORMERS CONFIGURATIONS:
13. LT GENERATORS
Backup power to the premises will be envisaged with Diesel Generators. The generator backup is
envisaged based on assumption:
CROWN MLCP - Back up for common areas and Emergency Loads. Generators housed in
acoustically treated hoods have been envisaged and will be located at ground level
The DG set envisaged is for prime duty application.
The connectivity between DG and DG Sync panel would be through aluminum conductor cables.
Page 20 of 67
MEP DBR
For MLCP- DG stack is planned 3 meters above building through as Exhaust pipe shaft
adjacent to building..
Generator stack will be separate shaft running adjacent to building or as independent structure. The
stack requirements & height above the terrace shall be as per pollution control board norms.
17. LT Panels
LT panels like Main LT panel, DG Panel, MDB, SMDB, Lift Panel, Emergency panel, SFU,and utility
panels are proposed at Ground floor level and Metering panel/ boards or meters are located at ground
floor electrical/ meter room. The clear spaces for placing the LT panels in the electrical room have
been addressed.
LT Panels to conform to Form-3b enclosures with Aluminum bus bars and indoor panels are of IP 4X
rated.
The distribution panels are designed with necessary feeders to cater power supply to ventilation fans,
lifts, PHE, fire & STP pumps, external lighting & clubhouse load, Retails, retails, offices, common
loads etc. The changovers/ ATS are provided in required panels to transfer power from EB to DG and
vice versa.
LV metering is envisaged for the Retail loads. Design of Metering / boards is strict as per M/s.
MSEDCL requirement. The panel is the indoor duty and located on the ground floor. Separate Ms.
MSEDCL metering panel/board will be envisaged with SFUs.
Changeover will be done after metering for common area and emergency load back up.
Cable connectivity between metering panel to DB of each Retail:
Generally, the below-mentioned methods are adopted for connectivity between the metering panel
and DB to every individual Retail –
Multi-strand copper conductor FRLS PVC insulated wire in FRLS PVC conduit
PVC / XLPE insulated, PVC sheathed multi-strand copper/aluminum conductor armored
cable.
Cable connectivity between metering panel to isolator of each retail/ tenant:
Generally, the below-mentioned methods are adopted for connectivity between the metering panel
and DB to every individual Retail –
Page 22 of 67
MEP DBR
Switchgear selection will be made after making curve simulation and considering relevant
features viz., metering, communication, harmonics analysis etc.,
Distribution Board
The distribution boards of Retails will be having below incomer and outgoings.
Incomer
Incomer will be RCCB 30mA. Rating will be as per final Retail load.
Outgoing
Raw power will be SP/DP MCB. Rating will be as per final Retail load.
Lighting will be SP/DP MCB. Rating will be as per final Retail load.
Page 23 of 67
MEP DBR
Switchgear in LT panels will be sized based on load, Short circuit capacity, discrimination, and co-
ordination study for each feeder up to the load.
Discrimination & coordination study is doing for each & every circuit & panels by using software and
ensure to achieve total /partial discrimination & coordination based on criticality in-circuit distribution.
Typical study & simulation is as below –
Page 24 of 67
MEP DBR
The wiring system is concealed conduit system confirming to IS 732. All the wires are PVC FRLS
copper conductor & conduit is PVC FRLS.
Point wiring will be with 2R x 1.5sqmm + 1R x 1.5sqmm (earth) wires in 20mm dia conduit.
(Wiring between switch and light /fan point or between light/fan points).
Lighting circuit main is with 2R x 2.5sqmm + 1R x 1.5sqmm (earth) wires in 20mm dia conduit.
(Wiring from Distribution board to the first switch point) and 3R x 1.5sqmm wires in 20mm dia conduit
looping between switchboard to switchboard).
Power circuit main is with 2R x 4.0sqmm + 1R x 2.5sqmm (earth) wires in 25mm dia conduit.
(Wiring from Distribution board to the first switch point and looping between switchboards).
Page 25 of 67
MEP DBR
Page 26 of 67
MEP DBR
e. Tower Earthing - Type B Earthing or Ring Earthing forms a perimeter around the
structure. Ring Earthing should: be a closed ring of conductors if it is not possible to
close the ring, a connection must be made inside the building using conductive
metallic equipment such as pipes. Be at least 0.5m below the surface.
f. Adequate number of earth pits need to provide to limit the earth resistance to less
than one ohm & to meet the statutory requirements:
For each generator & transformer, total four earth pits (2 nos. for body earthing & 2
nos. for neutral earthing).
The body earthing for transformers, generators, HT & LT Panels shall be connected
to a common earth bus.
All the cable trays shall have 2 nos. of GI Earth tapes of required size, throughout the
entire length.
All electrical equipment’s, panels, DB’s & Fixtures & noncurrent carrying metallic parts
shall be effectively earthed with GI tapes/ wires as required.
Single earth wire/ tape shall be used for 1 phase & double earth wire/ tape shall be
used for 3 phase equipment earthing respectively.
Dedicated earth pit for solar PV System.
Page 27 of 67
MEP DBR
General
Lightning Protection System shall be in accordance with IS/ IEC 62305-3 & IS 3043
28. TELECOMMUNICATION
The inside distribution will be done with conventional copper cable till telephone and LAN outlets.
We Assumed telephone points (RJ11) will be envisaged for Retail & Office.
Page 28 of 67
MEP DBR
1. SCOPE OF WORK
The facility shall be envisaged with the following for security of the users, building, and equipment.
The facility shall be envisaged with the following security systems for security of the Facility, buildings,
tenants and equipment’s.
Page 29 of 67
MEP DBR
Cameras will be strategically located at entry & exit gates, entry to building at Ground floor
level, ramp entries & in lobbies.
The system will have a digital video recording placed in security room or in Control
room for easy monitoring.
Cameras shall be placed at strategic locations.
The system will be placed in security room or in control room for easy monitoring, the system
is including,
- Dome type fixed cameras
- Bracket type fixed cameras
- PTZ cameras
- Monitors, switches
- Keyboard controller,
- Digital Video recorder
.
The system will be placed in a centralized room located in the tower area and Monitor shall be
provided in Estate Office for easy monitoring,
Dome Cameras
Network Video recorders
Servers
Monitors
Network switches
Racks
Keyboard controllers and other associated accessories.
Video management software will be installed on the computer which monitors and controls the
camera will have the following features.
Page 30 of 67
MEP DBR
Page 31 of 67
MEP DBR
And recent advances in GPON technology (NGPON2 and XGSPON) means GPON can continue to
exceed the bandwidth requirements of end users for the next two or three generations of technology.
GPON eliminates the need for multiple comms rooms full of duplicated infrastructure.
And because GPON only uses one cable, instead of multiple cables, GPON technology also reduces
special requirements for cable pathways by up to 80%.
Page 32 of 67
MEP DBR
Page 33 of 67
MEP DBR
1. SYSTEM OBJECTIVES:
Primary objective is to provide efficient fire protection & life safety system design for this project which
addresses the design requirement, functional and performance for the active & passive fire systems.
a. Primary functions of below described systems are to detect, extinguish & prevent fire incident. Fire
protection systems are envisaged to extinguish & prevent re-ignition of fire across all floors/areas
of this facility.
b. Design of fire protection systems for the facility focuses on two primary goals as mention below:
First, provision of a safe work environment for all employees.
Second, protection of building property and contents.
c. Safe work environment shall be designed to ensure that, all employees are provided at a minimum
code recognized levels of safe egress from the facility in the event of any emergency condition.
Protection of building property and contents is intended to mitigate economic losses in the event of
an emergency condition.
2. GENERAL:
Fire protection & life safety systems are proposed to meet requirements of NBC-2016, Indian
standards, local fire norms & jurisdictional fire authorities. Designing a fire protection system needs
three conditions to be met.
3. BUILDING DETAILS:
The height of the proposed MLCP building is 34.40 mtrs. The proposed building comprises of ground,
12 no’s upper parking floors and terrace.
Below plinth level Fire and PHE pump room with UG tanks.
3rd, 7th & 11th typical floors Lift lobby, toilets, parking’s.
4. BUILDING CLASSIFICATION:
Page 35 of 67
MEP DBR
NBC, 2016 : National building code of India Part IV for fire and life safety system
IS 1239: 2004 : Specification for galvanized iron (GI) Pipes
IS 3589: 2001 : Specification for GI Pipes
IS 3844: 1989 : Code of practice for installation and maintenance of internal hydrants & hose
reels on premises
IS 2190: 2016 : Code of practice for selection, installation and maintenance of first aid fire
extinguishers
IS 15683:2006 : ABC powder type fire extinguishers
IS 5 No.536:2008 : Paint shade for main equipment’s/accessories
IS 15301: 2003 : Installation and maintenance of firefighting pumps
IS 2189:2008 : Installation & maintenance of fire detection and alarm system
IS 13039:2014 : External hydrant system – provision and maintenance
IS 12469: 2019 : Specification of pumps for stationary firefighting installations
IS 15105: 2021 : Design, installation and maintenance of fixed automatic sprinkler fire
extinguishing systems — code of practice
Fire Regulation - Local norms as approved by local fire authorities.
7. BATTERY LIMITS:
Sl No. Battery Limits Builder
3 Fire hydrant system (yard & landing hydrants) with riser fire shafts √
5 Fire sprinkler network, valves & flow switch with drain assembly √
Panel protection system (for main electrical distribution panels, LT panels, Fire
8 √
MCC & main lift panel)
Page 36 of 67
MEP DBR
The fire hydrant system is the most effective, efficient and ultimate means of extinguishing very large
fires, which can prove to be devastating. The main advantage of fighting fires with fire hydrant system
is its accessibility and penetration capability, since fires can be fought from a very large distance and
to a very high reachability.
The hydrant network is pressurized with water at a definite pressure and is maintained in readiness
for any eventuality. Once the hydrant valve is manually opened during fire, the fall is pressure in the
pipe line is sensed by the pressure switches activating the pumps, thereby ensuring continuous
supply of water and pressure at the outlets (hydrant points).
Hydrant pipes will be laid at plinth level and isolating valves will be provided at external are from
maintenance point of view.
Air release valves (vents) at riser pipes at terrace level
All wet riser system pipes shall be based on IS 1239:2004 (Part-I) “Galvanized Iron (G.I)” ERW
heavy grade (“C” class) pipes up to 150 mm diameter pipes and 200 mm diameter and above
size pipes shall be as per IS: 3589:2001.
Pipe fittings shall be FM global approved ductile iron threaded fittings for sizes up to 50mm dia.
Further butt-welded fittings for sizes 65 NB & above as per ASTM A234 Gr. WPB. (Horizontal
Piping)
FM global approved Ductile iron type grooved fittings for vertical risers.
Pipes above ground & in exposed locations will be painted with one coat of etching primer & two
coats of synthetic enamel paint as per IS 5 (Shade 536) – 1994.
Underground pipes:
Underground pipes shall be laid 1m below the ground level & should be protected with wrapping
& coating material (coal tar enamel & coal tar impregnated glass fiber) with an overlapping of
15mm to 20mm as per IS: 10221 (2008).
Holiday test: Holiday test to be carried out for underground pipe.
All road crossings places, fire pipe should be run through RCC Hume pipes.
The internal fire hydrant system is proposed as per IS – 3844:1989. “One number of hydrant valve"
for every 1000 Sq mtrs of floor area. This building is provided with wet risers with landing valves on all
Page 37 of 67
MEP DBR
floors near each staircase area and each landing hydrant comprising of the following:
For fighting fires from outside the building at strategic locations on perimeter of the building, single
headed yard (external) hydrants have been proposed and 30.0 meters is the distance between two
hydrants. The hydrant valve distance should not exceed 2.0 m to 15.0 m from building line. Each
external (yard) hydrant comprising of the following:
Page 38 of 67
MEP DBR
Reference image for External Hydrant system and Brigade inlet connection
Static water storage tanks shall also be provided with a fire brigade draw out collecting head with 63
mm diameter instantaneous male draw out arranged in a valve box at a suitable point at street level.
This draw out shall be connected to galvanized iron pipe of 100 mm diameter with foot valve
arrangement in the tank.
Sprinklers have been designed with sprinkler riser, piping network, sprinkler control valve, floor control
valves, sprinkler alarm valve etc, complete.
All sprinklers are 68 deg C, temperature rating. The sprinkler system is fed by independent pump, the
delivery header of the pumps is designed in such a way and it is possible to feed water from the
hydrant pump to sprinkler system in case of emergency / requirement.
The sprinkler mains at each floor level consisting with flow switch which will transfer to fire alarm
panel in case of water flow in the pipes.
Isolation valve is considered at the tap off points with supervisory switch, from maintenance point
of view at respective levels.
Sprinkler system pipes shall be based on IS 1239:2004 (Part-I) “Galvanized Iron (G.I)” ERW
heavy grade (“C” class) pipes up to 150 mm diameter pipes and 200 mm diameter and above
size pipes shall be as per IS: 3589:2001.
Pipe fittings shall be FM global approved ductile iron threaded fittings for sizes up to 50mm dia.
Further butt-welded fittings for sizes 65 NB & above as per ASTM A234 Gr. WPB. (Horizontal
Piping)
FM global approved Ductile iron type grooved fittings for vertical risers.
Pipes above ground & in exposed locations will be painted with one coat of etching primer & two
coats of synthetic enamel paint as per IS 5 (Shade 536) – 1994.
Page 39 of 67
MEP DBR
Minimum pressure of 0.5 kg/cm2 will be ensured at the remotest sprinkler point.
Areas with false ceiling depth of 800 mm or more shall have two layers of sprinklers for both
voids and below false ceiling as per NBC-2016. Below false ceiling sprinkler shall be connected
with SS braided flexible hose pipe in common areas like corridors and lift lobby.
In common areas, pendent sprinklers installed on the false ceiling will have escutcheon plates
(rosette plate) which provide decorative recessed sprinkler installation (Color of rosette plate
shall be matched witch false ceiling color).
All ramps are protected with sprinklers.
Underground pipes:
Underground pipes shall be laid 1m below the ground level & should be protected with wrapping
& coating material (coal tar enamel & coal tar impregnated glass fiber) with an overlapping of
15mm to 20mm as per IS: 10221 (2008).
Holiday test: Holiday test to be carried out for underground pipe.
All road crossings places, fire pipe should be run through RCC Hume pipes.
Sprinkler
Sl
Type of area Type of sprinkler coverage Remarks
No
Area
Distance b/w two nozzles should be maximum of 2.5mts for better performance. Each system will be
consisting of deluge valve, water supply pipe lines, flow switches, water curtain nozzles.
Deluge valve shall be interlocked with smoke detection system through the flow switches. If any zone
comes on the adjacent zones also should discharge water and create curtain to avoid spread of fire /
smoke to another compartment.
Page 40 of 67
MEP DBR
However, drencher system will be catered by sprinkler pump set, since local authority
not recommending (by referring other LG projects CFO documents) to provide
dedicated pumps for drencher system.
As per NBC part – 4, 2016, Table-7, As per note-11: Provide required number of sets of pumps each
consisting of two electric and one diesel pump (stand by) of capacity 2280 litre/min and two electric
pump of capacity 180 litre/min (see also Notes 22 and 23).
As per note-22: One set of pumps shall be provided for each 100 hydrants or part thereof, with a
maximum of two sets. In case of more than one pump set installation, both pump sets shall be
interconnected at their delivery headers.
As per note-23: Alternative to provisions of additional set of pumps, the objective can be met by
providing additional diesel pump of the same capacity and doubling the water tank capacity as
required for one set of pumps.
Considering the total number of hydrants as less than 100 no’s, Following are the fire water storage
tank capacities required details.
Sl As per NBC
Description Remarks
no 2016
1 Underground tank capacity (Cum)
Fire pumps shall be provided with soft starter. A common compartmentalized control panel for all
pumps has been envisaged and located at pump room by pump set wise. Panel is designed to
operate pumps automatically on pressure loss basis with timers, contactors, indicators etc. The power
Page 41 of 67
MEP DBR
supply to the panel shall be from two sources i.e., electric city board (EB) power and diesel generator
(DG) power.
Description
Sl no Capacity Remark
2280 LPM
1 2 no’s of Electrical motor driven main pump
@88M
180 LPM @
3 2 no’s of Electrical motor driven Jockey pump
88M
900 LPM @
4 1 no of Booster pump At terrace level
40M
Page 42 of 67
MEP DBR
The diesel engine exhaust system shall be complete with silencer, silencer piping including bends and
accessories. This should take to outside the pump room at safe location. The total back pressure shall
not exceed the engine manufacture's recommendation.
The air vessel shall be provided to compensate for slight loss of pressure in the system and to provide
an air cushion for counter-acting pressure, surges, whenever the pumping sets come into operation.
Page 43 of 67
MEP DBR
Portable fire extinguishers are provided at locations mentioned below as per local fire authority,
Sl.
Type of fire extinguishers Area of application
No
One ABC powder extinguishers of 6.0 kgs and 2
1 For every 8 cars at parking areas
no’s fire buckets.
2 One ABC powder extinguishers of 6.0 kgs. Common areas and Staircase areas
3 One CO2 extinguishers of 4.5 kgs. Capacity Electrical room and FCC room
One mechanical Foam type extinguisher of 9.0 Transformer, Pump room & diesel
4
liters generator
5 One CO2 extinguishers of 2 Kgs. Capacity Lift machine room
Fire hose reel, fire extinguishers, emergency exits (at stairs), main fire alarm panel & MCP’s etc.
Photo luminescent safety signage plays a vital safety role in risk-prone areas and panic causing
situation. When the source of light suddenly goes off, photo luminescent materials glow settles to a
near continuous intensity.
Page 44 of 67
MEP DBR
Exit signs above doors or indicating exit routes will be provided where they will help people to find
a safe escape route. Signs on exit routes will have directional arrows according to the route to be
taken.
Battery operated exit signage’s are proposed for exit doors, exit corridors & driveway area
including all critical rooms. These shall be with inbuilt battery with back up for up to 90mins in case
of emergency.
Photo luminescent safety signage glows in darkness. This can be useful to find location of fire
fighting appliances in case of emergency even in darkness. Photo luminescent identification
signage’s are provided in exit staircases, lift lobby, extinguisher location, fire escape hydrant, hose
reel & near fire alarm panel, etc.
Fire safety plan: Indicating all fire exit points, extinguisher locations, you are here point, manual
call point & hydrant location shall be prepared & located at strategic locations (wall mounted) in
the floor. Size shall be as directed by consultant.
Fire order highlighting actions to be taken in case of fire shall be placed near to entrance.
Page 45 of 67
MEP DBR
As per LG policy Hybrid (Semi addressable) system has been provided for parking floors (MLCP
areas)
Addressable analogue type fire detection and alarm system shall be provided in retail shop areas
of the building as per the standards.
It is essential that when a fire breakout, it is detected as soon as possible, the earlier actions are
taken, the greater possibility of minimizing damage and loss in terms of human lives and property.
This includes an early warning, initiation of protection systems for safety of occupants and fire
brigades and for the control of fire.
Fire detectors are essentially sensing units located at strategic locations to detect one or more of
the characteristics of a fire, smoke, heat or flame. Choice of the type of detectors for particular
premises depends on the type of fire hazard present and the conditions prevailing in and around
the premises. In some cases, it may be useful to combine different types of detectors for early
detection of fire.
Manual call points and hooters are installed at strategic location to enable easy access and
audibility. In the event of fire, the occupant who is rushing through the staircase can operate the
manual call point. On operation of the manual call point the control panel, which is located in the
centralized location, being monitored around the clock, initiates an alarm through the electronic
hooters (External sounders), while registering the affected zone.
Addressable fire detection & alarm control panel will be placed in the fire command centre (FCC)
at ground floor.
Areas with false ceiling depth of 800mm or more shall have two layers of detectors for both void
and ceiling level as per NBC 2016.
Fire alarm control panel (FACP) proposed shall have an LCD display for indicating panel status,
alarm location, fault conditions etc.
Actuation of any initiating device like multi sensor detectors shall cause following operations to
occur.
Activates sounders & public address system.
Shut down of respective floor / area air handling units & de-activates access doors if any.
Shutdowns electrical power supply to the building.
Activation of smoke extractor system (if any) in the event of fire/emergency.
Design Parameters:
Multi sensor (smoke + heat) type smoke detectors for common areas like lobby, corridor, retail
shop areas etc. in the building (Except parking areas).
Retail shop (Tenant) below false ceiling area detection system will be in tenant scope.
Electronic hooters cum strobes and manual call points (MCP) shall be considered at every exits.
Multi sensor type smoke detectors considered for pump room, electrical rooms, STP and common
other utility areas.
Smoke detectors in across all the common areas & inside electrical, IT & ELV shafts.
Heat detectors in across parking areas.
Page 46 of 67
MEP DBR
Detectors shall be complying to latest version of UL268, 7th edition & UL864, 10th edition for
panel.
2C x 1.5 sq mm twisted pair PVC insulated armoured fire resistant, flame retardant low smoke
(FRLS) cable shall be used in complete fire detection and fire alarm system.
Fire detection and alarm system shall have a battery backup for 48 hours in standby / normal
mode and 30 minutes in alarm condition. Lithium – ion batteries shall be used.
Detector in each loop having a capacity of connecting a minimum of 125 addressable detectors
and 125 addressable modules or a mix of up to 250 detectors and devices in any combination in
any single loop.
230V, 6A UPS power supply shall be considered for FA system (part of electrical scope).
Response indicators for above ceiling detectors.
Fire alarm panels shall be integrated with BMS through BACnet over IP protocol.
The integration with various systems like exhaust & emergency fans, panic bars (if required) shall
be done through the hard wiring further it is proposed to extend the fire alarm panel
signals/indications to BMS control system for monitoring.
Networkable active repeater panel is proposed near reception for monitoring & remote controlling.
Parking floor alarm system circuit will be Class-B type wiring, further retail shop and common area
like lift lobby, corridors shall have Class-A type wiring.
Page 47 of 67
MEP DBR
Speakers: All speakers shall operate on 70 VRMS or with field selectable output taps from
3/6/10/12/15 Watts. Speakers shall produce nominal sound output of 85dBA at 10 feet (3m).
Page 48 of 67
MEP DBR
Audio message generator (pre-recorded voice)/speaker control: Intelligent device will interface
with an emergency voice communication system capable of transmitting a pre-recorded voice
message to all speakers in the floor & common announcement is done in the floor / area. Actuation of
any alarm initiating device will cause a pre-recorded message to sound over the speakers.
Fire stop sealants are proposed for all shaft closure at all levels to prevent spread of fire, smoke, toxic
fumes & moisture vertically.
Page 49 of 67
MEP DBR
The staircases may be either internal or external type. Staircases shall be located in such a way that
occupants shall not travel more than 45 meters to reach an exit and clear width of stairs shall be
minimum 1500 mm wide. The minimum width of tread without nosing shall be 300 mm. The treads
shall be constructed and maintained in a manner to prevent slipping. The maximum height of rise
shall be 150 mm. The number of risers shall be limited to 12 no’s per flight.
All the staircases shall fit with self closing type fire rated doors and staircases shall discharge at the
level of exit discharge, to the exit discharge, either,
Directly, or
Through an exit passageway, or
Through a large lobby.
At least 50% of the staircases shall discharge as per (a) and/or (b) above.
Please refer annexure-1 for the details of total egress width required for the proposed building.
This complete building need to be sprinklered, then the travel distance will be 45.0 meters from any
portion of the floor plate on all floors.
Page 50 of 67
MEP DBR
An enclosed shaft having protected area of 120 min fire resistance rating comprising protected lobby,
staircase and fireman’s lift, connected directly to exit discharge or through exit passageway with 120
min fire resistant wall at the level of exit discharge to exit discharge. The fire fighting shaft shall be
equipped with fireman talk back, wet riser and landing valve in its lobby. A typical fire tower details
shown below.
However, local authority not recommending fire tower with wet riser with landing valve,
hence it is not considered.
Page 51 of 67
MEP DBR
As per national building code, following details shall be followed for pressurization of staircases and
lift lobbies.
Note 1: The natural ventilation requirement of the staircase shall be, achieved through opening at
each landing, of an area 0.5 m2 in the external wall. A cross ventilated staircase shall have 2 no’s of
such openings in opposite/adjacent walls or the same shall be cross ventilated through the corridor.
b) Fire command centre shall be constructed with 120 min rating walls with a fire door and shall be
provided with emergency lighting. Interior finishes shall not use any flammable materials. All controls
and monitoring of fire alarm systems, pressurization systems, smoke management systems shall
happen from this room. Monitoring of integrated building management systems, CCTVs or any other
critical parameters in building may also be from the same room.
c) Details of all floor plans along with the details of fire fighting equipment and installations (2 sets
laminated and bound) shall be maintained in fire command centre.
d) The fire staff in charge of the fire command centre shall be responsible for the maintenance of the
various services and fire fighting equipment and installations in coordination with security, electrical
and civil staff of the building.
Page 52 of 67
MEP DBR
Page 53 of 67
MEP DBR
1. GENERAL:
Public health Systems proposed are specific to project requirement, economical, less maintenance,
time tested and following mandatory requirements of Standard codes and norms. This document
briefs on water demand, storage and rain water harvesting schemes.
2. PROJECT DESCRIPTION
3. Project consists single building with G+12 upper floors structure with terrace.
The height of the proposed MLCP building is 34.40 mtrs. The proposed building comprises of ground,
12 no’s upper parking floors and terrace.
Below plinth level Fire and PHE pump room with UG tanks.
3rd, 7th & 11th typical floors Lift lobby, toilets, parking’s.
Page 54 of 67
MEP DBR
Page 55 of 67
MEP DBR
5. DESIGN CONSIDERATIONS:
Occupancy considered per unit is as per the NBC -2016 & Lodha Policy.
1. Occupancy considered for retail area @ 3sq/m on carpet area for retail ground floor, refer the
water demand calculation (Refer Annexure 1).
2. Source of water supply could be from tanker, Municipal and rain water.
3. Refer Annexure-2 Water Balance chart for usage of STP treated water.
4. UG sumps are located in the ground floor.
5. STP is combined for the whole sector development – part of Infra design.
6. Storage, pumping and water supply piping for landscaping shall be as per the requirements of
landscape consultants.
7. The STP is designed to handle soil and waste water from toilets.
8. High efficiency plumbing fixtures are considered for water conservation, functional performance
and aesthetics, pandemic etc., further selection of sanitary fixtures and fittings is as per ID
requirement with recommended water flow rate.
9. The Rain Water pipes is connecting to Infra network, no rain water storage has been planned for
this building.
The storage provided as underground meets 1.0 days of domestic water demand and 1 day of
storage of flushing water demand at STP. (Gravity Design)
1. Flushing water (STP treated water) for landscaping and toilet flushing is taken from combined
Palava STP.
2. Domestic water is stored in the overhead tanks as half-day storage capacity on the terrace
OHT to serve for ground floor Retail & car wash through pressure booster pump for top 3
floors and gravity system for remaining floors.
3. Flushing treated water is stored in the overhead tanks as half day storage capacity on the
terrace to serve toilets through gravity system.
Page 56 of 67
MEP DBR
Water demand
Sl.
Description area in sqm Total population
No: Domestic water Flushing water
demand (LPCD) demand(LPCD)
A Retail floors
1 Ground floor - Retail floor (considered 3 sqmt/person) 1034 345
a) Fixed population- (Refer note - 'a') 34 862 689
b) Visitor population- (Refer note - 'a') 310 1551 3102
Total 2413 3791
Note:-
1 3sqmt/person has been considered for the retail population
2 Retail area total population is segregated into staff & visitor population.
a) Total population has been segregated into 10% for fixed & 90% for floating/visitor. Considered Domestic water 25LPCD, Flushing 20 LPCD for
fixed population and domestic 5LPCD, flushing 10LPCD for floating/visitor population as per NBC 2016.
Page 57 of 67
MEP DBR
Page 58 of 67
MEP DBR
Domestic water distribution scheme is proposed through Gravity system with booster system for top
3 floors as per Lodha policy. Domestic overhead tank (OHT) is provided on the terrace
Flushing water distribution scheme is proposed through Gravity system. Flushing overhead tank
(OHT) is provided on the terrace.
Water distribution Scheme is proposed to be through gravity system, Considering the below
mentioned points:
Minimum pressure of 1 bar is required for health faucet & wash basin.
are planned in the domestic pump room. All sumps and overhead
tank will have water level controller linked with pumps to monitor
pump operations and avoid dry run.
Minimum of 1 bar and 3 bar Maximum residual pressure is envisaged in the design.
Pressure reducing valves are provided in the water supply pipeline to regulate
or reduce the higher pressure which could affect the fixture and water flow (if
necessary).
Zoning of water supply lines will be addressed based on max/ min pressure
permissible to toilet fixtures.
Water hammer arresters will be proposed in the low side of distribution considering sudden surge due
to flush valves and sensor taps operation.
It is proposed to use CPVC SDR-11 pipes for hot and cold-water supply
distribution system up to 50mm diameter, only for internal toilet piping. CPVC
SDR-11 pipes & fittings meet the requirement of ASTM D-2846.
The working pressure of pipes is 400 psi at 23 deg. C and 100 psi at
82deg.C
Aesthetic installations.
Shaft piping, pump rising main (PRM) and external water lines from source to
sumps shall be of UPVC unthreaded pipes (Schedule-80) confirming to ASTM
D- 1785 and fittings confirming to ASTM D- 2467. –HDPE pipes. Refer below
piping material chart.
The sanitary system will be designed in conformity with National Building Code 2016 and SP – 35:
1987. The internal sewerage system shall be Double Stack System consisting separate line for soil
and waste (i.e. the waste from the wash basin and trap is taken in a separate pipe and the soil waste
from water closet is taken in a separate pipe)
Anti-siphon pipes are provided for each soil down takes. Vent cowls provided at every stack for
primary venting. Suitable traps are laid at required locations to provide water seal
and ensure efficient functioning of the drainage system.
The sewerage network comprises of horizontal and vertical stacks laid in the toilets
and in the plumbing shafts respectively and connected to the Infra sewage
network.
It is proposed to use UPVC pipes and fittings for the sewerage system. These
pipes and fittings conform to IS 13592: 2013.
The SWR pipes confirming to IS standards with one end of pipe plain and the other
end is self-socket type with integral grove to hold rubber gasket are used for vertical
stacks.
B. IS 4985 – for pipe diameter less than 75mm and greater than 160mm
These rubber ring joints ensure water tightness in the system and help to handle thermal
expansion/contraction.
Page 60 of 67
MEP DBR
Low noise system is an innovative product made of mineral-reinforced polypropylene. This base
material provides excellent mechanical and acoustic properties and made with a high molecular
structure, which enables absorption of airborne sound and structure borne sound. Sound energy does
not spread over the pipe wall.
Page 61 of 67
MEP DBR
Page 62 of 67
MEP DBR
Page 63 of 67
MEP DBR
All sanitary fittings shall be selected considering improved flow rates compared to conventional flow
fixtures as below to achieve savings in potable water consumption. Recommended flow rates are as
follows -
SL
No Schedule of Fixture / Fittings Mounting Heights from FFL of Toilet
1 EUROPEAN WATER CLOSET 410mm including seat cover
2 PAPER HOLDER 400mm
3 TOWEL RING 1200mm
4 SHOWER ARM WITH HOSE 2100mm
5 TOWEL RACK/RAIL/ROD 1800mm
6 EXPOSED 2 IN 1 WALL MIXER 750mm
7 SPOUT 750mm
8 SINGLE LEVER DIVERTOR 900mm
9 WASH BASIN MIRROR 600X400 1500mm
10 SINK COCK/TAP FOR SINK/SINK MIXER 1000mm
11 URINAL (UPTO LIPPING LEVEL) 600mm
AUTOMATIC FLUSHING SENSOR FOR
12 URINALS 1350mm
13 PT FOR URINAL SPREADER PIPE 1200mm
14 LONG BODY BIB COCK FOR SINK 1000mm
15 HEALTH FAUCET 450mm
16 2 WAY BIB COCK (Utility) 600mm
17 BOTTLE TRAP FOR WASH BASIN 450mm to 500mm
18 BOTTLE TRAP FOR URINAL 350mm to 450mm
19 WASH BASIN 800mm to max of 850mm
20 SOAP DISH 900mm to max of 1200mm
21 STAINLESS STEEL SINK 800mm to 900mm
NOTE: Water fixtures with very less flow rate should be considered during procurement to achieve
the maximum water savings.
Page 64 of 67
MEP DBR
Access to the service shaft can be through the toilets/utility. Proper ventilation should be provided at
alternate floors using Louvers to meet the oxygen demand for the person inside the shaft during
maintenance. Shafts should be designed with proper lighting and 2-hour fire rated wall. Cover slab
should be provided at the top of the shaft. Fire stop sealants/ PCC sealants are proposed at the shaft
entry to prevent the spread of fire, smoke, toxic fumes and moisture.
The Rain Water Harvesting system is designed based on the meteorological data obtained from
Indian Meteorological Department.
The rainwater from terrace run off’s will be collected through number of down take pipes at desired
locations, which will be connected to Infra storm water network.
The average intensity of rainfall in a year is found in the month of the July.
100mm/hr rain fall has been considered for calculation purpose.
Page 65 of 67
MEP DBR
External drains are proposed with open box drain for storm water drainage.
These shall be RCC drains with combination of perforated RCC covers. Roads
are sloped towards these drains. Sedimentation pits or filtration chamber is
proposed at ground level with screens and gravel filters. The overflow/excess
water to be disposed through gravity to external drain.
Each deep injection well generally harvested 25 cum of run-off per day and
normal recharge pit to harvest / hold 8-10 cum/day.
Deep well injection wells can also be planned below/next to the box drain.
The overflow from the drain/injection well to be routed to the external drain
(excess rain water only).
Page 66 of 67
MEP DBR
Water distribution scheme for both Domestic & Flushing will be through gravity.
STP will be combined for Palava development.
Booster pump has been considered for Top 3 floor for car wash.
Terrace rain water will be connected to Infra network, no storage has been planned for
Crown.
Page 67 of 67