Ⅰ. Scope Page
(1) Scope 1
(2) Work Descriptions 1
Ⅱ. Test Items 2
Ⅲ. Test Procedures 3
Page. 1
Ⅱ. Test Items
4 Tightness Test ― ― 〇
9 Test on CTs ― ― 〇
10 ― ― ― ―
11 ― ― ― ―
12 ― ― ― ―
13 ― ― ― ―
14 ― ― ― ―
15 ― ― ― ―
16 ― ― ― ―
17 ― ― ― ―
18 ― ― ― ―
19 ― ― ― ―
20 ― ― ― ―
Page. 3
Ⅲ. Test Procedures
1 Dielectric test on the main circuit
【Description】
(1)Measurement of the insulation resistance
The insulation resistance between the main circuit and Earth shall be measured
with a 1000V-meggar before and after this dielectric test.
500kV
400kV
318kV 60s.
200kV
100kV
Test duration
1 Fig.1 Volatge Steps
1
※ It shall check if the apply voltage and leak current (charging current) are stable
at each voltage steps. For reference, leak current shall be recorded at 318kV and 560kV.
【Criteria】
(1)More Than 2000 MΩ with a 1000V-meggar
(2)To be withstood
(3)To be withstood
【Criteria】
(1)More Than 5 MΩ with a 500V-meggar
Page. 4
【Criteria】
(1)Within ±10 % of the factory data or design values
4 Tightness Test
【Description】
(1)To measure gas-leakage, all gas seal surfaces are to be covered with plastic bags.
The first measurement is to obtain initial value and the secound one after 12 hours passed is
to obtain amount of gas leakage. The gas pressure must be rated during this test.
Gas Pressure : Rated Gas Pressure
Test duration : More than 12 hours
【Criteria】
(1)Less than 0.1% / year (Less than 8 ppm)
Page. 5
【Criteria】
(1)To be as the manufacturer's drawings and instructions
(2)No loosen bolts and no damages on all pipes.
5.2 Comformity of the wiring between LCCs and GIS units with the diagrams
【Description】
(1)Continuity checks with a buzzer
(2)Proper function of the electrical, pneumatic and other interlocks
(3)Proper function of the control, measuring, protective and regulating equipment
including heating and lightning
【Criteria】
(1)To be as the drawings.
(2)To be as the drawings.
(3)To be as the drawings.
Page. 6
【Criteria】
(1)To be operated normally.
【Criteria】
(1)Heaters SPH1 : 377.9 ± 10% Ω
SPH2 : 1058.0 ± 10% Ω
Coils for closing : 4.86 ~ 5.94 Ω (at 20℃)
series resistors for closing : 73.8 ~ 90.2 Ω
1
Coils for opening : 4.86 ~ 5.94 Ω (at 20℃) ※each Trip coil 1 & 2
series resistors for opening : 73.8 ~ 90.2 Ω
1 Hydraulic motor : for reference
【Criteria】
(1)To be as the drawings.
(2)To be as the drawings.
(3)No damage and no loosen bolts in the control box
【Criteria】
(1)Less than 15min. to pump up to 33.5 MPa.
(2)For reference
1 (3)For reference
【Criteria】
(1)Balance pressure : 38.0 ~ 39.5 MPa
(1)10min. after stopping pump : more than 34.5 MPa
Page. 8
【Criteria】
(1)Oil pressure switch shall be performed as per the table.2.
【Criteria】
(1)Not pumping
Page. 9
【Criteria】
(1)To be operated normally.
(2)To be operated normally.
【Criteria】
(1)Timing test will be evaluated under No.1 condition in the table 3.
・for close operation,
ES/DS Closing time : Less than 5 s
HSES Closing time : Less than 0.1 s ※from releasing spring to the main contact touch
【Criteria】
(1)For reference
【Criteria】
(1)To be as the drawings.
(2)To be as the drawings.
(3)No damage and no loosen bolts in the control box
Page. 10
【Criteria】
(1)GCB : Less than 150 ppm, GIS : Less than 300 ppm
(2)More than 97 %
【Criteria】
(1)The set and re-set pressure shall be as the table.4.
9 Test on CTs
【Description】
(1)Polarity check
(2)Ratio check
1 (3)Measurement of the secondary winding resistance for reference
1 (4)Magnetization curve check for reference
1 (5)Measurement of the insulation resistance of the secondary winding
【Criteria】
(1)To be as the drawings.
(2)±10% of the calculated value
1 (3)For reference
1 (4)For reference
(5)More Than 5 MΩ with a 500V-meggar
1