FABRIC PARK - MIDRAND

• PROCUREMENT SCHEDULE - BUILDING WORKS •


• REVISION: 1 - status as at the 23 October 2015

ITEM SUB-CONTRACTOR/SUPPLIER REF PRESENT 1 PRESENT 2 AGREE ISSUE ISSUE TENDER TENDER LEAD REQ'D MEET PROVIDE SIGN COMMENT
Days
NO. DESCRIPTION & TYPE CODE TENDER LIST SPECS TENDER CLOSE AWARD TIME (WKS) ON SITE REQ'TS SECURITY CONTRACT
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)

Structural Steelwork A730 N/A N/A Complete Complete Complete Complete Complete 56 8 20-Nov-15
1

Electrical C910 N/A N/A Complete Complete Complete Complete Complete 14 2 01-Dec-15
2

Concrete Surface Bed B600 N/A N/A 02-Dec-15 09-Dec-15 15-Jan-16 29-Jan-16 05-Feb-16 14 2 19-Feb-16
3

Louvres & HVAC to Offices V110 24-Oct-15 05-Dec-15 05-Dec-15 12-Dec-15 18-Jan-16 01-Feb-16 08-Feb-16 49 7 28-Mar-16
4

Sprinklers & Fire Systems B530 Complete Complete Complete Complete Complete Complete Complete 84 12 01-Feb-16
5

Roof sheeting and vertical cladding N490 14-Oct-15 28-Oct-15 28-Oct-15 04-Nov-15 11-Nov-15 25-Nov-15 02-Dec-15 70 10 10-Feb-16
6

Roller shutter doors 22-Nov-15 06-Dec-15 13-Dec-15 19-Jan-16 26-Jan-16 09-Feb-16 16-Feb-16 56 8 12-Apr-16
8

Dock Levellers N510 06-Dec-15 20-Dec-15 19-Jan-16 26-Jan-16 02-Feb-16 16-Feb-16 23-Feb-16 49 7 12-Apr-16
9

Steel staircase 16-Feb-15 02-Mar-15 02-Mar-15 09-Mar-15 16-Mar-15 30-Mar-15 06-Apr-15 49 7 25-May-15
10

Tiling floors and walls N590 14-Dec-15 28-Dec-15 04-Jan-16 11-Jan-16 18-Jan-16 01-Feb-16 08-Feb-16 70 10 18-Apr-16 DOMESTIC
11

Waterproofing (vertical) U530 15-Jun-15 29-Jun-15 06-Jul-15 13-Jul-15 20-Jul-15 03-Aug-15 10-Aug-15 105 15 23-Nov-15 DOMESTIC
12

Access Control V160 01-Dec-15 12-Jan-16 19-Jan-16 26-Jan-16 02-Feb-16 16-Feb-16 23-Feb-16 28 4 22-Mar-16
13

Data V160 12-Oct-15 26-Oct-15 02-Nov-15 09-Nov-15 16-Nov-15 30-Nov-15 07-Dec-15 63 9 08-Feb-16
14

Entrance Gates / Booms 22-Jan-16 05-Feb-16 12-Feb-16 19-Feb-16 26-Feb-16 11-Mar-16 18-Mar-16 14 2 01-Apr-16
15

Smoke detection V160 22-Dec-15 05-Jan-16 12-Jan-16 19-Jan-16 26-Jan-16 09-Feb-16 16-Feb-16 35 5 22-Mar-16
16

Directional signage 25-Jan-16 08-Feb-16 15-Feb-16 22-Feb-16 29-Feb-16 14-Mar-16 21-Mar-16 84 12 13-Jun-16
17

Shopfitting R60 22-Nov-15 06-Dec-15 13-Dec-15 19-Jan-16 26-Jan-16 09-Feb-16 16-Feb-16 98 14 24-May-16
18

Balustrading 29-Nov-15 13-Dec-15 12-Jan-16 19-Jan-16 26-Jan-16 09-Feb-16 16-Feb-16 84 12 10-May-16


19

Fire signage 29-Feb-16 14-Mar-16 21-Mar-16 28-Mar-16 04-Apr-16 18-Apr-16 25-Apr-16 49 7 13-Jun-16
20

Sanitary Fittings Q910 16-Nov-15 30-Nov-15 07-Dec-15 13-Jan-16 20-Jan-16 03-Feb-16 10-Feb-16 105 15 25-May-16 DOMESTIC
21

Kitchen cupboards R60 02-Feb-16 16-Feb-16 23-Feb-16 01-Mar-16 08-Mar-16 22-Mar-16 29-Mar-16 56 8 24-May-16 TENANT INSTALLATION
22

Landscaping 7830 05-Jan-16 19-Jan-16 26-Jan-16 02-Feb-16 09-Feb-16 23-Feb-16 01-Mar-16 28 4 29-Mar-16
23

Walk-off Mats 08-Feb-16 22-Feb-16 29-Feb-16 07-Mar-16 14-Mar-16 28-Mar-16 04-Apr-16 70 10 13-Jun-16
24

Stone Vanities 7880 10-Feb-16 24-Feb-16 02-Mar-16 09-Mar-16 16-Mar-16 30-Mar-16 06-Apr-16 49 7 25-May-16
25

Toilet Accessories R50 29-Feb-16 14-Mar-16 21-Mar-16 28-Mar-16 04-Apr-16 18-Apr-16 25-Apr-16 49 7 13-Jun-16
26

Paint, Epoxy and Roadmarking 30-Nov-15 14-Dec-15 13-Jan-16 20-Jan-16 27-Jan-16 10-Feb-16 17-Feb-16 56 8 13-Apr-16
27

Paving 7810 09-Nov-15 23-Nov-15 30-Nov-15 07-Dec-15 13-Jan-16 27-Jan-16 03-Feb-16 56 8 30-Mar-16
28

Not yet required


Required within 2 weeks
Late
Complete